CN112177167A - A kind of assembly and connection method of ALC wall panel and wooden structure main body - Google Patents

A kind of assembly and connection method of ALC wall panel and wooden structure main body Download PDF

Info

Publication number
CN112177167A
CN112177167A CN202011072419.XA CN202011072419A CN112177167A CN 112177167 A CN112177167 A CN 112177167A CN 202011072419 A CN202011072419 A CN 202011072419A CN 112177167 A CN112177167 A CN 112177167A
Authority
CN
China
Prior art keywords
alc
connecting piece
board
wood structure
alc board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011072419.XA
Other languages
Chinese (zh)
Inventor
夷红涛
卢好
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Yuejie Assembly Building Technology Co ltd
Original Assignee
Jiangsu Yuejie Assembly Building Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Yuejie Assembly Building Technology Co ltd filed Critical Jiangsu Yuejie Assembly Building Technology Co ltd
Priority to CN202011072419.XA priority Critical patent/CN112177167A/en
Publication of CN112177167A publication Critical patent/CN112177167A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention discloses an assembling and connecting method of an ALC wallboard and a wood structure main body, which comprises an ALC board, a wood structure and a nut, wherein a grouting layer and a connecting piece are arranged between the ALC board and the wood structure, a screw rod and a screw rod are arranged in the ALC board, and the nut penetrates through the wood structure and the connecting piece and is connected with the screw rod; the assembling and connecting method comprises the following steps: s1: pretreating the ALC board; s2: mounting the connecting piece on the ALC board; s3: a clamping groove for clamping a connecting piece is formed in the wood structure; s4: installing a screw and a screw rod in the ALC plate; s5: the ALC board is arranged on the wood structure, and a nut penetrates through the wood structure and the connecting piece and is connected with the screw; s6: and filling a grouting layer between the ALC board and the wood structure. According to the invention, the connecting piece can be clamped in the ALC strong plate and the wood structure, so that a good connecting and fixing effect is achieved, and the connecting piece can realize multi-directional limiting after being fixed by the bolts.

Description

一种ALC墙板与木结构主体的装配连接方法A kind of assembly and connection method of ALC wall panel and wooden structure main body

技术领域technical field

本发明涉及ALC墙板与木结构装配技术领域,具体是一种ALC墙板与木结构主体的装配连接方法。The invention relates to the technical field of assembly of ALC wall panels and wooden structures, in particular to a method for assembling and connecting an ALC wall panel and a wooden structure main body.

背景技术Background technique

随着社会发展,用工成本不断上涨,同时劳动力却随之日渐短缺,传统的砌筑工艺受到了严重挑战,建筑产业化构成建筑未来发展方向的趋势日渐明朗。建筑产业化的要求之一,就是建筑构部件的通用化和现场施工的装配化、机械化。With the development of society, labor costs continue to rise, and labor is increasingly scarce. The traditional masonry craftsmanship has been seriously challenged, and the trend of building industrialization forming the future development direction of buildings has become increasingly clear. One of the requirements of building industrialization is the generalization of building components and the assembly and mechanization of on-site construction.

ALC即蒸压加气轻质混凝土,是高性能预制混凝土中的其中一种,蒸压加气轻质混凝土是以粉煤灰(或硅砂)、水泥、石灰等为主原料,经过高压蒸汽养护而成的多气孔混凝土成型(内含经过处理的钢筋增强)。蒸压加气轻质混凝土既可做墙体材料,又可做屋面板,是一种性能优越的新型建材,其优点是:具备密度小、质量轻、保温、隔音、抗震、防火等性能。ALC is autoclaved aerated lightweight concrete, which is one of high-performance precast concrete. Autoclaved aerated lightweight concrete is mainly made of fly ash (or silica sand), cement, lime, etc. The formed porous concrete is formed (including treated steel reinforcement). Autoclaved aerated lightweight concrete can be used as both wall material and roof panel. It is a new type of building material with superior performance.

现有的ALC墙板与木结构在装配时,其连接强度不高,连接处容易松动,使用较为不便。When the existing ALC wall panel and the wood structure are assembled, the connection strength is not high, and the connection is easy to loosen, which is inconvenient to use.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于提供一种ALC墙板与木结构主体的装配连接方法,以解决现有技术中的问题。The purpose of the present invention is to provide a method for assembling and connecting an ALC wall panel and a wooden structure main body, so as to solve the problems in the prior art.

为实现上述目的,本发明提供如下技术方案:一种ALC墙板与木结构主体的装配连接方法,包括ALC板、木结构和螺母,所述ALC板和木结构之间设置有灌浆层和连接件,所述ALC板内设置有螺杆和丝杆,所述螺母贯穿木结构和连接件并与螺杆连接;其装配连接方法包括以下步骤:In order to achieve the above object, the present invention provides the following technical solutions: a method for assembling and connecting an ALC wall panel and a wooden structure main body, comprising an ALC board, a wooden structure and a nut, and a grouting layer and a connection are provided between the ALC board and the wooden structure. The ALC board is provided with a screw rod and a screw rod, and the nut penetrates the wooden structure and the connecting piece and is connected with the screw rod; its assembly and connection method includes the following steps:

S1:ALC板的预处理;S1: Pretreatment of ALC board;

S2:将连接件安装在ALC板上;S2: Install the connector on the ALC board;

S3:将木结构上开设有供连接件卡接的卡槽;S3: open the wooden structure with a card slot for the connector to be connected;

S4:将ALC板内安装螺杆和丝杆;S4: Install the screw and lead screw in the ALC board;

S5:将ALC板安装在木结构上,并采用螺母贯穿木结构和连接件并与螺杆连接;S5: Install the ALC board on the wooden structure, and use the nut to penetrate the wooden structure and the connecting piece and connect with the screw;

S6:将ALC板与木结构之间填充灌浆层。S6: Fill the grouting layer between the ALC board and the wooden structure.

优选的,所述连接件主要由卡板和限位板组成,所述限位板两端设置为弯折结构,所述限位板顶端的两侧均安装有卡板,所述限位板两侧的弯折结构上均开设有第一螺栓孔,所述限位板顶端开设有第二螺栓孔。Preferably, the connecting piece is mainly composed of a clamp plate and a limit plate, the two ends of the limit plate are arranged in a bending structure, and the clamp plates are installed on both sides of the top of the limit plate, and the limit plate The bending structures on both sides are provided with first bolt holes, and the top end of the limiting plate is provided with second bolt holes.

优选的,所述步骤S1中ALC板的预处理是将ALC板切割成所需的尺寸,切割前需要弹线定位,然后通过切割设备按照弹线进行切割。Preferably, the pretreatment of the ALC board in the step S1 is to cut the ALC board into a required size, and the elastic wire needs to be positioned before cutting, and then the cutting equipment is used to cut according to the elastic wire.

优选的,所述步骤S2中连接件的安装是将连接件卡在ALC板上,并将连接件两侧的弯折结构通过螺栓固定在ALC板上。Preferably, the installation of the connector in the step S2 is to clamp the connector on the ALC board, and fix the bending structures on both sides of the connector on the ALC board by bolts.

优选的,所述步骤S3中开设卡槽之前,需要测量卡板位于木结构处的位置,然后对开设的卡槽进行划线定位,且开设的卡槽略小于卡板的尺寸,使卡板与卡槽之间通过过盈配合。Preferably, before opening the card slot in the step S3, it is necessary to measure the position of the card board at the wooden structure, and then scribe and locate the opened card slot, and the opened card slot is slightly smaller than the size of the card board, so that the card board There is an interference fit with the card slot.

优选的,所述步骤S4中ALC板内安装螺杆和丝杆,是将螺杆和丝杆倾斜安装,倾斜角度设置为60°-80°,相邻螺杆和丝杆之间对称安装。Preferably, in the step S4, the screw and the lead screw are installed in the ALC board by tilting the screw and the lead screw.

优选的,所述步骤S5中ALC板安装在木结构上,需要将连接件的卡板对准木结构的卡槽。Preferably, in the step S5, when the ALC board is installed on the wooden structure, it is necessary to align the card board of the connector with the card slot of the wooden structure.

优选的,所述步骤S6中在填充灌浆层之前,需要在ALC板上安装碱性玻纤网格布,所述灌浆层采用粘粘剂。Preferably, in the step S6, before filling the grouting layer, it is necessary to install an alkaline glass fiber mesh cloth on the ALC board, and the grouting layer adopts an adhesive.

与现有技术相比,本发明的有益效果是:Compared with the prior art, the beneficial effects of the present invention are:

1、通过采用连接件,且连接件主要由卡板和限位板组成,限位板两端设置为弯折结构,限位板顶端的两侧均安装有卡板;使得连接件可卡在ALC强板和木结构内,起到很好的连接固定作用,且连接件通过螺栓固定后可实现多方向的限位;1. By adopting the connecting piece, and the connecting piece is mainly composed of a clip plate and a limit plate, the two ends of the limit plate are set to be bent structures, and the clip plates are installed on both sides of the top of the limit plate; ALC strong plate and wood structure play a very good role in connection and fixation, and the connector can be fixed in multiple directions after being fixed by bolts;

2、通过采用螺母贯穿木结构和连接件并与螺杆连接,将螺杆和丝杆倾斜安装,倾斜角度设置为60°-80°,相邻螺杆和丝杆之间对称安装;可实现对ALC板和木结构之间的固定;相邻之间的对称安装,使得整体的装配紧固性更好。2. By using the nut to penetrate the wooden structure and the connecting piece and connect with the screw, the screw and the screw rod are installed obliquely, the inclination angle is set to 60°-80°, and the adjacent screw rods and screw rods are installed symmetrically; the ALC board can be installed. The fixation between the wooden structure; the symmetrical installation between adjacent ones makes the overall assembly tighter.

附图说明Description of drawings

附图用来提供对本发明的进一步理解,并且构成说明书的一部分,与本发明的实施例一起用于解释本发明,并不构成对本发明的限制。在附图中:The accompanying drawings are used to provide a further understanding of the present invention, and constitute a part of the specification, and are used to explain the present invention together with the embodiments of the present invention, and do not constitute a limitation to the present invention. In the attached image:

图1为本发明的结构示意图。FIG. 1 is a schematic structural diagram of the present invention.

图2为本发明局部剖视的结构示意图。FIG. 2 is a partial cross-sectional structural schematic diagram of the present invention.

图3为本发明连接件的结构示意图。FIG. 3 is a schematic structural diagram of the connector of the present invention.

图中:1、ALC板;2、灌浆层;3、木结构;4、连接件;5、螺母;6、螺杆;7、丝杆;401、卡板;402、限位板;403、第一螺栓孔;404、第二螺栓孔。In the picture: 1, ALC board; 2, grouting layer; 3, wood structure; 4, connecting piece; 5, nut; 6, screw rod; 7, screw rod; A bolt hole; 404, a second bolt hole.

具体实施方式Detailed ways

为使本发明实施方式的目的、技术方案和优点更加清楚,下面将结合本发明实施方式中的附图,对本发明实施方式中的技术方案进行清楚、完整地描述,显然,所描述的实施方式是本发明一部分实施方式,而不是全部的实施方式。基于本发明中的实施方式,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施方式,都属于本发明保护的范围。因此,以下对在附图中提供的本发明的实施方式的详细描述并非旨在限制要求保护的本发明的范围,而是仅仅表示本发明的选定实施方式。基于本发明中的实施方式,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施方式,都属于本发明保护的范围。In order to make the purposes, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments These are some embodiments of the present invention, but not all of them. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention. Accordingly, the following detailed description of the embodiments of the invention provided in the accompanying drawings is not intended to limit the scope of the invention as claimed, but is merely representative of selected embodiments of the invention. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

请参阅图1-3,本发明实施例中,一种ALC墙板与木结构主体的装配连接方法,包括ALC板1、木结构3和螺母5,所述ALC板1和木结构3之间设置有灌浆层2和连接件4,所述ALC板1内设置有螺杆6和丝杆7,所述螺母5贯穿木结构3和连接件4并与螺杆6连接;其装配连接方法包括以下步骤:Referring to FIGS. 1-3 , in the embodiment of the present invention, a method for assembling and connecting an ALC wall panel and a wooden structure main body includes an ALC board 1 , a wooden structure 3 and a nut 5 . A grouting layer 2 and a connecting piece 4 are provided, a screw 6 and a screw rod 7 are arranged in the ALC board 1, and the nut 5 penetrates through the wooden structure 3 and the connecting piece 4 and is connected with the screw 6; its assembling and connecting method includes the following steps :

S1:ALC板1的预处理;S1: Preprocessing of ALC board 1;

S2:将连接件4安装在ALC板1上;S2: Install the connector 4 on the ALC board 1;

S3:将木结构3上开设有供连接件4卡接的卡槽;S3: the wooden structure 3 is provided with a card slot for the connecting piece 4 to be clipped;

S4:将ALC板1内安装螺杆6和丝杆7;S4: Install the screw 6 and the screw 7 in the ALC board 1;

S5:将ALC板1安装在木结构3上,并采用螺母5贯穿木结构3和连接件4并与螺杆6连接;S5: Install the ALC board 1 on the wooden structure 3, and use the nut 5 to penetrate the wooden structure 3 and the connecting piece 4 and connect with the screw 6;

S6:将ALC板1与木结构3之间填充灌浆层2。S6: Fill the grouting layer 2 between the ALC board 1 and the wooden structure 3.

优选的,所述连接件4主要由卡板401和限位板402组成,所述限位板402两端设置为弯折结构,所述限位板402顶端的两侧均安装有卡板401,所述限位板402两侧的弯折结构上均开设有第一螺栓孔403,所述限位板402顶端开设有第二螺栓孔404。Preferably, the connecting member 4 is mainly composed of a clamping plate 401 and a limiting plate 402 , both ends of the limiting plate 402 are set in a bending structure, and the clamping plate 401 is installed on both sides of the top of the limiting plate 402 The bending structures on both sides of the limiting plate 402 are provided with first bolt holes 403 , and the top of the limiting plate 402 is provided with a second bolt hole 404 .

优选的,所述步骤S1中ALC板1的预处理是将ALC板1切割成所需的尺寸,切割前需要弹线定位,然后通过切割设备按照弹线进行切割。Preferably, the pretreatment of the ALC board 1 in the step S1 is to cut the ALC board 1 into a required size, and the elastic wire needs to be positioned before cutting, and then the cutting equipment is used to cut according to the elastic wire.

优选的,所述步骤S2中连接件4的安装是将连接件4卡在ALC板1上,并将连接件4两侧的弯折结构通过螺栓固定在ALC板1上。Preferably, the installation of the connector 4 in the step S2 is to clamp the connector 4 on the ALC board 1 , and fix the bending structures on both sides of the connector 4 on the ALC board 1 by bolts.

优选的,所述步骤S3中开设卡槽之前,需要测量卡板401位于木结构3处的位置,然后对开设的卡槽进行划线定位,且开设的卡槽略小于卡板401的尺寸,使卡板401与卡槽之间通过过盈配合。Preferably, before opening the card slot in the step S3, it is necessary to measure the position of the card board 401 at the wooden structure 3, and then scribe and locate the opened card slot, and the opened card slot is slightly smaller than the size of the card board 401, Interference fit is used between the card board 401 and the card slot.

优选的,所述步骤S4中ALC板1内安装螺杆6和丝杆7,是将螺杆6和丝杆7倾斜安装,倾斜角度设置为60°-80°,相邻螺杆6和丝杆7之间对称安装。Preferably, in the step S4, the screw 6 and the screw 7 are installed in the ALC board 1, and the screw 6 and the screw 7 are installed obliquely, and the inclination angle is set to 60°-80°. Symmetrical installation.

优选的,所述步骤S5中ALC板1安装在木结构3上,需要将连接件4的卡板401对准木结构3的卡槽。Preferably, in the step S5, when the ALC board 1 is installed on the wooden structure 3, the clamping plate 401 of the connector 4 needs to be aligned with the clamping groove of the wooden structure 3.

优选的,所述步骤S6中在填充灌浆层2之前,需要在ALC板1上安装碱性玻纤网格布,所述灌浆层2采用粘粘剂。Preferably, in the step S6, before filling the grouting layer 2, an alkaline glass fiber mesh cloth needs to be installed on the ALC board 1, and the grouting layer 2 is made of adhesive.

本发明的工作原理是:将ALC板1切割成所需的尺寸,切割前需要弹线定位,然后通过切割设备按照弹线进行切割;将连接件4卡在ALC板1上,并将连接件4两侧的弯折结构通过螺栓固定在ALC板1上;测量卡板401位于木结构3处的位置,然后对开设的卡槽进行划线定位,且开设的卡槽略小于卡板401的尺寸,使卡板401与卡槽之间通过过盈配合;将螺杆6和丝杆7倾斜安装,倾斜角度设置为60°-80°,相邻螺杆6和丝杆7之间对称安装;ALC板1安装在木结构3上,需要将连接件4的卡板401对准木结构3的卡槽;将ALC板1与木结构3之间填充灌浆层2;通过采用连接件,且连接件主要由卡板和限位板组成,限位板两端设置为弯折结构,限位板顶端的两侧均安装有卡板;使得连接件可卡在ALC强板和木结构内,起到很好的连接固定作用,且连接件通过螺栓固定后可实现多方向的限位;通过采用螺母贯穿木结构和连接件并与螺杆连接,将螺杆和丝杆倾斜安装,倾斜角度设置为60°-80°,相邻螺杆和丝杆之间对称安装;可实现对ALC板和木结构之间的固定;相邻之间的对称安装,使得整体的装配紧固性更好。The working principle of the present invention is as follows: the ALC board 1 is cut into the required size, the elastic wire needs to be positioned before cutting, and then the cutting equipment is used to cut according to the elastic wire; the connecting piece 4 is clamped on the ALC board 1, and the connecting piece is 4. The bending structures on both sides are fixed on the ALC board 1 by bolts; the position of the card board 401 at the wooden structure 3 is measured, and then the opened card slot is scribed and positioned, and the opened card slot is slightly smaller than the card board 401. size, so that the card plate 401 and the card slot are fitted by interference; the screw 6 and the screw 7 are installed obliquely, and the inclination angle is set to 60°-80°, and the adjacent screw 6 and the screw 7 are installed symmetrically; ALC When the board 1 is installed on the wooden structure 3, the card board 401 of the connector 4 needs to be aligned with the slot of the wooden structure 3; the grouting layer 2 is filled between the ALC board 1 and the wooden structure 3; It is mainly composed of a card plate and a limit plate. The two ends of the limit plate are set to a bending structure, and the two sides of the top of the limit plate are installed with card plates; Good connection and fixation, and the connector can be fixed in multiple directions after being fixed by bolts; by using a nut to penetrate the wooden structure and the connector and connect with the screw, the screw and the screw are installed obliquely, and the inclination angle is set to 60° -80°, symmetrical installation between adjacent screw rods and lead screws; it can realize the fixation between ALC board and wooden structure; symmetrical installation between adjacent ones makes the overall assembly tighter.

最后应说明的是:以上所述仅为本发明的优选实施例而已,并不用于限制本发明,尽管参照前述实施例对本发明进行了详细的说明,对于本领域的技术人员来说,其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。Finally, it should be noted that the above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Although the present invention has been described in detail with reference to the foregoing embodiments, for those skilled in the art, the The technical solutions described in the foregoing embodiments may be modified, or some technical features thereof may be equivalently replaced. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.

Claims (8)

1. The method for assembling and connecting the ALC wallboard and the wood structure main body comprises an ALC board (1), a wood structure (3) and a nut (5), and is characterized in that: a grouting layer (2) and a connecting piece (4) are arranged between the ALC board (1) and the wood structure (3), a screw rod (6) and a screw rod (7) are arranged in the ALC board (1), and a nut (5) penetrates through the wood structure (3) and the connecting piece (4) and is connected with the screw rod (6); the assembling and connecting method comprises the following steps:
s1: pretreating the ALC board (1);
s2: mounting the connecting piece (4) on the ALC board (1);
s3: a clamping groove for clamping the connecting piece (4) is formed in the wood structure (3);
s4: a screw rod (6) and a screw rod (7) are arranged in the ALC plate (1);
s5: the ALC board (1) is arranged on the wood structure (3), and a nut (5) penetrates through the wood structure (3) and the connecting piece (4) and is connected with the screw rod (6);
s6: and filling a grouting layer (2) between the ALC board (1) and the wood structure (3).
2. The method for assembling and connecting an ALC wallboard to a wood structural body of claim 1, wherein: the connecting piece (4) mainly comprises a clamping plate (401) and a limiting plate (402), wherein two ends of the limiting plate (402) are arranged to be bent structures, the clamping plate (401) is installed on two sides of the top end of the limiting plate (402), first bolt holes (403) are formed in the bent structures on the two sides of the limiting plate (402), and second bolt holes (404) are formed in the top end of the limiting plate (402).
3. The method for assembling and connecting an ALC wallboard to a wood structural body of claim 1, wherein: the ALC board (1) is preprocessed in step S1 by cutting the ALC board (1) to a desired size, positioning with a spring wire before cutting, and then cutting with a cutting device according to the spring wire.
4. The method for assembling and connecting an ALC wallboard to a wood structural body of claim 2, wherein: in the step S2, the connecting piece (4) is installed by clamping the connecting piece (4) on the ALC board (1) and fixing the bending structures at two sides of the connecting piece (4) on the ALC board (1) through bolts.
5. The method for assembling and connecting an ALC wallboard to a wood structural body of claim 2, wherein: before the clamping groove is formed in the step S3, the position of the clamping plate (401) located at the wood structure (3) needs to be measured, then the formed clamping groove is scribed and located, and the formed clamping groove is slightly smaller than the size of the clamping plate (401), so that the clamping plate (401) and the clamping groove are in interference fit.
6. The method for assembling and connecting the ALC wallboard with the wood structural body of claim 1 or 2, wherein: and in the step S4, the screw rods (6) and the screw rods (7) are arranged in the ALC plate (1), the screw rods (6) and the screw rods (7) are obliquely arranged, the inclination angle is set to be 60-80 degrees, and the adjacent screw rods (6) and the screw rods (7) are symmetrically arranged.
7. The method for assembling and connecting an ALC wallboard to a wood structural body of claim 2, wherein: in the step S5, the ALC board (1) is mounted on the wood structure (3), and the clamping board (401) of the connecting piece (4) needs to be aligned with the clamping groove of the wood structure (3).
8. The method for assembling and connecting an ALC wallboard to a wood structural body of claim 1, wherein: in the step S6, before filling the grouting layer (2), it is necessary to install the alkali glass fiber mesh cloth on the ALC board (1), and the grouting layer (2) adopts an adhesive.
CN202011072419.XA 2020-10-09 2020-10-09 A kind of assembly and connection method of ALC wall panel and wooden structure main body Pending CN112177167A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011072419.XA CN112177167A (en) 2020-10-09 2020-10-09 A kind of assembly and connection method of ALC wall panel and wooden structure main body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011072419.XA CN112177167A (en) 2020-10-09 2020-10-09 A kind of assembly and connection method of ALC wall panel and wooden structure main body

Publications (1)

Publication Number Publication Date
CN112177167A true CN112177167A (en) 2021-01-05

Family

ID=73948581

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011072419.XA Pending CN112177167A (en) 2020-10-09 2020-10-09 A kind of assembly and connection method of ALC wall panel and wooden structure main body

Country Status (1)

Country Link
CN (1) CN112177167A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113323195A (en) * 2021-05-21 2021-08-31 中建科工集团有限公司 Connecting piece, ALC (automatic level control) installation node structure and construction method

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003119900A (en) * 2001-10-16 2003-04-23 Nobuo Kinoshita Joist hanger, manufacturing method therefor, and connection device
JP2003171989A (en) * 2001-12-07 2003-06-20 Minoru Hatanaka Building steel connecting member and method of connecting building steel using it
JP2004211455A (en) * 2003-01-07 2004-07-29 Porasu Kurashi Kagaku Kenkyusho:Kk Joining hardware for building
JP4020922B2 (en) * 2005-05-24 2007-12-12 株式会社ポラス暮し科学研究所 Joint structure of wood members
JP2009150206A (en) * 2007-11-28 2009-07-09 Sgc:Kk Bonding hardware and shaft structure
CN201746938U (en) * 2010-06-25 2011-02-16 珠海市瑞铭建筑装饰工程有限公司 Connecting structure for thin-wall C-shaped steel
CN204456455U (en) * 2015-01-26 2015-07-08 苏州新巢木结构系统工程有限公司 A kind of steady type column cap connector be applied in wooden construction
CN107419801A (en) * 2017-04-17 2017-12-01 浙江普天集成房屋有限公司 A kind of assembled individual layer ALC wood connecting building and its construction method and ALC board manufacturing methods
CN110565860A (en) * 2019-09-27 2019-12-13 南京工业大学 connecting system of prefabricated wood-concrete combined structure
CN111155659A (en) * 2020-01-22 2020-05-15 哈尔滨工业大学 Connection node and crack identification method
CN210713206U (en) * 2019-05-07 2020-06-09 胡兴明 Timber structure passive house secondary beam connection structure
CN111706088A (en) * 2020-06-23 2020-09-25 中建西部建设建材科学研究院有限公司 A detachable wall panel connector and its rapid installation process

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003119900A (en) * 2001-10-16 2003-04-23 Nobuo Kinoshita Joist hanger, manufacturing method therefor, and connection device
JP2003171989A (en) * 2001-12-07 2003-06-20 Minoru Hatanaka Building steel connecting member and method of connecting building steel using it
JP2004211455A (en) * 2003-01-07 2004-07-29 Porasu Kurashi Kagaku Kenkyusho:Kk Joining hardware for building
JP4020922B2 (en) * 2005-05-24 2007-12-12 株式会社ポラス暮し科学研究所 Joint structure of wood members
JP2009150206A (en) * 2007-11-28 2009-07-09 Sgc:Kk Bonding hardware and shaft structure
CN201746938U (en) * 2010-06-25 2011-02-16 珠海市瑞铭建筑装饰工程有限公司 Connecting structure for thin-wall C-shaped steel
CN204456455U (en) * 2015-01-26 2015-07-08 苏州新巢木结构系统工程有限公司 A kind of steady type column cap connector be applied in wooden construction
CN107419801A (en) * 2017-04-17 2017-12-01 浙江普天集成房屋有限公司 A kind of assembled individual layer ALC wood connecting building and its construction method and ALC board manufacturing methods
CN210713206U (en) * 2019-05-07 2020-06-09 胡兴明 Timber structure passive house secondary beam connection structure
CN110565860A (en) * 2019-09-27 2019-12-13 南京工业大学 connecting system of prefabricated wood-concrete combined structure
CN111155659A (en) * 2020-01-22 2020-05-15 哈尔滨工业大学 Connection node and crack identification method
CN111706088A (en) * 2020-06-23 2020-09-25 中建西部建设建材科学研究院有限公司 A detachable wall panel connector and its rapid installation process

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113323195A (en) * 2021-05-21 2021-08-31 中建科工集团有限公司 Connecting piece, ALC (automatic level control) installation node structure and construction method

Similar Documents

Publication Publication Date Title
CN112177167A (en) A kind of assembly and connection method of ALC wall panel and wooden structure main body
CN221567694U (en) Fully assembled steel-concrete structure roof
CN220666627U (en) A glass curtain wall that is easy to splice and construct
CN111997234A (en) Novel ALC plate steel structure antidetonation connected node
CN218628293U (en) Assembled building assembly is with preventing skew detection device
CN111335487A (en) Assembled smoke-blocking vertical wall structure, construction method thereof and glass installation auxiliary part
CN112832477B (en) An exterior wall concrete hanging board
CN108661212B (en) Partition plate installation connecting piece
CN217399991U (en) External hanging connection structure of composite wall board
CN206971539U (en) A kind of prefabricated assembled steel construction wallboard connecting component
CN211774644U (en) ALC panel convenient to installation and concatenation connection structure thereof
CN222796952U (en) A lateral installation structure of ALC strips
CN110984617B (en) Building structure's reinforcement connecting device
CN216810425U (en) Shear wall convenient to location installation
CN217480503U (en) Externally-hung wallboard installing and connecting structure
CN218091329U (en) An installation structure for fixing railings with ALC wall panels in prefabricated buildings
CN209891626U (en) Composite wallboard capable of being reused in assembly construction
CN218815412U (en) Prefabricated fiber cement high-ductility plate reinforced structure
CN222797086U (en) Glass hanging clamp device, glass hanging clamp system and large glass curtain wall
CN220014080U (en) Sound insulation building board
CN218668271U (en) Waterproof fastener of wallboard and wallboard installing the system
CN217420111U (en) Composite self-insulation external wall panel lower-supporting type connecting structure
CN223226803U (en) Assembled concrete building
CN222909141U (en) A connection structure between a steel structure steel beam and an ALC prefabricated wall panel
CN219060382U (en) An aerated concrete slab fixed pipe clip

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210105

RJ01 Rejection of invention patent application after publication