CN112360344A - Shield type rapid hole forming construction method - Google Patents

Shield type rapid hole forming construction method Download PDF

Info

Publication number
CN112360344A
CN112360344A CN202011151722.9A CN202011151722A CN112360344A CN 112360344 A CN112360344 A CN 112360344A CN 202011151722 A CN202011151722 A CN 202011151722A CN 112360344 A CN112360344 A CN 112360344A
Authority
CN
China
Prior art keywords
pile
concrete
drilling
hole
pile casing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011151722.9A
Other languages
Chinese (zh)
Inventor
王如军
黄佳伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Xunxi Construction Co ltd
Original Assignee
Zhejiang Xunxi Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Xunxi Construction Co ltd filed Critical Zhejiang Xunxi Construction Co ltd
Priority to CN202011151722.9A priority Critical patent/CN112360344A/en
Publication of CN112360344A publication Critical patent/CN112360344A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/04Directional drilling
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/13Methods or devices for cementing, for plugging holes, crevices, or the like
    • E21B33/138Plastering the borehole wall; Injecting into the formation

Abstract

The invention discloses a shield type rapid pore-forming construction method, which comprises the following steps of; step (1), arranging a protective cylinder; step (2), positioning a drilling machine; step (3), drilling equipment; step (4), cleaning the hole; step (5), manufacturing a reinforcement cage; step (6), immediately installing a concrete pouring guide pipe after the reinforcement cage is placed to the designed depth, and avoiding the collision between the guide pipe and the reinforcement cage, wherein the guide pipe is made of a steel pipe with the diameter of 200 and 300 mm; and (7) pouring underwater concrete. According to the invention, soil and rock are cut into powder and then conveyed to the mud pit for filtering and separating, and the powder is circulated into the hole for wall protection, the construction process is similar to shield push type hole forming, the drill lifting is not needed, the construction efficiency is high, the application range is very wide, the technical problem that the flow plastic layer collapses all the time is overcome, the drill lifting is not needed in the hole forming process, and the construction efficiency is high.

Description

Shield type rapid hole forming construction method
Technical Field
The invention relates to the technical field of building construction, in particular to a shield type rapid hole forming construction method.
Background
The mechanization degree of the bored concrete pile formed by the rotary drilling rig is high, and the method is a main trend of construction in the foundation and foundation industries in the future, but the rotary drilling construction can be carried out under the geological condition with complex geological conditions by matching with a deep pile casing, the difficulty of the rotary drilling under the condition of plastic soil and deep holes is high, the technical level and the benefit are low, and the shield type rapid hole forming construction method is provided.
Disclosure of Invention
The invention aims to provide a shield type rapid hole forming construction method to solve the problems in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme: a shield type rapid hole forming construction method comprises the following steps;
step (1), arranging a protective cylinder;
arranging a pile casing according to the pile site, wherein the inner diameter of the pile casing is 50-100mm larger than the diameter of the drill bit, the deviation between the center of the pile casing and the center of the pile site is not more than 50mm, the deviation of the inclination is not more than 0.5%, and the space between the pile casing and the pit wall is filled with clay;
step (2), positioning a drilling machine;
the drilling machine keeps stable and does not incline or displace, the drill bit is aligned with the hole position and the motor is started to open the hole, when the drill bit is aligned with the cross line of the center of the pile position, all data can be locked without adjustment, the center of the drill bit and the center of the pile are accurately aligned after the drilling machine is in place, and the error is controlled within 10 mm;
step (3), drilling equipment;
the drilling is started, the drilling speed is stable and cannot be too fast, a drilling machine is not forced to be pressurized when a rigid object, a steel bar and an old concrete foundation are met, the slurry construction is observed in the drilling process to meet the requirement of slurry wall protection, and a slurry blender and bentonite are added when necessary;
step (4), cleaning the hole;
a reverse circulation slurry drilling machine system is adopted, the hole bottom is very clean after the hole is formed, and after the slurry concentration is well mixed, the drill is slowly lifted through a valve;
step (5), manufacturing a reinforcement cage;
a reinforcement cage manufacturing machine is adopted, the reinforcement cage is ensured to be straight when being placed downwards, the steel reinforcement cage is strictly prevented from swinging and colliding with the hole wall, reinforcement protection blocks are added in the installation process, the set distance is 2 meters, and the thickness of the reinforcement cage protection layer is ensured;
step (6), immediately installing a concrete pouring guide pipe after the reinforcement cage is placed to the designed depth, and avoiding the collision between the guide pipe and the reinforcement cage, wherein the guide pipe is made of a steel pipe with the diameter of 200 and 300 mm;
pouring underwater concrete;
s1, when the concrete is poured, in order to discharge the water-proof bolt smoothly, the distance from the bottom of the guide pipe to the bottom of the hole is preferably 30-50cm, the guide pipe is buried more than 1.0m below the concrete surface once, the buried depth of the guide pipe is preferably 2-6m in the pouring process, the guide pipe is prevented from being lifted out of the concrete surface,
s2, continuously pouring concrete, wherein the height of the top of the poured pile is pre-increased by a certain height which is 50-100cm higher than the designed height, the pre-increased height can be chiseled after the foundation pit is excavated, and the pile body is prevented from being damaged during chiseling;
s3, the steel pile casing below the ground and the pile top can be lifted after the concrete is poured, and the influence on the quality of the pile body caused by the inclusion of filling sundries or silt into the concrete in the lifting process is prevented;
and S4, after the pouring is finished, finishing and flushing the site, and removing concrete deposits on equipment and tools.
Preferably, in the step (1), the embedding of the pile casing adopts a rotary drilling rig static pressure method to sink in sections, and the pile casing sinks to the designed depth in cooperation with a vibration hammer, and the concrete operation is as follows: and (3) correctly positioning the drilling machine to enable the perpendicularity of the machine body, the perpendicularity of the drill rod and the central line of the pile casing to be integrated, then bringing a cylindrical drill bit at the top of the drill rod, hoisting the pile casing by using a crane and correctly positioning, vertically pressing the pile casing into the soil body by using a rotary drilling rod, leading the pile position center back through four control pile casings after the pile casing is buried, enabling the center of the pile casing to coincide with the pile position center, and marking the position of the pile casing direction line by using red paint on the pile casing.
Preferably, in the step (2), the chassis of the rotary drilling rig is a telescopic automatic leveling device, and an instrument is arranged in an operation chamber to accurately display electronic readings.
Preferably, in the step (4), negative pressure is formed by avoiding too fast drilling of hands, so that the hole wall is shrunk, and the quality of formed holes cannot meet the requirement.
Preferably, in step (6), the inner wall surface of the conduit should be smooth and have sufficient strength and rigidity, and the joint of the pipe sections should be well sealed and easy to assemble and disassemble.
Preferably, the reverse circulation mud drilling machine system comprises the ground, a drilling machine, a mud pump, a drill rod, a drill bit, a conveying pipe, a mud storage cavity, a mud filtering device and a circulating pipe;
the drilling machine is arranged at the top end of the ground, a mud pump is arranged in the drilling machine, a driving end of the drilling machine drives a drill rod to move downwards, an input end of the mud pump is connected with the drill rod, a drill bit is assembled at the bottom end of the drill rod, an output end of the mud pump is connected with one end of a conveying pipe, the other end of the conveying pipe extends into a mud storage cavity formed in the upper surface of the ground, a mud filtering device is assembled on the side surface of the mud storage cavity, one end of a circulating pipe is assembled on the side surface of the mud filtering device, and the other end of.
The shield type rapid hole forming construction method provided by the invention has the beneficial effects that:
1. according to the invention, soil and rock are cut into powder and then conveyed to a mud pit for filtration and separation, and are circulated to the hole for wall protection, the construction process is similar to 'shield' push type hole forming, the drill lifting is not needed, and the construction efficiency is high;
2. the invention has wide application range, overcomes the technical problem of hole collapse of the flow plastic layer, does not need to lift a drill in the hole forming process and has high construction efficiency.
Drawings
FIG. 1 is a process flow diagram of a shield-type rapid hole-forming construction method according to the present invention;
FIG. 2 is a schematic diagram of a system mechanism of a reverse circulation mud drilling machine of the shield type rapid hole forming construction method.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example 1, please refer to fig. 1-2, the present invention provides a technical solution: a shield type rapid hole forming construction method comprises the following steps;
step (1), arranging a protective cylinder;
arranging a pile casing according to the pile site, wherein the inner diameter of the pile casing is 50-100mm larger than the diameter of the drill bit, the deviation between the center of the pile casing and the center of the pile site is not more than 50mm, the deviation of the inclination is not more than 0.5%, and the space between the pile casing and the pit wall is filled with clay;
the embedding of the pile casing adopts a rotary drilling rig static pressure method to sink in sections, the vibration hammer is matched to sink to the designed depth, and the concrete operation is as follows: a drilling machine is correctly positioned, the perpendicularity of a machine body, the perpendicularity of a drill rod and the central line of a pile casing are integrated, then a cylindrical drill bit is arranged at the top of the drill rod, the pile casing is hoisted by a crane and correctly positioned, the drill rod is rotationally dug to vertically press the pile casing into a soil body, the pile position center is led back through four control pile casings after the pile casing is buried, the center of the pile casing is coincided with the pile position center, and the position of the pile casing direction line is marked by red paint on the pile casing;
step (2), positioning a drilling machine;
the drilling machine keeps stable and does not incline or displace, the drill bit is aligned with the hole position and the motor is started to open the hole, when the drill bit is aligned with the cross line of the center of the pile position, all data can be locked without adjustment, the center of the drill bit and the center of the pile are accurately aligned after the drilling machine is in place, and the error is controlled within 10 mm;
the chassis of the rotary drilling rig is a telescopic automatic leveling device, and an instrument accurately displays electronic readings in an operation chamber;
step (3), drilling equipment;
the drilling is started, the drilling speed is stable and cannot be too fast, a drilling machine is not forced to be pressurized when a rigid object, a steel bar and an old concrete foundation are met, the slurry construction is observed in the drilling process to meet the requirement of slurry wall protection, and a slurry blender and bentonite are added when necessary;
step (4), cleaning holes:
by adopting a reverse circulation mud drilling machine system, the bottom of a hole is very clean after the hole is formed, and after the mud concentration is well regulated, the drill is slowly lifted by opening a valve, so that the situation that the hole wall is shrunk due to negative pressure formed by too fast lifting of the drill is avoided, and the hole forming quality cannot meet the requirements;
the reverse circulation mud drilling machine system comprises a ground 1, a drilling machine 2, a mud pump 3, a drill rod 4, a drill bit 5, a conveying pipe 6, a mud storage cavity 7, a mud filtering device 8 and a circulating pipe 9;
the top end of the ground 1 is provided with a drilling machine 2, a slurry pump 3 is arranged in the drilling machine 2, a driving end of the drilling machine 2 drives a drill rod 4 to move downwards, an input end of the slurry pump 3 is connected with the drill rod 4, the bottom end of the drill rod 4 is provided with a drill bit 5, an output end of the slurry pump 3 is connected with one end of a conveying pipe 6, the other end of the conveying pipe 6 extends into a sludge storage cavity 7 formed in the upper surface of the ground 1, the side surface of the sludge storage cavity 7 is provided with a sludge filtering device 8, the side surface of the sludge filtering device 8 is provided with one end of a circulating;
the mud produced by mechanical construction is utilized in the pore-forming process, and is circulated into the hole for wall protection after being filtered, so that the technical requirement of stability in the hole is met, the hole is cleaned after the hole is drilled to the designed hole depth, the drill bit is provided with a one-way opening and closing mud hole, negative pressure is avoided in the drill bit lifting process, the hole wall is ensured to be stable and not collapse, and then reinforcement cage installation and concrete pouring construction are carried out, so that a bored pile is formed;
step (5), manufacturing a reinforcement cage;
a reinforcement cage manufacturing machine is adopted, the reinforcement cage is ensured to be straight when being placed downwards, the steel reinforcement cage is strictly prevented from swinging and colliding with the hole wall, reinforcement protection blocks are added in the installation process, the set distance is 2 meters, and the thickness of the reinforcement cage protection layer is ensured;
step (6), immediately installing a concrete pouring guide pipe after the reinforcement cage is placed to the designed depth, so as to avoid the collision between the guide pipe and the reinforcement cage, wherein the guide pipe is made of a steel pipe with the diameter of 200 plus 300mm, the surface of the inner wall of the guide pipe is smooth and has enough strength and rigidity, and the joint of the pipe section is well sealed and convenient to assemble and disassemble;
pouring underwater concrete;
s1, when the concrete is poured, in order to discharge the water-proof bolt smoothly, the distance from the bottom of the guide pipe to the bottom of the hole is preferably 30-50cm, the guide pipe is buried more than 1.0m below the concrete surface once, the buried depth of the guide pipe is preferably 2-6m in the pouring process, the guide pipe is prevented from being lifted out of the concrete surface,
s2, continuously pouring concrete, wherein the height of the top of the poured pile is pre-increased by a certain height which is 50-100cm higher than the designed height, the pre-increased height can be chiseled after the foundation pit is excavated, and the pile body is prevented from being damaged during chiseling;
s3, the steel pile casing below the ground and the pile top can be lifted after the concrete is poured, and the influence on the quality of the pile body caused by the inclusion of filling sundries or silt into the concrete in the lifting process is prevented;
and S4, after the pouring is finished, finishing and flushing the site, and removing concrete deposits on equipment and tools.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. A shield type rapid hole forming construction method is characterized in that: comprises the following steps;
step (1), arranging a protective cylinder;
arranging a pile casing according to the pile site, wherein the inner diameter of the pile casing is 50-100mm larger than the diameter of the drill bit, the deviation between the center of the pile casing and the center of the pile site is not more than 50mm, the deviation of the inclination is not more than 0.5%, and the space between the pile casing and the pit wall is filled with clay;
step (2), positioning a drilling machine;
the drilling machine keeps stable and does not incline or displace, the drill bit is aligned with the hole position and the motor is started to open the hole, when the drill bit is aligned with the cross line of the center of the pile position, all data can be locked without adjustment, the center of the drill bit and the center of the pile are accurately aligned after the drilling machine is in place, and the error is controlled within 10 mm;
step (3), equipment drilling:
the drilling is started, the drilling speed is stable and cannot be too fast, a drilling machine is not forced to be pressurized when a rigid object, a steel bar and an old concrete foundation are met, the slurry construction is observed in the drilling process to meet the requirement of slurry wall protection, and a slurry blender and bentonite are added when necessary;
step (4), cleaning holes:
a reverse circulation slurry drilling machine system is adopted, the hole bottom is very clean after the hole is formed, and after the slurry concentration is well mixed, the drill is slowly lifted through a valve;
step (5), manufacturing a reinforcement cage;
a reinforcement cage manufacturing machine is adopted, the reinforcement cage is ensured to be straight when being placed downwards, the steel reinforcement cage is strictly prevented from swinging and colliding with the hole wall, reinforcement protection blocks are added in the installation process, the set distance is 2 meters, and the thickness of the reinforcement cage protection layer is ensured;
step (6), immediately installing a concrete pouring guide pipe after the reinforcement cage is placed to the designed depth, and avoiding the collision between the guide pipe and the reinforcement cage, wherein the guide pipe is made of a steel pipe with the diameter of 200 and 300 mm;
pouring underwater concrete;
s1, when the concrete is poured, in order to discharge the water-proof bolt smoothly, the distance from the bottom of the guide pipe to the bottom of the hole is preferably 30-50cm, the guide pipe is buried more than 1.0m below the concrete surface once, the buried depth of the guide pipe is preferably 2-6m in the pouring process, the guide pipe is prevented from being lifted out of the concrete surface,
s2, continuously pouring concrete, wherein the height of the top of the poured pile is pre-increased by a certain height which is 50-100cm higher than the designed height, the pre-increased height can be chiseled after the foundation pit is excavated, and the pile body is prevented from being damaged during chiseling;
s3, the steel pile casing below the ground and the pile top can be lifted after the concrete is poured, and the influence on the quality of the pile body caused by the inclusion of filling sundries or silt into the concrete in the lifting process is prevented;
and S4, after the pouring is finished, finishing and flushing the site, and removing concrete deposits on equipment and tools.
2. The shield type rapid hole forming construction method according to claim 1, characterized in that: in the step (1), the embedding of the pile casing adopts a rotary drilling rig static pressure method to sink in sections, and the pile casing sinks to the designed depth in cooperation with a vibration hammer, and the concrete operation is as follows: and (3) correctly positioning the drilling machine to enable the perpendicularity of the machine body, the perpendicularity of the drill rod and the central line of the pile casing to be integrated, then bringing a cylindrical drill bit at the top of the drill rod, hoisting the pile casing by using a crane and correctly positioning, vertically pressing the pile casing into the soil body by using a rotary drilling rod, leading the pile position center back through four control pile casings after the pile casing is buried, enabling the center of the pile casing to coincide with the pile position center, and marking the position of the pile casing direction line by using red paint on the pile casing.
3. The shield type rapid hole forming construction method according to claim 1, characterized in that: in the step (2), the chassis of the rotary drilling rig is a telescopic automatic leveling device, and an instrument is arranged in an operation room to accurately display electronic readings.
4. The shield type rapid hole forming construction method according to claim 1, characterized in that: in the step (4), negative pressure is formed when the hands-free drill is avoided from being too fast, so that the hole wall is shrunk, and the hole forming quality cannot meet the requirement.
5. The shield type rapid hole forming construction method according to claim 1, characterized in that: in the step (6), the surface of the inner wall of the conduit is smooth and has enough strength and rigidity, and the joint of the pipe section is well sealed and convenient to assemble and disassemble.
6. The shield type rapid hole forming construction method according to claim 1, characterized in that: the reverse circulation mud drilling machine system comprises a ground (1), a drilling machine (2), a mud pump (3), a drill rod (4), a drill bit (5), a conveying pipe (6), a mud storage cavity (7), a mud filtering device (8) and a circulating pipe (9);
the top on ground (1) is provided with rig (2), be provided with slush pump (3) in rig (2), the drive end drive drilling rod (4) of rig (2) move down, the input and the drilling rod (4) of slush pump (3) are connected, the bottom of drilling rod (4) is equipped with drill bit (5), the output of slush pump (3) is connected with the one end of conveyer pipe (6), the other end of conveyer pipe (6) extends into storage mud chamber (7) that ground (1) upper surface was seted up, the side of storing up mud chamber (7) is equipped with mud filter equipment (8), the side of mud filter equipment (8) is equipped with the one end of circulating pipe (9), the other end of circulating pipe (9) is located the drill bit (5) and becomes downtheholely.
CN202011151722.9A 2020-10-23 2020-10-23 Shield type rapid hole forming construction method Pending CN112360344A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011151722.9A CN112360344A (en) 2020-10-23 2020-10-23 Shield type rapid hole forming construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011151722.9A CN112360344A (en) 2020-10-23 2020-10-23 Shield type rapid hole forming construction method

Publications (1)

Publication Number Publication Date
CN112360344A true CN112360344A (en) 2021-02-12

Family

ID=74512075

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011151722.9A Pending CN112360344A (en) 2020-10-23 2020-10-23 Shield type rapid hole forming construction method

Country Status (1)

Country Link
CN (1) CN112360344A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080128172A1 (en) * 2006-10-26 2008-06-05 Tt Technologies, Inc. Drill stem connection and method
CN203441414U (en) * 2013-09-13 2014-02-19 中国海洋石油总公司 Wide-area overshot
CN104120716A (en) * 2013-04-28 2014-10-29 杨哲 Slurry wall protection construction method for bored pile
CN110965937A (en) * 2019-12-31 2020-04-07 福建建中建设科技有限责任公司 Double-power whole-course pump suction reverse circulation punching equipment and construction process

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080128172A1 (en) * 2006-10-26 2008-06-05 Tt Technologies, Inc. Drill stem connection and method
CN104120716A (en) * 2013-04-28 2014-10-29 杨哲 Slurry wall protection construction method for bored pile
CN203441414U (en) * 2013-09-13 2014-02-19 中国海洋石油总公司 Wide-area overshot
CN110965937A (en) * 2019-12-31 2020-04-07 福建建中建设科技有限责任公司 Double-power whole-course pump suction reverse circulation punching equipment and construction process

Similar Documents

Publication Publication Date Title
CN110566114B (en) Hard rock drilling pile-forming construction method of rotary excavating cluster type down-the-hole hammer
CN107407131B (en) Shaft enlargement arrangement for a drilling system
CN109853571B (en) Device and method for removing slag at bottom of local gas lift reverse circulation hole before concrete pouring of cast-in-situ bored pile
MX2007014765A (en) Apparatus and method for driving casing or conductor pipe.
CN111236216A (en) Construction method of bridge drilled pile
KR100880439B1 (en) Apparatus and method for removing slime in a cast-in place pile construstion
CN111594041A (en) Rapid hole forming construction method for large-diameter deep hole pile foundation under karst geology
CN107587502B (en) Construction method for rotary drilling hole-forming pressure-grouting cement soil occlusion curtain pile
CN111456055A (en) Foundation pit dewatering construction method
CN112682044B (en) Construction method of small-caliber dewatering well between narrow cracks
CN104141300A (en) Foundation pile hole drilling construction process
CN111502538A (en) Gas lift pore-forming construction method for building construction drilling
CN112360344A (en) Shield type rapid hole forming construction method
KR20090115702A (en) Ground excavating method of concrete file construction
CN115787627A (en) Construction method for manually driving cast-in-place pile
CN110965549B (en) Cast-in-situ bored pile construction method
CN211735404U (en) Anti-over-irrigation system for long spiral bored pile
CN114250801A (en) Pipe well and light well point combined dewatering construction method
CN112983265A (en) Drilling construction process
CN113089649A (en) Construction process of long spiral cast-in-place pile
RU133557U1 (en) DRILLING RIG FOR WATER WELL CONSTRUCTION IN RELIEF WATERFLOW HORIZONS WITH HEADS
CN114658017B (en) Precipitation construction method for shield zone
CN117071554A (en) Construction process of bored pile
CN1082133A (en) Cross castinplace pile and piling method thereof
CN114411787B (en) Well point dewatering method for steel cofferdam in water

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210212