CN112343603A - Comprehensive construction method suitable for tunneling of shield tunnel with ultra-large section - Google Patents

Comprehensive construction method suitable for tunneling of shield tunnel with ultra-large section Download PDF

Info

Publication number
CN112343603A
CN112343603A CN202011064990.7A CN202011064990A CN112343603A CN 112343603 A CN112343603 A CN 112343603A CN 202011064990 A CN202011064990 A CN 202011064990A CN 112343603 A CN112343603 A CN 112343603A
Authority
CN
China
Prior art keywords
section
shield
tunneling
backfill
replacement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011064990.7A
Other languages
Chinese (zh)
Inventor
史世波
刘继国
杨林松
舒恒
陈坤
曾琛超
郭锐
武建力
刘夏临
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Highway Survey and Design Institute Co Ltd
Original Assignee
CCCC Second Highway Survey and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Highway Survey and Design Institute Co Ltd filed Critical CCCC Second Highway Survey and Design Institute Co Ltd
Priority to CN202011064990.7A priority Critical patent/CN112343603A/en
Publication of CN112343603A publication Critical patent/CN112343603A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0607Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a comprehensive construction method suitable for tunneling a shield tunnel with an oversized section, which comprises the following steps: adopting a mining method to construct and form an outer contour section tunneled by the shield tunneling machine; gradually removing the temporary support applied in the mine construction in the section by taking the fixed length distance as a node in the section, and synchronously applying backfill material for replacement and backfill when removing the temporary support until the space of the whole section is completely replaced and backfilled; and (3) tunneling and assembling a segment structure in the backfill material after replacement and backfilling by adopting a shield tunneling machine to form a permanent functional space. According to the construction method, the backfill material is used for replacement and backfill, then the oversized-section shield tunnel is tunneled, the construction difficulty and risk that the shield machine directly passes through a local high-strength hard rock section are reduced, the problem that backfill construction is difficult to carry out in a tunnel excavated by a mine method is solved, in addition, the backfill material can provide counter force for segment assembly, a waterproof sealing gasket is compressed, the leakage risk is reduced, and meanwhile, the risk of segment dislocation in the air pushing process of the shield machine is reduced.

Description

Comprehensive construction method suitable for tunneling of shield tunnel with ultra-large section
Technical Field
The invention relates to the technical field of tunnel engineering, in particular to a comprehensive construction method suitable for tunneling a shield tunnel with an oversized section.
Background
For weak stratum, it is suitable for mechanical construction, i.e. adopting shield scheme, which is the commonly used construction method at present. And for the condition that the whole tunnel line is positioned in a rock stratum with better geological conditions, the traditional mining method is adopted for construction, namely a method for performing preliminary bracing and deslagging after blasting.
With the development of infrastructure construction, the geological problems faced by tunnel construction are more and more, the problems are more and more new, the geological difference of the same tunnel is more and more, and the situation that part of road sections are soft stratums and part of road sections are hard rocks is often caused.
In the past engineering experience, when the small-diameter shield construction is met, the problem of directly tunneling hard rock by adopting the shield is relatively small. However, for a tunnel with an oversized section, namely the diameter of the shield exceeds 15 meters, the section of the shield is 6 times of the excavation area of a small shield of a conventional subway, the problem that the shield is difficult to excavate, the cutter is seriously abraded, the construction efficiency is low and the like when the shield directly excavates in hard rock is solved, even the shield cannot adapt to a hard rock section with extremely high strength, and further equipment of the shield cannot be paralyzed and cannot work.
In the small-section shield construction, when the shield machine tunnels in the hard rock stratum of a local road section, in order to reduce the construction difficulty and risk, a scheme that the outer contour section of the shield machine is excavated in a mine and then the shield machine is pushed to pass through in the air is adopted sometimes.
For the shield tunnel with the ultra-large section, if a scheme of small shield mine and air pushing is adopted, the risks of large excavation span of a mining method, difficulty in dismantling a temporary support in the mining method, serious slab staggering of a shield air pushing section pipe segment, large later-stage leakage risk and the like can be met.
Disclosure of Invention
The invention aims to provide a comprehensive construction method suitable for tunneling an oversized section shield tunnel aiming at the existing technical current situation, the construction method utilizes backfill materials to replace and backfill the oversized section shield tunnel, reduces the construction difficulty and risk of the shield tunneling machine directly passing through a local high-strength hard rock section, solves the problem that backfill construction is difficult to carry out in a tunnel excavated by a mine method, and in addition, the backfill materials can provide counter force for segment assembly, compress a waterproof sealing gasket, reduce leakage risk and reduce the risk of segment dislocation in the idle pushing process of the shield tunneling machine.
In order to achieve the purpose, the invention adopts the following technical scheme:
a comprehensive construction method suitable for tunneling of a shield tunnel with an oversized section comprises the following steps:
s1, forming an outer contour section tunneled by the shield tunneling machine by adopting a mining method;
s2, gradually removing the temporary support applied by the mine construction method in the section by taking a fixed length distance as a node in the outer contour section tunneled by the shield tunneling machine, synchronously applying backfill material for replacement and backfilling when removing the temporary support, and performing a temporary support removing process and a replacement and backfilling process in the next node after the backfill material applied in the previous node reaches the strength until the space of the whole section is completely replaced and backfilled;
and S3, tunneling and assembling a segment structure in the backfill material after replacement and backfilling by using a shield tunneling machine to form a permanent functional space and apply a tunnel internal structure in the permanent functional space.
Further, in step S2, the length of each node is 3-5 m.
Further, in step S2, the temporary brace dismantling process in each node is performed in a segmented manner from bottom to top, and the replacement backfill process is performed step by step along with each segment of the temporary brace dismantling process.
Further, in step S2, the backfill material is a fluid cement mortar.
Further, in step S3, the excavation diameter of the shield machine is smaller than the diameter of the cross section formed by the mining method.
The invention has the beneficial effects that:
1. according to the construction method, the backfill material is used for replacement and backfill, and then the oversized-section shield tunnel is tunneled, so that the construction difficulty and risk that the shield machine directly passes through a local high-strength hard rock section are reduced, the problem that backfill construction is difficult to carry out in a tunnel excavated by a mine method is solved, in addition, the backfill material can provide counter force for segment assembly, a waterproof sealing gasket is compressed, the leakage risk is reduced, and meanwhile, the risk of segment dislocation in the air pushing process of the shield machine is reduced; 2. the invention is suitable for tunneling of the tunnel with the ultra-large section, and the application range of the shield machine construction scheme is expanded.
Drawings
FIG. 1 is a schematic structural diagram of a cross-section formed in step S1 according to the present invention;
fig. 2 is a schematic structural diagram of the present invention after segment replacement backfill in step S2.
Description of the labeling: 1. the method comprises the steps of (1) tunneling outer contour section of the shield tunneling machine, (2) temporary support, (3) system anchor rod, and (4) advance support.
Detailed Description
The invention will be further explained with reference to the drawings.
A comprehensive construction method suitable for tunneling of a shield tunnel with an oversized section comprises the following steps:
and S1, forming the outer contour section 1 tunneled by the shield tunneling machine by adopting the mining method construction, wherein the advance support 4, the system anchor rod 3, the temporary support 2 and the sprayed concrete are required to be applied during the mining method construction as shown in figure 1. In order to solve the safety problem between different excavation procedures in the ultra-large section mine method construction, an excavation method adopting a double-side-wall pilot tunnel and a temporary support 2, namely a 5-step and 11-step excavation method, is selected.
And S2, before the shield tunneling machine tunnels, all temporary supports 2 in the section need to be removed, and the secondary lining is not implemented at the moment. In order to solve the problem that the primary support is difficult to ensure the structural stability requirement of a tunnel excavated by a mining method, namely, the structural safety is ensured, the temporary support 2 applied in the mining method construction in the section is gradually removed by taking a fixed length distance as a node in the outer contour section 1 excavated by the shield tunneling machine, backfill is synchronously applied to replace and backfill when the temporary support 2 is removed, after the backfill applied in the previous node reaches the strength, the temporary support 2 removing process and the replacement and backfill process in the next node are carried out until the space of the whole section is completely replaced and backfilled, and the section after replacement and backfill is shown in figure 2.
The length of each node is 3-5m, the dismantling process of the temporary support 2 in each node is performed in a segmented mode from bottom to top, and the replacement backfilling process is performed step by step along with the dismantling process of each segment of the temporary support 2. The backfill is flowable cement mortar or other flowable materials.
S3, tunneling and assembling a segment structure in the backfill material after replacement and backfilling by using a shield tunneling machine to form a permanent functional space and apply a tunnel internal structure inside the permanent functional space, wherein the tunnel internal structure comprises but is not limited to an upper lane, a lower lane, a discharge flue, a stair arranged at intervals, a smoke pipe, a pipeline space, a waste water pump room and a cable well. Preferably, the excavation diameter of the shield machine is smaller than the diameter of a cross section formed by the mine method construction, and the difference between the diameters is generally controlled to be about 0.5 m.
Compared with the scheme that the subway small shield is directly pushed in the air after being excavated by adopting a mining method, the method has the following advantages and innovations:
1. the backfill material is used for replacement and backfill, and then the ultra-large section shield tunnel is tunneled, so that the construction difficulty and risk of the shield machine directly passing through a local high-strength hard rock section are reduced;
2. the fluidity cement mortar or other fluidity materials are backfilled, so that the safety of the oversized section mine method tunnel is improved;
3. the flowable cement mortar is used as backfill, so that a backfill scheme can be smoothly implemented in a narrow space with 2-density temporary supports;
4. the section is larger than that of the subway;
5. the backfill can provide counter force for segment assembly, compress the waterproof sealing gasket, reduce leakage risk and reduce the risk of segment dislocation in the air thrust process of the shield tunneling machine;
6. the problem of the little shield of subway empty push backfill pea gravel fill not full, even unable construction is solved.
The invention enlarges the application range of the shield construction scheme with higher mechanization degree.
It should be understood that the above-mentioned embodiments are merely preferred embodiments of the present invention, and not intended to limit the scope of the invention, therefore, all equivalent changes in the principle of the present invention should be included in the protection scope of the present invention.

Claims (5)

1. A comprehensive construction method suitable for tunneling of a shield tunnel with an oversized section is characterized by comprising the following steps: the method comprises the following steps:
s1, forming an outer contour section tunneled by the shield tunneling machine by adopting a mining method;
s2, gradually removing the temporary support applied by the mine construction method in the section by taking a fixed length distance as a node in the outer contour section tunneled by the shield tunneling machine, synchronously applying backfill material for replacement and backfilling when removing the temporary support, and performing a temporary support removing process and a replacement and backfilling process in the next node after the backfill material applied in the previous node reaches the strength until the space of the whole section is completely replaced and backfilled;
and S3, tunneling and assembling a segment structure in the backfill material after replacement and backfilling by using a shield tunneling machine to form a permanent functional space and apply a tunnel internal structure in the permanent functional space.
2. The comprehensive construction method suitable for extra-large section shield tunneling according to claim 1, characterized in that: in step S2, each node has a length of 3-5 m.
3. The comprehensive construction method suitable for extra-large section tunneling according to claim 2, characterized in that: in step S2, the temporary brace dismantling process in each node is performed in segments from bottom to top, and the replacement backfilling process is performed step by step along with each segment of the temporary brace dismantling process.
4. A comprehensive construction method suitable for ultra-large section shield tunneling according to any one of claims 1 to 3, characterized in that: in step S2, the backfill material is a fluid cement mortar.
5. The comprehensive construction method suitable for extra-large section shield tunneling according to claim 1, characterized in that: in step S3, the excavation diameter of the shield machine is smaller than the diameter of the cross section formed by the mine method construction.
CN202011064990.7A 2020-09-30 2020-09-30 Comprehensive construction method suitable for tunneling of shield tunnel with ultra-large section Pending CN112343603A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011064990.7A CN112343603A (en) 2020-09-30 2020-09-30 Comprehensive construction method suitable for tunneling of shield tunnel with ultra-large section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011064990.7A CN112343603A (en) 2020-09-30 2020-09-30 Comprehensive construction method suitable for tunneling of shield tunnel with ultra-large section

Publications (1)

Publication Number Publication Date
CN112343603A true CN112343603A (en) 2021-02-09

Family

ID=74360537

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011064990.7A Pending CN112343603A (en) 2020-09-30 2020-09-30 Comprehensive construction method suitable for tunneling of shield tunnel with ultra-large section

Country Status (1)

Country Link
CN (1) CN112343603A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005016009A (en) * 2003-06-23 2005-01-20 Ohbayashi Corp Excavated soil recycling method in shield tunneling method
CN105201518A (en) * 2015-10-13 2015-12-30 铁道第三勘察设计院集团有限公司 Method for receiving and disassembly of large-diameter slurry balance shield in hole
CN108775244A (en) * 2018-05-28 2018-11-09 中铁十六局集团有限公司 A kind of Mining Method receives shield machine and shield sky pushes away construction method
CN110159309A (en) * 2019-05-27 2019-08-23 中国水利水电第八工程局有限公司 A kind of construction method using foam concrete backfill Tunneling by mining method
CN110410144A (en) * 2019-07-18 2019-11-05 中交第二公路勘察设计研究院有限公司 A kind of waterproof/drainage structure of shield tunnel
CN110878696A (en) * 2019-12-11 2020-03-13 中铁二十局集团第四工程有限公司 Method for reinforcing surrounding rock of tunnel section at junction of upper soft and lower hard stratum shield method and mine method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005016009A (en) * 2003-06-23 2005-01-20 Ohbayashi Corp Excavated soil recycling method in shield tunneling method
CN105201518A (en) * 2015-10-13 2015-12-30 铁道第三勘察设计院集团有限公司 Method for receiving and disassembly of large-diameter slurry balance shield in hole
CN108775244A (en) * 2018-05-28 2018-11-09 中铁十六局集团有限公司 A kind of Mining Method receives shield machine and shield sky pushes away construction method
CN110159309A (en) * 2019-05-27 2019-08-23 中国水利水电第八工程局有限公司 A kind of construction method using foam concrete backfill Tunneling by mining method
CN110410144A (en) * 2019-07-18 2019-11-05 中交第二公路勘察设计研究院有限公司 A kind of waterproof/drainage structure of shield tunnel
CN110878696A (en) * 2019-12-11 2020-03-13 中铁二十局集团第四工程有限公司 Method for reinforcing surrounding rock of tunnel section at junction of upper soft and lower hard stratum shield method and mine method

Similar Documents

Publication Publication Date Title
CN110985025B (en) Method for reconstructing shield tunnel to carry out mine construction
CN109356596B (en) Method for launching and receiving shield tunneling machine by utilizing recyclable underground continuous wall and steel sleeve
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN109209392B (en) Full-ring excavation method suitable for IV-V-grade surrounding rock of large-section tunnel
CN109372518B (en) Reverse excavation construction method for tunnel abrupt-change section
CN109736827B (en) Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing
WO2022083096A1 (en) Tunnel excavation method for upper-soft and lower-hard stratum
Hou et al. Excavation failure due to pipeline damage during shallow tunnelling in soft ground
CN103485790A (en) Shallow tunneling method for pipe-proof-supporting structure combined system
CN105332710A (en) Construction method suitable for up-down overlapped tunnel with small clear space and long distance under weak geological condition
CN110259490B (en) Subway underground excavation station construction method
CN112160755B (en) Subway line construction method for expanding excavation station after shield tunnel construction in advance
CN113803074A (en) Construction method of tunnel structure for artificial and mechanical combined obstacle removal of water-rich sand layer
CN113374931B (en) Non-excavation capacity-expansion method for old urban pipeline
CN108915702B (en) Shield receiving method in circular small-section tunnel
CN113062750A (en) Construction method of tunnel structure with underground structure uplift pile penetrating downwards
CN113513322A (en) Soil pressure balance jacking construction method for water-rich shallow-buried large-section rectangular jacking pipe
CN112343603A (en) Comprehensive construction method suitable for tunneling of shield tunnel with ultra-large section
CN114704272B (en) Construction method of underground tunnel with first building and then digging
CN110985002A (en) Tunnel construction method for horizontal semi-soft semi-hard section stratum
CN113187498B (en) TBM tunnel collapsed cavity backfilling and advanced pipe shed construction method
CN106640098B (en) Subway tunnel shield construction method
CN214273663U (en) Weak surrounding rock tunnel geological disaster punishment structure
CN214997645U (en) Be applicable to subway station goes out inlet pipe curtain construction pipe curtain structure
CN113931640A (en) Construction method for empty pushing and starting of shield in mine tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210209