CN112252315A - Construction method for protecting static pressure steel casing of manual bored pile with water-bearing sand interlayer - Google Patents

Construction method for protecting static pressure steel casing of manual bored pile with water-bearing sand interlayer Download PDF

Info

Publication number
CN112252315A
CN112252315A CN202011219626.3A CN202011219626A CN112252315A CN 112252315 A CN112252315 A CN 112252315A CN 202011219626 A CN202011219626 A CN 202011219626A CN 112252315 A CN112252315 A CN 112252315A
Authority
CN
China
Prior art keywords
steel
water
static pressure
section
protection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011219626.3A
Other languages
Chinese (zh)
Inventor
江真
蒲世维
胡建波
阳长江
张志飞
李洪玲
王淼
王莉
龚欣
严浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Construction Engineering Municipal Traffic Engineering Co ltd
Chongqing Construction Engineering Group Co Ltd
Original Assignee
Chongqing Construction Engineering Municipal Traffic Engineering Co ltd
Chongqing Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Construction Engineering Municipal Traffic Engineering Co ltd, Chongqing Construction Engineering Group Co Ltd filed Critical Chongqing Construction Engineering Municipal Traffic Engineering Co ltd
Priority to CN202011219626.3A priority Critical patent/CN112252315A/en
Publication of CN112252315A publication Critical patent/CN112252315A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/68Mould-pipes or other moulds for making bulkheads or elements thereof
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/20Placing by pressure or pulling power

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a static pressure steel pile casing protection construction method for a manual hole digging pile in a water-containing sand layer, which belongs to the technical field of underground engineering construction, wherein during hole digging, a locking opening is poured at an orifice, a concrete retaining wall is poured for protection after a soil layer is dug downwards for a certain distance, then the concrete retaining wall is dug downwards until a water-containing sand interlayer is formed, the steel pile casing is adopted for protection, a jack is adopted for carrying out downward static pressure on the steel pile casing, the soil layer in the steel pile casing is not constructed in the static pressure process, and the operation is repeated until the required depth is reached; compared with the prior art, the concrete retaining wall protection and the steel retaining cylinder protection are flexibly applied to the construction of the manual hole digging and pile pouring foundation of the water-bearing sand interlayer soil layer, the construction period is greatly shortened, the waste of materials is avoided, the engineering quantity is smaller, no vibration and low noise are generated in the construction process, and the concrete retaining wall protection and the steel retaining cylinder protection are environment-friendly.

Description

Construction method for protecting static pressure steel casing of manual bored pile with water-bearing sand interlayer
Technical Field
The invention relates to the technical field of underground engineering construction, in particular to a static pressure steel casing protection construction method for a manual hole digging pile in a water-containing sand layer.
Background
In recent years, the mechanical hole forming of the pile foundation promoted by the nation plays a good promoting role in the aspects of reducing the occurrence of safety production accidents, improving the construction operation environment, improving the working efficiency and the like, embodies people-oriented reasons and accords with the development direction of construction science and technology. But under certain specific conditions, such as: the conditions for prohibiting manual hole digging and filling of the pile are immature due to complex geology, inconvenient traffic, restriction of surrounding environment and the like. When the situation that manual hole digging and pile filling are forced to be adopted and geological conditions are poor occurs in the field, the project progress is influenced certainly.
The water-bearing sand interlayer is a common unfavorable geological structure of a water area adjacent to the southwest area, and measures usually adopted by construction units mainly include reduction of hydrodynamic pressure and reduction of disturbance to a soil body. The former adopts well point dewatering, mud jacking and the like, has large engineering quantity and long construction period, and is very uneconomical when the engineering quantity of the pile foundation is small. The latter adopts the excavation cycle footage shortening, the steel casing setting and the like, the work load is relatively small, the construction period is relatively short, and the construction unit can easily accept the construction period.
Shortening the excavation depth of each cycle and reducing the normal 1 m-cycle to 0.5 m-cycle will increase the working period. By adopting the steel casing, if the common soil layer on the upper part of the water-bearing sand interlayer is thick, certain waste can be caused.
In conclusion, the applicant provides a static pressure steel casing protection construction method for a manual hole digging pile with a water-bearing sand interlayer.
Disclosure of Invention
In view of the problems of complex process, long construction period and material waste in the prior art, the technical scheme of the invention provides a static pressure steel casing protection construction method for a manual hole digging pile with a water-bearing sand interlayer, which solves the problems.
In order to achieve the technical purpose, the technical scheme adopted by the invention is as follows:
a static pressure steel casing protection construction method for a manual hole digging pile with a water-bearing sand interlayer comprises the following steps:
001. determining the position of an opening by utilizing the burial depth of the water-bearing sand interlayer determined in geological survey, and pouring a locking notch 1 by using concrete at the position of the opening;
002. digging holes downwards in a common soil layer in the locking opening in the step 001, and when the digging depth is 5m, ventilating the holes at intervals by using an air blower for 5-10 minutes and continuously ventilating when the depth is more than 10 m;
003. pouring concrete retaining walls in the 002 holes, wherein the concrete retaining walls are poured in a sectional manner;
004. stopping the operation when the distance between the concrete protecting wall and the water-bearing sand interlayer is 0.5m, forming a section steel mounting hole on the concrete protecting wall in the step 003, and placing a steel protecting cylinder after the hole is formed;
005. after the steel protection cylinder is placed, sequentially placing the section steel at the top of the steel protection cylinder, the jack and the reaction frame section steel, installing the reaction frame section steel into the section steel installation hole, and taking the section steel at the top of the steel protection cylinder and the reaction frame section steel as supporting points of the jack;
006. starting a jack to carry out downward static pressure on the steel casing, checking whether a concrete retaining wall has a crack or not in the static pressure process, and continuing the static pressure if no crack exists;
007. when a second section of steel casing is placed, a plurality of positioning steel bars are uniformly welded on the inner side of the bottom of the second section of steel casing, half of the positioning steel bars are welded in the second section of steel casing, and the second section of steel casing is aligned with the first section of steel casing and then is firmly welded;
008. repeating the 004-007 step until the water-bearing sand interlayer is penetrated, and then hollowing out the soil body in the steel casing;
009. after the soil body is hollowed, the reinforcement cage can be lifted into the soil body for placement, and pouring is carried out after placement is finished.
Through adopting the concrete dado to protect when the manual hole that digs in general soil layer, adopt the steel to protect a section of thick bamboo protection when the manual hole that digs in water-bearing sand intermediate layer, this two kinds of methods of flexible application are dug the hole and are irritated the pile foundation operation, the waste of a steel dado has been avoided, and do not reduce the degree of depth of circulating excavation, construction cycle is shorter, the engineering volume is littleer, great improvement the manual efficiency of digging the hole and irritating the pile foundation, the cost is saved, and do not have vibration trompil equipment, no vibration, the noise is little, green.
Further limiting, the number of the section steel mounting holes is two, and the depths of the two corresponding section steel mounting holes are different; one of them is for deepening the hole in two shaped steel mounting holes, and the degree of depth of the shaped steel mounting hole that corresponds sets up to inconsistent more convenient shaped steel's installation and tearing open and get.
Further limiting, the thickness of the concrete retaining wall is 100cm-200 cm; the thickness of the concrete retaining wall is made to be the size, so that better protection can be achieved.
Further limiting, the number of each layer of positioning steel bars is four, the length of each positioning steel bar is 30cm, and the diameter of each positioning steel bar is 16 mm; the steel bar with the size is used as a positioning steel bar, four steel protection cylinders are uniformly arranged on the inner side of each steel protection cylinder to match and position the two steel protection cylinders, and the steel protection cylinders are very stable.
Compared with the prior art, the concrete retaining wall protection and the steel retaining cylinder protection are flexibly applied to the construction of the manual hole digging and pile pouring foundation of the water-bearing sand interlayer soil layer, the construction period is greatly shortened, the waste of materials is avoided, the engineering quantity is smaller, no vibration and low noise are generated in the construction process, and the concrete retaining wall protection and the steel retaining cylinder protection are environment-friendly.
Drawings
FIG. 1 is a simple schematic diagram of the construction structure of the present invention;
fig. 2 is an enlarged schematic view of a portion a in fig. 1.
The corresponding labels in the figures are: 1-locking notch, 2-concrete retaining wall, 3-steel retaining cylinder, 4-steel retaining cylinder top section steel, 5-jack, 6-reaction frame section steel, 7-positioning steel bar, 8-general soil layer and 9-water-bearing sand interlayer.
Detailed Description
In order that those skilled in the art can better understand the technical solution of the present invention, the following embodiments are further described with reference to the accompanying drawings and examples.
As shown in fig. 1 and 2, a static pressure steel casing protection construction method for a manual bored pile with a water-bearing sand interlayer comprises the following steps:
001. determining the position of an opening by utilizing the burial depth of the water-bearing sand interlayer determined in geological survey, and pouring a locking notch 1 by using concrete at the position of the opening; through geological survey reports, the position of the open hole can be determined, the strength of the open hole, namely the section of the retaining wall concrete, is enhanced, and the concrete can bear the load in back pressure without being damaged.
002. Digging holes downwards in a common soil layer 8 in the locking notch 1 in the step 001, and when the digging depth is 5m, ventilating the holes at intervals by using an air blower for 5-10 minutes and continuously ventilating when the depth is more than 10 m;
003. pouring the concrete retaining wall 2 in the 002 holes, wherein the concrete retaining wall 2 is poured in a sectional manner;
004. stopping the operation when the distance between the section of the concrete retaining wall and the water-bearing sand interlayer 9 is 0.5m, forming section steel mounting holes in the second section of the concrete retaining wall 2 from bottom to top in the step 003, and putting the steel retaining cylinder 3 into the concrete retaining wall by using a crane after the hole is formed;
005. after the steel casing 3 is placed, sequentially placing the steel casing top section steel 4, the jack 5 and the reaction frame section steel 6, installing the reaction frame section steel 6 into the section steel installation hole, and taking the steel casing top section steel 4 and the reaction frame section steel 6 as supporting points of the jack 5;
006. the jack 5 is started to carry out downward static pressure on the steel casing 3, the static pressure is to avoid vibration compaction of a sand interlayer caused by vibration pressing, so that the steel casing is prevented from sinking, whether a crack exists in the concrete retaining wall 2 is checked in the static pressure process, if no crack exists, the static pressure can be continuously carried out, the soil of the steel casing 3 is not excavated in the static pressure process, the verticality of the steel casing 3 is observed at any time in the static pressure process, if the slope occurs, the adjustment is carried out in time, and the static pressure can be carried out until the next section of the steel casing 3 can be in place;
007. when the second section of steel casing 3 is placed, a plurality of positioning steel bars 7 are uniformly welded on the inner side of the bottom of the second section of steel casing 3, half of the positioning steel bars 7 are welded in the second section of steel casing 3, and the second section of steel casing 3 is aligned with the first section of steel casing 3 and then is welded firmly; the positioning steel bars 7 are convenient for accurate alignment of the axes of the two sections of the protective cylinders.
008. Repeating the steps of 004 and 007 until the water-bearing sand interlayer 9 is penetrated, and then hollowing out the soil body in the steel casing 3;
009. after the soil body is hollowed, the reinforcement cage can be lifted and placed, and pouring is carried out after placement is finished;
the section steel mounting holes are correspondingly two, the depths of the two corresponding section steel mounting holes are different, one of the two section steel mounting holes is a deep hole, and the length of the section steel is greater than the diameter of the pile foundation, so that the two ends of the section steel can be successfully fed into the two holes, and the depth of the deep hole is greater than the length of the section steel; the thickness of the concrete retaining wall 2 is 100cm-200 cm; the number of each layer of positioning steel bars 7 is four, the length of each layer of positioning steel bars 7 is 30cm, and the diameter of each layer of positioning steel bars 7 is 16 mm;
the concrete retaining wall 2 is adopted for protection when a common soil layer 8 is used for manual hole digging, and the steel retaining cylinder 3 is adopted for protection when a water-bearing sand interlayer 9 is used for manual hole digging, so that the hole digging and pile foundation grouting operation is flexibly carried out by using the two methods, the waste of the steel retaining cylinder 3 is avoided, the depth of circular excavation is not reduced, the construction period is shorter, the engineering quantity is smaller, the efficiency of the manual hole digging and pile foundation grouting is greatly improved, the cost is saved, no vibration and hole opening equipment is provided, the noise is low, and the environment is protected; the depth of the corresponding section steel mounting holes is set to be inconsistent, so that the section steel is more convenient to mount and dismount; the thickness of the concrete retaining wall 2 is made into the size, so that better protection can be realized; the steel bar with the size is used as the positioning steel bar 7, four steel protection cylinders 3 are uniformly arranged on the inner side of each steel protection cylinder 3 to match and position the two steel protection cylinders 3, and the steel protection cylinders are very stable.
The method is suitable for the construction of the pile foundation of the artificial hole digging and grouting of the unfavorable geological structure of the adjacent water area in the southwest region.
Compared with the prior art, the concrete retaining wall protection and the steel retaining cylinder protection are flexibly applied to the construction of the manual hole digging and pile pouring foundation of the water-bearing sand interlayer soil layer, the construction period is greatly shortened, the waste of materials is avoided, the engineering quantity is smaller, no vibration and low noise are generated in the construction process, and the concrete retaining wall protection and the steel retaining cylinder protection are environment-friendly.
The construction method for protecting the static pressure steel casing of the manual bored pile with the water-bearing sand interlayer provided by the invention is described in detail above, and the description of the specific embodiment is only used for helping to understand the method and the core idea of the invention. It should be noted that, for those skilled in the art, it is possible to make various improvements and modifications to the present invention without departing from the principle of the present invention, and those improvements and modifications also fall within the scope of the claims of the present invention.

Claims (4)

1. A static pressure steel pile casing protection construction method for a manual hole digging pile with a water-bearing sand interlayer is characterized by comprising the following steps of: the method comprises the following steps:
001. determining the position of an opening by utilizing the burial depth of the water-bearing sand interlayer determined in geological survey, and pouring a locking notch 1 by using concrete at the position of the opening;
002. digging holes downwards in a common soil layer in the locking opening in the step 001, and when the digging depth is 5m, ventilating the holes at intervals by using an air blower for 5-10 minutes and continuously ventilating when the depth is more than 10 m;
003. pouring concrete retaining walls in the 002 holes, wherein the concrete retaining walls are poured in a sectional manner;
004. stopping the operation when the distance between the concrete protecting wall and the water-bearing sand interlayer is 0.5m, forming a section steel mounting hole on the concrete protecting wall in the step 003, and placing a steel protecting cylinder after the hole is formed;
005. after the steel protection cylinder is placed, sequentially placing the section steel at the top of the steel protection cylinder, the jack and the reaction frame section steel, installing the reaction frame section steel into the section steel installation hole, and taking the section steel at the top of the steel protection cylinder and the reaction frame section steel as supporting points of the jack;
006. starting a jack to carry out downward static pressure on the steel casing, checking whether a concrete retaining wall has a crack or not in the static pressure process, and continuing the static pressure if no crack exists;
007. when a second section of steel casing is placed, a plurality of positioning steel bars are uniformly welded on the inner side of the bottom of the second section of steel casing, half of the positioning steel bars are welded in the second section of steel casing, and the second section of steel casing is aligned with the first section of steel casing and then is firmly welded;
008. repeating the 004-007 step until the water-bearing sand interlayer is penetrated, and then hollowing out the soil body in the steel casing;
009. after the soil body is hollowed, the reinforcement cage can be lifted into the soil body for placement, and pouring is carried out after placement is finished.
2. The construction method for protecting the static pressure steel casing of the manual bored pile with the water-bearing sand interlayer according to claim 1, characterized in that: the shaped steel mounting hole is two for corresponding, and one of them is the deepening hole in two shaped steel mounting holes.
3. The construction method for protecting the static pressure steel casing of the manual bored pile with the water-bearing sand interlayer according to claim 1, characterized in that: the thickness of the concrete retaining wall is 100cm-200 cm.
4. The construction method for protecting the static pressure steel casing of the manual bored pile with the water-bearing sand interlayer according to claim 1, characterized in that: the number of each layer of positioning steel bars is four, the length of each layer of positioning steel bars is 30cm, and the diameter of each layer of positioning steel bars is 16 mm.
CN202011219626.3A 2020-11-04 2020-11-04 Construction method for protecting static pressure steel casing of manual bored pile with water-bearing sand interlayer Pending CN112252315A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011219626.3A CN112252315A (en) 2020-11-04 2020-11-04 Construction method for protecting static pressure steel casing of manual bored pile with water-bearing sand interlayer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011219626.3A CN112252315A (en) 2020-11-04 2020-11-04 Construction method for protecting static pressure steel casing of manual bored pile with water-bearing sand interlayer

Publications (1)

Publication Number Publication Date
CN112252315A true CN112252315A (en) 2021-01-22

Family

ID=74268896

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011219626.3A Pending CN112252315A (en) 2020-11-04 2020-11-04 Construction method for protecting static pressure steel casing of manual bored pile with water-bearing sand interlayer

Country Status (1)

Country Link
CN (1) CN112252315A (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105002915A (en) * 2015-07-21 2015-10-28 中厦建设集团有限公司 Construction method of steel casing guard wall of manual hole digging pile
CN107083771A (en) * 2017-06-15 2017-08-22 中铁六局集团天津铁路建设有限公司 A kind of drilling construction method of artificial digging pile

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105002915A (en) * 2015-07-21 2015-10-28 中厦建设集团有限公司 Construction method of steel casing guard wall of manual hole digging pile
CN107083771A (en) * 2017-06-15 2017-08-22 中铁六局集团天津铁路建设有限公司 A kind of drilling construction method of artificial digging pile

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《地基处理手册》(第二版)编写委员会: "《地基处理手册(第二版)》", 31 March 2001, 中国建筑工业出版社 *

Similar Documents

Publication Publication Date Title
KR100964796B1 (en) Method for constructing the steel pipe-concrete composite pile structurized of burying and unifying into the bedrock, and a pile construction
CN214530750U (en) Bridge pile foundation structure suitable for rock mass abrupt slope
CN112761644A (en) Suspension sinking vertical shaft well completion process
CN113756330A (en) Foundation pit support construction method close to existing operation railway
CN114033388B (en) Shaft construction method for water-rich silty sand layer underground tunnel roof pipe
KR20090007826A (en) Process of blocking water penetration and blocking earth collapsing by using impermeable wall without strut
CN110206039B (en) Construction method of Larsen steel sheet pile in pit under complex geological conditions
KR100975988B1 (en) The Method for Constructing Underwater Structure
CN111827280B (en) Ex-situ pouring, jacking and in-place hole digging pile retaining wall device and construction method thereof
CN112942322A (en) Anti-floating pile structure and construction method thereof
CN110528528B (en) Vertical support system for prestressed concrete pipe pile and construction method thereof
CN112252315A (en) Construction method for protecting static pressure steel casing of manual bored pile with water-bearing sand interlayer
CN206368375U (en) A kind of electric power pylon basis
CN111155429A (en) Construction method for bridge sand blowing island building in still water deep water area
CN115012429A (en) Supporting structure for exposing foundation pit for long time and construction method thereof
CN112813984A (en) Deep foundation pit construction method under complex geological condition
CN210194639U (en) Foundation pit support structure applying miniature piles
CN104775448A (en) Basement construction method in soft soil area
KR200293048Y1 (en) shoring structure using prestressed retaining wall
CN214883595U (en) Anti-floating pile structure
CN219240525U (en) Maintenance and stability system for bored pile construction
CN214089887U (en) Improvement structure and foundation ditch fender pile based on existing fender pile
CN220468928U (en) Filling type hidden karst cave reinforcing structure of rock wall crane beam part
KR20060066836A (en) A construction method for foundation which connected a column
CN212582661U (en) Manual hole digging pile for overhead line

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210122

RJ01 Rejection of invention patent application after publication