CN112067540A - Test method for rolling parameters in dam filling engineering construction - Google Patents

Test method for rolling parameters in dam filling engineering construction Download PDF

Info

Publication number
CN112067540A
CN112067540A CN202010898631.5A CN202010898631A CN112067540A CN 112067540 A CN112067540 A CN 112067540A CN 202010898631 A CN202010898631 A CN 202010898631A CN 112067540 A CN112067540 A CN 112067540A
Authority
CN
China
Prior art keywords
test
rolling
measuring
test unit
engineering construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010898631.5A
Other languages
Chinese (zh)
Inventor
江新
张婧怡
江东平
杨尚取
王耀威
王婧雯
姚成铭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Three Gorges University CTGU
Original Assignee
China Three Gorges University CTGU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Three Gorges University CTGU filed Critical China Three Gorges University CTGU
Priority to CN202010898631.5A priority Critical patent/CN112067540A/en
Publication of CN112067540A publication Critical patent/CN112067540A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N19/00Investigating materials by mechanical methods
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N15/00Investigating characteristics of particles; Investigating permeability, pore-volume or surface-area of porous materials
    • G01N15/08Investigating permeability, pore-volume, or surface area of porous materials

Landscapes

  • Chemical & Material Sciences (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Biochemistry (AREA)
  • General Health & Medical Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Immunology (AREA)
  • Pathology (AREA)
  • Dispersion Chemistry (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

A test method for dam filling engineering construction rolling parameters comprises the following steps: 1) selecting a test site; 2) selecting excavation stones as fillers; 3) measuring and paying off, and arranging a plurality of test units; 4) measuring the elevation of each test unit; 5) determining a sinking measuring point, a test pit measuring point and a vertical penetration point; 6) paving a reverse filter layer, a cushion layer, a transition layer and a rockfill material in the test unit; 7) flattening; 8) vibrating static pressure of a grinding field and measuring elevation of a filling layer; 9) sprinkling water to the test units; 10) starting vibration of the vibration roller and rolling the test unit; 11) measuring the elevation of the test unit and measuring the amount of subsidence; 12) detecting the compaction density and the particle composition; 13) and (5) carrying out permeability coefficient detection. By adopting the method, the optimal rolling compaction coefficients of various fillers in the dam body can be measured and calculated, the influence of water sprinkling on the compaction performance of the rockfill material is determined, and the compaction control standards of various fillers are determined.

Description

Test method for rolling parameters in dam filling engineering construction
Technical Field
The invention relates to the field of dam construction, in particular to a test method for rolling parameters of dam filling engineering construction.
Background
In recent years, with the rapid development of economic construction in China, concrete-faced rockfill dams are also rapidly developed, and with the application of a new concrete extrusion-type side wall construction technology to a plurality of large-scale face rockfill dams such as water distribution beaks, the concrete-faced rockfill dams are gradually accepted by people due to the advantages of simplicity and convenience in construction, low manufacturing cost, short construction period and the like.
The dam filling simulation test selects representative dam materials, carries out on-site productivity test similar to actual construction conditions, and can calculate and measure rolling parameters of the dam filling materials so as to guarantee construction quality, but related records are not recorded in the prior art.
Disclosure of Invention
The invention aims to solve the technical problem of providing a test method of the rolling parameters in dam filling engineering construction, which measures and calculates the optimal rolling coefficients of various fillers in a dam, determines the influence of water sprinkling on the compaction performance of rockfill materials, and determines the compaction control standards of various fillers.
In order to solve the technical problems, the technical scheme adopted by the invention is as follows: a test method for dam filling engineering construction rolling parameters comprises the following steps:
1) selecting a rigid foundation test field in a reservoir area on a dam body;
2) selecting excavated stones at a water inlet and a water outlet of an upper reservoir as test site fillers;
3) carrying out measurement paying-off on a test site, and arranging a plurality of test units;
4) measuring and recording the elevation of each test unit;
5) randomly selecting and determining a sinking point, a test pit point and a vertical penetration point in a single test unit;
6) paving a reverse filter layer, a cushion layer, a transition layer and a rockfill material in the test unit;
7) leveling the materials in the test unit by using a bulldozer;
8) vibrating the ground, performing static pressure of a plurality of test units in the whole test field, and measuring the elevation of a filling layer;
9) sprinkling water to the test units;
10) after the watering operation is finished for several hours, starting vibration of the vibration roller and rolling the test unit;
11) measuring the elevations of the filling layers in the rolled test units, and measuring the amount of subsidence at subsidence measuring points;
12) excavating to a rigid foundation at a test pit measuring point, and detecting compaction density and grain composition in the pit;
13) and detecting the permeability coefficient of the rolled filling layer at the vertical penetration point by adopting a pit test method.
In a preferred embodiment, the area of the test unit is not less than 13m × 30 m.
In a preferable scheme, in the step 6), the rockfill material is spread by adopting an occupancy method, and the spreading thickness of the rockfill material is the compacted thickness plus the pre-compression amount.
In a preferred embodiment, the precompression is in the range of 10-15% of the overall laydown thickness.
In a preferable scheme, in the step 7), after the material leveling operation is completed, the thickness of the paving layer is detected by using a level gauge so as to ensure that the thickness of the paving material reaches the required thickness.
In a preferable scheme, in the step 8), a single test unit is subjected to static pressure twice by using a vibration roller, and the static pressure operation of all the test units is completed in the test field at one time by using the vibration roller.
In a preferable scheme, in the step 10), a single test unit is vibrated and rolled for multiple times by using vibration rolls, each rolling is performed in a serpentine path, the vibration rolls enter from one side of the test unit and exit from the same side after being rolled along the serpentine path, and the rolling paths in different rows of test units are different in length.
In a preferred embodiment, in the step 9), the sprinkling amount of the sprinkling operation in the test units in different rows is different.
In a preferable scheme, in the step 10), when the rolling operation of the test unit positioned in the middle is carried out, the vibration rolling is carried out from the test unit which has finished rolling and measuring.
The test method for the rolling parameters in dam filling engineering construction provided by the invention has the following beneficial effects by adopting the structure:
(1) the simulation test is carried out under the condition closer to the actual construction condition, so that dam material filling parameters can be accurately determined;
(2) the data caused by the difference of standard conditions caused by repeated rolling of the rolled areas in the process of vibrating rolling in and out of the field is avoided.
Drawings
The invention is further illustrated by the following examples in conjunction with the accompanying drawings:
FIG. 1 is a diagram showing the overall layout of a test site according to the present invention.
FIG. 2 is a diagram of the vibro-hydrostatic route of the present invention.
Fig. 3 is a plot of crush lane of the vibrations of the present invention within a single test cell.
In the figure: test cell 1, sink station 2, test pit station 3, vertical penetration point 4.
Detailed Description
Example 1:
as shown in fig. 1, a test method for rolling parameters in dam filling engineering construction includes the following steps:
1) selecting a rigid foundation test field in a reservoir area on a dam body;
2) selecting excavated stones at a water inlet and a water outlet of an upper reservoir as test site fillers;
3) carrying out measurement paying-off on a test site, and arranging a plurality of test units 1;
4) measuring and recording the elevation of each test unit 1;
5) randomly selecting and determining a sinking point 2, a test pit point 3 and a vertical penetration point 4 in a single test unit 1, wherein the distance between the test points is 2m multiplied by 2m, and the precision is +/-1 mm;
6) paving a reverse filter layer, a cushion layer, a transition layer and an rockfill material in the test unit 1;
7) leveling the material in the test unit 1 by using a bulldozer;
8) vibrating the ground, performing static pressure of a plurality of test units 1 in the whole test field, and measuring the elevation of a filling layer;
9) performing sprinkling operation on the plurality of test units 1;
10) after the watering operation is finished for several hours, starting vibration of the vibration roller and rolling the test unit 1;
11) measuring the elevations of the filling layers in the plurality of test units 1 after rolling compaction, and measuring the amount of subsidence at subsidence measuring points 2;
12) excavating to a rigid foundation at a test pit measuring point 3, and detecting the compaction density and the grain composition in the pit;
13) and detecting the permeability coefficient of the rolled filling layer at the vertical penetration point 4 by adopting a pit test method.
In a preferred embodiment, the area of the test unit 1 is not less than 13m × 30 m.
In a preferable scheme, in the step 6), the rockfill material is spread by adopting an occupancy method, and the spreading thickness of the rockfill material is the compacted thickness plus the pre-compression amount.
In a preferred embodiment, the precompression is in the range of 10-15% of the overall laydown thickness.
In a preferable scheme, in the step 7), after the material leveling operation is completed, the thickness of the paving layer is detected by using a level gauge so as to ensure that the thickness of the paving material reaches the required thickness.
Example 2:
as shown in fig. 2, on the basis of example 1, a single test unit 1 uses vibration to grind static pressure twice, the vibration grinding completes static pressure operation of all test units 1 in a test field at one time, and a static pressure route completes static pressure operation in all test units 1 at one time according to the graph shown in fig. 2.
Example 3:
referring to fig. 3, on the basis of example 1, a single test unit 1 is vibrated and rolled for a plurality of times by using vibration rolls, each rolling is carried out in a serpentine path, the vibration rolls enter from one side of the test unit 1 and exit from the same side after being rolled along the serpentine path, and the rolling path lengths in different rows of test units are different. (one type of rolling path is shown, and the density and the number of turns of the rolling path in different test units 1 are different)
In a preferred embodiment, in the step 9), the amount of water sprayed in the water spraying operation in the test units 1 in different rows is different.
In a preferred scheme, in the step 10), when the rolling operation of the test unit 1 positioned in the middle is carried out, the vibration rolling is carried out from the test unit 1 which has finished rolling and measuring.
In a single test unit 1, static pressure and vibration rolling conditions are the same, water spraying amount is the same, pre-pressing elevation and post-pressing elevation measurement of a plurality of subsidence measuring points 2 are carried out in the single test unit 1, the elevation difference is a subsidence value, and the average of a plurality of subsidence values is the subsidence value in the test unit 1;
in a plurality of test units 1 in the same row, the static pressure and vibration rolling conditions are the same, the water spraying amount is different, a plurality of test pit measuring points 3 are excavated in a single test unit 1, the in-pit compaction density and the grain grading in the test pit measuring points 3 are detected, and the influence of different water spraying amount conditions on the compaction density, the grain grading and the subsidence value of the filling material can be measured;
in a plurality of test units 1 in the same row, different static pressure and vibration rolling conditions and the same water spraying amount are adopted, and a plurality of vertical penetration points 4 are used for detecting penetration in a single test unit 1, so that the influences of different rolling conditions on the compaction density, the grain grading and the settlement value of the filling material can be measured;
and finally, selecting the optimal rolling parameters of the filling materials by referring to the actual dam body condition according to different data results.

Claims (9)

1. A test method for dam filling engineering construction rolling parameters is characterized by comprising the following steps:
1) selecting a rigid foundation test field in a reservoir area on a dam body;
2) selecting excavated stones at a water inlet and a water outlet of an upper reservoir as test site fillers;
3) carrying out measurement paying-off on a test site, and arranging a plurality of test units (1);
4) measuring and recording the elevation of each test unit (1);
5) randomly selecting and determining a sinking point (2), a test pit point (3) and a vertical penetration point (4) in a single test unit (1);
6) the spreading of a reverse filter layer, a cushion layer, a transition layer and an rockfill material is carried out in the test unit (1);
7) leveling the material in the test unit (1) by using a bulldozer;
8) vibrating the ground, performing static pressure of a plurality of test units (1) in the whole test field, and measuring the elevation of a filling layer;
9) carrying out a water sprinkling operation on the plurality of test units (1);
10) after the watering operation is finished for several hours, starting vibration of the vibration roller and rolling the test unit (1);
11) measuring the elevations of filling layers in the rolled test units (1), and measuring the amount of subsidence at subsidence measuring points (2);
12) excavating to a rigid foundation at a test pit measuring point (3), and detecting the compaction density and the grain composition in the pit;
13) and (4) detecting the permeability coefficient of the rolled filling layer at the vertical penetration point (4) by adopting a pit test method.
2. The test method for the rolling parameters in dam filling engineering construction according to claim 1, wherein: the area of the test unit (1) is not less than 13m multiplied by 30 m.
3. The test method for the rolling parameters in dam filling engineering construction according to claim 1, wherein: and 6), paving the rockfill material by adopting an occupation method, wherein the paving thickness of the rockfill material is the compacted thickness plus the pre-compression amount.
4. The test method for the rolling parameters in dam filling engineering construction according to claim 3, wherein: the pre-compression amount is 10-15% of the whole paving thickness.
5. The test method for the rolling parameters in dam filling engineering construction according to claim 1, wherein: and 7), after the material flattening operation is finished, detecting the thickness of the paving layer by using a level gauge so as to ensure that the thickness of the paving material reaches the required thickness.
6. The test method for the rolling parameters in dam filling engineering construction according to claim 1, wherein: in the step 8), the single test unit (1) utilizes vibration grinding and static pressure twice, and the vibration grinding completes static pressure operation of all the test units (1) in the test field at one time.
7. The test method for the rolling parameters in dam filling engineering construction according to claim 1, wherein: in the step 10), a single test unit (1) utilizes vibration rolling to vibrate and roll for multiple times, each rolling is carried out in a snake-shaped route, vibration rolling enters from one side of the test unit (1) and exits from the same side after rolling along the snake-shaped route, and the lengths of the rolling routes in the test units (1) in different rows are different.
8. The test method for the rolling parameters in dam filling engineering construction according to claim 1, wherein: in the step 9), the sprinkling amount of the sprinkling operation in the test units (1) in different rows is different.
9. The test method for the rolling parameters in dam filling engineering construction according to claim 7, wherein: in the step 10), when the rolling operation of the test unit (1) positioned in the middle is carried out, the vibration rolling is carried out from the test unit (1) which finishes rolling and measuring.
CN202010898631.5A 2020-08-31 2020-08-31 Test method for rolling parameters in dam filling engineering construction Pending CN112067540A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010898631.5A CN112067540A (en) 2020-08-31 2020-08-31 Test method for rolling parameters in dam filling engineering construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010898631.5A CN112067540A (en) 2020-08-31 2020-08-31 Test method for rolling parameters in dam filling engineering construction

Publications (1)

Publication Number Publication Date
CN112067540A true CN112067540A (en) 2020-12-11

Family

ID=73665893

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010898631.5A Pending CN112067540A (en) 2020-08-31 2020-08-31 Test method for rolling parameters in dam filling engineering construction

Country Status (1)

Country Link
CN (1) CN112067540A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0979924A (en) * 1995-09-13 1997-03-28 Hazama Gumi Ltd Method for estimating compaction degree
CN102619208A (en) * 2012-04-18 2012-08-01 贵州正业工程技术投资有限公司 In-situ test method for carbonate rock boulder filler
CN107831217A (en) * 2017-11-02 2018-03-23 清华大学 One kind fills Continuous compacting acoustic wave sensing system and method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0979924A (en) * 1995-09-13 1997-03-28 Hazama Gumi Ltd Method for estimating compaction degree
CN102619208A (en) * 2012-04-18 2012-08-01 贵州正业工程技术投资有限公司 In-situ test method for carbonate rock boulder filler
CN107831217A (en) * 2017-11-02 2018-03-23 清华大学 One kind fills Continuous compacting acoustic wave sensing system and method

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
付军 等: "水布垭面板堆石坝填筑碾压参数的合理选择", 《水力发电》, vol. 31, no. 12, 21 December 2005 (2005-12-21), pages 36 - 38 *
李兆喜: "黄水河水库面板堆石坝填筑施工质量控制", 《云南水力发电》, vol. 32, no. 06, 15 December 2016 (2016-12-15), pages 150 - 152 *
江华 等: "三峡茅坪溪土石坝沥青混凝土心墙骑缝碾压工艺参数研究与选定", 《水利水电技术》, vol. 35, no. 9, 31 December 2004 (2004-12-31), pages 98 - 100 *
王波 等: "仙居抽水蓄能电站上水库面板堆石坝碾压试验参数合理选择", 《土石坝技术》2015年论文集, 1 December 2015 (2015-12-01), pages 275 - 277 *
王贵杰 等: "黏土心墙堆石坝碾压试验技术研究", 《混凝土》, no. 05, 27 May 2010 (2010-05-27), pages 138 - 141 *
陈帮生 等: "武隆接龙水库面板堆石坝填筑碾压参数的合理选择", 《重庆建筑》, no. 07, 15 July 2008 (2008-07-15), pages 39 - 41 *

Similar Documents

Publication Publication Date Title
Aursudkij et al. Cyclic loading of railway ballast under triaxial conditions and in a railway test facility
CN110106838B (en) Cemented dam construction method based on whole-process quality control
CN103255755B (en) Lossless method for fast evaluating filling compaction quality of soil building stones in real time and evaluating device thereof
CN110939043B (en) Rapid detection method for compaction quality of soil-rock mixed filling roadbed
Hunt et al. Breach widening observations from earthen embankment tests
CN112030638A (en) High-fill embankment filling construction process
CN107543775A (en) The method that stockpile fills standard and live filled soils detect is determined based on fractal theory
CN108052709B (en) Method for measuring and calculating water storage coefficient of coal mine underground reservoir
CN106908349B (en) Method for determining maximum dry density of dam primary sand gravel distribution material
CN111236199A (en) Highway subgrade compaction quality rapid detection method based on dynamic resilience modulus
CN112698011A (en) Centrifugal physical test model and test method for rainfall-induced ancient landslide resurgence
CN108570909B (en) Filling and compacting method for fine sand roadbed
CN105571959A (en) Method for rapidly detecting and evaluating compaction quality of road inorganic stabilized grain base
CN110714447A (en) Construction method for filling and rolling in dam subareas
CN112067540A (en) Test method for rolling parameters in dam filling engineering construction
CN111576487A (en) Underground engineering foundation bottom plate structure and construction method thereof
CN111827033A (en) Construction method for widening and filling solidified soil of expressway intercommunicating ramp roadbed
CN108981657B (en) Monitoring and analyzing method for peat soil soft soil roadbed settlement
CN109765260B (en) Flexible non-contact frost heaving monomer for detecting soil, detection device and detection method thereof
CN114813374A (en) Method for testing and calculating settlement of loess subgrade
CN113605350A (en) Dynamic compaction construction process based on environmental protection
Look Elements of expansive clay roadway specifications
CN114250675B (en) Construction method for widening and filling solidified soil of expressway intercommunicating ramp roadbed
CN117306465A (en) Construction method for filling vibration grinding of rock-fill dam
CN213390256U (en) Isolation structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination