CN112177167A - A kind of assembly and connection method of ALC wall panel and wooden structure main body - Google Patents
A kind of assembly and connection method of ALC wall panel and wooden structure main body Download PDFInfo
- Publication number
- CN112177167A CN112177167A CN202011072419.XA CN202011072419A CN112177167A CN 112177167 A CN112177167 A CN 112177167A CN 202011072419 A CN202011072419 A CN 202011072419A CN 112177167 A CN112177167 A CN 112177167A
- Authority
- CN
- China
- Prior art keywords
- alc
- connecting piece
- board
- wood structure
- alc board
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 19
- 239000002023 wood Substances 0.000 claims abstract description 30
- 238000005452 bending Methods 0.000 claims description 9
- 239000000853 adhesive Substances 0.000 claims description 3
- 230000001070 adhesive effect Effects 0.000 claims description 3
- 239000004744 fabric Substances 0.000 claims description 3
- 239000003365 glass fiber Substances 0.000 claims description 3
- 239000003513 alkali Substances 0.000 claims 1
- 239000011111 cardboard Substances 0.000 description 10
- 238000009434 installation Methods 0.000 description 6
- 239000004567 concrete Substances 0.000 description 4
- VYPSYNLAJGMNEJ-UHFFFAOYSA-N Silicium dioxide Chemical compound O=[Si]=O VYPSYNLAJGMNEJ-UHFFFAOYSA-N 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- 235000008733 Citrus aurantifolia Nutrition 0.000 description 1
- 229910000831 Steel Inorganic materials 0.000 description 1
- 235000011941 Tilia x europaea Nutrition 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000004566 building material Substances 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 239000010881 fly ash Substances 0.000 description 1
- 239000004571 lime Substances 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 238000007781 pre-processing Methods 0.000 description 1
- 239000011178 precast concrete Substances 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 239000000377 silicon dioxide Substances 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
Description
技术领域technical field
本发明涉及ALC墙板与木结构装配技术领域,具体是一种ALC墙板与木结构主体的装配连接方法。The invention relates to the technical field of assembly of ALC wall panels and wooden structures, in particular to a method for assembling and connecting an ALC wall panel and a wooden structure main body.
背景技术Background technique
随着社会发展,用工成本不断上涨,同时劳动力却随之日渐短缺,传统的砌筑工艺受到了严重挑战,建筑产业化构成建筑未来发展方向的趋势日渐明朗。建筑产业化的要求之一,就是建筑构部件的通用化和现场施工的装配化、机械化。With the development of society, labor costs continue to rise, and labor is increasingly scarce. The traditional masonry craftsmanship has been seriously challenged, and the trend of building industrialization forming the future development direction of buildings has become increasingly clear. One of the requirements of building industrialization is the generalization of building components and the assembly and mechanization of on-site construction.
ALC即蒸压加气轻质混凝土,是高性能预制混凝土中的其中一种,蒸压加气轻质混凝土是以粉煤灰(或硅砂)、水泥、石灰等为主原料,经过高压蒸汽养护而成的多气孔混凝土成型(内含经过处理的钢筋增强)。蒸压加气轻质混凝土既可做墙体材料,又可做屋面板,是一种性能优越的新型建材,其优点是:具备密度小、质量轻、保温、隔音、抗震、防火等性能。ALC is autoclaved aerated lightweight concrete, which is one of high-performance precast concrete. Autoclaved aerated lightweight concrete is mainly made of fly ash (or silica sand), cement, lime, etc. The formed porous concrete is formed (including treated steel reinforcement). Autoclaved aerated lightweight concrete can be used as both wall material and roof panel. It is a new type of building material with superior performance.
现有的ALC墙板与木结构在装配时,其连接强度不高,连接处容易松动,使用较为不便。When the existing ALC wall panel and the wood structure are assembled, the connection strength is not high, and the connection is easy to loosen, which is inconvenient to use.
发明内容SUMMARY OF THE INVENTION
本发明的目的在于提供一种ALC墙板与木结构主体的装配连接方法,以解决现有技术中的问题。The purpose of the present invention is to provide a method for assembling and connecting an ALC wall panel and a wooden structure main body, so as to solve the problems in the prior art.
为实现上述目的,本发明提供如下技术方案:一种ALC墙板与木结构主体的装配连接方法,包括ALC板、木结构和螺母,所述ALC板和木结构之间设置有灌浆层和连接件,所述ALC板内设置有螺杆和丝杆,所述螺母贯穿木结构和连接件并与螺杆连接;其装配连接方法包括以下步骤:In order to achieve the above object, the present invention provides the following technical solutions: a method for assembling and connecting an ALC wall panel and a wooden structure main body, comprising an ALC board, a wooden structure and a nut, and a grouting layer and a connection are provided between the ALC board and the wooden structure. The ALC board is provided with a screw rod and a screw rod, and the nut penetrates the wooden structure and the connecting piece and is connected with the screw rod; its assembly and connection method includes the following steps:
S1:ALC板的预处理;S1: Pretreatment of ALC board;
S2:将连接件安装在ALC板上;S2: Install the connector on the ALC board;
S3:将木结构上开设有供连接件卡接的卡槽;S3: open the wooden structure with a card slot for the connector to be connected;
S4:将ALC板内安装螺杆和丝杆;S4: Install the screw and lead screw in the ALC board;
S5:将ALC板安装在木结构上,并采用螺母贯穿木结构和连接件并与螺杆连接;S5: Install the ALC board on the wooden structure, and use the nut to penetrate the wooden structure and the connecting piece and connect with the screw;
S6:将ALC板与木结构之间填充灌浆层。S6: Fill the grouting layer between the ALC board and the wooden structure.
优选的,所述连接件主要由卡板和限位板组成,所述限位板两端设置为弯折结构,所述限位板顶端的两侧均安装有卡板,所述限位板两侧的弯折结构上均开设有第一螺栓孔,所述限位板顶端开设有第二螺栓孔。Preferably, the connecting piece is mainly composed of a clamp plate and a limit plate, the two ends of the limit plate are arranged in a bending structure, and the clamp plates are installed on both sides of the top of the limit plate, and the limit plate The bending structures on both sides are provided with first bolt holes, and the top end of the limiting plate is provided with second bolt holes.
优选的,所述步骤S1中ALC板的预处理是将ALC板切割成所需的尺寸,切割前需要弹线定位,然后通过切割设备按照弹线进行切割。Preferably, the pretreatment of the ALC board in the step S1 is to cut the ALC board into a required size, and the elastic wire needs to be positioned before cutting, and then the cutting equipment is used to cut according to the elastic wire.
优选的,所述步骤S2中连接件的安装是将连接件卡在ALC板上,并将连接件两侧的弯折结构通过螺栓固定在ALC板上。Preferably, the installation of the connector in the step S2 is to clamp the connector on the ALC board, and fix the bending structures on both sides of the connector on the ALC board by bolts.
优选的,所述步骤S3中开设卡槽之前,需要测量卡板位于木结构处的位置,然后对开设的卡槽进行划线定位,且开设的卡槽略小于卡板的尺寸,使卡板与卡槽之间通过过盈配合。Preferably, before opening the card slot in the step S3, it is necessary to measure the position of the card board at the wooden structure, and then scribe and locate the opened card slot, and the opened card slot is slightly smaller than the size of the card board, so that the card board There is an interference fit with the card slot.
优选的,所述步骤S4中ALC板内安装螺杆和丝杆,是将螺杆和丝杆倾斜安装,倾斜角度设置为60°-80°,相邻螺杆和丝杆之间对称安装。Preferably, in the step S4, the screw and the lead screw are installed in the ALC board by tilting the screw and the lead screw.
优选的,所述步骤S5中ALC板安装在木结构上,需要将连接件的卡板对准木结构的卡槽。Preferably, in the step S5, when the ALC board is installed on the wooden structure, it is necessary to align the card board of the connector with the card slot of the wooden structure.
优选的,所述步骤S6中在填充灌浆层之前,需要在ALC板上安装碱性玻纤网格布,所述灌浆层采用粘粘剂。Preferably, in the step S6, before filling the grouting layer, it is necessary to install an alkaline glass fiber mesh cloth on the ALC board, and the grouting layer adopts an adhesive.
与现有技术相比,本发明的有益效果是:Compared with the prior art, the beneficial effects of the present invention are:
1、通过采用连接件,且连接件主要由卡板和限位板组成,限位板两端设置为弯折结构,限位板顶端的两侧均安装有卡板;使得连接件可卡在ALC强板和木结构内,起到很好的连接固定作用,且连接件通过螺栓固定后可实现多方向的限位;1. By adopting the connecting piece, and the connecting piece is mainly composed of a clip plate and a limit plate, the two ends of the limit plate are set to be bent structures, and the clip plates are installed on both sides of the top of the limit plate; ALC strong plate and wood structure play a very good role in connection and fixation, and the connector can be fixed in multiple directions after being fixed by bolts;
2、通过采用螺母贯穿木结构和连接件并与螺杆连接,将螺杆和丝杆倾斜安装,倾斜角度设置为60°-80°,相邻螺杆和丝杆之间对称安装;可实现对ALC板和木结构之间的固定;相邻之间的对称安装,使得整体的装配紧固性更好。2. By using the nut to penetrate the wooden structure and the connecting piece and connect with the screw, the screw and the screw rod are installed obliquely, the inclination angle is set to 60°-80°, and the adjacent screw rods and screw rods are installed symmetrically; the ALC board can be installed. The fixation between the wooden structure; the symmetrical installation between adjacent ones makes the overall assembly tighter.
附图说明Description of drawings
附图用来提供对本发明的进一步理解,并且构成说明书的一部分,与本发明的实施例一起用于解释本发明,并不构成对本发明的限制。在附图中:The accompanying drawings are used to provide a further understanding of the present invention, and constitute a part of the specification, and are used to explain the present invention together with the embodiments of the present invention, and do not constitute a limitation to the present invention. In the attached image:
图1为本发明的结构示意图。FIG. 1 is a schematic structural diagram of the present invention.
图2为本发明局部剖视的结构示意图。FIG. 2 is a partial cross-sectional structural schematic diagram of the present invention.
图3为本发明连接件的结构示意图。FIG. 3 is a schematic structural diagram of the connector of the present invention.
图中:1、ALC板;2、灌浆层;3、木结构;4、连接件;5、螺母;6、螺杆;7、丝杆;401、卡板;402、限位板;403、第一螺栓孔;404、第二螺栓孔。In the picture: 1, ALC board; 2, grouting layer; 3, wood structure; 4, connecting piece; 5, nut; 6, screw rod; 7, screw rod; A bolt hole; 404, a second bolt hole.
具体实施方式Detailed ways
为使本发明实施方式的目的、技术方案和优点更加清楚,下面将结合本发明实施方式中的附图,对本发明实施方式中的技术方案进行清楚、完整地描述,显然,所描述的实施方式是本发明一部分实施方式,而不是全部的实施方式。基于本发明中的实施方式,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施方式,都属于本发明保护的范围。因此,以下对在附图中提供的本发明的实施方式的详细描述并非旨在限制要求保护的本发明的范围,而是仅仅表示本发明的选定实施方式。基于本发明中的实施方式,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施方式,都属于本发明保护的范围。In order to make the purposes, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments These are some embodiments of the present invention, but not all of them. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention. Accordingly, the following detailed description of the embodiments of the invention provided in the accompanying drawings is not intended to limit the scope of the invention as claimed, but is merely representative of selected embodiments of the invention. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.
请参阅图1-3,本发明实施例中,一种ALC墙板与木结构主体的装配连接方法,包括ALC板1、木结构3和螺母5,所述ALC板1和木结构3之间设置有灌浆层2和连接件4,所述ALC板1内设置有螺杆6和丝杆7,所述螺母5贯穿木结构3和连接件4并与螺杆6连接;其装配连接方法包括以下步骤:Referring to FIGS. 1-3 , in the embodiment of the present invention, a method for assembling and connecting an ALC wall panel and a wooden structure main body includes an
S1:ALC板1的预处理;S1: Preprocessing of
S2:将连接件4安装在ALC板1上;S2: Install the
S3:将木结构3上开设有供连接件4卡接的卡槽;S3: the
S4:将ALC板1内安装螺杆6和丝杆7;S4: Install the
S5:将ALC板1安装在木结构3上,并采用螺母5贯穿木结构3和连接件4并与螺杆6连接;S5: Install the
S6:将ALC板1与木结构3之间填充灌浆层2。S6: Fill the
优选的,所述连接件4主要由卡板401和限位板402组成,所述限位板402两端设置为弯折结构,所述限位板402顶端的两侧均安装有卡板401,所述限位板402两侧的弯折结构上均开设有第一螺栓孔403,所述限位板402顶端开设有第二螺栓孔404。Preferably, the connecting
优选的,所述步骤S1中ALC板1的预处理是将ALC板1切割成所需的尺寸,切割前需要弹线定位,然后通过切割设备按照弹线进行切割。Preferably, the pretreatment of the
优选的,所述步骤S2中连接件4的安装是将连接件4卡在ALC板1上,并将连接件4两侧的弯折结构通过螺栓固定在ALC板1上。Preferably, the installation of the
优选的,所述步骤S3中开设卡槽之前,需要测量卡板401位于木结构3处的位置,然后对开设的卡槽进行划线定位,且开设的卡槽略小于卡板401的尺寸,使卡板401与卡槽之间通过过盈配合。Preferably, before opening the card slot in the step S3, it is necessary to measure the position of the
优选的,所述步骤S4中ALC板1内安装螺杆6和丝杆7,是将螺杆6和丝杆7倾斜安装,倾斜角度设置为60°-80°,相邻螺杆6和丝杆7之间对称安装。Preferably, in the step S4, the
优选的,所述步骤S5中ALC板1安装在木结构3上,需要将连接件4的卡板401对准木结构3的卡槽。Preferably, in the step S5, when the
优选的,所述步骤S6中在填充灌浆层2之前,需要在ALC板1上安装碱性玻纤网格布,所述灌浆层2采用粘粘剂。Preferably, in the step S6, before filling the
本发明的工作原理是:将ALC板1切割成所需的尺寸,切割前需要弹线定位,然后通过切割设备按照弹线进行切割;将连接件4卡在ALC板1上,并将连接件4两侧的弯折结构通过螺栓固定在ALC板1上;测量卡板401位于木结构3处的位置,然后对开设的卡槽进行划线定位,且开设的卡槽略小于卡板401的尺寸,使卡板401与卡槽之间通过过盈配合;将螺杆6和丝杆7倾斜安装,倾斜角度设置为60°-80°,相邻螺杆6和丝杆7之间对称安装;ALC板1安装在木结构3上,需要将连接件4的卡板401对准木结构3的卡槽;将ALC板1与木结构3之间填充灌浆层2;通过采用连接件,且连接件主要由卡板和限位板组成,限位板两端设置为弯折结构,限位板顶端的两侧均安装有卡板;使得连接件可卡在ALC强板和木结构内,起到很好的连接固定作用,且连接件通过螺栓固定后可实现多方向的限位;通过采用螺母贯穿木结构和连接件并与螺杆连接,将螺杆和丝杆倾斜安装,倾斜角度设置为60°-80°,相邻螺杆和丝杆之间对称安装;可实现对ALC板和木结构之间的固定;相邻之间的对称安装,使得整体的装配紧固性更好。The working principle of the present invention is as follows: the
最后应说明的是:以上所述仅为本发明的优选实施例而已,并不用于限制本发明,尽管参照前述实施例对本发明进行了详细的说明,对于本领域的技术人员来说,其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。Finally, it should be noted that the above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Although the present invention has been described in detail with reference to the foregoing embodiments, for those skilled in the art, the The technical solutions described in the foregoing embodiments may be modified, or some technical features thereof may be equivalently replaced. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202011072419.XA CN112177167A (en) | 2020-10-09 | 2020-10-09 | A kind of assembly and connection method of ALC wall panel and wooden structure main body |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202011072419.XA CN112177167A (en) | 2020-10-09 | 2020-10-09 | A kind of assembly and connection method of ALC wall panel and wooden structure main body |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN112177167A true CN112177167A (en) | 2021-01-05 |
Family
ID=73948581
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202011072419.XA Pending CN112177167A (en) | 2020-10-09 | 2020-10-09 | A kind of assembly and connection method of ALC wall panel and wooden structure main body |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN112177167A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113323195A (en) * | 2021-05-21 | 2021-08-31 | 中建科工集团有限公司 | Connecting piece, ALC (automatic level control) installation node structure and construction method |
Citations (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2003119900A (en) * | 2001-10-16 | 2003-04-23 | Nobuo Kinoshita | Joist hanger, manufacturing method therefor, and connection device |
| JP2003171989A (en) * | 2001-12-07 | 2003-06-20 | Minoru Hatanaka | Building steel connecting member and method of connecting building steel using it |
| JP2004211455A (en) * | 2003-01-07 | 2004-07-29 | Porasu Kurashi Kagaku Kenkyusho:Kk | Joining hardware for building |
| JP4020922B2 (en) * | 2005-05-24 | 2007-12-12 | 株式会社ポラス暮し科学研究所 | Joint structure of wood members |
| JP2009150206A (en) * | 2007-11-28 | 2009-07-09 | Sgc:Kk | Bonding hardware and shaft structure |
| CN201746938U (en) * | 2010-06-25 | 2011-02-16 | 珠海市瑞铭建筑装饰工程有限公司 | Connecting structure for thin-wall C-shaped steel |
| CN204456455U (en) * | 2015-01-26 | 2015-07-08 | 苏州新巢木结构系统工程有限公司 | A kind of steady type column cap connector be applied in wooden construction |
| CN107419801A (en) * | 2017-04-17 | 2017-12-01 | 浙江普天集成房屋有限公司 | A kind of assembled individual layer ALC wood connecting building and its construction method and ALC board manufacturing methods |
| CN110565860A (en) * | 2019-09-27 | 2019-12-13 | 南京工业大学 | connecting system of prefabricated wood-concrete combined structure |
| CN111155659A (en) * | 2020-01-22 | 2020-05-15 | 哈尔滨工业大学 | Connection node and crack identification method |
| CN210713206U (en) * | 2019-05-07 | 2020-06-09 | 胡兴明 | Timber structure passive house secondary beam connection structure |
| CN111706088A (en) * | 2020-06-23 | 2020-09-25 | 中建西部建设建材科学研究院有限公司 | A detachable wall panel connector and its rapid installation process |
-
2020
- 2020-10-09 CN CN202011072419.XA patent/CN112177167A/en active Pending
Patent Citations (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2003119900A (en) * | 2001-10-16 | 2003-04-23 | Nobuo Kinoshita | Joist hanger, manufacturing method therefor, and connection device |
| JP2003171989A (en) * | 2001-12-07 | 2003-06-20 | Minoru Hatanaka | Building steel connecting member and method of connecting building steel using it |
| JP2004211455A (en) * | 2003-01-07 | 2004-07-29 | Porasu Kurashi Kagaku Kenkyusho:Kk | Joining hardware for building |
| JP4020922B2 (en) * | 2005-05-24 | 2007-12-12 | 株式会社ポラス暮し科学研究所 | Joint structure of wood members |
| JP2009150206A (en) * | 2007-11-28 | 2009-07-09 | Sgc:Kk | Bonding hardware and shaft structure |
| CN201746938U (en) * | 2010-06-25 | 2011-02-16 | 珠海市瑞铭建筑装饰工程有限公司 | Connecting structure for thin-wall C-shaped steel |
| CN204456455U (en) * | 2015-01-26 | 2015-07-08 | 苏州新巢木结构系统工程有限公司 | A kind of steady type column cap connector be applied in wooden construction |
| CN107419801A (en) * | 2017-04-17 | 2017-12-01 | 浙江普天集成房屋有限公司 | A kind of assembled individual layer ALC wood connecting building and its construction method and ALC board manufacturing methods |
| CN210713206U (en) * | 2019-05-07 | 2020-06-09 | 胡兴明 | Timber structure passive house secondary beam connection structure |
| CN110565860A (en) * | 2019-09-27 | 2019-12-13 | 南京工业大学 | connecting system of prefabricated wood-concrete combined structure |
| CN111155659A (en) * | 2020-01-22 | 2020-05-15 | 哈尔滨工业大学 | Connection node and crack identification method |
| CN111706088A (en) * | 2020-06-23 | 2020-09-25 | 中建西部建设建材科学研究院有限公司 | A detachable wall panel connector and its rapid installation process |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113323195A (en) * | 2021-05-21 | 2021-08-31 | 中建科工集团有限公司 | Connecting piece, ALC (automatic level control) installation node structure and construction method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN112177167A (en) | A kind of assembly and connection method of ALC wall panel and wooden structure main body | |
| CN221567694U (en) | Fully assembled steel-concrete structure roof | |
| CN220666627U (en) | A glass curtain wall that is easy to splice and construct | |
| CN111997234A (en) | Novel ALC plate steel structure antidetonation connected node | |
| CN218628293U (en) | Assembled building assembly is with preventing skew detection device | |
| CN111335487A (en) | Assembled smoke-blocking vertical wall structure, construction method thereof and glass installation auxiliary part | |
| CN112832477B (en) | An exterior wall concrete hanging board | |
| CN108661212B (en) | Partition plate installation connecting piece | |
| CN217399991U (en) | External hanging connection structure of composite wall board | |
| CN206971539U (en) | A kind of prefabricated assembled steel construction wallboard connecting component | |
| CN211774644U (en) | ALC panel convenient to installation and concatenation connection structure thereof | |
| CN222796952U (en) | A lateral installation structure of ALC strips | |
| CN110984617B (en) | Building structure's reinforcement connecting device | |
| CN216810425U (en) | Shear wall convenient to location installation | |
| CN217480503U (en) | Externally-hung wallboard installing and connecting structure | |
| CN218091329U (en) | An installation structure for fixing railings with ALC wall panels in prefabricated buildings | |
| CN209891626U (en) | Composite wallboard capable of being reused in assembly construction | |
| CN218815412U (en) | Prefabricated fiber cement high-ductility plate reinforced structure | |
| CN222797086U (en) | Glass hanging clamp device, glass hanging clamp system and large glass curtain wall | |
| CN220014080U (en) | Sound insulation building board | |
| CN218668271U (en) | Waterproof fastener of wallboard and wallboard installing the system | |
| CN217420111U (en) | Composite self-insulation external wall panel lower-supporting type connecting structure | |
| CN223226803U (en) | Assembled concrete building | |
| CN222909141U (en) | A connection structure between a steel structure steel beam and an ALC prefabricated wall panel | |
| CN219060382U (en) | An aerated concrete slab fixed pipe clip |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20210105 |
|
| RJ01 | Rejection of invention patent application after publication |