CN112036953A - Power transmission and transformation project cost calculation system and cost calculation method based on three-dimensional model - Google Patents

Power transmission and transformation project cost calculation system and cost calculation method based on three-dimensional model Download PDF

Info

Publication number
CN112036953A
CN112036953A CN202010919317.0A CN202010919317A CN112036953A CN 112036953 A CN112036953 A CN 112036953A CN 202010919317 A CN202010919317 A CN 202010919317A CN 112036953 A CN112036953 A CN 112036953A
Authority
CN
China
Prior art keywords
project
cost
price
construction
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010919317.0A
Other languages
Chinese (zh)
Inventor
史卓鹏
王亚臣
罗炜
吴东洵
王淼
于国梅
任春光
薛凯
陈涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Economic and Technological Research Institute of State Grid Shanxi Electric Power Co Ltd
Original Assignee
State Grid Shanxi Electric Power Survey And Design Institute Co ltd
Economic and Technological Research Institute of State Grid Shanxi Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Shanxi Electric Power Survey And Design Institute Co ltd, Economic and Technological Research Institute of State Grid Shanxi Electric Power Co Ltd filed Critical State Grid Shanxi Electric Power Survey And Design Institute Co ltd
Priority to CN202010919317.0A priority Critical patent/CN112036953A/en
Publication of CN112036953A publication Critical patent/CN112036953A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/02Marketing; Price estimation or determination; Fundraising
    • G06Q30/0283Price estimation or determination
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Physics & Mathematics (AREA)
  • Finance (AREA)
  • Accounting & Taxation (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Primary Health Care (AREA)
  • Tourism & Hospitality (AREA)
  • Game Theory and Decision Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a power transmission and transformation project cost calculation system and a cost calculation method based on a three-dimensional model, wherein the method comprises the following steps: acquiring three-dimensional design result data of a power transmission and transformation project from a three-dimensional design platform and converting the data into construction cost project data; secondly, dividing the construction project of the construction cost project data; thirdly, calculating the project amount according to the construction cost project data; fourthly, calculating the project cost according to the project amount through a preset quota mode, and realizing project budget estimate planning; and fifthly, compiling the engineering quantity list, the bid limit price and the bid price according to the engineering quantity pricing specification through a list mode. By carrying out standardized management on quota and list pricing data, the problems that the calculation of the engineering quantity is difficult, manual pricing and fee adjustment are easy to make mistakes, the pricing data cannot be traced, the compiling result is difficult to share and apply and the like in the traditional manufacturing cost compiling process are solved.

Description

Power transmission and transformation project cost calculation system and cost calculation method based on three-dimensional model
Technical Field
The application relates to a power project cost calculation technology, in particular to a power transmission and transformation project cost calculation system and a cost calculation method based on a three-dimensional model
Background
The construction cost comprises two parts of cost establishment and whole-process cost management. The working content of cost compilation is that theoretical investment cost is calculated according to design results and pricing basis, and the engineering cost result is commonly used for engineering investment management and control, risk assessment and the like. The cost is compiled according to the preliminary setting of the approximate calculation, construction diagram budget, bidding price limit, completion settlement and the like in the engineering stage; and according to the pricing mode of the sub-quota and the pricing mode of the list, compiling.
The project cost compilation comprises two links of project calculation amount and project pricing. The engineering calculation work is to measure and calculate the engineering quantity of the component according to the constraint of the calculation rule in the standard specification, and finally form an engineering calculation book through classified statistics and summarization. The project pricing work is to compile expenses on the basis of project amount, complete the price combination, price adjustment and fee collection operation of each expense according to the project expense, and finally realize the complete output of the project cost.
The existing engineering cost needs manual calculation through a two-dimensional drawing, the calculation is various in variety and changeable in rule, and items are easy to leak and make mistakes during calculation; meanwhile, the quota is usually applied manually during calculation, the individual experience is highly depended on, and people without experience can easily make mistakes; the price of material and equipment, the personnel cost and the like are manually collected, the timeliness is poor, and the material and the equipment cannot be used in the later period; some expenses need manual adjustment, and the project is more, and in addition non-standardized data also easily leaks the item. In summary, the existing engineering cost mode has low efficiency, difficult modification and no reusability.
Disclosure of Invention
The invention aims to effectively share the data of the three-dimensional design result into the engineering cost based on the problem of the existing engineering cost efficiency according to the condition that the existing power grid construction is mainly applied to a digital design technology so as to provide the engineering cost efficiency.
Therefore, the invention provides a power transmission and transformation project cost calculation method based on a three-dimensional model, which comprises the following steps:
acquiring three-dimensional design result data of a power transmission and transformation project from a three-dimensional design platform and converting the data into construction cost project data;
step two, dividing the construction project according to preset power grid construction budget compilation and calculation regulations of the construction cost engineering data;
step three, calculating the project amount according to the construction cost project data;
and step four, calculating the project cost according to the project amount through a preset quota mode to realize project budget estimate arrangement, wherein the quota mode is used for calculating and managing the construction and installation project body cost, site charge, other cost, project cost and reference period price difference adjustment.
And fifthly, compiling the engineering quantity list, the bid limit price and the bid price according to the engineering quantity pricing specification through a list mode, wherein the list mode is used for calculating and managing the construction and installation engineering cost, other projects, daily work, engineering cost and benchmark period price difference adjustment.
Further, the three-dimensional design result data comprises a three-dimensional model or a two-dimensional drawing, and the engineering quantity is calculated according to the three-dimensional model or the two-dimensional drawing in a manual supplementing mode.
The quota mode is used for calculating the construction and safety project body cost through preset budget cost and a price adjusting coefficient, quota, main material and equipment budget cost are quoted in a numbering or name mode in the calculation process to calculate the construction and safety project body cost, and site charge, other cost and project cost are counted and summarized according to a preset project level calculation base number; the reference period price difference adjustment is used for setting the artificial difference adjustment coefficient, the material difference adjustment coefficient and the mechanical difference adjustment coefficient of the construction and installation project in batches.
The quota comprises labor cost, material cost and mechanical cost, wherein the labor cost, the material cost and the mechanical cost can be subjected to price and project modification according to local construction conditions, and the modified data are automatically stored in preset market price items, compared with budget price to obtain price difference and stored in price difference items; the main materials and the equipment display the supply mode, the loss rate, the freight rate and the budget price, the budget price can be modified according to the local construction situation, the modified data are automatically stored in the preset market price entry and are compared with the budget price to obtain the price difference, and the price difference is stored in the price difference entry.
The charge quota and the price adjusting coefficient in the quota mode can be modified, added and stored according to the local construction situation, and the quota, the main material, the equipment information price and the price adjusting coefficient can be stored.
The list mode imports the budget estimate data in the project establishing and securing body charge calculated in the fourth step, carries out clearing and pricing according to partial items to obtain the project establishing and securing list charge, checks out the clear item without price and hides the clear item, the project establishing and securing body charge also comprises a measure charge (I), a measure charge (II) and a planning charge, the measure charge (I) is the measure project charge of project pricing listed by bidding, and the measure charge (II) is the measure project charge of project pricing in the form of comprehensive unit price.
The power transmission and transformation three-dimensional design system comprises a three-dimensional design platform and a cost management system, wherein the three-dimensional design platform provides power transmission and transformation three-dimensional design result data; the construction cost management system comprises an acquisition module, a calculation module and a project setting module, wherein the acquisition module is used for acquiring three-dimensional design result data from a three-dimensional design platform, the calculation module is used for converting the three-dimensional design result data into construction cost engineering data and calculating the engineering quantity through a construction cost engineering book, and the project setting module is used for dividing a power transmission and transformation project according to preset power grid engineering construction budget compilation and calculation regulations; the rating module calculates the project cost according to the project quantity, carries out project budget estimate compilation, and the list module compiles a project quantity list, a bid limit price and a bid price according to the project quantity pricing standard; and the report management module outputs the project budget estimate compiled by the quota module, the project quantity list compiled by the list module, the bid limit price and the bid quotation project in a report form.
And the system knowledge base management module is used for increasing, modifying and deleting data in a basic database, a quota database, a human machine base, a component base, a calculation rule base, a dimension relation base or a benchmark period price difference base.
Has the advantages that:
by carrying out standardized management on quota and list pricing data, the problems that the calculation of the engineering quantity is difficult, manual pricing and fee adjustment are easy to make mistakes, the pricing data cannot be traced, the compiling result is difficult to share and apply and the like in the traditional manufacturing cost compiling process are solved.
Drawings
FIG. 1 is a flow chart of a method for calculating construction costs of a power transmission and transformation project using a three-dimensional model;
FIG. 2 is a schematic structural diagram of a power transmission and transformation project cost calculation system of a three-dimensional model;
fig. 3 is a schematic diagram of the structure of the computer device of the present invention.
Detailed Description
In order to make the technical solutions better understood by those skilled in the art, the technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application, and it is obvious that the described embodiments are only partial embodiments of the present application, but not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present application.
The invention discloses a power transmission and transformation project cost calculation method based on a three-dimensional model, which comprises the following steps as shown in figure 1:
a power transmission and transformation project cost calculation method based on a three-dimensional model comprises the following steps:
step S101, acquiring three-dimensional design result data of a power transmission and transformation project from a three-dimensional design platform and converting the data into construction cost project data;
step S102, dividing construction projects according to preset power grid construction budgeting and calculation regulations by the construction cost engineering data;
step S103, calculating the project amount through the construction cost project data;
step S104, calculating project cost according to the project amount through a preset rating mode to realize project budget estimate planning, wherein the rating mode is used for calculating and managing the setting and installation project body cost, site charge, other cost, project cost and reference period price difference adjustment;
and 105, compiling the engineering quantity list, the bid limit price and the bid price according to the engineering quantity pricing specification through a list mode, wherein the list mode is used for calculating and managing the construction and installation engineering cost, other projects, daily work, engineering cost and benchmark period price difference adjustment.
As shown in fig. 2, the power transmission and transformation project cost calculation system based on the three-dimensional model of the present invention includes a three-dimensional design platform 1 and a cost management platform 2, wherein the three-dimensional design platform 1 is used for providing three-dimensional design result data of the power transmission and transformation project, and the cost management platform 2 performs cost management of the power transmission and transformation project according to the three-dimensional design result data and cost compiling requirements of each stage of the power transmission and transformation project. The construction cost management platform comprises an acquisition module 21, a project setting module 22, an accounting module 23, a quota management module 24, a list management module 25, a report management module 26 and a knowledge base management module 27, wherein the acquisition module 21 acquires three-dimensional design result data from the three-dimensional design platform 1, converts the three-dimensional design result into construction cost engineering data and then sends the construction cost engineering data to the project setting module 22, the project setting module 22 divides projects according to relevant regulations, the project setting module 22 transmits the construction cost engineering data divided by the projects to the accounting module 23, the accounting module 23 converts the construction cost data into engineering quantity and can carry out design and capital lifting, technology information summarization, two-dimensional drawing checking and the like, the accounting module 23 comprises a design and capital summarizing unit, the design and capital summarizing unit is used for three-dimensional checking of design data and summarizing checking of design engineering quantity, and the technology information summarizing unit is used for three-dimensional checking of technology data, three-dimensional checking, And (4) carrying out statistics on technical and economic projects according to project division, displaying technical and economic projects in detail and manually supplementing the technical and economic projects. The quota management module 24 calculates the project cost according to the project amount, realizes project budget estimate planning, and comprises calculation management of setting up and installing project body cost, site symbol cost, other cost, project cost and reference period price difference adjustment, and can quote quota database data and national network information price data in a knowledge base and calculate the project cost according to calculation rules in the knowledge base.
The list management module 25 compiles the engineering quantity list, the bid limit price and the bid price according to the engineering quantity and the engineering quantity pricing standard, and the list mode is used for calculating and managing the construction and installation project proper cost, other projects, daily work, project cost and benchmark period price difference adjustment.
The invention relates to a power transmission and transformation project cost calculation method based on a three-dimensional model, which supports three-dimensional cost compilation and cost management work in a web integrated mode.
The construction cost management platform 2 can identify three-dimensional design result data exported by the three-dimensional design platform 1(STD _ R), and the data is imported and automatically converted into construction cost engineering data. The computation module 23 supports functions such as design funding, skill summary, two-dimensional drawing viewing, project division adjustment and the like.
The quota mode is used for calculating the construction and safety project body cost through preset budget cost and a price adjusting coefficient, quota, main material and equipment budget cost are quoted in a numbering or name mode in the calculation process to calculate the construction and safety project body cost, and site charge, other cost and project cost are counted and summarized according to a preset project level calculation base number; the reference period price difference adjustment is used for setting the artificial difference adjustment coefficient, the material difference adjustment coefficient and the mechanical difference adjustment coefficient of the construction and installation project in batches.
The quota comprises labor cost, material cost and mechanical cost, wherein the labor cost, the material cost and the mechanical cost can be subjected to price and project modification according to local construction conditions, and the modified data are automatically stored in preset market price items, compared with budget price to obtain price difference and stored in price difference items; the main materials and the equipment display the supply mode, the loss rate, the freight rate and the budget price, the budget price can be modified according to the local construction situation, the modified data are automatically stored in the preset market price entry and are compared with the budget price to obtain the price difference, and the price difference is stored in the price difference entry.
The charge quota and the price adjusting coefficient in the quota mode can be modified, added and stored according to the local construction situation, and the quota, the main material, the equipment information price and the price adjusting coefficient can be stored.
The list mode imports the budget estimate data in the project establishing and securing body charge calculated in the fourth step, carries out clearing and pricing according to partial items to obtain the project establishing and securing list charge, checks out the clear item without price and hides the clear item, the project establishing and securing body charge also comprises a measure charge (I), a measure charge (II) and a planning charge, the measure charge (I) is the measure project charge of project pricing listed by bidding, and the measure charge (II) is the measure project charge of project pricing in the form of comprehensive unit price.
The power transmission and transformation three-dimensional design system comprises a three-dimensional design platform and a cost management system, wherein the three-dimensional design platform provides power transmission and transformation three-dimensional design result data; the construction cost management system comprises an acquisition module, a calculation module and a project setting module, wherein the acquisition module is used for acquiring three-dimensional design result data from a three-dimensional design platform, the calculation module is used for converting the three-dimensional design result data into construction cost engineering data and calculating the engineering quantity through a construction cost engineering book, and the project setting module is used for dividing a power transmission and transformation project according to preset power grid engineering construction budget compilation and calculation regulations; the rating module calculates the project cost according to the project quantity, carries out project budget estimate compilation, and the list module compiles a project quantity list, a bid limit price and a bid price according to the project quantity pricing standard; and the report management module outputs the project budget estimate compiled by the quota module, the project quantity list compiled by the list module, the bid limit price and the bid quotation project in a report form.
And the system knowledge base management module is used for increasing, modifying and deleting data in a basic database, a quota database, a human machine base, a component base, a calculation rule base, a dimension relation base or a benchmark period price difference base.
The three-dimensional design platform and the cost management system of the present application are provided on a computer device, as shown in fig. 3, the computer device 20 may include: the at least one processor 201, e.g., CPU, the at least one network interface 204, the user interface 203, the memory 205, the at least one communication bus 202, and optionally, a display 206. Wherein a communication bus 202 is used to enable the connection communication between these components. The user interface 203 may include a touch screen, a keyboard or a mouse, among others. The network interface 204 may optionally include a standard wired interface, a wireless interface (e.g., WI-FI interface), and a communication connection may be established with the server via the network interface 204. The memory 205 may be a high-speed RAM memory or a non-volatile memory (non-volatile memory), such as at least one disk memory, and the memory 205 includes a flash in the embodiment of the present invention. The memory 205 may optionally be at least one memory system located remotely from the processor 201. Memory 205, which is a type of computer storage medium, may include an operating system, a network communication module, a user interface module, and program instructions.
It should be noted that the network interface 204 may be connected to a receiver, a transmitter or other communication module, and the other communication module may include, but is not limited to, a WiFi module, a bluetooth module, etc., and it is understood that the computer device in the embodiment of the present invention may also include a receiver, a transmitter, other communication module, etc.
Processor 201 may be used to call program instructions stored in memory 205 and cause computer device 20 to
As will be appreciated by one skilled in the art, embodiments of the present description may be provided as a method, system, or computer program product. Accordingly, embodiments of the present description may take the form of an entirely hardware embodiment, an entirely software embodiment or an embodiment combining software and hardware aspects.
The embodiments of this specification may be described in the general context of computer-executable instructions, such as program modules, being executed by a computer. Generally, program modules include routines, programs, objects, components, data structures, etc. that perform particular tasks or implement particular abstract data types. The described embodiments may also be practiced in distributed computing environments where tasks are performed by remote processing devices that are linked through a communications network. In a distributed computing environment, program modules may be located in both local and remote computer storage media including memory storage devices.
The above description is only an example of the present specification, and is not intended to limit the present specification. Various modifications and variations to the embodiments described herein will be apparent to those skilled in the art. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the embodiments of the present specification should be included in the scope of the claims of the embodiments of the present specification.

Claims (7)

1. A power transmission and transformation project cost calculation method based on a three-dimensional model is characterized by comprising the following steps:
acquiring three-dimensional design result data of a power transmission and transformation project from a three-dimensional design platform and converting the data into construction cost project data;
step two, dividing the construction project according to preset power grid construction budget compilation and calculation regulations of the construction cost engineering data;
step three, calculating the project amount according to the construction cost project data;
step four, calculating the project cost according to the project amount through a preset rating mode to realize project budget estimate arrangement, wherein the rating mode is used for calculating and managing the construction and installation project body cost, site charge, other cost, project cost and reference period price difference adjustment;
and fifthly, compiling the engineering quantity list, the bid limit price and the bid price according to the engineering quantity pricing specification through a list mode, wherein the list mode is used for calculating and managing the construction and installation engineering cost, other projects, daily work, engineering cost and benchmark period price difference adjustment.
2. The power transmission and transformation project cost calculation method based on the three-dimensional model according to claim 1, wherein the three-dimensional design result data comprises a three-dimensional model or a two-dimensional drawing, and the amount of work is calculated by manual supplementation according to the three-dimensional model or the two-dimensional drawing.
3. The power transmission and transformation project cost calculation method based on the three-dimensional model according to claim 1, wherein the quota mode is used for calculating construction and safety project cost according to preset budget cost and price adjustment coefficient, quota, main material and equipment budget cost are quoted in a number or name mode in the calculation process to calculate construction and safety project cost, and site charge, other cost and project cost are counted and summarized according to a preset project level calculation base number; the reference period price difference adjustment is used for setting the artificial difference adjustment coefficient, the material difference adjustment coefficient and the mechanical difference adjustment coefficient of the construction and installation project in batches.
4. The power transmission and transformation project cost calculation method based on the three-dimensional model according to claim 3, wherein the quota includes labor cost, material cost and mechanical cost, wherein the labor cost, the material cost and the mechanical cost can be modified according to the local construction situation, the modified data is automatically stored in a preset market price item, compared with the budget price to obtain a price difference and stored in a price difference item; the main materials and the equipment display the supply mode, the loss rate, the freight rate and the budget price, the budget price can be modified according to the local construction situation, the modified data are automatically stored in the preset market price entry and are compared with the budget price to obtain the price difference, and the price difference is stored in the price difference entry.
5. The method as claimed in claim 4, wherein the inventory model is introduced into budget estimate data in the project planning and security entity cost calculated in the fourth step, and the inventory price is calculated according to the partial items to obtain the project planning and security entity cost, and the un-priced entity is checked and hidden, and the project planning and security entity cost further includes a measure fee (one), a measure fee (two) and a plan fee, wherein the measure fee (one) is a measure project cost charged by a project listed in the bid, and the measure fee (two) is a measure project cost charged by a comprehensive unit price.
6. A power transmission and transformation project cost calculation system based on a three-dimensional model is characterized by comprising a three-dimensional design platform and a cost management system, wherein the three-dimensional design platform provides power transmission and transformation three-dimensional design result data; the construction cost management system comprises an acquisition module, a calculation module and a project setting module, wherein the acquisition module is used for acquiring three-dimensional design result data from a three-dimensional design platform, the calculation module is used for converting the three-dimensional design result data into construction cost engineering data and calculating the engineering quantity through a construction cost engineering book, and the project setting module is used for dividing a power transmission and transformation project according to preset power grid engineering construction budget compilation and calculation regulations; the rating module calculates the project cost according to the project quantity, carries out project budget estimate compilation, and the list module compiles a project quantity list, a bid limit price and a bid price according to the project quantity pricing standard; and the report management module outputs the project budget estimate compiled by the quota module, the project quantity list compiled by the list module, the bid limit price and the bid quotation project in a report form.
7. The three-dimensional model-based electric transmission and transformation project cost calculation system of claim 1, wherein the system knowledge base management module adds, modifies and deletes data in a basic database, a rating base, a human-machine base, a component base, a calculation rule base, a dimension relation base or a benchmark price-difference base.
CN202010919317.0A 2020-09-04 2020-09-04 Power transmission and transformation project cost calculation system and cost calculation method based on three-dimensional model Pending CN112036953A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010919317.0A CN112036953A (en) 2020-09-04 2020-09-04 Power transmission and transformation project cost calculation system and cost calculation method based on three-dimensional model

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010919317.0A CN112036953A (en) 2020-09-04 2020-09-04 Power transmission and transformation project cost calculation system and cost calculation method based on three-dimensional model

Publications (1)

Publication Number Publication Date
CN112036953A true CN112036953A (en) 2020-12-04

Family

ID=73592024

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010919317.0A Pending CN112036953A (en) 2020-09-04 2020-09-04 Power transmission and transformation project cost calculation system and cost calculation method based on three-dimensional model

Country Status (1)

Country Link
CN (1) CN112036953A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112734392A (en) * 2021-01-15 2021-04-30 广州市新誉工程咨询有限公司 BIM project cost rapid calculation system and method
CN112861500A (en) * 2021-01-14 2021-05-28 佛山轨道交通设计研究院有限公司 Engineering pricing table generation method and device based on engineering quantity list
CN112926165A (en) * 2021-03-16 2021-06-08 国网福建省电力有限公司漳州供电公司 Method for settling progress of power distribution network overhead line project of 20kV or below based on three-dimensional design
CN113095922A (en) * 2021-05-10 2021-07-09 广东明正项目管理有限公司 Engineering quota pricing method and system
CN113469744A (en) * 2021-07-05 2021-10-01 四川明星电力股份有限公司 Modular budget method and system based on typical design of distribution network
CN113592538A (en) * 2021-07-01 2021-11-02 广州珠合工程技术有限公司 Method and system for calculating approximate construction cost
CN113592536A (en) * 2021-07-01 2021-11-02 广州珠合工程技术有限公司 Engineering cost approximate calculation method and device special for soil remediation engineering
CN114418611A (en) * 2021-12-15 2022-04-29 北京北咨信息工程咨询有限公司 Weak current construction cost calculation method and device, electronic equipment and storage medium
CN113592538B (en) * 2021-07-01 2024-05-31 广州珠合工程技术有限公司 Project cost approximate calculation method and system

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112861500A (en) * 2021-01-14 2021-05-28 佛山轨道交通设计研究院有限公司 Engineering pricing table generation method and device based on engineering quantity list
CN112734392A (en) * 2021-01-15 2021-04-30 广州市新誉工程咨询有限公司 BIM project cost rapid calculation system and method
CN112734392B (en) * 2021-01-15 2023-09-01 广州市新誉工程咨询有限公司 BIM engineering project cost rapid calculation system and method
CN112926165A (en) * 2021-03-16 2021-06-08 国网福建省电力有限公司漳州供电公司 Method for settling progress of power distribution network overhead line project of 20kV or below based on three-dimensional design
CN113095922A (en) * 2021-05-10 2021-07-09 广东明正项目管理有限公司 Engineering quota pricing method and system
CN113592538A (en) * 2021-07-01 2021-11-02 广州珠合工程技术有限公司 Method and system for calculating approximate construction cost
CN113592536A (en) * 2021-07-01 2021-11-02 广州珠合工程技术有限公司 Engineering cost approximate calculation method and device special for soil remediation engineering
CN113592536B (en) * 2021-07-01 2023-12-29 广州珠合工程技术有限公司 Project cost approximate calculation method and device special for soil remediation project
CN113592538B (en) * 2021-07-01 2024-05-31 广州珠合工程技术有限公司 Project cost approximate calculation method and system
CN113469744A (en) * 2021-07-05 2021-10-01 四川明星电力股份有限公司 Modular budget method and system based on typical design of distribution network
CN114418611A (en) * 2021-12-15 2022-04-29 北京北咨信息工程咨询有限公司 Weak current construction cost calculation method and device, electronic equipment and storage medium
CN114418611B (en) * 2021-12-15 2022-09-30 北京北咨信息工程咨询有限公司 Weak current construction cost calculation method and device, electronic equipment and storage medium

Similar Documents

Publication Publication Date Title
CN112036953A (en) Power transmission and transformation project cost calculation system and cost calculation method based on three-dimensional model
CN106846176B (en) Electricity charge accounting system
CN109493003A (en) Item data management method and terminal device
CN111275297A (en) Building engineering EPC (electronic product code) cost and progress management system and management method based on BIM (building information modeling) technology
CN103699966A (en) Multidimensional overall-process data control system and control method based on user requirement
CN104468259A (en) Method for automatically testing communication service expense
CN113626914A (en) Engineering project management method, device and system based on digital twins
CN110942204A (en) New power grid capital construction project annual planning model construction method and system
CN112488654A (en) Integrated intelligent cooperation method and device for electric power material design
CN111681054A (en) Intelligent pricing method for project cost list
CN102222285B (en) Multi-dimensional data linkage computing device and multi-dimensional data linkage computing method
CN103699963A (en) Mounting work amount calculation method and system for nuclear power project
CN111651818A (en) BIM model rapid change method
CN112541749A (en) Construction progress management system based on BIM technology
CN111931279A (en) BIM + GIS-based construction progress intelligent simulation method, information data processing terminal and storage medium
CN116303385A (en) Data auditing method and device, electronic equipment and storage medium
CN112036759A (en) Power grid engineering material list compiling and reporting method and system
CN109583534B (en) Equipment purchase fee automatic statistical method based on material ID and Internet of things label
CN111105204A (en) Construction project progress reporting and managing method and information processing device
CN110968751A (en) Dynamic display method and device for engineering project capital curve
CN112861500A (en) Engineering pricing table generation method and device based on engineering quantity list
Garcia et al. Integrating functional metrics, COCOMO II and earned value analysis for software projects using PMBoK
CN103605866A (en) System and method for simulation training of power distribution network engineering design
CN114154862A (en) Engineering cost automatic allocation method and system based on engineering whole-process management
CN113781017A (en) Railway four-electric engineering construction organization management method and system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20210520

Address after: 030000 15 / F, building 1, No.89, Fudong street, Xinghualing District, Taiyuan City, Shanxi Province

Applicant after: ECONOMIC RESEARCH INSTITUTE OF STATE GRID SHANXI ELECTRIC POWER Co.

Address before: 030000 15 / F, building 1, No.89, Fudong street, Xinghualing District, Taiyuan City, Shanxi Province

Applicant before: ECONOMIC RESEARCH INSTITUTE OF STATE GRID SHANXI ELECTRIC POWER Co.

Applicant before: STATE GRID SHANXI ELECTRIC POWER SURVEY AND DESIGN INSTITUTE Co.,Ltd.

TA01 Transfer of patent application right
RJ01 Rejection of invention patent application after publication

Application publication date: 20201204

RJ01 Rejection of invention patent application after publication