CN112132427A - Power grid multi-layer planning method considering user side multiple resource access - Google Patents
Power grid multi-layer planning method considering user side multiple resource access Download PDFInfo
- Publication number
- CN112132427A CN112132427A CN202010946881.1A CN202010946881A CN112132427A CN 112132427 A CN112132427 A CN 112132427A CN 202010946881 A CN202010946881 A CN 202010946881A CN 112132427 A CN112132427 A CN 112132427A
- Authority
- CN
- China
- Prior art keywords
- line
- power
- planning
- constraint
- photovoltaic
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 67
- 238000004422 calculation algorithm Methods 0.000 claims abstract description 18
- 238000009434 installation Methods 0.000 claims abstract description 9
- 238000010276 construction Methods 0.000 claims description 65
- 239000000243 solution Substances 0.000 claims description 36
- 239000000126 substance Substances 0.000 claims description 28
- 238000013178 mathematical model Methods 0.000 claims description 16
- 230000005611 electricity Effects 0.000 claims description 8
- 238000007689 inspection Methods 0.000 claims description 8
- 239000007983 Tris buffer Substances 0.000 claims description 4
- 230000002035 prolonged effect Effects 0.000 claims description 4
- 238000013461 design Methods 0.000 abstract description 8
- 238000004364 calculation method Methods 0.000 abstract description 5
- 238000005457 optimization Methods 0.000 description 10
- 238000013459 approach Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 230000010485 coping Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005315 distribution function Methods 0.000 description 1
- 230000009977 dual effect Effects 0.000 description 1
- 238000003672 processing method Methods 0.000 description 1
- 238000004088 simulation Methods 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06315—Needs-based resource requirements planning or analysis
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/008—Circuit arrangements for ac mains or ac distribution networks involving trading of energy or energy transmission rights
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/38—Arrangements for parallely feeding a single network by two or more generators, converters or transformers
- H02J3/381—Dispersed generators
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2203/00—Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
- H02J2203/10—Power transmission or distribution systems management focussing at grid-level, e.g. load flow analysis, node profile computation, meshed network optimisation, active network management or spinning reserve management
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2203/00—Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
- H02J2203/20—Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2300/00—Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation
- H02J2300/20—The dispersed energy generation being of renewable origin
- H02J2300/22—The renewable source being solar energy
- H02J2300/24—The renewable source being solar energy of photovoltaic origin
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2300/00—Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation
- H02J2300/20—The dispersed energy generation being of renewable origin
- H02J2300/28—The renewable source being wind energy
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2300/00—Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation
- H02J2300/40—Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation wherein a plurality of decentralised, dispersed or local energy generation technologies are operated simultaneously
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/50—Photovoltaic [PV] energy
- Y02E10/56—Power conversion systems, e.g. maximum power point trackers
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Economics (AREA)
- Power Engineering (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- General Physics & Mathematics (AREA)
- Health & Medical Sciences (AREA)
- Marketing (AREA)
- Theoretical Computer Science (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Water Supply & Treatment (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Public Health (AREA)
- Game Theory and Decision Science (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
A power grid multi-layer planning method considering multiple resource accesses at a user side comprises the following steps: aiming at the uncertainty of various resources at a user side, modeling the uncertainty of fan output, photovoltaic output and load power by adopting a robust optimized box-type uncertain set; aiming at the uncertainty of adapting to various resources at a user side, and taking the access positions, the installation number and the newly-built grid structure of the distributed power supplies as investment decision content, establishing a double-layer power distribution network planning model considering the whole life cycle investment cost and the operation cost of a planning scheme; providing a two-stage robust planning method for a power distribution network based on an extreme scene method; and splitting the two-stage robust planning problem into main and sub problems through an improved C & CG algorithm based on an extreme scene method to solve the main and sub problems in an iterative manner. The design can improve the robustness and economy of power distribution network planning and the capability of the power distribution network for dealing with uncertain risks, and the model is simple to solve and high in calculation efficiency.
Description
Technical Field
The invention relates to the field of power distribution network planning, in particular to a power distribution network multilayer planning method considering multiple resource accesses of a user side.
Background
In recent years, with the large-scale access of various resources such as distributed power sources and electric vehicles to a power distribution network, uncertain factors of the power distribution network can challenge the planning and operation of the power distribution network. At present, the processing method for uncertain factors mainly comprises random optimization, opportunity constraint optimization and robust optimization. Although the random optimization can simulate daily uncertain scenes, the random optimization is difficult to deal with extreme scenes; opportunity constraint optimization requires calculation of an accurate probability distribution function of an uncertain variable, and data acquisition difficulty is high; the robust optimization adopts an interval to describe the uncertainty of parameters, so that the requirements on the accuracy probability and the fuzzy membership degree of the uncertain parameters are avoided, and the robustness of the power distribution network is improved.
Disclosure of Invention
The invention aims to overcome the defects and problems of low reliability and economy of power distribution network planning, complex model solution and low efficiency in the prior art, and provides a power grid multi-layer planning method which has high reliability and economy of power distribution network planning, simple model solution and high efficiency and considers the access of various resources at a user side.
In order to achieve the above purpose, the technical solution of the invention is as follows: a power grid multi-layer planning method considering multiple resource accesses at a user side comprises the following steps:
A. aiming at the uncertainty of various resources at a user side, modeling the uncertainty of fan output, photovoltaic output and load power by adopting a robust optimized box-type uncertain set;
B. aiming at the uncertainty of adapting to various resources at a user side, and taking the access positions, the installation number and the newly-built grid structure of the distributed power supplies as investment decision content, establishing a double-layer power distribution network planning model considering the whole life cycle investment cost and the operation cost of a planning scheme, wherein a planning layer objective function is the lowest total construction cost and operation cost, and an operation layer objective function is the lowest operation cost under the determined planning scheme;
C. an extreme scene method is adopted to process uncertainty factors of a double-layer power distribution network planning model, and a power distribution network two-stage robust planning method based on the extreme scene method is provided; the first stage is a planning construction stage, and the access positions and the installation number of the distributed power supplies and the newly-built positions of the lines are determined; the second stage is an operation stage, under the planning scheme of the first stage, the operation condition of the power distribution network under each limit scene is simulated, and the worst scene is optimized;
D. the method comprises the steps of splitting a two-stage robust planning problem into main and sub problems through an improved C & CG algorithm based on a limit scene method, iteratively solving the main problem, solving an optimal planning scheme under a single limit scene through the main problem, transmitting the optimal planning scheme to the sub problems, searching the worst scene under the current planning scheme through the limit scene method through the sub problems, influencing main problem decision through adding relevant operation constraint conditions of the worst scene to the main problem, and finally solving the optimal solution of the iterative robust planning problem through the main and sub problems.
In the step a, uncertainty of fan output, photovoltaic output and load power is represented as:
wherein the content of the first and second substances,respectively representing fan output data, photovoltaic output data and load power requirements;respectively predicting the output of a fan, the photovoltaic output and the load power; beta is a1、β2、β3The maximum ranges of the possible deviation predicted values of the fan output, the photovoltaic output and the load power are respectively.
In the step B, the double-layer power distribution network planning model is expressed by a mathematical model as follows:
wherein, CINVThe investment cost; cOPEFor operating costs; g (-) and H (-) are planning layer constraints; g (-) and f (-) are constraint conditions of the operation layer; x is the number ofinvDetermining the commissioning of the lines and the distributed power supply for constructing variables; x is the number ofopeOperating variables including line power and node voltage; xi is uncertainty parameter of fan, photovoltaic and load, and is mainly concentrated on the operation layer.
In step B, the planning layer objective function is min F ═ CINV+COPEThe method specifically comprises the following steps:
CINV=CWTG+CPVG+CLINE
wherein subscript j represents the node number; subscript ij denotes a line between node i and node j; cLINE、CWTG、CPVGRespectively converting the total construction cost of the line, the fan and the photovoltaic into the total construction cost of the line, the fan and the photovoltaic; z is the inflation rate for the cargo; y isLINE、YWTG、YPVGThe service lives of the line, the fan and the photovoltaic are respectively prolonged;the construction cost per kilometer of the line; c. CWTG、cPVGThe construction cost of each fan and each photovoltaic unit is respectively the construction cost of each fan and each photovoltaic unit; l isijThe length of each alternative line; omegaLINE、ΩWTG、ΩPVGRespectively obtaining a candidate set of lines to be built, a candidate node set of fans to be built and a candidate node set of photovoltaic cells to be built;is a variable of 0 to 1, determines whether a line, a fan and a photovoltaic are put into operation or not, and for the established line,is 1;
wherein T is the number of time periods of operation in one day; Δ t is the time of each time interval;the electricity price for purchasing electricity from the main network for the t period; c. Closs、cLS、cLW、cLPVRespectively unit network loss cost, load loss cost, wind abandoning cost and light abandoning cost;respectively obtaining main network output, loss load power, fan output data, fan actual output, photovoltaic output data and photovoltaic actual output; i isij,tIs the line current; r isijIs a line electric group; omegaTRIs a collection of transformer nodes; elineCollecting all the lines which are built and are to be built for the power distribution network; omegaENSIs the set of all load nodes;
the running layer objective function is:
min f=COPE。
in the step B, the constraint conditions of the planning layer comprise equipment investment construction constraint, network radial constraint and network connectivity constraint;
assuming that the maximum number of the connected fans and the maximum number of the photovoltaic circuits are specified in the power distribution network planning, and the number of the newly-built lines is also determined, the equipment investment construction constraint is specifically as follows:
wherein N isWTGSetting the maximum number of the newly built fans; n is a radical ofPVGSetting the maximum number of newly-built photovoltaic cells; n is a radical ofLINEPredicting the number of newly built lines;
in order to ensure the connectivity of each node of the planned power grid and avoid the operation of the roundabout, the connectivity inspection and radial inspection of the topological structure of the planned distribution network are required.
In the step B, the constraint conditions of the operation layer comprise node power balance constraint, line voltage balance constraint, line capacity constraint, transformer capacity constraint, safety constraint, distributed power supply output constraint and loss load constraint;
to eliminate non-linear terms in the AC power flow, for the current Iij,tSum voltage Uj,tThrough variable replacement and second-order cone relaxation, the nonlinear constraint in the alternating current power flow is converted into a second-order cone constraint:
wherein the content of the first and second substances,is the square of the current value of line ij;is the square of the voltage value of node j;
then the run level constraints are:
node power balance constraint:
wherein, (j) is a line set with the node j as a head end; k is the end node of the line jk; pi (j) is a line set taking the node j as a tail end; omegaFIs a collection of load nodes; pjk,tThe active power transmitted by the line jk at the moment t; qjk,tThe reactive power transmitted by the line jk at the moment t; pij,t、Qij,tRespectively the active power and the reactive power transmitted by the line ij at the moment t;respectively the active load demand and the reactive load demand of the node j; x is the number ofijIs the reactance value of line ij;the main network reactive power, the fan reactive power, the photovoltaic reactive power and the loss load reactive power are respectively;is the square of the voltage value of the node i;
line voltage balance constraint:
wherein M is a large enough solidCounting; elineCollecting all the lines which are built and are to be built for the power distribution network;
and (3) line capacity constraint:
wherein the content of the first and second substances,the maximum current-carrying capacity of the line;
and (3) transformer capacity constraint:
wherein the content of the first and second substances,minimum active and reactive output thresholds of the transformer are respectively set;the maximum active and reactive output thresholds of the transformer are respectively set;
safety restraint:
wherein the content of the first and second substances,is the minimum value of the node voltage;is the maximum value of the node voltage;is the maximum line current;
and (3) output constraint of the distributed power supply:
and (4) load loss constraint:
wherein the content of the first and second substances,is the maximum load loss percentage for node j;is the load power factor.
In the step C, a specific mathematical model of the two-stage robust planning of the power distribution network is as follows:
Dx≤d
Ex=e
wherein x is a construction variable of a line, a fan and a photovoltaic; subscript s denotes the limit scene number; n is a radical ofsRepresenting the number of limit scenes; xisRepresenting values of fan output, photovoltaic output and load power under a limit scene s; y issRepresenting the operation decision variables of the line power and the voltage under the limit scene; ax is the construction cost; bys+CξsThe running cost under the limit scene s; A. b, C, D, E, F, G, H, L, M, D, E, F, G, H are coefficient matrixes.
In step D, the mathematical model of the main problem is as follows:
Dx≤d
Ex=e
wherein x is a construction variable of a line, a fan and a photovoltaic; eta is the actual operation cost of the power distribution network; n is C&The iteration times of the CG algorithm; k is a radical ofmNumbering the limit scenes selected in the mth iteration;as extreme scene kmRunning decision variables;as extreme scene kmAnd values of uncertain variables of lower fan output, photovoltaic output and load power.
In step D, the mathematical model of the subproblem is:
wherein the content of the first and second substances,and constructing and planning an optimal solution for the main problem in the nth iteration.
In the step D, the specific flow of the improved C & CG algorithm based on the extreme scene method is as follows:
(1) setting a lower bound LB ═ infinity, an upper bound UB +∞, and an algorithm iteration number n ═ 1;
(2) solving the main problem to obtain the optimal solution of the construction planAnd operating costs under the scenarioAnd updating the lower bound value
(3) Fixed construction plan optimal solutionSolving the sub-problems to obtain the sub-problems under all limit scenes
If all the sub-problems in the extreme scenes have solutions, finding the maximum value of feasible solutions in all the scenesObtaining the number s of the limit scene and updating the upper bound value
If the subproblem is not feasible under the limit scene s, the current worst limit scene is s;
(4) if UB-LB <, the convergence precision is given, then the iteration is finished, and the optimal solution of the current construction plan is obtainedOtherwise, updating the worst limit scene s under the current planning condition, and adding the constraint condition corresponding to the scene to the main problem;
(5) and (4) returning to the step (2) when n is n + 1.
Compared with the prior art, the invention has the beneficial effects that:
the power grid multilayer planning method considering the access of various resources at the user side can effectively improve the capability of a power distribution network for coping with the uncertainty of various resources at the user side, simultaneously reduces the operating cost of the power distribution network, and considers the economy of power distribution network planning; in addition, compared with a two-stage robust programming model adopting a conventional method, the design is simpler in solution and higher in calculation efficiency. According to the design, a power distribution network planning model considering various resources at the user side is established, scientific planning basis is provided for power distribution network planning personnel, and the reliability and economy of power distribution network planning are improved.
Drawings
Fig. 1 is a flowchart of a power grid multi-layer planning method considering multiple resource accesses at a user side according to the present invention.
FIG. 2 is a schematic diagram of a limit scenario approach.
Fig. 3 is a flow chart of a C & CG algorithm based on the extreme scene method.
Fig. 4 is a power distribution network planning scheme obtained according to simulation calculation in the present invention.
Detailed Description
The present invention will be described in further detail with reference to the following description and embodiments in conjunction with the accompanying drawings.
Referring to fig. 1 to 4, a method for multi-layer planning of a power grid considering multiple resource accesses at a user side includes the following steps:
A. aiming at the uncertainty of various resources at a user side, modeling the uncertainty of fan output, photovoltaic output and load power by adopting a robust optimized box-type uncertain set;
B. aiming at the uncertainty of adapting to various resources at a user side, and taking the access positions, the installation number and the newly-built grid structure of the distributed power supplies as investment decision content, establishing a double-layer power distribution network planning model considering the whole life cycle investment cost and the operation cost of a planning scheme, wherein a planning layer objective function is the lowest total construction cost and operation cost, and an operation layer objective function is the lowest operation cost under the determined planning scheme;
C. an extreme scene method is adopted to process uncertainty factors of a double-layer power distribution network planning model, and a power distribution network two-stage robust planning method based on the extreme scene method is provided; the first stage is a planning construction stage, and the access positions and the installation number of the distributed power supplies and the newly-built positions of the lines are determined; the second stage is an operation stage, under the planning scheme of the first stage, the operation condition of the power distribution network under each limit scene is simulated, and the worst scene is optimized;
D. the method comprises the steps of splitting a two-stage robust planning problem into main and sub problems through an improved C & CG algorithm based on a limit scene method, iteratively solving the main problem, solving an optimal planning scheme under a single limit scene through the main problem, transmitting the optimal planning scheme to the sub problems, searching the worst scene under the current planning scheme through the limit scene method through the sub problems, influencing main problem decision through adding relevant operation constraint conditions of the worst scene to the main problem, and finally solving the optimal solution of the iterative robust planning problem through the main and sub problems.
In the step a, uncertainty of fan output, photovoltaic output and load power is represented as:
wherein the content of the first and second substances,respectively representing fan output data, photovoltaic output data and load power requirements;respectively predicting the output of a fan, the photovoltaic output and the load power; beta is a1、β2、β3The maximum ranges of the possible deviation predicted values of the fan output, the photovoltaic output and the load power are respectively.
In the step B, the double-layer power distribution network planning model is expressed by a mathematical model as follows:
wherein, CINVThe investment cost; cOPEFor operating costs;g (-) and H (-) are planning layer constraints; g (-) and f (-) are constraint conditions of the operation layer; x is the number ofinvDetermining the commissioning of the lines and the distributed power supply for constructing variables; x is the number ofopeOperating variables including line power and node voltage; xi is uncertainty parameter of fan, photovoltaic and load, and is mainly concentrated on the operation layer.
In step B, the planning layer objective function is min F ═ CINV+COPEThe method specifically comprises the following steps:
CINV=CWTG+CPVG+CLINE
wherein subscript j represents the node number; subscript ij denotes a line between node i and node j; cLINE、CWTG、CPVGRespectively converting the total construction cost of the line, the fan and the photovoltaic into the total construction cost of the line, the fan and the photovoltaic; z is the inflation rate for the cargo; y isLINE、YWTG、YPVGThe service lives of the line, the fan and the photovoltaic are respectively prolonged;the construction cost per kilometer of the line; c. CWTG、cPVGThe construction cost of each fan and each photovoltaic unit is respectively the construction cost of each fan and each photovoltaic unit; l isijThe length of each alternative line; omegaLNE、ΩWTG、ΩPVGRespectively obtaining a candidate set of lines to be built, a candidate node set of fans to be built and a candidate node set of photovoltaic cells to be built;is a variable of 0 to 1, determines whether a line, a fan and a photovoltaic are put into operation or not, and for the established line,is 1;
wherein T is the number of time periods of operation in one day; Δ t is the time of each time interval;the electricity price for purchasing electricity from the main network for the t period; c. Closs、cLS、cLW、cLPVRespectively unit network loss cost, load loss cost, wind abandoning cost and light abandoning cost;respectively obtaining main network output, loss load power, fan output data, fan actual output, photovoltaic output data and photovoltaic actual output; i isij,tIs the line current; r isijIs a line electric group; omegaTRIs a collection of transformer nodes; elineCollecting all the lines which are built and are to be built for the power distribution network; omegaENSIs the set of all load nodes;
the running layer objective function is:
min f=COPE。
in the step B, the constraint conditions of the planning layer comprise equipment investment construction constraint, network radial constraint and network connectivity constraint;
assuming that the maximum number of the connected fans and the maximum number of the photovoltaic circuits are specified in the power distribution network planning, and the number of the newly-built lines is also determined, the equipment investment construction constraint is specifically as follows:
wherein N isWTGSetting the maximum number of the newly built fans; n is a radical ofPVGSetting the maximum number of newly-built photovoltaic cells; n is a radical ofLINEPredicting the number of newly built lines;
in order to ensure the connectivity of each node of the planned power grid and avoid the operation of the roundabout, the connectivity inspection and radial inspection of the topological structure of the planned distribution network are required.
In the step B, the constraint conditions of the operation layer comprise node power balance constraint, line voltage balance constraint, line capacity constraint, transformer capacity constraint, safety constraint, distributed power supply output constraint and loss load constraint;
to eliminate non-linear terms in the AC power flow, for the current Iij,tSum voltage Uj,tThrough variable replacement and second-order cone relaxation, the nonlinear constraint in the alternating current power flow is converted into a second-order cone constraint:
wherein the content of the first and second substances,is the square of the current value of line ij;is the square of the voltage value of node j;
then the run level constraints are:
node power balance constraint:
wherein, (j) is a line set with the node j as a head end; k is the end node of the line jk; pi (j) is a line set taking the node j as a tail end; omegaFIs a collection of load nodes; pjk,tThe active power transmitted by the line jk at the moment t; qjk,tThe reactive power transmitted by the line jk at the moment t; pij,t、Qij,tRespectively the active power and the reactive power transmitted by the line ij at the moment t;respectively the active load demand and the reactive load demand of the node j; x is the number ofijIs the reactance value of line ij;the main network reactive power, the fan reactive power, the photovoltaic reactive power and the loss load reactive power are respectively;is the square of the voltage value of the node i;
line voltage balance constraint:
wherein M is a sufficiently large positive real number; elineFor all the built and to-be-built power distribution networksThe line set of (2);
and (3) line capacity constraint:
wherein the content of the first and second substances,the maximum current-carrying capacity of the line;
and (3) transformer capacity constraint:
wherein the content of the first and second substances,minimum active and reactive output thresholds of the transformer are respectively set;the maximum active and reactive output thresholds of the transformer are respectively set;
safety restraint:
wherein the content of the first and second substances,is the minimum value of the node voltage;is the maximum value of the node voltage;is the maximum line current;
and (3) output constraint of the distributed power supply:
and (4) load loss constraint:
wherein the content of the first and second substances,is the maximum load loss percentage for node j;is the load power factor.
In the step C, a specific mathematical model of the two-stage robust planning of the power distribution network is as follows:
Dx≤d
Ex=e
wherein x is a construction variable of a line, a fan and a photovoltaic; subscript s denotes the limit scene number; n is a radical ofsRepresenting the number of limit scenes; xisRepresenting values of fan output, photovoltaic output and load power under a limit scene s; y issRepresenting the operation decision variables of the line power and the voltage under the limit scene; ax is the construction cost; bys+CξsThe running cost under the limit scene s; A. b, C, D, E, F, G, H, L, M, D, E, F, G, H are coefficient matrixes.
In step D, the mathematical model of the main problem is as follows:
Dx≤d
Ex=e
wherein x is a line,Construction variables of fans and photovoltaics; eta is the actual operation cost of the power distribution network; n is C&The iteration times of the CG algorithm; k is a radical ofmNumbering the limit scenes selected in the mth iteration;as extreme scene kmRunning decision variables;as extreme scene kmAnd values of uncertain variables of lower fan output, photovoltaic output and load power.
In step D, the mathematical model of the subproblem is:
wherein the content of the first and second substances,and constructing and planning an optimal solution for the main problem in the nth iteration.
In the step D, the specific flow of the improved C & CG algorithm based on the extreme scene method is as follows:
(1) setting a lower bound LB ═ infinity, an upper bound UB +∞, and an algorithm iteration number n ═ 1;
(2) solving the main problem to obtain the optimal solution of the construction planAnd operating costs under the scenarioAnd updating the lower bound value
(3) Fixed construction plan optimal solutionSolving the sub-problems to obtain the sub-problems under all limit scenes
If all the sub-problems in the extreme scenes have solutions, finding the maximum value of feasible solutions in all the scenesObtaining the number s of the limit scene and updating the upper bound value
If the subproblem is not feasible under the limit scene s, the current worst limit scene is s;
(4) if UB-LB <, the convergence precision is given, then the iteration is finished, and the optimal solution of the current construction plan is obtainedOtherwise, updating the worst limit scene s under the current planning condition, and adding the constraint condition corresponding to the scene to the main problem;
(5) and (4) returning to the step (2) when n is n + 1.
The principle of the invention is illustrated as follows:
in the step A, a robust optimized box-type uncertain set model is adopted to model uncertainty of user side resources, and user side uncertainty factors such as fan output, photovoltaic output and load power are mainly considered; the robust optimization considers that the wind turbine output, the photovoltaic output and the load power possibly deviate from the predicted value under the actual condition, and the uncertainty is described by adopting an interval.
In the step B, the planning layer determines construction variables and transmits the construction variables to the operation layer, and the operation layer influences planning layer decision by adding operation constraints to the planning layer.
In the step C, error scenes are defined as scenes of fan output, photovoltaic output and load power deviation predicted values, robust optimization must meet operation constraints of all the error scenes, but the number of the error scenes is infinite, and solution cannot be carried out, so that a limit scene method is introduced. The limit scene is defined as a scene in which all uncertain parameters take extreme values, the output time sequence characteristics of all fans, photovoltaic and loads in a power distribution network area are considered to have similarity, and in order to simplify the number of the uncertain parameters, three uncertain factors, namely the fans, the photovoltaic and the loads, are assumed to have the same time sequence characteristics in the area, and eight limit scenes are formed. In convex optimization, an extreme value necessarily exists at a certain endpoint of a polyhedral solution space, and an extreme scene has complete robustness for all error scenes and a construction variable xinvAs long as the operating variable x is adjustedopeThe method can adapt to all limit scenes, and can adapt to all error scenes, so that the robustness of power distribution network planning is ensured.
In the step D, the main problem determines the value of a construction decision variable x of a fan, a photovoltaic, a line and the like, and transmits the value to the sub-problem, and the sub-problem searches the worst scene under the construction condition of the main problem by a limit scene method; solving the running cost of each sub-problem under each limit scene by adopting an enumeration method, wherein if the sub-problems under all the limit scenes are solved, the scene with the largest running cost is the worst scene under the current planning condition; if a certain scene exists, so that no feasible solution exists in the planning, the scene is the worst scene; the sub-problem affects the main problem decision by adding the relevant operational constraints of the severe scenario to the main problem. Compared with the conventional dual method, the sub-problems of each limit scene in the method are linear programming problems without integer variables, and the solution is relatively simple.
Example (b):
referring to fig. 1 to 4, a method for multi-layer planning of a power grid considering multiple resource accesses at a user side includes the following steps:
A. aiming at the uncertainty of various resources at a user side, modeling the uncertainty of fan output, photovoltaic output and load power by adopting a robust optimized box-type uncertain set;
the uncertainty of the fan output, the photovoltaic output and the load power is represented as follows:
wherein the content of the first and second substances,respectively representing fan output data, photovoltaic output data and load power requirements;respectively predicting the output of a fan, the photovoltaic output and the load power; beta is a1、β2、β3The maximum ranges of the predicted values of the possible deviation of the fan output, the photovoltaic output and the load power are respectively analyzed by combining with actual scenes so as to obtain specific output deviation values, and the design beta is1、β2、β3Taking the weight percentage to be 30 percent;
B. aiming at the uncertainty of adapting to various resources at a user side, and taking the access positions, the installation number and the newly-built grid structure of the distributed power supplies as investment decision content, establishing a double-layer power distribution network planning model considering the whole life cycle investment cost and the operation cost of a planning scheme, wherein a planning layer objective function is the lowest total construction cost and operation cost, and an operation layer objective function is the lowest operation cost under the determined planning scheme;
the double-layer power distribution network planning model is expressed by a mathematical model as follows:
wherein, CINVThe investment cost; cOPEFor operating costs; g (-) and H (-) are planning layer constraints; g (-) and f (-) are constraint conditions of the operation layer; x is the number ofinvDetermining the commissioning of the lines and the distributed power supply for constructing variables; x is the number ofopeOperating variables including line power and node voltage; xi is uncertainty parameter of fan, photovoltaic and load, mainly concentrated on the operation layer;
planning a layer objective function to min F ═ CINV+COPEThe method specifically comprises the following steps:
CINV=CWTG+CPVG+CLINE
wherein subscript j represents the node number; subscript ij denotes a line between node i and node j; cLINE、CWTG、CPVGRespectively converting the total construction cost of the line, the fan and the photovoltaic into the total construction cost of the line, the fan and the photovoltaic; z is the inflation rate for the cargo; y isLINE、YWTG、YPVGThe service lives of the line, the fan and the photovoltaic are respectively prolonged;the construction cost per kilometer of the line; c. CWTG、cPVGThe construction cost of each fan and each photovoltaic unit is respectively the construction cost of each fan and each photovoltaic unit; l isijThe length of each alternative line; omegaLINE、ΩWTG、ΩPVGAre respectively candidates of the line to be establishedThe method comprises the steps of collecting, a candidate node set of a fan to be built and a candidate node set of a photovoltaic to be built;is a variable of 0 to 1, determines whether a line, a fan and a photovoltaic are put into operation or not, and for the established line,is 1;
wherein T is the number of time periods of operation in one day; Δ t is the time of each time interval;the electricity price for purchasing electricity from the main network for the t period; c. Closs、cLS、cLW、cLPVRespectively unit network loss cost, load loss cost, wind abandoning cost and light abandoning cost;respectively obtaining main network output, loss load power, fan output data, fan actual output, photovoltaic output data and photovoltaic actual output; i isij,tIs the line current; r isijIs a line electric group; omegaTRIs a collection of transformer nodes; elineCollecting all the lines which are built and are to be built for the power distribution network; omegaENSIs the set of all load nodes;
the running layer objective function is:
min f=COPE;
the planning layer constraint conditions comprise equipment investment construction constraint, network radial constraint and network connectivity constraint;
assuming that the maximum number of the connected fans and the maximum number of the photovoltaic circuits are specified in the power distribution network planning, and the number of the newly-built lines is also determined, the equipment investment construction constraint is specifically as follows:
wherein N isWTGSetting the maximum number of the newly built fans; n is a radical ofPVGSetting the maximum number of newly-built photovoltaic cells; n is a radical ofLINEPredicting the number of newly built lines;
in order to ensure the connectivity of each node of the planned power grid and avoid the operation of a rotary island, the connectivity inspection and radial inspection of the topological structure of the planned distribution network are required;
the operation layer constraint conditions comprise node power balance constraint, line voltage balance constraint, line capacity constraint, transformer capacity constraint, safety constraint, distributed power supply output constraint and loss load constraint;
to eliminate non-linear terms in the AC power flow, for the current Iij,tSum voltage Uj,tThrough variable replacement and second-order cone relaxation, the nonlinear constraint in the alternating current power flow is converted into a second-order cone constraint:
wherein the content of the first and second substances,is the square of the current value of line ij;is the square of the voltage value of node j;
then the run level constraints are:
node power balance constraint:
wherein, (j) is a line set with the node j as a head end; k is the end node of the line jk; pi (j) is a line set taking the node j as a tail end; omegaFIs a collection of load nodes; pjk,tThe active power transmitted by the line jk at the moment t; qjk,tThe reactive power transmitted by the line jk at the moment t; pij,t、Qij,tRespectively the active power and the reactive power transmitted by the line ij at the moment t;respectively the active load demand and the reactive load demand of the node j; x is the number ofijIs the reactance value of line ij;the main network reactive power, the fan reactive power, the photovoltaic reactive power and the loss load reactive power are respectively;is the square of the voltage value of the node i;
line voltage balance constraint:
the quantity level of M is higher than other variables in the formula, the M is a positive real number which is large enough to reduce the operation error, but the calculation efficiency is reduced when the M is too large, and the design M is 100000; elineCollecting all the lines which are built and are to be built for the power distribution network;
and (3) line capacity constraint:
wherein the content of the first and second substances,the maximum current-carrying capacity of the line;
and (3) transformer capacity constraint:
wherein the content of the first and second substances,minimum active and reactive output thresholds of the transformer are respectively set;the maximum active and reactive output thresholds of the transformer are respectively set;
safety restraint:
wherein the content of the first and second substances,is the minimum value of the node voltage;is the maximum value of the node voltage;is the maximum line current;
and (3) output constraint of the distributed power supply:
and (4) load loss constraint:
wherein the content of the first and second substances,is the maximum load loss percentage for node j;is the load power factor;
C. an extreme scene method is adopted to process uncertainty factors of a double-layer power distribution network planning model, and a power distribution network two-stage robust planning method based on the extreme scene method is provided; the first stage is a planning construction stage, and the access positions and the installation number of the distributed power supplies and the newly-built positions of the lines are determined; the second stage is an operation stage, under the planning scheme of the first stage, the operation condition of the power distribution network under each limit scene is simulated, and the worst scene is optimized;
the specific mathematical model of the two-stage robust planning of the power distribution network is as follows:
Dx≤d
Ex=e
wherein x is a construction variable of a line, a fan and a photovoltaic; subscript s denotes the limit scene number; n is a radical ofsRepresenting the number of limit scenes; xisRepresenting values of fan output, photovoltaic output and load power under a limit scene s; y issRepresenting the operation decision variables of the line power and the voltage under the limit scene; ax is the construction cost; bys+CξsThe running cost under the limit scene s; A. b, C, D, E, F, G, H, L, M, D, E, F, G and H are coefficient matrixes;
D. splitting a two-stage robust planning problem into main and sub problems through an improved C & CG algorithm based on a limit scene method, iteratively solving the main problem, solving the optimal planning scheme under a single limit scene by the main problem, transmitting the optimal planning scheme to the sub problems, searching the worst scene under the current planning scheme by the limit scene method by the sub problems, adding relevant operation constraint conditions of the worst scene to the main problem to influence the decision of the main problem, and finally solving the optimal solution of the iterative robust planning problem through the main and sub problems;
the mathematical model of the main problem is:
Dx≤d
Ex=e
wherein x is a construction variable of a line, a fan and a photovoltaic; eta is the actual operation cost of the power distribution network; n is C&The iteration times of the CG algorithm; k is a radical ofmNumbering the limit scenes selected in the mth iteration;as extreme scene kmRunning decision variables;as extreme scene kmValues of uncertain variables of lower fan output, photovoltaic output and load power;
the mathematical model of the subproblem is:
wherein the content of the first and second substances,constructing and planning an optimal solution for the main problem in the nth iteration;
the specific flow of the improved C & CG algorithm based on the extreme scene method is as follows:
(1) setting a lower bound LB ═ infinity, an upper bound UB +∞, and an algorithm iteration number n ═ 1;
(2) solving the main problem to obtain the optimal solution of the construction planAnd operating costs under the scenarioAnd updating the lower bound value
(3) Fixed construction plan optimal solutionSolving the sub-problems to obtain the sub-problems under all limit scenes
If all the sub-problems in the extreme scene have solutions, thenFinding the maximum of feasible solutions under all scenesObtaining the number s of the limit scene and updating the upper bound value
If the subproblem is not feasible under the limit scene s, the current worst limit scene is s;
(4) if UB-LB is less than the given convergence precision, the value is 0.1, the iteration is finished, and the optimal solution of the current construction plan is obtainedOtherwise, updating the worst limit scene s under the current planning condition, and adding the constraint condition corresponding to the scene to the main problem;
(5) and (4) returning to the step (2) when n is n + 1.
In order to test the reliability and effectiveness of the design, under the condition of the same planning condition, the power distribution network is planned by using the design and compared with a power distribution network deterministic planning model, and the conclusion is as follows: the method provided by the design can effectively improve the capability of the power distribution network to cope with uncertainty of various resources at the user side, simultaneously reduces the operating cost of the power distribution network, and considers the economy of power distribution network planning.
Claims (10)
1. A power grid multi-layer planning method considering multiple resource accesses at a user side is characterized by comprising the following steps:
A. aiming at the uncertainty of various resources at a user side, modeling the uncertainty of fan output, photovoltaic output and load power by adopting a robust optimized box-type uncertain set;
B. aiming at the uncertainty of adapting to various resources at a user side, and taking the access positions, the installation number and the newly-built grid structure of the distributed power supplies as investment decision content, establishing a double-layer power distribution network planning model considering the whole life cycle investment cost and the operation cost of a planning scheme, wherein a planning layer objective function is the lowest total construction cost and operation cost, and an operation layer objective function is the lowest operation cost under the determined planning scheme;
C. an extreme scene method is adopted to process uncertainty factors of a double-layer power distribution network planning model, and a power distribution network two-stage robust planning method based on the extreme scene method is provided; the first stage is a planning construction stage, and the access positions and the installation number of the distributed power supplies and the newly-built positions of the lines are determined; the second stage is an operation stage, under the planning scheme of the first stage, the operation condition of the power distribution network under each limit scene is simulated, and the worst scene is optimized;
D. the method comprises the steps of splitting a two-stage robust planning problem into main and sub problems through an improved C & CG algorithm based on a limit scene method, iteratively solving the main problem, solving an optimal planning scheme under a single limit scene through the main problem, transmitting the optimal planning scheme to the sub problems, searching the worst scene under the current planning scheme through the limit scene method through the sub problems, influencing main problem decision through adding relevant operation constraint conditions of the worst scene to the main problem, and finally solving the optimal solution of the iterative robust planning problem through the main and sub problems.
2. The multi-layer planning method for power grid considering multiple resource accesses at user side according to claim 1, characterized in that:
in the step a, uncertainty of fan output, photovoltaic output and load power is represented as:
wherein the content of the first and second substances,respectively representing fan output data, photovoltaic output data and load power requirements;are respectively asThe predicted output of fan output, photovoltaic output and load power; beta is a1、β2、β3The maximum ranges of the possible deviation predicted values of the fan output, the photovoltaic output and the load power are respectively.
3. The multi-layer planning method for power grid considering multiple resource accesses at user side according to claim 2, characterized in that:
in the step B, the double-layer power distribution network planning model is expressed by a mathematical model as follows:
wherein, CINVThe investment cost; cOPEFor operating costs; g (-) and H (-) are planning layer constraints; g (-) and f (-) are constraint conditions of the operation layer; x is the number ofinvDetermining the commissioning of the lines and the distributed power supply for constructing variables; x is the number ofopeOperating variables including line power and node voltage; xi is uncertainty parameter of fan, photovoltaic and load, and is mainly concentrated on the operation layer.
4. The multi-layer planning method for power grid considering multiple resource accesses at user side according to claim 3, characterized in that:
in step B, the planning layer objective function is min F ═ CINV+COPEThe method specifically comprises the following steps:
CINV=CWTG+CPVG+CLINE
wherein subscript j represents the node number; subscript ij denotes a line between node i and node j; cLINE、CWTG、CPVGRespectively converting the total construction cost of the line, the fan and the photovoltaic into the total construction cost of the line, the fan and the photovoltaic; z is the inflation rate of the currency; y isLINE、YWTG、YPVGThe service lives of the line, the fan and the photovoltaic are respectively prolonged;the construction cost per kilometer of the line; c. CWTG、cPVGThe construction cost of each fan and each photovoltaic unit is respectively the construction cost of each fan and each photovoltaic unit; l isijThe length of each alternative line; omegaLINE、ΩWTG、ΩPVGRespectively obtaining a candidate set of lines to be built, a candidate node set of fans to be built and a candidate node set of photovoltaic cells to be built;is a variable of 0 to 1, determines whether a line, a fan and a photovoltaic are put into operation or not, and for the established line,is 1;
wherein T is the number of time periods of operation in one day; Δ t is the time of each time interval;the electricity price for purchasing electricity from the main network for the t period; c. Closs、cLS、cLW、cLPVRespectively unit network loss cost, load loss cost, wind abandoning cost and light abandoning cost;respectively obtaining main network output, loss load power, fan output data, fan actual output, photovoltaic output data and photovoltaic actual output; i isij,tIs the line current; r isijIs a line electric group; omegaTRIs a collection of transformer nodes; elineCollecting all the lines which are built and are to be built for the power distribution network; omegaENSIs the set of all load nodes;
the running layer objective function is:
min f=COPE。
5. the multi-layer planning method for power grid considering multiple resource accesses at user side according to claim 4, characterized in that:
in the step B, the constraint conditions of the planning layer comprise equipment investment construction constraint, network radial constraint and network connectivity constraint;
assuming that the maximum number of the connected fans and the maximum number of the photovoltaic circuits are specified in the power distribution network planning, and the number of the newly-built lines is also determined, the equipment investment construction constraint is specifically as follows:
wherein N isWTGSetting the maximum number of the newly built fans; n is a radical ofPVGSetting the maximum number of newly-built photovoltaic cells; n is a radical ofLINEPredicting the number of newly built lines;
in order to ensure the connectivity of each node of the planned power grid and avoid the operation of the roundabout, the connectivity inspection and radial inspection of the topological structure of the planned distribution network are required.
6. The multi-layer planning method for power grid considering multiple resource accesses at user side according to claim 4, characterized in that:
in the step B, the constraint conditions of the operation layer comprise node power balance constraint, line voltage balance constraint, line capacity constraint, transformer capacity constraint, safety constraint, distributed power supply output constraint and loss load constraint;
to eliminate non-linear terms in the AC power flow, for the current Iij,tSum voltage Uj,tThrough variable replacement and second-order cone relaxation, the nonlinear constraint in the alternating current power flow is converted into a second-order cone constraint:
wherein the content of the first and second substances,is the square of the current value of line ij;is the square of the voltage value of node j;
then the run level constraints are:
node power balance constraint:
wherein, (j) is a line set with the node j as a head end; k is the end node of the line jk; pi (j) is a line set taking the node j as a tail end; omegaFIs a collection of load nodes; pjk,tThe active power transmitted by the line jk at the moment t; qjk,tThe reactive power transmitted by the line jk at the moment t; pij,t、Qij,tRespectively the active power and the reactive power transmitted by the line ij at the moment t;respectively the active load demand and the reactive load demand of the node j; x is the number ofijIs the reactance value of line ij;the main network reactive power, the fan reactive power, the photovoltaic reactive power and the loss load reactive power are respectively;is the square of the voltage value of the node i;
line voltage balance constraint:
wherein M is a sufficiently large positive real number; elineCollecting all the lines which are built and are to be built for the power distribution network;
and (3) line capacity constraint:
wherein the content of the first and second substances,the maximum current-carrying capacity of the line;
and (3) transformer capacity constraint:
wherein the content of the first and second substances,minimum active and reactive output thresholds of the transformer are respectively set;the maximum active and reactive output thresholds of the transformer are respectively set;
safety restraint:
wherein the content of the first and second substances,is the minimum value of the node voltage;is the maximum value of the node voltage;is the maximum line current;
and (3) output constraint of the distributed power supply:
and (4) load loss constraint:
7. The multi-layer planning method for power grid considering multiple resource accesses at user side according to claim 4, characterized in that:
in the step C, a specific mathematical model of the two-stage robust planning of the power distribution network is as follows:
Dx≤d
Ex=e
wherein x is a construction variable of a line, a fan and a photovoltaic; subscript S denotes a limit scene number; n is a radical ofsRepresenting the number of limit scenes; xisRepresenting values of fan output, photovoltaic output and load power under a limit scene S; y issRepresenting the operation decision variables of the line power and the voltage under the limit scene; ax is the construction cost; bys+CξsThe operating cost in the extreme scenario S; A. b, C, D, E, F, G, H, L, M, D, E, F, G, H are coefficient matrixes.
8. The multi-layer planning method for power grid considering multiple resource accesses at user side according to claim 7, characterized in that:
in step D, the mathematical model of the main problem is as follows:
Dx≤d
Ex=e
wherein x is a construction variable of a line, a fan and a photovoltaic; eta is the actual operation cost of the power distribution network; n is C&The iteration times of the CG algorithm; k is a radical ofmNumbering the limit scenes selected in the mth iteration;as extreme scene kmRunning decision variables;as extreme scene kmAnd values of uncertain variables of lower fan output, photovoltaic output and load power.
9. The multi-layer planning method for power grid considering multiple resource accesses at user side according to claim 8, characterized in that:
in step D, the mathematical model of the subproblem is:
10. The multi-layer planning method for power grid considering multiple resource accesses at user side according to claim 9, wherein:
in the step D, the specific flow of the improved C & CG algorithm based on the extreme scene method is as follows:
(1) setting a lower bound LB ═ infinity, an upper bound UB +∞, and an algorithm iteration number n ═ 1;
(2) solving the main problem to obtain the optimal solution of the construction planAnd operating costs under the scenarioAnd updating the lower bound value
(3) Fixed construction plan optimal solutionSolving the sub-problems to obtain the sub-problems under all limit scenes
If all the sub-problems in the extreme scenes have solutions, finding the maximum value of feasible solutions in all the scenesTo obtainThe extreme scene number S is updated, and the upper bound value is updated
If the subproblem is not feasible under the limit scene S, the current worst limit scene is S;
(4) if UB-LB <, the convergence precision is given, then the iteration is finished, and the optimal solution of the current construction plan is obtainedOtherwise, updating the worst limit scene S under the current planning condition, and adding the constraint condition corresponding to the scene to the main problem;
(5) and (4) returning to the step (2) when n is n + 1.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010946881.1A CN112132427B (en) | 2020-09-10 | 2020-09-10 | Power grid multi-layer planning method considering user side multiple resource access |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010946881.1A CN112132427B (en) | 2020-09-10 | 2020-09-10 | Power grid multi-layer planning method considering user side multiple resource access |
Publications (2)
Publication Number | Publication Date |
---|---|
CN112132427A true CN112132427A (en) | 2020-12-25 |
CN112132427B CN112132427B (en) | 2022-11-22 |
Family
ID=73846713
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010946881.1A Active CN112132427B (en) | 2020-09-10 | 2020-09-10 | Power grid multi-layer planning method considering user side multiple resource access |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112132427B (en) |
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112952806A (en) * | 2021-02-09 | 2021-06-11 | 上海电力大学 | Multi-stage optimization planning method for micro-grid group considering load uncertainty |
CN113361078A (en) * | 2021-05-20 | 2021-09-07 | 国网湖北省电力有限公司电力科学研究院 | Power distribution network cloud edge cooperative regulation and control method considering photovoltaic power generation uncertainty |
CN113421004A (en) * | 2021-06-30 | 2021-09-21 | 国网山东省电力公司潍坊供电公司 | Transmission and distribution cooperative active power distribution network distributed robust extension planning system and method |
CN113705892A (en) * | 2021-08-30 | 2021-11-26 | 天津大学 | Demand side resource and intelligent soft switch distribution robustness joint planning method |
CN113988427A (en) * | 2021-10-29 | 2022-01-28 | 东南大学 | AC/DC power distribution network multi-stage expansion planning method considering investment flexibility |
CN114048809A (en) * | 2021-11-10 | 2022-02-15 | 天津大学 | Hybrid power distribution network adaptability planning method and device considering interval voltage overlimit |
CN114142893A (en) * | 2021-12-02 | 2022-03-04 | 广东电网有限责任公司 | Layered identification control method of power communication network and power communication network |
CN114759602A (en) * | 2022-04-24 | 2022-07-15 | 国网山东省电力公司潍坊供电公司 | Power distribution network acceptance capacity assessment method considering photovoltaic extreme scene |
CN114818379A (en) * | 2022-05-24 | 2022-07-29 | 四川大学 | Information physics active power distribution system interactive planning method considering multidimensional uncertainty |
CN115149523A (en) * | 2022-06-27 | 2022-10-04 | 国网山西省电力公司经济技术研究院 | Charging station configuration method and system considering wind-solar output uncertainty |
CN115313438A (en) * | 2022-07-04 | 2022-11-08 | 华中科技大学 | AC/DC power transmission network and energy storage collaborative planning method and medium |
CN116722536A (en) * | 2023-06-05 | 2023-09-08 | 上海交通大学 | Flexible power distribution network distribution robust extension planning method and system based on data driving |
CN116720358A (en) * | 2023-06-09 | 2023-09-08 | 上海交通大学 | Resource optimization configuration method for toughness multi-stage promotion of power distribution-traffic system |
CN117039884A (en) * | 2023-08-22 | 2023-11-10 | 四川大学 | Flexible interconnection planning method of low-voltage distribution network suitable for improving power supply capacity of multiple scenes |
CN116526589B (en) * | 2023-05-25 | 2023-12-05 | 国网江苏省电力有限公司电力科学研究院 | Reactive configuration method, equipment and medium considering source-load multi-time sequence combined scene |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106815657A (en) * | 2017-01-05 | 2017-06-09 | 国网福建省电力有限公司 | A kind of power distribution network bi-level programming method for considering timing and reliability |
CN110032828A (en) * | 2019-05-10 | 2019-07-19 | 四川大学 | It is a kind of meter and demand response soft readjustment power distribution network two stages distribution robust D G distribute linear method rationally |
CN111027807A (en) * | 2019-11-12 | 2020-04-17 | 国网河北省电力有限公司经济技术研究院 | Distributed power generation site selection and volume fixing method based on power flow linearization |
-
2020
- 2020-09-10 CN CN202010946881.1A patent/CN112132427B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106815657A (en) * | 2017-01-05 | 2017-06-09 | 国网福建省电力有限公司 | A kind of power distribution network bi-level programming method for considering timing and reliability |
CN110032828A (en) * | 2019-05-10 | 2019-07-19 | 四川大学 | It is a kind of meter and demand response soft readjustment power distribution network two stages distribution robust D G distribute linear method rationally |
CN111027807A (en) * | 2019-11-12 | 2020-04-17 | 国网河北省电力有限公司经济技术研究院 | Distributed power generation site selection and volume fixing method based on power flow linearization |
Cited By (23)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112952806B (en) * | 2021-02-09 | 2023-09-26 | 上海电力大学 | Multi-stage optimization planning method for micro-grid group considering load uncertainty |
CN112952806A (en) * | 2021-02-09 | 2021-06-11 | 上海电力大学 | Multi-stage optimization planning method for micro-grid group considering load uncertainty |
CN113361078A (en) * | 2021-05-20 | 2021-09-07 | 国网湖北省电力有限公司电力科学研究院 | Power distribution network cloud edge cooperative regulation and control method considering photovoltaic power generation uncertainty |
CN113421004A (en) * | 2021-06-30 | 2021-09-21 | 国网山东省电力公司潍坊供电公司 | Transmission and distribution cooperative active power distribution network distributed robust extension planning system and method |
CN113705892B (en) * | 2021-08-30 | 2023-08-15 | 天津大学 | Demand side resource and intelligent soft switch distribution robust joint planning method |
CN113705892A (en) * | 2021-08-30 | 2021-11-26 | 天津大学 | Demand side resource and intelligent soft switch distribution robustness joint planning method |
CN113988427A (en) * | 2021-10-29 | 2022-01-28 | 东南大学 | AC/DC power distribution network multi-stage expansion planning method considering investment flexibility |
CN114048809A (en) * | 2021-11-10 | 2022-02-15 | 天津大学 | Hybrid power distribution network adaptability planning method and device considering interval voltage overlimit |
CN114048809B (en) * | 2021-11-10 | 2024-04-19 | 天津大学 | Series-parallel power distribution network adaptive planning method and device considering interval voltage beyond limit |
CN114142893A (en) * | 2021-12-02 | 2022-03-04 | 广东电网有限责任公司 | Layered identification control method of power communication network and power communication network |
CN114142893B (en) * | 2021-12-02 | 2023-10-27 | 广东电网有限责任公司 | Hierarchical identification control method of power communication network and power communication network |
CN114759602B (en) * | 2022-04-24 | 2024-04-05 | 国网山东省电力公司潍坊供电公司 | Power distribution network acceptance assessment method considering photovoltaic extreme scenes |
CN114759602A (en) * | 2022-04-24 | 2022-07-15 | 国网山东省电力公司潍坊供电公司 | Power distribution network acceptance capacity assessment method considering photovoltaic extreme scene |
CN114818379B (en) * | 2022-05-24 | 2023-10-24 | 四川大学 | Information physical active power distribution system interactive planning method considering multidimensional uncertainty |
CN114818379A (en) * | 2022-05-24 | 2022-07-29 | 四川大学 | Information physics active power distribution system interactive planning method considering multidimensional uncertainty |
CN115149523A (en) * | 2022-06-27 | 2022-10-04 | 国网山西省电力公司经济技术研究院 | Charging station configuration method and system considering wind-solar output uncertainty |
CN115149523B (en) * | 2022-06-27 | 2024-05-07 | 国网山西省电力公司经济技术研究院 | Charging station configuration method and system considering uncertainty of wind-solar power output |
CN115313438A (en) * | 2022-07-04 | 2022-11-08 | 华中科技大学 | AC/DC power transmission network and energy storage collaborative planning method and medium |
CN116526589B (en) * | 2023-05-25 | 2023-12-05 | 国网江苏省电力有限公司电力科学研究院 | Reactive configuration method, equipment and medium considering source-load multi-time sequence combined scene |
CN116722536A (en) * | 2023-06-05 | 2023-09-08 | 上海交通大学 | Flexible power distribution network distribution robust extension planning method and system based on data driving |
CN116720358A (en) * | 2023-06-09 | 2023-09-08 | 上海交通大学 | Resource optimization configuration method for toughness multi-stage promotion of power distribution-traffic system |
CN116720358B (en) * | 2023-06-09 | 2024-02-02 | 上海交通大学 | Resource optimization configuration method for toughness multi-stage promotion of power distribution-traffic system |
CN117039884A (en) * | 2023-08-22 | 2023-11-10 | 四川大学 | Flexible interconnection planning method of low-voltage distribution network suitable for improving power supply capacity of multiple scenes |
Also Published As
Publication number | Publication date |
---|---|
CN112132427B (en) | 2022-11-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112132427B (en) | Power grid multi-layer planning method considering user side multiple resource access | |
CN112217202B (en) | Distributed new energy, energy storage and power distribution network planning method considering flexibility investment | |
CN111639870B (en) | Multi-target flexible planning method and system for power transmission network considering source load uncertainty | |
CN107832905B (en) | Power distribution network planning method suitable for distributed power generation and energy storage station development | |
CN106385025B (en) | A kind of distributed generation resource and interconnection multistage collaborative planning method | |
Ghadimi et al. | PSO based fuzzy stochastic long-term model for deployment of distributed energy resources in distribution systems with several objectives | |
CN107316113B (en) | Power transmission network planning method and system | |
CN109818369B (en) | Distributed power supply planning method considering output fuzzy randomness | |
CN112884270A (en) | Multi-scene power distribution network planning method and system considering uncertainty factors | |
CN105207573A (en) | Quantitative optimal configuration method of wind-solar hybrid power system based on discrete probability model | |
CN107453396A (en) | A kind of Multiobjective Optimal Operation method that distributed photovoltaic power is contributed | |
CN113128786B (en) | Wind, light and water complementary capacity and site selection optimization method based on space grid search | |
CN112380694A (en) | Power distribution network optimization planning method based on differential reliability requirements | |
Chen et al. | Research on wind power prediction method based on convolutional neural network and genetic algorithm | |
CN115496273A (en) | Renewable energy cluster distribution robustness optimization configuration method and system | |
CN110363334A (en) | Grid-connected grid line loss prediction technique based on Grey Neural Network Model | |
CN114970986A (en) | Distributed power supply and energy storage collaborative planning method based on Nash equilibrium | |
CN114142461B (en) | New energy differential configuration method considering grid morphology evolution and structure development | |
CN110739719A (en) | Two-step decision method for optimized access of flexible multi-state switch | |
CN112713621B (en) | Multi-objective optimal configuration method and system for AC/DC hybrid system | |
CN113690930B (en) | NSGA-III algorithm-based medium and long term locating and sizing method for distributed photovoltaic power supply | |
CN110059871A (en) | Photovoltaic power generation power prediction method | |
CN116128211A (en) | Wind-light-water combined short-term optimization scheduling method based on wind-light uncertainty prediction scene | |
CN113488990B (en) | Micro-grid optimal scheduling method based on improved bat algorithm | |
CN115021269A (en) | Two-stage optimal power flow solving method based on data driving |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |