CN112045841A - Construction method of assembly type beam-making pedestal for prefabricating high-speed railway box beam - Google Patents
Construction method of assembly type beam-making pedestal for prefabricating high-speed railway box beam Download PDFInfo
- Publication number
- CN112045841A CN112045841A CN202010889285.4A CN202010889285A CN112045841A CN 112045841 A CN112045841 A CN 112045841A CN 202010889285 A CN202010889285 A CN 202010889285A CN 112045841 A CN112045841 A CN 112045841A
- Authority
- CN
- China
- Prior art keywords
- pedestal
- making pedestal
- concrete
- making
- foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B17/00—Details of, or accessories for, apparatus for shaping the material; Auxiliary measures taken in connection with such shaping
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B23/00—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B23/00—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
- B28B23/02—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
Landscapes
- Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Ceramic Engineering (AREA)
- Mechanical Engineering (AREA)
- Manufacturing & Machinery (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明为一种用于预制高速铁路箱梁的装配式制梁台座的施工方法,属于高速铁路箱梁预制技术领域。本发明方法首先是对既有路基进行防水保护施工,然后在路基上吊装装配式制梁台座基础,最后通过装配式制梁台座基础进行预制箱梁工作即可。装配式制梁台座基础包括多节依次连接的制梁台座单体,相邻的两节制梁台座单体的连接端采用卯榫结构拼装连接,并且在卯榫结构连接部分采用长杆螺栓进行固定连接。本发明施工方法绿色环保,施工工艺简单,通用性强,推广实用价值高。台座混凝土构件可周转重复利用,降低了能耗,经济效果明显,能够满足铁路箱梁预制的规范要求,不需要台座结构本身进行加强设计,台座基础采用装配式设计与施工,节能环保。
The invention relates to a construction method of an assembled beam-making pedestal for prefabricating high-speed railway box girder, belonging to the technical field of high-speed railway box girder prefabrication. The method of the invention firstly performs waterproof protection construction on the existing roadbed, then hoists the prefabricated beam-making pedestal foundation on the roadbed, and finally performs prefabricated box girder work through the prefabricated beam-making pedestal foundation. The prefabricated beam-making pedestal foundation includes multiple beam-making pedestal monomers connected in sequence. The connecting ends of the adjacent two-section beam-making pedestal monomers are assembled and connected by a mortise and tenon structure, and the connecting part of the mortise and tenon structure is fixed with long rod bolts. connect. The construction method of the invention is green and environmentally friendly, the construction process is simple, the versatility is strong, and the popularization and practical value are high. The concrete components of the pedestal can be recycled and reused, which reduces energy consumption and has obvious economic effects. It can meet the specification requirements of railway box girder prefabrication, and does not require the pedestal structure itself to be strengthened. Design and construction of the pedestal foundation are energy-saving and environmentally friendly.
Description
技术领域technical field
本发明涉及属于高速铁路箱梁预制技术领域,具体是一种用于预制高速铁路箱梁的装配式制梁台座的施工方法。The invention relates to the technical field of high-speed railway box girder prefabrication, in particular to a construction method for a prefabricated beam-making pedestal for prefabricating high-speed railway box girder.
背景技术Background technique
2019年全国铁路投产新线8489公里,其中高速铁路5474公里,2020年开通26个项目、新线4000公里以上,桥梁占比45%以上。在国内高速铁路建设中,一般根据线路和桥梁的分布,在桥群集中地段或特大桥两端位置,最大运距不宜超过20km~30km布置一处集中预制箱梁的预制场,每年国内新建高速铁路预制箱梁在90余处以上。In 2019, 8,489 kilometers of new railway lines were put into operation across the country, including 5,474 kilometers of high-speed railways. In 2020, 26 projects and more than 4,000 kilometers of new lines will be opened, with bridges accounting for more than 45%. In the construction of high-speed railways in China, according to the distribution of lines and bridges, a prefabricated yard with a centralized prefabricated box girder should be arranged in the middle section of the bridge cluster or at both ends of the super bridge, and the maximum distance should not exceed 20km to 30km. There are more than 90 railway prefabricated box girders.
预制梁场的土建主要包括了制梁台座、静载试验台座。制梁台座通常采用井格式、墙式或钢支墩与混凝土板组合式台座,基础采用桩基础或筏板基础。无论预制台座采用何种结构,其台座与基础均为混凝土现浇,每处梁场仅预制台座及基础混凝土现浇量均在2000m3以上,混凝土圬工结构不能循环使用。箱梁预制完成后(一般预制工期在12月以内),预制台座直接破除、丢弃,复垦制梁场。每年高速铁路预制箱梁仅预制台座产生混凝土建筑垃圾18000m3以上,对混凝土建筑材料的消耗与浪费严重,也增加弃碴处用地;且在破除过程中产生大量扬尘、噪音,环境污染严重。The civil construction of the prefabricated beam yard mainly includes the beam making pedestal and the static load test bench. Beam-making pedestals usually adopt well-type, wall-type or steel pier and concrete slab combination pedestals, and the foundation adopts pile foundation or raft foundation. No matter what kind of structure the precast pedestal adopts, its pedestal and foundation are all cast-in-place concrete. In each beam yard, only the prefabricated pedestal and foundation concrete cast-in - situ amount is more than 2000m3, and the concrete masonry structure cannot be recycled. After the prefabrication of the box girder is completed (generally, the prefabrication period is within 12 months), the prefabricated pedestal is directly demolished and discarded, and the beam yard is reclaimed. Every year, the prefabricated box girder of the high-speed railway only produces more than 18,000m3 of concrete construction waste, which is a serious consumption and waste of concrete construction materials, and also increases the land for ballast abandonment. In addition, a large amount of dust and noise are generated during the removal process, and the environment is seriously polluted.
发明内容SUMMARY OF THE INVENTION
本发明是为了解决高速铁路箱梁预制台座及基础不能循环使用、一次性使用混凝土能耗浪费严重、预制台座结构混凝土圬工量过大、梁场拆除复垦过程对环境破坏严重、用地浪费等一系列问题,而提供一种用于预制高速铁路箱梁的装配式制梁台座的施工方法。该方法是基于绿色无污染、装配式建筑理念的施工方法,特别适于350Km高速铁路900t箱梁的预制施工。The invention is to solve the problem that the prefabricated pedestal and foundation of the high-speed railway box girder cannot be recycled, the waste of one-time use of concrete is serious, the amount of concrete masonry for the prefabricated pedestal structure is too large, the demolition and reclamation process of the beam yard causes serious damage to the environment, waste of land, etc. A series of problems are provided, and a construction method of a prefabricated beam-making pedestal for a prefabricated high-speed railway box girder is provided. This method is a construction method based on the concept of green, pollution-free and prefabricated buildings, and is especially suitable for the prefabricated construction of 900t box girder of 350Km high-speed railway.
本发明是通过如下技术方案实现的:The present invention is achieved through the following technical solutions:
一种用于预制高速铁路箱梁的装配式制梁台座的施工方法,包括如下步骤:A construction method for a prefabricated beam-making pedestal for a prefabricated high-speed railway box girder, comprising the following steps:
1)对既有路基进行防水保护施工,具体为:在路面上先施做5cm厚的水稳层,水稳层上铺设一层土工膜,土工膜上铺设一层土工布,土工布上再浇筑一层无砂混凝土作为面层,最后找平;1) Carry out waterproof protection construction for the existing roadbed, specifically: first build a 5cm-thick water stable layer on the road surface, lay a layer of geomembrane on the water stable layer, lay a layer of geotextile on the geomembrane, and then lay a layer of geotextile on the geotextile. A layer of sand-free concrete is poured as the surface layer, and finally leveled;
2)制作装配式制梁台座基础,并将装配式制梁台座基础坐落在施工好的路基顶面上,最后通过装配式制梁台座基础进行预制箱梁工作即可;其中,装配式制梁台座基础包括多节依次连接的制梁台座单体,相邻的两节制梁台座单体的连接端采用卯榫结构拼装连接,并且在卯榫结构连接部分采用长杆螺栓进行固定连接。2) Make the prefabricated beam-making pedestal foundation, and place the prefabricated beam-making pedestal foundation on the top surface of the constructed subgrade, and finally perform the prefabricated box girder work through the prefabricated beam-making pedestal foundation; among them, the prefabricated beam-making pedestal foundation The pedestal foundation includes a plurality of beam-making pedestal monomers connected in sequence, the connecting ends of the adjacent two-section beam-making pedestal monomers are assembled and connected by a mortise and tenon structure, and the connecting part of the mortise and tenon structure is fixedly connected by a long rod bolt.
进一步的,制梁台座单体为一体浇筑成型的长条状混凝土结构,由下部的宽条体和上部的窄条体组成,其竖截面为“凸”字型;制梁台座单体分为两种外型样式,一种制梁台座单体是其两端的上部窄条体向外延设凸出,另一种制梁台座单体是其两端的下部宽条体向外延设凸出;两种外形样式的制梁台座单体依次交替相邻连接,凸出的窄条体与凸出的宽条体相互搭接形成卯榫结构并通过长杆螺栓进行固定连接。Further, the beam-making pedestal monomer is a long-strip concrete structure formed by pouring into one piece, which is composed of a wide strip body at the lower part and a narrow strip body at the upper part, and its vertical cross-section is a "convex" shape; the beam-making pedestal monomer is divided into There are two types of exterior styles, one is the beam-making pedestal unit whose upper narrow strips at both ends are protruding outward, and the other beam-making pedestal unit is that the lower wide strips at both ends are protruding outward; two The beam-making pedestal units of various shapes are alternately connected adjacently in turn, and the protruding narrow strips and the protruding wide strips overlap each other to form a mortise and tenon structure and are fixedly connected by long rod bolts.
进一步的,制梁台座单体上,凸出的窄条体及凸出的宽条体上均设置有供长杆螺栓穿插的预埋管,凸出的窄条体与凸出的宽条体相互搭接后,二者上的预埋管对接连通且长杆螺栓穿插在对接好的预埋管内并将二者连接固定。Further, on the single body of the beam-making pedestal, the protruding narrow strip body and the protruding wide strip body are provided with embedded pipes for the long rod bolts to be inserted, and the protruding narrow strip body and the protruding wide strip body are provided with embedded pipes. After overlapping each other, the pre-embedded pipes on the two are connected and connected, and the long rod bolts are inserted into the butted pre-embedded pipes to connect and fix the two.
进一步的,制梁台座单体的制作方法包括如下步骤:1)组模:先对模板进行打磨清理,然后再进行模板拼装,控制模板拼装后尺寸误差在1cm以内,采用测量长宽及斜向对角的方式进行检查,模板拼装完成后涂刷脱模剂;2)钢筋绑扎:钢筋的绑扎要确保半成品钢筋的下料尺寸,控制偏差在2cm以内,钢筋绑扎后控制绑扎位置偏差,控制偏差小于1cm;3)预埋件安装:锚栓预留孔套筒安装要求误差在1cm范围内,吊钉吊具预埋允许误差2cm;4)混凝土浇筑:混凝土浇筑前检查模板尺寸,要求合模严紧,如若模板缝隙过大调整模板,若为结构缝隙,则用泡沫胶进行封堵防止混凝土浇筑过程中出现漏浆;浇筑过程严格按要求振捣,做到快插慢拔,振点分部均匀,每次振捣时间为20s~30s,以混凝土不再显著下沉、不出现气泡、开始泛浆时为准;5)预制构件养护:混凝土浇筑完毕后,覆盖土工布或塑料薄膜,洒水养护,保持混凝土面湿润;6)脱模:以试验室通知为准,检测混凝土强度,拆模时防止模板碰撞混凝土造成缺棱掉角;7)成品检查:使用卷尺检测预制构件长度尺寸,使用水平尺及塞尺检测构件平整度。Further, the production method of the beam-making pedestal monomer includes the following steps: 1) Forming: firstly, the template is polished and cleaned, and then the template is assembled, and the size error after the template is controlled to be within 1cm after assembly. Check it diagonally, and apply mold release agent after the template is assembled; 2) Reinforcing bar binding: The bar binding should ensure the blanking size of the semi-finished steel bar, and the deviation should be controlled within 2cm. Less than 1cm; 3) Installation of pre-embedded parts: the installation error of the anchor bolt reserved hole and sleeve shall be within 1cm, and the allowable error of the pre-embedding of the hanger and hanger is 2cm; Tight, if the formwork gap is too large, adjust the formwork, if it is a structural gap, use foam glue to seal it to prevent leakage during the concrete pouring process; the pouring process is strictly vibrated according to the requirements, so as to achieve fast insertion and slow extraction, and vibration points are divided into parts. Evenly, the time of each vibration is 20s ~ 30s, when the concrete no longer sinks significantly, bubbles do not appear, and the grouting starts; 5) Precast component maintenance: After the concrete is poured, cover it with geotextile or plastic film, sprinkle with water Maintenance, keep the concrete surface moist; 6) Demoulding: check the strength of the concrete according to the notice of the laboratory, and prevent the formwork from colliding with the concrete to cause missing edges and corners; 7) Finished product inspection: use a tape measure to detect the length and size of the prefabricated components, use A spirit level and a feeler gauge are used to detect the flatness of components.
本发明用于预制高速铁路箱梁的装配式制梁台座的施工方法,其关键的技术基础就是装配式的、可重复利用的制梁台座基础。运输时,组成制梁台座基础的制梁台座单体结构小,便于运输;施工时,通过长杆螺栓将多节制梁台座单体依次拼装连接至制梁台座基础长度,快捷方便,便于现场的快速安装,并且依靠预埋管及长杆螺栓的连接方式可对下段制梁台座单体的顺直度进行调节,不需要借用其他设备,调节快速。制梁台座基础施工完成后,即可进行高速铁路箱梁预制的施工了。最后施工完成后,可对制梁台座基础进行拆除,拆除时仅需将长杆螺栓抽出,即可将制梁台座基础分割成若干单个的制梁台座单体,以便之后的重复利用。The construction method of the prefabricated beam-making pedestal used for the prefabricated high-speed railway box girder of the present invention, the key technical basis of which is the assembled and reusable beam-making pedestal foundation. During transportation, the single structure of the beam-making pedestal that forms the foundation of the beam-making pedestal is small, which is convenient for transportation; during construction, the multi-section beam-making pedestal monomers are sequentially assembled and connected to the length of the beam-making pedestal foundation through long rod bolts, which is fast and convenient, and is convenient for on-site installation. It can be installed quickly, and the straightness of the lower beam-making pedestal unit can be adjusted depending on the connection method of the embedded pipe and the long rod bolt, without the need to borrow other equipment, and the adjustment is fast. After the foundation construction of the girder pedestal is completed, the prefabrication of the high-speed railway box girder can be carried out. After the final construction is completed, the foundation of the beam-making pedestal can be dismantled. When dismantling, only the long rod bolts are pulled out, and the beam-making pedestal foundation can be divided into several individual beam-making pedestal units for subsequent reuse.
与现有技术相比,本发明具有以下有益效果:Compared with the prior art, the present invention has the following beneficial effects:
本发明施工方法绿色环保,施工工艺简单,通用性强,推广实用价值高。台座混凝土构件可周转重复利用,降低了能耗,经济效果明显,能够满足铁路箱梁预制的规范要求,不需要台座结构本身进行加强设计,台座基础采用装配式设计与施工,节能环保。The construction method of the invention is green and environmentally friendly, the construction process is simple, the versatility is strong, and the popularization and practical value are high. The concrete components of the pedestal can be recycled and reused, which reduces energy consumption and has obvious economic effects. It can meet the specification requirements of railway box girder prefabrication, and does not require the pedestal structure itself to be strengthened. Design and construction of the pedestal foundation are energy-saving and environmentally friendly.
附图说明Description of drawings
此处的附图用来提供对本发明的进一步说明,构成本申请的一部分,本发明的示意性实施例及其说明用来解释本发明,并不构成对本发明的不当限定。The accompanying drawings here are used to provide further descriptions of the present invention and constitute a part of the present application. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention.
图1为本发明方法中装配式制梁台座基础的结构示意图。FIG. 1 is a schematic structural diagram of an assembled beam-making pedestal foundation in the method of the present invention.
图2为图1的俯视图。FIG. 2 is a top view of FIG. 1 .
图3为本发明方法中制梁台座单体的一种外型样式的结构示意图。FIG. 3 is a schematic structural diagram of an exterior style of a beam-making pedestal unit in the method of the present invention.
图4为图3的俯视图。FIG. 4 is a top view of FIG. 3 .
图5为本发明方法中制梁台座单体的另一种外型样式的结构示意图。FIG. 5 is a schematic structural diagram of another exterior style of the beam-making pedestal unit in the method of the present invention.
图6为图5的俯视图。FIG. 6 is a top view of FIG. 5 .
图7为本发明方法中制梁台座单体的竖向截面图。FIG. 7 is a vertical cross-sectional view of a beam-making base unit in the method of the present invention.
图8为本发明方法中两种外形样式的制梁台座单体的连接固定示意图。FIG. 8 is a schematic diagram of the connection and fixation of the beam-making pedestal monomers of two shapes in the method of the present invention.
图中:1-制梁台座单体、1-1-宽条体、1-2-窄条体、2-长杆螺栓、3-预埋管。In the picture: 1-beam-making pedestal monomer, 1-1-wide strip body, 1-2-narrow strip body, 2-long rod bolt, 3-pre-embedded pipe.
具体实施方式Detailed ways
为了使本领域技术人员更好的理解本发明,以下结合参考附图并结合实施例对本发明作进一步清楚、完整的说明。需要说明的是,在不冲突的情况下,本申请中的实施例及实施例中的特征可以相互组合。In order to make those skilled in the art better understand the present invention, the present invention will be further clearly and completely described below with reference to the accompanying drawings and the embodiments. It should be noted that the embodiments in the present application and the features of the embodiments may be combined with each other in the case of no conflict.
如图1至图8所示,一种用于预制高速铁路箱梁的装配式制梁台座的施工方法,包括如下步骤:As shown in Figures 1 to 8, a construction method for a prefabricated beam-making pedestal for a prefabricated high-speed railway box girder includes the following steps:
1)对既有路基进行防水保护施工,具体为:在路面上先施做5cm厚的水稳层,水稳层上铺设一层土工膜,土工膜上铺设一层土工布,土工布上再浇筑一层无砂混凝土作为面层,最后找平。1) Carry out waterproof protection construction for the existing roadbed, specifically: first build a 5cm-thick water stable layer on the road surface, lay a layer of geomembrane on the water stable layer, lay a layer of geotextile on the geomembrane, and then lay a layer of geotextile on the geotextile. A layer of sand-free concrete is poured as the surface layer and finally leveled.
2)制作装配式制梁台座基础,并将装配式制梁台座基础坐落在施工好的路基顶面上,最后通过装配式制梁台座基础进行预制箱梁工作即可;其中,装配式制梁台座基础包括多节依次连接的制梁台座单体1,相邻的两节制梁台座单体1的连接端采用卯榫结构拼装连接,并且在卯榫结构连接部分采用长杆螺栓2进行固定连接。制梁台座单体1为一体浇筑成型的长条状混凝土结构,由下部的宽条体1-1和上部的窄条体1-2组成,其竖截面为“凸”字型;制梁台座单体1分为两种外型样式,一种制梁台座单体1是其两端的上部窄条体1-2向外延设凸出,另一种制梁台座单体1是其两端的下部宽条体1-1向外延设凸出;两种外形样式的制梁台座单体1依次交替相邻连接,凸出的窄条体1-2与凸出的宽条体1-1相互搭接形成卯榫结构并通过长杆螺栓2进行固定连接,具体为:凸出的窄条体1-2及凸出的宽条体1-1上均设置有供长杆螺栓穿插的预埋管3,凸出的窄条体1-2与凸出的宽条体1-1相互搭接后,二者上的预埋管3对接连通且长杆螺栓2穿插在对接好的预埋管3内将二者连接固定。使用长杆螺栓2加预埋管3的连接固定方式,既可以在高程上控制基础高度,又能够控制基础的顺直度。2) Make the prefabricated beam-making pedestal foundation, and place the prefabricated beam-making pedestal foundation on the top surface of the constructed subgrade, and finally perform the prefabricated box girder work through the prefabricated beam-making pedestal foundation; among them, the prefabricated beam-making pedestal foundation The pedestal foundation includes a plurality of beam-making
制梁台座单体的制作方法包括如下步骤:The manufacturing method of the beam-making pedestal monomer comprises the following steps:
1)组模:先对模板进行打磨清理,然后再进行模板拼装,控制模板拼装后尺寸误差在1cm以内,采用测量长宽及斜向对角的方式进行检查,模板拼装完成后涂刷脱模剂;1) Formwork: first grind and clean the formwork, and then assemble the formwork. After the formwork is assembled, the size error is within 1cm, and the inspection is carried out by measuring the length, width and diagonal angle. After the formwork is assembled, paint and demould. agent;
2)钢筋绑扎:钢筋的绑扎要确保半成品钢筋的下料尺寸,控制偏差在2cm以内,钢筋绑扎后控制绑扎位置偏差,控制偏差小于1cm;2) Binding of steel bars: The binding of steel bars should ensure the cutting size of semi-finished steel bars, and the control deviation should be within 2cm. After the steel bars are bound, the deviation of the binding position should be controlled, and the control deviation should be less than 1cm;
3)预埋件安装:锚栓预埋管3安装要求误差在1cm范围内,吊钉吊具预埋允许误差2cm;3) Installation of embedded parts: the installation error of anchor bolt embedded
4)混凝土浇筑:混凝土浇筑前检查模板尺寸,要求合模严紧,如若模板缝隙过大调整模板,若为结构缝隙,则用泡沫胶进行封堵防止混凝土浇筑过程中出现漏浆;浇筑过程严格按要求振捣,做到快插慢拔,振点分部均匀,每次振捣时间为20s~30s,以混凝土不再显著下沉、不出现气泡、开始泛浆时为准;4) Concrete pouring: Check the size of the formwork before concrete pouring, and the formwork is required to be tightly closed. If the gap between the formwork is too large, adjust the formwork. If it is a structural gap, use foam glue to seal it to prevent leakage during concrete pouring. It is required to vibrate, so that it can be inserted quickly and pulled out slowly, and the vibration points are evenly distributed. The time of each vibration is 20s to 30s, and the time when the concrete no longer sinks significantly, does not appear bubbles, and starts to splatter shall prevail;
5)预制构件养护:混凝土浇筑完毕后,覆盖土工布或塑料薄膜,洒水养护,保持混凝土面湿润;5) Precast component maintenance: After the concrete is poured, cover it with geotextile or plastic film, sprinkle water for maintenance, and keep the concrete surface moist;
6)脱模:以试验室通知为准,检测混凝土强度,拆模时防止模板碰撞混凝土造成缺棱掉角;6) Demoulding: Check the strength of the concrete according to the notification from the laboratory, and prevent the formwork from colliding with the concrete and causing missing edges and corners when demoulding;
7)成品检查:使用卷尺检测预制构件长度尺寸,使用水平尺及塞尺检测构件平整度。7) Finished product inspection: use a tape measure to detect the length of the prefabricated components, and use a level and feeler gauge to detect the flatness of the components.
具体实施时,一条装配式制梁台座基础的长度为33.7m、宽度为1m,采用三条装配式制梁台座基础并列布置,用以箱梁预制的施工。对于每条装配式制梁台座基础,由十块制梁台座单体1拼装而成,其中包括尺寸为4×1×0.6m的制梁台座单体1八块、尺寸为3.1×1×0.6m的制梁台座单体1两块,其中,尺寸为3.1×1×0.6m的两块制梁台座单体1位于整条装配式制梁台座基础的两端,并且位于端部处的制梁台座单体1的宽条体1-1和窄条体1-2对齐设置;单块制梁台座单体1的重量控制在6t以内,方便现场吊装作业,制梁台座单体1吊装拼接,利用制梁台座单体1之间的卯榫搭接结构以及长杆螺栓2、预埋管3固定相邻的制梁台座单体1,具体为:制梁台座单体1之间采用上下卯榫搭接方式进行连接,搭接结构长度为50cm,在搭接处预留Φ50的预埋管3,用于长杆螺栓2进行锚固。In the specific implementation, the length of a prefabricated beam-making pedestal foundation is 33.7m and the width is 1m, and three prefabricated beam-making pedestal foundations are arranged side by side for the construction of box girder prefabrication. For each prefabricated beam-making pedestal foundation, ten pieces of beam-making
在箱梁预制施工时,上述可重复利用的装配式制梁台座基础与常规的制梁台座基础使用方式相同,可承载混凝土支撑压力及钢模板、支座板等配件;箱梁预制施工完成后,需拆除装配式制梁台座基础,拆除时,将长杆螺栓2拔出即可,制梁台座单体1可重复利用。During the prefabrication of box girder, the above-mentioned reusable prefabricated girder pedestal foundation is used in the same way as the conventional girder pedestal foundation, and can carry concrete support pressure and accessories such as steel formwork and support plate; after the completion of box girder prefabrication construction , it is necessary to dismantle the foundation of the assembled beam-making pedestal. When dismantling, just pull out the
本发明相对目前国内传统的预制梁台座优势明显:一是装配式制梁台座基础是提前匹配预制的,缩短了建设预制梁场工期(至少28天);二是装配式制梁台座基础既可以工厂化预制也可以在现场集中封闭预制,成品质量好,过程环保;三是装配式制梁台座基础构造简单,制作和安装工艺简便;四是装配式制梁台座基础可周转循环使用,经济性好,减少混凝土建筑垃圾产生,无需增加弃碴用地处置废弃垃圾,节能绿色,节地环保;五是进一步优化了装配式制梁台座基础结构尺寸,每个台座减少混凝土95m3,经济性高,节材节能;六是预制梁场复垦过程中,装配式制梁台座基础可吊装拆除,无需大型破碎锤进行破除,拆除过程无噪音、扬尘污染,施工过程环保;七是装配式制梁台座基础地基承载力达到300Kpa即可,在传统预制台座地基处理的基础上无需进一步加强地基处理,对场地要求不高,适用性和通用性强;八是装配式制梁台座基础可在铁路新建车站或区间路基上进行拼装运用,进一步节约铁路箱梁预制梁场用地。Compared with the current domestic traditional prefabricated beam pedestal, the present invention has obvious advantages: first, the prefabricated beam pedestal foundation is matched and prefabricated in advance, which shortens the construction period of the prefabricated beam yard (at least 28 days); second, the prefabricated beam pedestal foundation can be Factory prefabrication can also be closed and prefabricated on site, the finished product is of good quality, and the process is environmentally friendly; third, the base structure of the prefabricated beam pedestal is simple, and the production and installation process is simple; fourth, the foundation of the prefabricated beam pedestal can be recycled and used, which is economical Good, reduce the generation of concrete construction waste, do not need to increase the waste land for disposal of waste waste, energy saving, green, land saving and environmental protection; Fifth, the basic structure size of the prefabricated beam-making pedestal is further optimized, each pedestal reduces concrete by 95m 3 , and the economy is high. Material saving and energy saving; Sixth, in the process of reclamation of prefabricated beam yard, the foundation of the prefabricated beam-making pedestal can be hoisted and dismantled, without the need for a large breaking hammer to break it down, the demolition process is free of noise and dust pollution, and the construction process is environmentally friendly; Seventh, the prefabricated beam-making pedestal The bearing capacity of the foundation foundation can reach 300Kpa. On the basis of the traditional prefabricated pedestal foundation treatment, there is no need to further strengthen the foundation treatment, the site requirements are not high, and the applicability and versatility are strong; Eighth, the prefabricated beam pedestal foundation can be used in new railway stations. Or it can be assembled and used on the subgrade of the interval to further save the land for the railway box girder prefabricated beam field.
实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其它实施例,都属于本发明保护的范围。The embodiments are only some of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010889285.4A CN112045841B (en) | 2020-08-28 | 2020-08-28 | Construction method of assembly type beam-making pedestal for prefabricating high-speed railway box beam |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010889285.4A CN112045841B (en) | 2020-08-28 | 2020-08-28 | Construction method of assembly type beam-making pedestal for prefabricating high-speed railway box beam |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN112045841A true CN112045841A (en) | 2020-12-08 |
| CN112045841B CN112045841B (en) | 2021-08-27 |
Family
ID=73606993
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202010889285.4A Active CN112045841B (en) | 2020-08-28 | 2020-08-28 | Construction method of assembly type beam-making pedestal for prefabricating high-speed railway box beam |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN112045841B (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN112454644A (en) * | 2020-12-10 | 2021-03-09 | 谢少明 | Prestress movable splicing pedestal |
| CN114986666A (en) * | 2022-06-01 | 2022-09-02 | 中交第四公路工程局有限公司 | Box girder manufacturing system based on tenon-and-mortise structure combined prefabricated pedestal |
| CN115897652A (en) * | 2022-11-16 | 2023-04-04 | 国网安徽省电力有限公司滁州供电公司 | A new prefabricated mortise and tenon structure power distribution facility foundation |
| CN118081946A (en) * | 2024-03-19 | 2024-05-28 | 中铁四局集团有限公司 | A box beam mold for on-site casting of prefabricated highway small box beams |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE1609535B1 (en) * | 1966-02-26 | 1971-02-25 | Trent Concrete Ltd | Connection of reinforced concrete beams with supports made of reinforced concrete |
| CN202610705U (en) * | 2012-06-27 | 2012-12-19 | 衡水宝力工程橡胶有限公司 | Tension-resisting and pressing-resisting rubber support |
| CN104912000A (en) * | 2015-06-05 | 2015-09-16 | 衡水橡胶股份有限公司 | Method for realizing on-site quick assembly of bridge support |
| CN205443922U (en) * | 2016-03-24 | 2016-08-10 | 青海省兴利公路桥梁工程公司 | Bridge bearing |
| CN108340331A (en) * | 2018-01-16 | 2018-07-31 | 石家庄铁道大学 | A kind of assembled steel deposits beam pedestal |
| CN207841707U (en) * | 2018-02-05 | 2018-09-11 | 中铁十七局集团第三工程有限公司 | Assembled beam making bench |
-
2020
- 2020-08-28 CN CN202010889285.4A patent/CN112045841B/en active Active
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE1609535B1 (en) * | 1966-02-26 | 1971-02-25 | Trent Concrete Ltd | Connection of reinforced concrete beams with supports made of reinforced concrete |
| CN202610705U (en) * | 2012-06-27 | 2012-12-19 | 衡水宝力工程橡胶有限公司 | Tension-resisting and pressing-resisting rubber support |
| CN104912000A (en) * | 2015-06-05 | 2015-09-16 | 衡水橡胶股份有限公司 | Method for realizing on-site quick assembly of bridge support |
| CN205443922U (en) * | 2016-03-24 | 2016-08-10 | 青海省兴利公路桥梁工程公司 | Bridge bearing |
| CN108340331A (en) * | 2018-01-16 | 2018-07-31 | 石家庄铁道大学 | A kind of assembled steel deposits beam pedestal |
| CN207841707U (en) * | 2018-02-05 | 2018-09-11 | 中铁十七局集团第三工程有限公司 | Assembled beam making bench |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN112454644A (en) * | 2020-12-10 | 2021-03-09 | 谢少明 | Prestress movable splicing pedestal |
| CN114986666A (en) * | 2022-06-01 | 2022-09-02 | 中交第四公路工程局有限公司 | Box girder manufacturing system based on tenon-and-mortise structure combined prefabricated pedestal |
| CN115897652A (en) * | 2022-11-16 | 2023-04-04 | 国网安徽省电力有限公司滁州供电公司 | A new prefabricated mortise and tenon structure power distribution facility foundation |
| CN118081946A (en) * | 2024-03-19 | 2024-05-28 | 中铁四局集团有限公司 | A box beam mold for on-site casting of prefabricated highway small box beams |
| CN118081946B (en) * | 2024-03-19 | 2024-11-01 | 中铁四局集团有限公司 | A box girder mold for on-site casting of prefabricated highway small box girder |
Also Published As
| Publication number | Publication date |
|---|---|
| CN112045841B (en) | 2021-08-27 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN112045841A (en) | Construction method of assembly type beam-making pedestal for prefabricating high-speed railway box beam | |
| CN110509417A (en) | A kind of floorings are prefabricated and its installation method | |
| CN105755954B (en) | A kind of construction technology of intercommunication clear-water concrete anticollision barrier | |
| CN111764216A (en) | A kind of prefabricated concrete road slab construction method and application | |
| CN104372890A (en) | Construction method of bare concrete prefabricated box beam with complicated structure | |
| CN111676759A (en) | Assembly type temporary construction road and construction method | |
| CN108086113A (en) | A kind of road surface precast assembly fast repairing method for being suitable for southern damp-heat area | |
| CN103334359B (en) | Prefabricated reinforced concrete pavement plate and pavement construction method | |
| CN103334356A (en) | Bridge type precast reinforced concrete hidden beam slab pavement system and construction method thereof | |
| CN108457243B (en) | Construction method of a prefabricated concrete wave retaining wall | |
| CN108193572A (en) | A kind of method recycled to precast beam precasting yard hardened layer | |
| CN103334361B (en) | Prefabricated hollow steel bar concrete wear resistant road surface plate and pavement construction method | |
| CN103343503B (en) | Bridge-type prefabricated reinforced concrete trough slab wear resistant road surface structural system and construction method | |
| CN114182756A (en) | Construction method for simply and movably pouring cable trench by using internal mold support system | |
| CN112045840B (en) | Construction method of prefabricated beam storage pedestal for prefabricated high-speed railway box girder | |
| CN108005255A (en) | A method of building a wall | |
| CN103334360B (en) | The dark beam slab wear-resistant pavement system of bridge-type prefabricated reinforced concrete and construction method thereof | |
| CN103334358B (en) | Prefabricated hollow steel bar concrete flag and pavement construction method | |
| CN103334362B (en) | Prefabricated steel concrete wear resistant road surface plate and pavement construction method | |
| CN203373635U (en) | Prefabricated hollow reinforced concrete wearproof pavement slab | |
| CN116427711A (en) | Construction method of a prefabricated two-way dense rib cavity floor slab | |
| CN203373630U (en) | Prefabricated hollow reinforced concrete pavement slab | |
| CN203429528U (en) | Bridge-type precast-reinforced-concrete-trough-plate wear-resistant pavement structure system | |
| CN203373631U (en) | Prefabricated reinforced concrete pavement slab | |
| CN203373624U (en) | Bridge prefabricated reinforced concrete hidden beam slab wearproof pavement system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| PP01 | Preservation of patent right |
Effective date of registration: 20251022 Granted publication date: 20210827 |
|
| PP01 | Preservation of patent right |
