CN112227814A - Method for dismantling straight-barrel type concrete tower body - Google Patents

Method for dismantling straight-barrel type concrete tower body Download PDF

Info

Publication number
CN112227814A
CN112227814A CN202011053745.6A CN202011053745A CN112227814A CN 112227814 A CN112227814 A CN 112227814A CN 202011053745 A CN202011053745 A CN 202011053745A CN 112227814 A CN112227814 A CN 112227814A
Authority
CN
China
Prior art keywords
concrete
layer
scaffold
tower
dismantled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202011053745.6A
Other languages
Chinese (zh)
Other versions
CN112227814B (en
Inventor
宿双超
李林
万鹏飞
郑波
刘准
牟少月
张宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Chemical Engineering Sixth Construction Co Ltd
Original Assignee
China National Chemical Engineering Sixth Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Chemical Engineering Sixth Construction Co Ltd filed Critical China National Chemical Engineering Sixth Construction Co Ltd
Priority to CN202011053745.6A priority Critical patent/CN112227814B/en
Publication of CN112227814A publication Critical patent/CN112227814A/en
Application granted granted Critical
Publication of CN112227814B publication Critical patent/CN112227814B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • E04H12/348Arrangements for demolition towers or the like

Abstract

The invention discloses a method for dismantling a straight-barrel type concrete tower body, which comprises the following steps of 1: vertically paying off from top to bottom until the paying off is in conical grounding; step 2: the tower body is dismantled in layers, and hoisting equipment is installed on each layer by drilling; and step 3: a group of scaffolds is installed on each layer of the tower body, the scaffolds are dismantled layer by layer, and the temporary scaffold on the layer is synchronously dismantled after the layer is dismantled, so that the straight cylindrical concrete tower body is gradually dismantled from top to bottom; and 4, step 4: dividing a concrete member of the concrete tower body into blocks, wherein each block of concrete is divided into blocks by 2-2.5 tons; and 5: conveying the cut concrete blocks to the bottom of the tower by using hoisting equipment; step 6: and intensively cleaning the concrete fragments scattered on each layer of scaffold, and transporting to the tower bottom. The method solves the problems that the demolition work of the existing concrete tower mostly adopts a blasting mode, and the blasting demolition mode causes serious environmental pollution.

Description

Method for dismantling straight-barrel type concrete tower body
Technical Field
The invention relates to the technical field of concrete tower body dismantling, in particular to a method for dismantling a straight-tube type concrete tower body.
Background
Concrete is a general term for engineering composite materials in which aggregate is cemented into a whole by a cementing material. The term concrete generally refers to cement as the cementing material and sand and stone as the aggregate; the cement concrete, also called ordinary concrete, is widely used in civil engineering, and has the characteristics of rich raw materials, low price and simple production process, so that the dosage of the concrete is increased more and more. Meanwhile, the concrete also has the characteristics of high compressive strength, good durability, wide strength grade range and the like. The characteristics make the application range of the concrete tower quite wide, the concrete is also an important material in various civil engineering, namely shipbuilding industry, mechanical industry, ocean development, geothermal engineering and the like, the demolition engineering of the domestic concrete tower is visible, most of the demolition engineering adopts a blasting mode, and a non-blasting section-by-section demolition technological mode is rarely used, so that the development of a new demolition technology for reducing the construction cost and improving the engineering progress is necessary.
The existing concrete tower dismantling engineering mostly adopts a blasting mode, the blasting dismantling mode has serious pollution to the environment, and a non-blasting section-by-section dismantling process mode is rarely used, so that a straight-barrel type concrete tower dismantling method is provided.
Disclosure of Invention
An object of the present invention is to solve at least the above problems and to provide at least the advantages described later.
The invention also aims to provide a method for dismantling the straight-barrel type concrete tower body, which realizes the effect of dismantling the tower body section by section without blasting, and overcomes the problems that the existing concrete tower dismantling engineering mostly adopts a blasting mode, and the blasting dismantling mode has serious pollution to the environment.
In order to achieve the above objects and other objects, the present invention adopts the following technical solutions:
a method for dismantling a straight-barrel type concrete tower body comprises the following steps:
step 1: vertically paying off from top to bottom until the paying off is in conical grounding;
step 2: the tower body is dismantled in layers, and hoisting equipment is installed on each layer by drilling;
and step 3: a group of scaffolds is installed on each layer of the tower body, the scaffolds are dismantled layer by layer, and the temporary scaffold on the layer is synchronously dismantled after the layer is dismantled, so that the straight cylindrical concrete tower body is gradually dismantled from top to bottom;
and 4, step 4: dividing a concrete member of the concrete tower body into blocks, wherein each block of concrete is divided into blocks by 2-2.5 tons;
and 5: conveying the cut concrete blocks to the bottom of the tower by using hoisting equipment;
step 6: intensively cleaning concrete fragments scattered on each layer of scaffold, and transporting the concrete fragments to the tower bottom;
and 7: the concrete blocks and the cleaned concrete fragments are cleaned by truck loading and transportation.
Preferably, the step 1 tower body paying-off comprises the following steps:
step 1-1: paying off the tower body from top to bottom, and performing the steps 1-1 according to the axis positioning pile and the axis datum line of the external guide: paying off the tower body from top to bottom, constructing and paying off according to the axis positioning pile and an axis datum line led out, driving the axis onto a building by using a theodolite, popping up the axis on the construction layer of the building, and paying off side lines such as columns, walls and the like according to the axis, wherein the number of the layers is the same;
step 1-2: the method comprises the following steps of adopting a part through which a tower surface stay wire can pass, namely one meter away from the axis of a column, drilling a # -shaped auxiliary control axis through a total station or a theodolite, then using the auxiliary control axis to reversely push out the axes of other columns and beams by using a large ruler or a small ruler, wherein the position of the auxiliary control axis of each layer is unchanged, and the auxiliary control axes are transmitted layer by layer;
step 1-3: the elevation marks of each layer are marked on the control auxiliary axis, the elevation of the tower layer floats 200mm downwards, the side faces of the peripheral beams and the paint marks are transmitted to a plurality of main column steel angle bars through the elevation, and the paint marks lay a foundation for subsequently confirming hoisting points and building temporary scaffolds.
Preferably, the step 3 support system installation comprises the following steps:
step 3-1: firstly, erecting a concrete support operation scaffold to a support bottom, and then chiseling and cutting off the concrete support by means of an air compressor;
step 3-2: then hoisting and cutting off part of the concrete support by using a gantry crane; then slag removal and outward transportation are carried out on the slag stones generated by the dismantling;
step 3-3: and after the concrete tower on one layer is dismantled, dismantling the temporary scaffold on the corresponding layer, and then entering the next layer for continuous dismantling.
Preferably, the step 3-1 of erecting the concrete support operation scaffold to the support bottom comprises the following steps:
step 3-1-1: erecting an operation scaffold by adopting a phi 48X3.5 steel pipe under a support to be chiseled, and paving a double-layer straw bag under a concrete support;
step 3-1-2: firstly, erecting an operation scaffold to be flush with the supporting concrete bottom of the concrete tower, then operating the scaffold by using a steel pipe, vertically and horizontally adjusting the vertical rods to be 900mm, then adding a temporary top support at the bottom of the supporting beam, and finally jacking the concrete supporting beam bottom by using the top support steel pipe;
step 3-1-3: then, a floor sweeping rod is arranged at the position 20cm away from the ground by the steel pipe scaffold, then a floor sweeping rod is arranged at the position where the height interval of the horizontal rods is smaller than 1.8m, then 1.0m high protective railings are arranged around the operation scaffold, and finally the floor sweeping rod is arranged at a height of 200mm away from the ground.
Preferably, the step 4 cutting comprises the following steps:
step 4-1: dividing the concrete member into blocks, wherein the size of each block is based on the bearing capacity of the existing floor slab structure, and each concrete block is divided by 2-2.5 tons;
step 4-2: cutting, positioning and paying off are carried out according to the standard, and before each cutting, a hole is drilled and a cutting machine is arranged;
step 4-3: during cutting construction, firstly, the flowing water construction is carried out from the top to the bottom horizontally and then from the left to the right vertically.
Preferably, in the step 3-1-1, square timber is padded under the steel pipe operation scaffold vertical pipe, the cross braces are arranged at three steps, a 1.0m high protection railing and an outer safety basketry are arranged outside the scaffold, two joists and a traction bar are firmly tied by lead wires under the bottom basketry, the two joists are firmly fastened with a cross rod at the lower part of the scaffold basketry, and the binding point of the scaffold basketry and the joists is not less than four points.
Preferably, after the steel pipe operation scaffold is erected in the step 3-5, chiseling the concrete support by using an air compressor, stripping off the main reinforcing steel bars and cutting off the main reinforcing steel bars, then hanging off the cut-off part of the concrete support by using a gantry crane, dismantling the temporary scaffold after the concrete support is completely hung off, installing a group of scaffolds on each layer of the tower body, dismantling the scaffolds in layers, and synchronously dismantling the temporary scaffold on the layer after the layer is dismantled.
Preferably, the hoisting load after the hoisting and cutting in the step 5 is limited to 2-2.5T, the blocking treatment is carried out after the hoisting and the light placing are finished, and the load is stacked on the floor by the removed sundries.
The invention at least comprises the following beneficial effects:
1. the invention relates to a straight cylinder type concrete tower dismantling technology, which is a novel comprehensive dismantling technology and provides technical support for similar projects in terms of project cost, safety and construction progress.
2. According to the invention, the concrete member is divided into a plurality of blocks, the size of each block is based on the bearing capacity of the existing floor structure, the field condition, the hoisting capacity of hoisting equipment, the safety of a supporting roof and the like are combined, the overlarge concrete block and the dynamic load in the construction process influence the floor, so that each block is divided into 2-2.5 tons according to each concrete block, and the problems that severe shock waves generated at the moment of falling down to the ground are likely to damage equipment in the running device if the concrete block is dismantled by adopting an explosion method, and a large amount of generated dust can influence the passing of vehicles on a plasticized road and the lives of residents on two sides of the road are avoided.
3. Hoisting should be slowly and lightly carried out to avoid impact damage to the floor slab, and the load of the removed sundries stacked on the floor slab should not be larger than the actual bearing load capacity of the floor slab; for guaranteeing hoist and mount safety, the hoist and mount load thing restriction after the cutting is at 2 ~ 2.5T, and the hoist and mount is gently put and is carried out the blocking after finishing and handle, and every piece of concrete member that is cut all is the operation under the safe prerequisite to accomplish, and for guaranteeing to demolish safety when machinery is demolishd, the hoist and mount point should be firm, and the support system can bear and demolish hoisting structure load to make the work of hoist and mount downward clearance concrete piece safe and stable more.
4. The steel pipe operation scaffold is erected on the surface of a structural roof plate, square timber is arranged below a vertical pipe of the steel pipe operation scaffold, cross braces are arranged at three steps to ensure the uniform stress and stability of the bottom of the scaffold, and a 1.0m high protective railing and an outer paving safety fence are arranged on the outer side of the scaffold. Two joists are additionally arranged below the bottom basketry and are firmly tied with the pulling bar by lead wires, the two joists are firmly buckled with the cross bar at the lower part of the scaffold basketry, the scaffold basketry is bound with the joists, and the binding point of each basketry is not less than four points, so that the structure of each layer of scaffold is more stable, and the subsequent dismantling of the scaffold is facilitated.
Drawings
FIG. 1 is a flow chart of a method for dismantling a straight tubular concrete tower provided by the present invention;
FIG. 2 is a flow chart of a tower paying-off process of a method for dismantling a straight-tube concrete tower provided by the present invention;
FIG. 3 is a flow chart of a support system installation process for a method of demolishing a spar-type concrete tower provided by the present invention;
FIG. 4 is a flow chart of concrete support operation scaffold erection to support underflow in the method for dismantling a cylindrical concrete tower according to the present invention;
fig. 5 is a cutting flow chart of the method for removing the straight-tube type concrete tower provided by the invention.
Detailed Description
The present invention is described in detail below with reference to the attached drawings so that those skilled in the art can implement the invention by referring to the description.
As shown in fig. 1 to 5, a method for dismantling a straight-tube type concrete tower body includes the following steps:
step 1: vertically paying off from top to bottom until the paying off is in conical grounding;
step 2: the tower body is dismantled in layers, and hoisting equipment is installed on each layer by drilling;
and step 3: a group of scaffolds is installed on each layer of the tower body, the scaffolds are dismantled layer by layer, and the temporary scaffold on the layer is synchronously dismantled after the layer is dismantled, so that the straight cylindrical concrete tower body is gradually dismantled from top to bottom;
and 4, step 4: dividing a concrete member of the concrete tower body into blocks, wherein each block of concrete is divided into blocks by 2-2.5 tons;
and 5: conveying the cut concrete blocks to the bottom of the tower by using hoisting equipment;
step 6: intensively cleaning concrete fragments scattered on each layer of scaffold, and transporting the concrete fragments to the tower bottom;
and 7: the concrete blocks and the cleaned concrete fragments are cleaned by truck loading and transportation.
In a preferred scheme, the step 1 tower body paying-off method comprises the following steps:
step 1-1: paying off the tower body from top to bottom, constructing and paying off according to the axis positioning pile and an axis datum line led out, driving the axis onto a building by using a theodolite, popping up the axis on the construction layer of the building, and paying off side lines such as columns, walls and the like according to the axis, wherein the number of the layers is the same;
step 1-2: the method comprises the following steps of adopting a part through which a tower surface stay wire can pass, namely one meter away from the axis of a column, drilling a # -shaped auxiliary control axis through a total station or a theodolite, then using the auxiliary control axis to reversely push out the axes of other columns and beams by using a large ruler or a small ruler, wherein the position of the auxiliary control axis of each layer is unchanged, and the auxiliary control axes are transmitted layer by layer;
step 1-3: the elevation marks of each layer are marked on the control auxiliary axis, the elevation of the tower layer floats 200mm downwards, the side faces of the peripheral beams and the paint marks are transmitted to a plurality of main column steel angle bars through the elevation, and the paint marks lay a foundation for subsequently confirming hoisting points and building temporary scaffolds.
In a preferred embodiment, the step 3 of installing the support system comprises the following steps:
step 3-1: firstly, erecting a concrete support operation scaffold to a support bottom, and then chiseling and cutting off the concrete support by means of an air compressor;
step 3-2: then hoisting and cutting off part of the concrete support by using a gantry crane; then slag removal and outward transportation are carried out on the slag stones generated by the dismantling;
step 3-3: and after the concrete tower on one layer is dismantled, dismantling the temporary scaffold on the corresponding layer, and then entering the next layer for continuous dismantling.
In a preferred embodiment, the step 3-1 of erecting the concrete support operation scaffold to the support bottom comprises the following steps:
step 3-1-1: erecting an operation scaffold by adopting a phi 48X3.5 steel pipe under a support to be chiseled, and paving a double-layer straw bag under a concrete support;
step 3-1-2: firstly, erecting an operation scaffold to be flush with the supporting concrete bottom of the concrete tower, then operating the scaffold by using a steel pipe, vertically and horizontally adjusting the vertical rods to be 900mm, then adding a temporary top support at the bottom of the supporting beam, and finally jacking the concrete supporting beam bottom by using the top support steel pipe;
step 3-1-3: then, a floor sweeping rod is arranged at the position 20cm away from the ground by the steel pipe scaffold, then a floor sweeping rod is arranged at the position where the height interval of the horizontal rods is smaller than 1.8m, then 1.0m high protective railings are arranged around the operation scaffold, and finally the floor sweeping rod is arranged at a height of 200mm away from the ground.
In a preferred embodiment, the step 4 cutting comprises the following steps:
step 4-1: dividing the concrete member into blocks, wherein the size of each block is based on the bearing capacity of the existing floor slab structure, and each concrete block is divided by 2-2.5 tons;
step 4-2: cutting, positioning and paying off are carried out according to the standard, and before each cutting, a hole is drilled and a cutting machine is arranged;
step 4-3: during cutting construction, firstly, the flowing water construction is carried out from the top to the bottom horizontally and then from the left to the right vertically.
In a preferable scheme, square timber is padded under the steel pipe operation scaffold vertical pipe in the step 3-1-1, cross braces are arranged at three steps every so as to ensure the even stress and stability of the bottom of the scaffold, and a 1.0m high protective railing and an outer paving safety fence are arranged on the outer side of the scaffold. Two joists are firmly tied with the pulling bar by lead wires under the bottom basketry, two joists are firmly buckled with the cross bar under the scaffold basketry, and the scaffold basketry is tied with the joists, wherein the tying point of each basketry is not less than four points.
In a preferable scheme, after the steel pipe operation scaffold is erected in the step 3-5, chiseling the concrete support by using an air compressor, stripping off the main reinforcing steel bars and cutting off the main reinforcing steel bars, then hanging off the cut-off part of the concrete support by using a gantry crane, dismantling the temporary scaffold after the concrete support is completely hung off, installing a group of scaffolds on each layer of the tower body, dismantling the scaffolds in layers, and synchronously dismantling the temporary scaffold 2 on the layer after the layer is dismantled.
In a preferable scheme, the hoisting load after the hoisting and cutting in the step 5 is limited to 2-2.5T, the hoisting is performed in a blocking mode after the hoisting is finished, and the load is stacked on the floor by the removed sundries.
While embodiments of the invention have been described above, it is not limited to the applications set forth in the description and the embodiments, which are fully applicable in various fields of endeavor to which the invention pertains, and further modifications may readily be made by those skilled in the art, it being understood that the invention is not limited to the details shown and described herein without departing from the general concept defined by the appended claims and their equivalents.

Claims (8)

1. A method for dismantling a straight-barrel type concrete tower body is characterized by comprising the following steps:
step 1: vertically paying off from top to bottom until the paying off is in conical grounding;
step 2: the tower body is dismantled in layers, and hoisting equipment is installed on each layer by drilling;
and step 3: a group of scaffolds is installed on each layer of the tower body, the scaffolds are dismantled layer by layer, and the temporary scaffold on the layer is synchronously dismantled after the layer is dismantled, so that the straight cylindrical concrete tower body is gradually dismantled from top to bottom;
and 4, step 4: dividing a concrete member of the concrete tower body into blocks, wherein each block of concrete is divided into blocks by 2-2.5 tons;
and 5: conveying the cut concrete blocks to the bottom of the tower by using hoisting equipment;
step 6: intensively cleaning concrete fragments scattered on each layer of scaffold, and transporting the concrete fragments to the tower bottom;
and 7: the concrete blocks and the cleaned concrete fragments are cleaned by truck loading and transportation.
2. A method of demolishing a spar type concrete tower according to claim 1, wherein said step 1 tower payoff comprises the steps of:
step 1-1: paying off the tower body from top to bottom, constructing and paying off according to the axis positioning pile and an axis datum line led out, driving the axis onto a building by using a theodolite, popping up the axis on the construction layer of the building, and paying off side lines such as columns, walls and the like according to the axis, wherein the number of the layers is the same;
step 1-2: the method comprises the following steps of adopting a part through which a tower surface stay wire can pass, namely one meter away from the axis of a column, drilling a # -shaped auxiliary control axis through a total station or a theodolite, then using the auxiliary control axis to reversely push out the axes of other columns and beams by using a large ruler or a small ruler, wherein the position of the auxiliary control axis of each layer is unchanged, and the auxiliary control axes are transmitted layer by layer;
step 1-3: the elevation marks of each layer are marked on the control auxiliary axis, the elevation of the tower layer floats 200mm downwards, the side faces of the peripheral beams and the paint marks are transmitted to a plurality of main column steel angle bars through the elevation, and the paint marks lay a foundation for subsequently confirming hoisting points and building temporary scaffolds.
3. A method of demolishing a spar type concrete tower as recited in claim 1, wherein said step 3 support system installation comprises the steps of:
step 3-1: firstly, erecting a concrete support operation scaffold to a support bottom, and then chiseling and cutting off the concrete support by means of an air compressor;
step 3-2: then hoisting and cutting off part of the concrete support by using a gantry crane; then slag removal and outward transportation are carried out on the slag stones generated by the dismantling;
step 3-3: and after the concrete tower on one layer is dismantled, dismantling the temporary scaffold on the corresponding layer, and then entering the next layer for continuous dismantling.
4. A method of demolishing a spar type concrete tower according to claim 2, wherein said step 3-1 of erecting a concrete support handling scaffold to a support base comprises the steps of:
step 3-1-1: erecting an operation scaffold by adopting a phi 48X3.5 steel pipe under a support to be chiseled, and paving a double-layer straw bag under a concrete support;
step 3-1-2: firstly, erecting an operation scaffold to be flush with the supporting concrete bottom of the concrete tower, then operating the scaffold by using a steel pipe, vertically and horizontally adjusting the vertical rods to be 900mm, then adding a temporary top support at the bottom of the supporting beam, and finally jacking the concrete supporting beam bottom by using the top support steel pipe;
step 3-1-3: then, a floor sweeping rod is arranged at the position 20cm away from the ground by the steel pipe scaffold, then a floor sweeping rod is arranged at the position where the height interval of the horizontal rods is smaller than 1.8m, then 1.0m high protective railings are arranged around the operation scaffold, and finally the floor sweeping rod is arranged at a height of 200mm away from the ground.
5. A method of demolishing a spar type concrete tower as recited in claim 1, wherein said step 4 cutting comprises the steps of:
step 4-1: dividing the concrete member into blocks, wherein the size of each block is based on the bearing capacity of the existing floor slab structure, and each concrete block is divided by 2-2.5 tons;
step 4-2: cutting, positioning and paying off are carried out according to the standard, and before each cutting, a hole is drilled and a cutting machine is arranged;
step 4-3: during cutting construction, firstly, the flowing water construction is carried out from the top to the bottom horizontally and then from the left to the right vertically.
6. The method for demolishing a straight tubular concrete tower according to claim 3, wherein in step 3-1-1, square timber is laid under a steel pipe operation scaffold vertical pipe, a cross brace is arranged at three steps, a 1.0m high guard rail and an outer safety basketry are arranged outside the scaffold, two joists are additionally arranged under the bottom basketry and are firmly tied with a pulling bar by lead wires, two joists are arranged under the scaffold basketry and are firmly buckled with a cross bar, and the scaffold basketry is tied with the joists, wherein the tying point of each basketry is not less than four.
7. The method for dismantling the straight-tube type concrete tower body according to claim 2, wherein after the steel tube operation scaffold is erected in step 3-1, an air compressor is used for chiseling the concrete support, main reinforcing steel bars are stripped and cut off, then a gantry crane is used for hoisting the cut-off part of the concrete support, after the concrete support is completely hoisted out, the temporary scaffold is dismantled, a group of scaffolds is installed on each layer of the tower body, the dismantling is carried out in a layered manner, and the temporary scaffold on the layer is synchronously dismantled after the layer is dismantled.
8. The method for dismantling the cylindrical concrete tower body according to claim 2, wherein the hoisting load after the hoisting and cutting in the step 5 is limited to 2-2.5T, the blocking treatment is performed after the hoisting is finished, and the load is piled on the floor by the dismantled sundries.
CN202011053745.6A 2020-09-29 2020-09-29 Method for dismantling straight-barrel type concrete tower body Active CN112227814B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011053745.6A CN112227814B (en) 2020-09-29 2020-09-29 Method for dismantling straight-barrel type concrete tower body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011053745.6A CN112227814B (en) 2020-09-29 2020-09-29 Method for dismantling straight-barrel type concrete tower body

Publications (2)

Publication Number Publication Date
CN112227814A true CN112227814A (en) 2021-01-15
CN112227814B CN112227814B (en) 2022-04-15

Family

ID=74119624

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011053745.6A Active CN112227814B (en) 2020-09-29 2020-09-29 Method for dismantling straight-barrel type concrete tower body

Country Status (1)

Country Link
CN (1) CN112227814B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115354882A (en) * 2022-07-15 2022-11-18 安徽送变电工程有限公司 Method for dismantling ultra-large spanning old electric tower

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103015744A (en) * 2012-12-27 2013-04-03 中铁一局集团有限公司 Method for removing reinforced concrete chimney
JP2014058778A (en) * 2012-09-14 2014-04-03 Takenaka Komuten Co Ltd Cutting/disassembling method of large-sized tubular structure formed from reinforced concrete construction, and cutting/disassembling device
CN104153598A (en) * 2014-08-06 2014-11-19 刘建国 Self-lifting detachment method for structures with chimneys
CN104797766A (en) * 2012-11-08 2015-07-22 贝斯特罗株式会社 Scaffolding equipment for aggregate smokestack dismantling and dismantling method for aggregate smokestack using same equipment
CN106522581A (en) * 2016-12-04 2017-03-22 河南理工大学 Method for demolish chimney manually
CN108518083A (en) * 2018-03-27 2018-09-11 五冶集团上海有限公司 The Demolition Construction method of main sintering building
CN108678422A (en) * 2018-05-29 2018-10-19 五冶集团上海有限公司 The method for dismounting of steel stack
CN110905232A (en) * 2019-11-29 2020-03-24 上海宝冶市政工程有限公司 Mechanical static force dismantling method for concrete structure

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014058778A (en) * 2012-09-14 2014-04-03 Takenaka Komuten Co Ltd Cutting/disassembling method of large-sized tubular structure formed from reinforced concrete construction, and cutting/disassembling device
CN104797766A (en) * 2012-11-08 2015-07-22 贝斯特罗株式会社 Scaffolding equipment for aggregate smokestack dismantling and dismantling method for aggregate smokestack using same equipment
CN103015744A (en) * 2012-12-27 2013-04-03 中铁一局集团有限公司 Method for removing reinforced concrete chimney
CN104153598A (en) * 2014-08-06 2014-11-19 刘建国 Self-lifting detachment method for structures with chimneys
CN106522581A (en) * 2016-12-04 2017-03-22 河南理工大学 Method for demolish chimney manually
CN108518083A (en) * 2018-03-27 2018-09-11 五冶集团上海有限公司 The Demolition Construction method of main sintering building
CN108678422A (en) * 2018-05-29 2018-10-19 五冶集团上海有限公司 The method for dismounting of steel stack
CN110905232A (en) * 2019-11-29 2020-03-24 上海宝冶市政工程有限公司 Mechanical static force dismantling method for concrete structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115354882A (en) * 2022-07-15 2022-11-18 安徽送变电工程有限公司 Method for dismantling ultra-large spanning old electric tower
CN115354882B (en) * 2022-07-15 2023-08-22 安徽送变电工程有限公司 Method for dismantling ultra-large spanning old electric tower

Also Published As

Publication number Publication date
CN112227814B (en) 2022-04-15

Similar Documents

Publication Publication Date Title
CN205025086U (en) Strength nature skeleton concrete beam construction suspend template in midair
CN110184941B (en) Bridge main tower construction method
CN113235467A (en) Construction method for dismantling large-span prestressed cast-in-place box girder
CN104975719A (en) Novel material distribution device and floor concrete casting construction method of novel material distribution device
CN103603359A (en) Deep foundation pit diagonal bracing support structure demolition method
CN108330902B (en) Construction method for cast-in-situ lower cross beam of high-pile wharf
CN111997066A (en) Manufacturing and construction method of assembled prestressed anchor cable frame beam for slope reinforcement
CN114150593B (en) Simple arch bridge dismantling and reconstructing structure and arch bridge dismantling and reconstructing method
CN112227814B (en) Method for dismantling straight-barrel type concrete tower body
CN111485573A (en) Transmission project prefabricated foundation installation and iron tower assembly coherent construction method
CN103993739B (en) The construction method of granulation tower spraying layer stiff beam
CN113550335A (en) Construction method for high slope concrete slope protection engineering
CN106120871B (en) A kind of poured band of outer wall of basement outboard template construction method
CN111648256A (en) Pier body reinforcing construction method
CN111576878A (en) Construction process for quick-release system of aluminum alloy template
CN109457814B (en) Construction method for top cover of high-rise and large-diameter building based on Bailey truss structure
CN114277672B (en) Large-span prestressed concrete bent cap structure and construction method thereof
CN109024670B (en) Underground comprehensive pipe gallery protection and reinforcement system penetrating through buried high-voltage cable and reinforcement method
CN216515083U (en) High bridge cushion cap structure of filling
CN113774972B (en) Reinforcing method for overload punching damage of independent foundation under column
CN110258339A (en) A kind of overbridge roof beam structure bridge construction method
CN115126254A (en) Construction method of assembled composite floor slab support
CN114109123A (en) Construction method of chimney barrel body
CN113846714A (en) Method for repairing and reinforcing raft foundation
CN113622328A (en) Box culvert construction assembly, application thereof and box culvert construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant