CN112359728A - 一种预应力管道压浆加热的方法 - Google Patents
一种预应力管道压浆加热的方法 Download PDFInfo
- Publication number
- CN112359728A CN112359728A CN202011408431.3A CN202011408431A CN112359728A CN 112359728 A CN112359728 A CN 112359728A CN 202011408431 A CN202011408431 A CN 202011408431A CN 112359728 A CN112359728 A CN 112359728A
- Authority
- CN
- China
- Prior art keywords
- pipeline
- prestressed
- metal corrugated
- electric tracing
- tracing band
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/12—Mounting of reinforcing inserts; Prestressing
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
- E01D2101/28—Concrete reinforced prestressed
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Reinforcement Elements For Buildings (AREA)
Abstract
本发明公开了一种预应力管道压浆加热的方法,涉及波纹管道压浆施工技术领域。该预应力管道压浆加热的方法,其特征在于:包括如下步骤:S1、在预应力金属波纹管道安装时,将电伴热带螺旋状缠绕于预应力金属波纹管道表面,用胶带将电伴热带固定在金属管道表面上,电伴热带露出金属管道外50cm,S2、在预应力金属波纹管道安装时,梁预应力金属波纹管道每隔5米设置一个测温点一根测温线。该预应力管道压浆加热的方法,通过用连接电源的电缆线与缠绕于预应力金属波纹管道表面的电伴热带接通电,通过电加热电伴热带,从而加热金属管道,到达施工要求的环境温度,加快了冬季施工的进度,大大降低了施工成本。
Description
技术领域
本发明涉及波纹管道压浆施工技术领域,具体为一种预应力管道压浆加热的方法。
背景技术
在冬季现浇连续梁预应力金属波纹管道压浆施工时需要达到一定的温度才能施工。
传统的施工方法为在连续梁外侧搭设保温棚,采用加热设施对保温棚进行加热,从而达到施工要求的环境温度,此施工方法,施工时间长、施工成本相当高,且施工不安全,降低工作效率的同时给使用者的使用带来不便。
发明内容
(一)解决的技术问题
针对现有技术的不足,本发明提供了一种预应力管道压浆加热的方法,解决了传统的施工方法为在连续梁外侧搭设保温棚,采用加热设施对保温棚进行加热,从而达到施工要求的环境温度,此施工方法,施工时间长、施工成本相当高,且施工不安全的问题。
(二)技术方案
为实现以上目的,本发明通过以下技术方案予以实现:一种预应力管道压浆加热的方法,包括如下步骤:
S1、在预应力金属波纹管道安装时,将电伴热带螺旋状缠绕于预应力金属波纹管道表面,用胶带将电伴热带固定在金属管道表面上,电伴热带露出金属管道外50cm;
S2、在预应力金属波纹管道安装时,梁预应力金属波纹管道每隔5米设置一个测温点一根测温线,测温线一端测温探头用胶带固定于预应力金属波纹管道表面,另一端测温探头露出梁顶表面,测温探头用胶带缠绕保护好;
S3、用连接电源的3平方毫米电缆线与电伴热带接通电,通过电加热电伴热带,从而加热预应力金属波纹管道,用测温计对测温探头进行测温,待其温度达到5℃以上,方可进行预应力金属波纹管道压浆;
S4、压浆完成后继续对预应力金属波纹管道继续进行加热保温,保持温度5℃以上养护5天,养护完成后将电伴热带与电缆线断开,切除露出梁体的电伴热带。
(三)有益效果
本发明提供了一种预应力管道压浆加热的方法。具备以下有益效果:该预应力管道压浆加热的方法,通过在预应力金属波纹管道表面设置电伴热带,通过电加热电伴热带,从而加热金属管道,达到冬季施工要求的环境温度。解决了传统的搭保温棚施工方法存在的施工时间长、施工成本相当高、施工不安全的问题。加快了冬季施工的进度,大大降低了施工成本。
附图说明
图1为本发明结构示意图。
图中:1、预应力金属波纹管道;2、电伴热带;3、测温线;4、电缆线;5、现浇连续梁体。
具体实施方式
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。
请参阅图1,本发明提供一种技术方案:一种预应力管道压浆加热的方法,包括如下步骤:
S1、在预应力金属波纹管道安装时,将电伴热带螺旋状缠绕于预应力金属波纹管道表面,用胶带将电伴热带固定在金属管道表面上,电伴热带露出金属管道外50cm;
S2、在预应力金属波纹管道安装时,梁预应力金属波纹管道每隔5米设置一个测温点一根测温线,测温线一端测温探头用胶带固定于预应力金属波纹管道表面,另一端测温探头露出梁顶表面,测温探头用胶带缠绕保护好;
S3、用连接电源的3平方毫米电缆线与电伴热带接通电,通过电加热电伴热带,从而加热预应力金属波纹管道,用测温计对测温探头进行测温,待其温度达到5℃以上,方可进行预应力金属波纹管道压浆;
S4、压浆完成后继续对预应力金属波纹管道继续进行加热保温,保持温度5℃以上养护5天,养护完成后将电伴热带与电缆线断开,切除露出梁体的电伴热带。
综上所述,该预应力管道压浆加热的方法,通过在预应力金属波纹管道表面设置电伴热带,通过电加热电伴热带,从而加热金属管道,达到冬季施工要求的环境温度。解决了传统的搭保温棚施工方法存在的施工时间长、施工成本相当高、施工不安全的问题。加快了冬季施工的进度,大大降低了施工成本。
需要说明的是,在本文中,诸如第一和第二等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。
尽管已经示出和描述了本发明的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本发明的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本发明的范围由所附权利要求及其等同物限定。
Claims (1)
1.一种预应力管道压浆加热的方法,其特征在于:包括如下步骤:
S1、在预应力金属波纹管道安装时,将电伴热带螺旋状缠绕于预应力金属波纹管道表面,用胶带将电伴热带固定在金属管道表面上,电伴热带露出金属管道外50cm;
S2、在预应力金属波纹管道安装时,梁预应力金属波纹管道每隔5米设置一个测温点一根测温线,测温线一端测温探头用胶带固定于预应力金属波纹管道表面,另一端测温探头露出梁顶表面,测温探头用胶带缠绕保护好;
S3、用连接电源的3平方毫米电缆线与电伴热带接通电,通过电加热电伴热带,从而加热预应力金属波纹管道,用测温计对测温探头进行测温,待其温度达到5℃以上,方可进行预应力金属波纹管道压浆;
S4、压浆完成后继续对预应力金属波纹管道继续进行加热保温,保持温度5℃以上养护5天,养护完成后将电伴热带与电缆线断开,切除露出梁体的电伴热带。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011408431.3A CN112359728A (zh) | 2020-12-04 | 2020-12-04 | 一种预应力管道压浆加热的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011408431.3A CN112359728A (zh) | 2020-12-04 | 2020-12-04 | 一种预应力管道压浆加热的方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112359728A true CN112359728A (zh) | 2021-02-12 |
Family
ID=74535985
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202011408431.3A Pending CN112359728A (zh) | 2020-12-04 | 2020-12-04 | 一种预应力管道压浆加热的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112359728A (zh) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011032843A (ja) * | 2009-08-06 | 2011-02-17 | Zenitaka Corp | Pcグラウト材の寒中養生施工システム及び施工方法 |
CN202531190U (zh) * | 2012-02-10 | 2012-11-14 | 广州市盾建地下工程有限公司 | 即热式注浆装置 |
CN205035737U (zh) * | 2015-06-19 | 2016-02-17 | 中铁六局集团天津铁路建设有限公司 | 梁体注浆管加热装置 |
CN105625179A (zh) * | 2014-10-29 | 2016-06-01 | 中铁十四局集团有限公司 | 电热丝加热预应力管道的方法 |
CN210864435U (zh) * | 2019-10-16 | 2020-06-26 | 上海建工二建集团有限公司 | 基坑抢险注浆控温装置 |
-
2020
- 2020-12-04 CN CN202011408431.3A patent/CN112359728A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011032843A (ja) * | 2009-08-06 | 2011-02-17 | Zenitaka Corp | Pcグラウト材の寒中養生施工システム及び施工方法 |
CN202531190U (zh) * | 2012-02-10 | 2012-11-14 | 广州市盾建地下工程有限公司 | 即热式注浆装置 |
CN105625179A (zh) * | 2014-10-29 | 2016-06-01 | 中铁十四局集团有限公司 | 电热丝加热预应力管道的方法 |
CN205035737U (zh) * | 2015-06-19 | 2016-02-17 | 中铁六局集团天津铁路建设有限公司 | 梁体注浆管加热装置 |
CN210864435U (zh) * | 2019-10-16 | 2020-06-26 | 上海建工二建集团有限公司 | 基坑抢险注浆控温装置 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104330659A (zh) | 一种基于电缆传热模型的准动态增容方法 | |
CN102522161B (zh) | 具有温度监测功能的绝缘子 | |
CN105119227A (zh) | 一种opgw直流融冰系统 | |
CN112359728A (zh) | 一种预应力管道压浆加热的方法 | |
CN102518310B (zh) | 玻膜光电幕墙的施工方法 | |
CN104499716A (zh) | 一种砼冬期施工的保温装置 | |
Foss et al. | Dynamic thermal line ratings part ii conductor temperature sensor and laboratory field test evaluation | |
CN106851867B (zh) | 一种电热管道 | |
RU2415517C2 (ru) | Установка индукционного нагрева трубопроводов | |
CN105911663B (zh) | 一种变电站opgw终端预留缆及其制造方法 | |
CN206224026U (zh) | 一种opgw光缆盘 | |
CN204966185U (zh) | 用于架空导线的绝缘护套组件 | |
CN104837228A (zh) | 超长碳纤维发热电缆 | |
CN220962872U (zh) | 一种抗冻型电缆 | |
US1983862A (en) | Soil warming device and method of manufacturing same | |
CN104766665A (zh) | 一种用于架空导线的修护管 | |
SU905575A1 (ru) | Способ защиты труб армированным покрытием | |
Arkell et al. | Design and construction of the 400 kV cable system for the Severn Tunnel | |
CN204102623U (zh) | 一种光电复合缆 | |
CN103779018B (zh) | 一种智能电网用超高压电复合电缆的连接方法 | |
CN219395073U (zh) | 一种铁氟龙芯线硅胶外被双导发热电缆 | |
RU193157U1 (ru) | Краевая плита железнодорожной платформы | |
RU2802460C1 (ru) | Обогреватель электрический и способ его производства | |
CN215254554U (zh) | 一种钢模板装置 | |
CN204834192U (zh) | 绝缘护套机构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20210212 |