CN112027827B - Method for shifting along household power conductor by matching with existing house and additionally installing elevator - Google Patents

Method for shifting along household power conductor by matching with existing house and additionally installing elevator Download PDF

Info

Publication number
CN112027827B
CN112027827B CN202010815070.8A CN202010815070A CN112027827B CN 112027827 B CN112027827 B CN 112027827B CN 202010815070 A CN202010815070 A CN 202010815070A CN 112027827 B CN112027827 B CN 112027827B
Authority
CN
China
Prior art keywords
power supply
elevator
power
wires
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010815070.8A
Other languages
Chinese (zh)
Other versions
CN112027827A (en
Inventor
郑熠
陆茂鑫
吴静
顾岳峰
傅佳红
申意文
陈文哲
沈立
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Shanghai Electric Power Co Ltd
Original Assignee
State Grid Shanghai Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Shanghai Electric Power Co Ltd filed Critical State Grid Shanghai Electric Power Co Ltd
Priority to CN202010815070.8A priority Critical patent/CN112027827B/en
Publication of CN112027827A publication Critical patent/CN112027827A/en
Application granted granted Critical
Publication of CN112027827B publication Critical patent/CN112027827B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B1/00Control systems of elevators in general
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B1/00Control systems of elevators in general
    • B66B1/34Details, e.g. call counting devices, data transmission from car to control system, devices giving information to the control system

Landscapes

  • Engineering & Computer Science (AREA)
  • Automation & Control Theory (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Elevator Control (AREA)

Abstract

A method for moving along a household power conductor by matching with an existing house and additionally installing an elevator belongs to the field of power construction. The method provides a set of typical design suitable for power conductor relocation engineering reference under various working conditions by aiming at the research on the environmental characteristics, power supply point configuration and elevator installation positions of different residential houses and combining the requirements of power operation maintenance departments through comparative analysis, cost measurement and three-dimensional modeling. The system adheres to the principles of safety, reliability, advanced technology, reasonable investment, unified standard, environment coordination, local conditions and scientific design, adopts a modular design means, and achieves the coordinated unification of uniformity, reliability, advancement, economy, adaptability and flexibility. The technical scheme is beneficial to unifying the construction standard and the equipment standard, reducing the resource consumption and land occupation, improving the working efficiency, reducing the construction and operation cost and laying a solid foundation for the work of power grid planning, cost control, capital management, bid procurement and the like.

Description

一种配合既有住宅加装电梯沿户电力导线移位方法A method for shifting power conductors along households in conjunction with the installation of elevators in existing residences

技术领域technical field

本发明属于电力施工领域,尤其涉及一种用于配合既有住宅加装电梯沿户电力导线移位的方法。The invention belongs to the field of electric power construction, and in particular relates to a method for shifting along household power conductors in conjunction with the installation of an elevator in an existing residence.

背景技术Background technique

近年来,为适应社会经济发展和人口老龄化的需求,进一步改善市民居住条件,给既有住宅加装电梯已得到广泛推广。In recent years, in order to meet the needs of social and economic development and population aging, and further improve the living conditions of citizens, the installation of elevators to existing houses has been widely promoted.

众所周知,老旧住宅小区多为架空线供电,低压架空导线沿门洞侧墙担装置水平架设,支接后进用户供电。As we all know, the old residential quarters are mostly powered by overhead wires, and the low-voltage overhead wires are erected horizontally along the side wall of the doorway, and are connected to the power supply of the backward users.

而加装电梯位置为楼道墙体外侧,电梯井道从一楼至顶楼垂直安装,不可避免的与沿墙架设的电力导线交叉,路径冲突,为保证安全供电和电梯的可靠运行,交叉处需留有足够的安全距离。The installation of the elevator is outside the corridor wall, and the elevator shaft is installed vertically from the first floor to the top floor. It will inevitably intersect with the power wires erected along the wall, and the path conflicts. In order to ensure safe power supply and reliable operation of the elevator, the intersection must be left There is enough safety distance.

现阶段由于电力线路搬迁申请流程繁琐,拟定搬迁方案不易协调,设计周期长等问题,加装电梯项目实际实施中对架空导线未留有足够的安全距离,甚至有私自改接、搬迁、移位,完全不符合电力运行维护要求,给居民用电留下巨大的安全隐患。At this stage, due to the cumbersome application process for the relocation of power lines, the difficulty of coordinating the drafting of the relocation plan, and the long design cycle, etc., in the actual implementation of the elevator installation project, there is not enough safety distance for the overhead conductors, and even unauthorized reconnection, relocation, and displacement , It does not meet the requirements of power operation and maintenance at all, leaving a huge safety hazard for residents to use electricity.

现有改接、搬迁、移位方案产生的不良影响主要有以下几类:The adverse effects caused by the existing reconnection, relocation and displacement schemes mainly fall into the following categories:

1、电梯违规施工,易发人身安全事故1. Illegal construction of elevators, prone to personal safety accidents

2、导线与建筑物安全距离不足2. The safety distance between the conductor and the building is insufficient

3、运维检修难度增加3. Increased difficulty in operation and maintenance

4、用户私自改接沿户电力线路,供电可靠性降低,供电安全隐患增加。4. If the user reconnects to the power line along the household without authorization, the reliability of power supply is reduced, and the hidden danger of power supply safety increases.

因此,对给既有住宅加装电梯配合搬迁沿户电力导线类工程方案典型化是有必要的。Therefore, it is necessary to typicalize the engineering scheme of adding elevators to existing houses and relocating household power wires.

发明内容Contents of the invention

本发明所要解决的技术问题是提供一种配合既有住宅加装电梯沿户电力导线移位方法。该技术方案遵循“物料更精简、典设更精细、技术更先进、方案更适用”的原则,坚持“安全可靠、技术先进、投资合理、标准统一、协调环境、因地制宜、科学设计”的原则,采用模块化设计手段,努力做到统一性与可靠性、先进性、经济性、适应性和灵活性的协调统一。该技术方案的实施,有利于统一建设标准、统一设备规范,有利于减少资源消耗和土地占用,有利于提高工作效益,有利于降低建设和运营成本,为电网规划、成本控制、资金管理、招标采购等工作奠定坚实的基础。The technical problem to be solved by the present invention is to provide a method for shifting the electric wires along the house in conjunction with the installation of an elevator in an existing house. The technical solution follows the principles of "less materials, finer design, more advanced technology, and more applicable solutions", and adheres to the principles of "safety and reliability, advanced technology, reasonable investment, unified standards, coordinated environment, adapting measures to local conditions, and scientific design". Using modular design means, strive to achieve the coordination and unification of unity and reliability, advancement, economy, adaptability and flexibility. The implementation of this technical solution is conducive to the unification of construction standards and equipment specifications, the reduction of resource consumption and land occupation, the improvement of work efficiency, and the reduction of construction and operation costs. Procurement and other work to lay a solid foundation.

本发明的技术方案是:提供一种配合既有住宅加装电梯沿户电力导线移位方法,其特征是所述的沿户电力导线移位方法包括:The technical solution of the present invention is to provide a method for shifting the power conductor along the household in conjunction with the installation of an elevator in the existing house, which is characterized in that the method for shifting the power conductor along the household includes:

1、由原单侧串行架空供电改为两侧并行供电;1. Change the original single-side serial overhead power supply to parallel power supply on both sides;

2、通过新立电杆新放导线避让电梯结构供电;2. Avoid the power supply of the elevator structure through the new wires of the new poles;

3、通过电梯结构预制横担改接导线供电;3. Power supply through the prefabricated cross-arm of the elevator structure and the connection of wires;

4、通过跨越电缆连接电梯两侧导线供电;4. Connect the wires on both sides of the elevator to supply power through the spanning cable;

5、通过电缆架空敷设绕开电梯结构连接两侧导线供电;5. Bypassing the elevator structure and connecting the wires on both sides for power supply through overhead cable laying;

6、整栋住宅采用低压分支箱供电;6. The whole house is powered by a low-voltage branch box;

7、全小区电网配套优化采用低压分支箱供电;7. The power grid of the whole community is optimized to use low-voltage branch boxes for power supply;

8、通过修改电力线路进户点位置供电;8. Power supply by modifying the location of the power line entry point;

9、电梯自身结构避开沿户导线;9. The structure of the elevator itself avoids the wire along the door;

所述的配合既有住宅加装电梯沿户电力导线移位方法,针对不同住宅房屋的环境特点、电源点配置、电梯安装位置的研究,结合电力运行维护部门需要,经过对比分析、成本测算、三维建模,提出了一套适用于各种工况电力导线搬迁工程参照的典型设计,为居民安全用电和电梯的可靠运行提供保障。The method of shifting the power wires along the households with the addition of elevators in existing houses is based on the research on the environmental characteristics of different houses, the configuration of power points, and the installation location of elevators, combined with the needs of the power operation and maintenance department, after comparative analysis, cost calculation, Three-dimensional modeling proposes a set of typical designs applicable to the reference of power conductor relocation projects in various working conditions, providing guarantee for residents' safe use of electricity and reliable operation of elevators.

具体的,所述的由原单侧串行架空供电改为两侧并行供电,适用于该栋楼两侧临近楼有低压电源线路可供改接的单元楼。Specifically, the above-mentioned change from one-side serial overhead power supply to two-side parallel power supply is applicable to unit buildings where low-voltage power supply lines can be reconnected to adjacent buildings on both sides of the building.

具体的,所述的通过新立电杆新放导线避让电梯结构,适用于加装电梯楼前有立杆空间的单元楼。Specifically, the structure of avoiding elevators through newly erected electric poles and new wires is applicable to unit buildings with space for poles in front of the elevator building.

具体的,所述的通过电梯结构预制横担改接导线供电,适用于电梯结构可安装横担架设导线的情况。Specifically, the power supply through the prefabricated cross-arm of the elevator structure and the connection of wires is applicable to the situation that the elevator structure can be installed with cross-arms to erect wires.

具体的,所述的通过跨越电缆连接电梯两侧导线供电,适用于有条件开挖路面的单元楼。Specifically, the power supply by connecting the wires on both sides of the elevator across the cable is applicable to unit buildings where roads are conditionally excavated.

具体的,所述的通过电缆架空敷设绕开电梯结构连接两侧导线供电,适用于单元楼空间狭窄且电梯结构可安装横担架设电缆的情况。Specifically, the power supply connected to the wires on both sides by bypassing the elevator structure through overhead cable laying is applicable to the situation where the space of the unit building is narrow and the elevator structure can be installed with cross-arm erection cables.

具体的,所述的整栋住宅采用低压分支箱改电缆进户供电,适用于整栋楼批量加装电梯,具备开挖条件的小区。Specifically, the whole house described above uses low-voltage branch boxes to convert cables into households for power supply, which is suitable for residential areas where elevators are installed in batches in the whole building and where excavation conditions are available.

具体的,所述的全小区电网配套优化采用低压分支箱供电,适用于配合电网配套优化和整个小区供电改造的小区。Specifically, the optimization of the power grid in the whole community uses low-voltage branch boxes for power supply, which is suitable for communities that cooperate with the optimization of the power grid and the power supply transformation of the entire community.

具体的,所述的通过改进户点位置供电,适用于线路末端单元楼。Specifically, the power supply by improving the location of the household is applicable to the unit building at the end of the line.

具体的,所述的电梯自身结构避开沿户导线,适用于2层电梯结构无连廊的情况。Specifically, the structure of the elevator itself avoids the door-to-door conductors, and is applicable to the situation where the elevator structure on two floors has no corridors.

与现有技术比较,本发明的优点是:Compared with prior art, the advantages of the present invention are:

1.本技术方案遵循“物料更精简、典设更精细、技术更先进、方案更适用”的原则,坚持“安全可靠、技术先进、投资合理、标准统一、协调环境、因地制宜、科学设计”的原则,采用模块化设计手段,努力做到统一性与可靠性、先进性、经济性、适应性和灵活性的协调统一;1. This technical solution follows the principle of "more streamlined materials, more refined design, more advanced technology, and more applicable solutions", and adheres to the principles of "safety and reliability, advanced technology, reasonable investment, unified standards, coordinated environment, adapting measures to local conditions, and scientific design" Principle, adopt modular design means, and strive to achieve the coordination and unification of unity and reliability, advancement, economy, adaptability and flexibility;

2.该技术方案的实施,有利于统一建设标准、统一设备规范,有利于减少资源消耗和土地占用,有利于提高工作效益,有利于降低建设和运营成本,为电网规划、成本控制、资金管理、招标采购等工作奠定坚实的基础。2. The implementation of this technical solution is conducive to the unification of construction standards and equipment specifications, the reduction of resource consumption and land occupation, the improvement of work efficiency, and the reduction of construction and operation costs. , bidding and procurement work to lay a solid foundation.

附图说明Description of drawings

图1是本发明由原单侧串行架空供电改为两侧并行供电的布局示意图;Figure 1 is a schematic diagram of the layout of the present invention from the original one-side serial overhead power supply to two-side parallel power supply;

图2是本发明通过新立电杆新放导线避让电梯结构供电的布局示意图;Fig. 2 is the layout schematic diagram of the present invention avoiding the power supply of the elevator structure through the newly erected electric pole and the newly laid wire;

图3是本发明通过电梯结构预制横担改接导线供电的布局示意图;Fig. 3 is the layout diagram of the present invention through the prefabricated cross-arm of the elevator structure and reconnecting the wires for power supply;

图4是本发明通过跨越电缆连接电梯两侧导线供电的布局示意图;Fig. 4 is a schematic layout diagram of the present invention connecting wires on both sides of the elevator across the cable to supply power;

图5是本发明通过电缆架空敷设绕开电梯结构连接两侧导线供电方案的布局示意图;Fig. 5 is a schematic layout diagram of the power supply scheme of the wires on both sides connected to the elevator structure by overhead cable laying in the present invention;

图6是本发明整栋住宅采用低压分支箱改电缆进户供电方案的布局示意图;Fig. 6 is a schematic layout diagram of the whole house of the present invention adopting the low-voltage branch box to change the cable into the household power supply scheme;

图7是本发明全小区电网配套优化采用低压分支箱供电方案的布局示意图;Fig. 7 is a schematic layout diagram of a low-voltage branch box power supply scheme for the supporting optimization of the power grid in the whole community of the present invention;

图8是本发明通过改进户点位置供电方案的布局示意图;Fig. 8 is a schematic diagram of the layout of the power supply scheme by improving the location of households in the present invention;

图9是本发明电梯自身结构避开沿户导线供电方案的布局示意图。Fig. 9 is a schematic layout diagram of the structure of the elevator itself avoiding the power supply scheme along the household wires of the present invention.

具体实施方式Detailed ways

下面结合附图对本发明做进一步说明。The present invention will be further described below in conjunction with the accompanying drawings.

本发明的技术方案,主要在于保障电力导线搬迁改造后的安全性、可实施性、经济性、美观性;针对不同住宅环境特点推荐可靠的设计方案,最终得出可用于电力导线搬迁工程参照的典型设计。The technical solution of the present invention is mainly to ensure the safety, practicability, economy and aesthetics after the relocation and transformation of the electric wires; to recommend reliable design schemes according to the characteristics of different residential environments, and finally to obtain a reference that can be used for the relocation project of the electric wires typical design.

其针对不同住宅房屋的环境特点、电源点配置、电梯安装位置的研究,结合电力运行维护部门需要,整合大量案例,经过对比分析、成本测算、三维建模等,最终提出一套适用于各种工况电力导线搬迁工程参照的典型设计,为居民安全用电和电梯的可靠运行提供保障。According to the research on the environmental characteristics of different residential houses, the configuration of power points, and the location of elevator installation, combined with the needs of the power operation and maintenance department, a large number of cases were integrated. The typical design referred to in the relocation project of the working condition power conductor provides guarantee for the safe use of electricity for residents and the reliable operation of elevators.

具体的,所述的沿户电力导线移位方法包括以下供电布局和模式:Specifically, the described method of shifting power wires along households includes the following power supply layouts and modes:

(1)由原单侧串行架空供电改为两侧并行供电:(1) From the original unilateral serial overhead power supply to parallel power supply on both sides:

适用条件:适用于该栋楼两侧临近楼有低压电源线路可供改接的单元楼。Applicable conditions: Applicable to unit buildings with low-voltage power lines available for reconnection in adjacent buildings on both sides of the building.

优点:经济性较高,施工方便,运行检修方便。Advantages: high economy, convenient construction, convenient operation and maintenance.

缺点:满足该条件的单元楼较少,使用范围较窄。Disadvantages: There are fewer unit buildings that meet this condition, and the scope of use is narrow.

注:Note:

1、该方案涉及电系变化,需核实改接后台区容量及主线路导线截面是否满足需求,可能涉及全线导线调换,使工程建设费用增加。1. This plan involves changes in the electrical system. It is necessary to verify whether the capacity of the reconnected background area and the cross-section of the main line conductor meet the requirements. It may involve the replacement of the entire line of conductors, which will increase the construction cost of the project.

2、楼间墙担装置档距小于40m。2. The span of the wall bearing device between buildings is less than 40m.

主要材料:导线60m*4相、墙担装置5套等。Main materials: wire 60m*4 phases, 5 sets of wall bearing devices, etc.

投资分析:预估总费用3.5万元。导线架设费用约500元/米(三相四线),横担装置2000元/套。Investment analysis: The estimated total cost is 35,000 yuan. The wire erection cost is about 500 yuan/m (three-phase four-wire), and the cross-arm device is 2,000 yuan/set.

(2)通过新立电杆新放导线避让电梯结构:(2) Avoid the structure of the elevator through the new wires of the new poles:

适用条件:适用于加装电梯楼前有立杆空间的单元楼。Applicable conditions: suitable for unit buildings with pole space in front of the elevator building.

优点:不改变电系,运行检修方便。Advantages: do not change the electrical system, convenient operation and maintenance.

缺点:新立电杆遮挡光线、占用土地资源,需取得该小区物业及居委会的书面认可。Disadvantages: Xinli electric poles block light and occupy land resources, and need to obtain written approval from the property and neighborhood committee of the community.

注:水泥杆较经济,但需打拉线,占用土地空间较大;钢管杆占用空间小,但经济性较低。Note: Concrete poles are more economical, but they need to be pulled and take up a lot of land space; steel pipe poles take up less space, but are less economical.

主要材料:钢管杆/水泥杆2基、导线80m*4相、杆上/墙担装置4套等。Main materials: 2 bases of steel pipe poles/cement poles, 80m*4 phase wires, 4 sets of pole/wall bearing devices, etc.

投资分析:Investment Analysis:

水泥杆约5000元/基;钢管杆约27000元/基;导线架设费用约500元/米(三相四线),墙担装置约2000元/套。The cement pole is about 5,000 yuan/base; the steel pipe pole is about 27,000 yuan/base; the wire erection cost is about 500 yuan/m (three-phase four-wire), and the wall support device is about 2,000 yuan/set.

采用水泥杆方案预估总费用6.9万元;采用钢管杆方案预估总费用10万元。若两个临近门栋都装电梯,总费用约为单个门栋加装电梯的1.5倍,均摊费用可降至5万元,故临近门栋加装数量越多越经济。The estimated total cost of the cement pole scheme is 69,000 yuan; the estimated total cost of the steel pipe pole scheme is 100,000 yuan. If elevators are installed in two adjacent gate buildings, the total cost is about 1.5 times that of installing an elevator in a single gate building, and the average cost can be reduced to 50,000 yuan. Therefore, the more adjacent gate buildings are installed, the more economical.

投资折算公式:采用水泥杆总费用(元)=(水泥杆数量×5000+杆上装置数量×3000+三相四线导线路径长m×500+新增墙担装置数量×2000)×(1±5%)Investment conversion formula: the total cost of using cement poles (yuan) = (number of cement poles x 5000 + number of devices on poles x 3000 + length of three-phase four-wire wire path m x 500 + number of new wall support devices x 2000) x (1 ±5%)

采用钢管杆总费用(元)=(钢杆数量×27000+杆上装置×3000+三相四线导线路径长m×500+新增墙担装置数量×2000)×(1±5%)The total cost of using steel pipe poles (yuan) = (number of steel poles × 27000 + device on the pole × 3000 + length of three-phase four-wire conductor path m × 500 + number of new wall load devices × 2000) × (1 ± 5%)

(3)通过电梯结构预制横担改接导线供电:(3) Power supply through the prefabricated cross-arm of the elevator structure and the connection of wires:

适用条件:电梯结构可安装横担架设导线。Applicable conditions: The elevator structure can be installed with cross-arm erection wires.

优点:经济性较高,不改变电系,施工方便。Advantages: high economy, no change of electric system, convenient construction.

缺点:电梯安装施工前期需采取临时改接措施。Disadvantages: Temporary reconnection measures need to be taken in the early stage of elevator installation and construction.

注:电梯安装施工前期,为避让电梯施工范围需采取临时改接措施,待电梯井道主体结构完成后方可实施本方案。本方案包含临时保护措施费。Note: In the early stage of elevator installation and construction, temporary reconnection measures need to be taken to avoid the scope of elevator construction. This plan can only be implemented after the main structure of the elevator shaft is completed. This package includes a fee for interim protective measures.

预制横担角钢型号不小于∠50*5*650mm+230mm,焊接于电梯主体结构上,另应镀锌防腐且带钢斜撑。The type of prefabricated cross-arm angle steel is not less than ∠50*5*650mm+230mm, welded to the main structure of the elevator, and should be galvanized and anti-corrosion with steel diagonal braces.

主要材料:导线30m*4相等。Main material: wire 30m*4 equal.

投资分析:预估总费用4.1万元,导线架设费用约500元/米(三相四线)。Investment analysis: The estimated total cost is 41,000 yuan, and the wire erection cost is about 500 yuan/m (three-phase four-wire).

投资折算公式:总费用(元)=(三相四线导线路径长m×500)×(1±5%)+临时方案费用25000元。Investment conversion formula: total cost (yuan) = (three-phase four-wire conductor path length m × 500) × (1±5%) + temporary plan cost 25,000 yuan.

(4)通过跨越电缆连接电梯两侧导线供电:(4) Power supply by connecting the wires on both sides of the elevator across the cable:

适用条件:适用于有条件开挖路面的单元楼。Applicable Conditions: Applicable to unit buildings with conditional excavation of road surface.

优点:不改变电系。Advantages: No changes to the electrical system.

缺点:经济性较低,增加线路故障点,需开挖路面。Disadvantages: low economy, increase line fault points, and need to excavate the road surface.

主要材料:电缆45m及保护杆和路面开挖等。Main materials: cable 45m, protective pole and road excavation, etc.

注:涉及路面开挖需取得该小区物业及居委会的书面认可。Note: Involving road excavation requires the written approval of the community property and neighborhood committee.

投资分析:预估总费用:11万元,电缆敷设费用:1700元/米(含路面开挖),墙担装置约2000元/套。Investment analysis: Estimated total cost: 110,000 yuan, cable laying cost: 1,700 yuan/m (including road excavation), and wall load device about 2,000 yuan/set.

(5)通过电缆架空敷设绕开电梯结构连接两侧导线供电:(5) Bypassing the elevator structure and connecting the wires on both sides for power supply through overhead cable laying:

适用条件:单元楼空间狭窄且电梯结构可安装横担架设电缆。Applicable conditions: The space of the unit building is narrow and the elevator structure can be installed with cross arms to erect cables.

优点:不改变电系,经济性较高。Advantages: do not change the electric system, high economy.

缺点:电梯安装施工前期需采取临时改接措施。Disadvantages: Temporary reconnection measures need to be taken in the early stage of elevator installation and construction.

主要材料:电缆20m、墙担装置等。Main materials: cable 20m, wall load device, etc.

注:电梯安装施工前期,为避让电梯施工范围需采取临时改接措施,待电梯井道主体结构完成后方可实施本方案。本方案包含临时保护措施费。Note: In the early stage of elevator installation and construction, temporary reconnection measures need to be taken to avoid the scope of elevator construction. This plan can only be implemented after the main structure of the elevator shaft is completed. This program includes a fee for interim protective measures.

投资分析:Investment Analysis:

预估总费用:5.6万元,电缆敷设费用:650元/米,墙担装置约2000元/套。Estimated total cost: 56,000 yuan, cable laying cost: 650 yuan/m, wall support device about 2,000 yuan/set.

投资折算公式:总费用(元)=(电缆敷设路径长m×650+墙担装置数量×2000)×(1±5%)+临时方案费用25000元。Investment conversion formula: total cost (yuan) = (length of cable laying path m × 650 + number of wall loaders × 2000) × (1±5%) + temporary plan cost 25,000 yuan.

(6)整栋住宅采用低压分支箱改电缆进户供电:(6) The whole house adopts the low-voltage branch box to change the cable into the household for power supply:

适用条件:适用于整栋楼批量加装电梯,具备开挖条件的小区。Applicable conditions: It is suitable for the batch installation of elevators in the whole building and the community with excavation conditions.

优点:供电可靠性高。Advantages: high power supply reliability.

缺点:经济性较低,需占用小区用地。Disadvantages: low economy, need to occupy the land of the community.

主要材料:分支箱1座、电缆(5回)共100m及保护杆和路面开挖等。Main materials: 1 branch box, cables (5 loops) totaling 100m, protective poles and road excavation, etc.

注:涉及新设分支箱占地、路面开挖需取得该小区物业及居委会的书面认可。Note: The land occupation and road excavation involved in the new branch box need to obtain the written approval of the community property and the neighborhood committee.

投资分析:Investment Analysis:

预估总费用:30万元,电缆敷设费用:650元/米,分支箱:17000元/座。Estimated total cost: 300,000 yuan, cable laying cost: 650 yuan/m, branch box: 17,000 yuan/seat.

投资折算公式:总费用(元)=(分支箱数量×17000+低压电缆路径长m×650+白色路面开挖长度×2700+墙担装置数量×2000)×(1±5%)Investment conversion formula: total cost (yuan) = (number of branch boxes × 17000 + low-voltage cable path length m × 650 + white road excavation length × 2700 + number of wall loaders × 2000) × (1 ± 5%)

本方案按分支箱供4回低压出线考虑,加装电梯数量为4个,均摊费用最低,为8万元。随着加装电梯数量减少,均摊费用升高。当只有1个门栋加装电梯时,采用该方案费用约为25万元。In this plan, the branch box is used for 4 low-voltage outgoing lines, and the number of additional elevators is 4, and the average cost is the lowest, which is 80,000 yuan. As the number of additional elevators decreases, the average cost increases. When only one door building is equipped with an elevator, the cost of adopting this scheme is about 250,000 yuan.

(7)全小区电网配套优化采用低压分支箱供电:(7) The power grid of the whole community is optimized to use low-voltage branch boxes for power supply:

适用条件:适用于配合电网配套优化和整个小区供电改造的小区Applicable conditions: suitable for communities that cooperate with the optimization of power grids and the power supply transformation of the entire community

优点:电网配套优化,供电可靠性高。Advantages: Power grid supporting optimization, high reliability of power supply.

缺点:经济性相对较低,占用小区用地较大。Disadvantages: The economy is relatively low, and it occupies a lot of land in the community.

主要材料:箱变1座、分支箱1座、电缆(10回)共500m及保护杆和路面开挖等。Main materials: 1 box substation, 1 branch box, cables (10 loops) totaling 500m, protective poles and road excavation, etc.

注:Note:

1.涉及新设箱变、分支箱占地,路面开挖需取得该小区物业及居委会的书面认可。1. Involving newly installed box substations and branch boxes occupying land, the excavation of the road surface needs to obtain the written approval of the property and neighborhood committee of the community.

2.本方案不含10kV箱变进线。2. This scheme does not include 10kV box transformer incoming lines.

投资分析:预估总费用:222万元,单个门栋造价约28万元,电缆敷设费用:650元/米,箱变:53万元/座,分支箱:17000元/座。Investment analysis: Estimated total cost: 2.22 million yuan, the cost of a single gate building is about 280,000 yuan, the cost of cable laying: 650 yuan/m, the box transformer: 530,000 yuan/seat, and the branch box: 17,000 yuan/seat.

投资折算公式:总费用(元)=(箱变数量×530000+分支箱数量×17000+低压电缆路径长m×650+白色路面开挖长度×2700+墙担装置数量×2000)×(1±5%)Investment conversion formula: total cost (yuan) = (number of box transformers × 530000 + number of branch boxes × 17000 + length of low-voltage cable path m × 650 + length of white road excavation × 2700 + number of wall loaders × 2000) × (1± 5%)

本方案按加装电梯数量为8个考虑,均摊费用为28万元。In this plan, the number of elevators to be installed is 8, and the average cost is 280,000 yuan.

(8)通过改进户点位置供电:(8) Power supply by improving the location of households:

适用条件:适用于线路末端单元楼。Applicable conditions: Applicable to unit buildings at the end of the line.

优点:经济性较高。Advantages: Higher economy.

缺点:满足该条件的单元楼较少。Disadvantage: There are fewer unit buildings that meet this condition.

主要材料:导线20m*4相、墙担装置1套等。Main materials: wire 20m*4 phases, 1 set of wall bearing device, etc.

注:改变进户点位置,在墙上开孔需取得该小区物业及居委会的书面认可。Note: Changing the location of the entry point and opening holes on the wall requires the written approval of the community property and the neighborhood committee.

投资分析:预估总费用:1.3万元。导线架设费用:500元/米,墙担装置约2000元/套。Investment analysis: Estimated total cost: 13,000 yuan. Wire erection cost: 500 yuan/m, wall load device about 2000 yuan/set.

投资折算公式:总费用(元)=(三相四线导线路径长m×500+新增墙担装置数量×2000)×(1±5%)。Investment conversion formula: total cost (yuan) = (three-phase four-wire conductor path length m × 500 + the number of new wall load devices × 2000) × (1 ± 5%).

(9)电梯自身结构避开沿户导线:(9) The structure of the elevator itself avoids the wire along the door:

通过电梯自身结构调整,避开现状导线安装。电力设施无需移位。Through the structural adjustment of the elevator itself, the current wire installation is avoided. Electric facilities do not need to be moved.

适用条件:2层电梯结构无连廊。Applicable conditions: 2-story elevator structure without corridors.

优点:电力设施无需移位,不产生费用,不影响电梯安装进度。Advantages: There is no need to relocate the power facilities, no cost is incurred, and the progress of elevator installation is not affected.

注:Note:

1、需用户与电梯厂商协调优化电梯设计结构。1. The user and the elevator manufacturer need to coordinate and optimize the design structure of the elevator.

2、电梯安装施工时需采取保护措施。2. Protective measures should be taken during elevator installation and construction.

(10)推荐典型设计方案:(10) Recommended typical design scheme:

方案对比表Scheme comparison table

Figure BDA0002632378800000071
Figure BDA0002632378800000071

综合经济性、安全性、便捷性等,在满足适用条件下,推荐采用如下方案:In consideration of economy, safety, convenience, etc., the following schemes are recommended if applicable conditions are met:

1、方案九:电梯自身结构避开沿户导线:1. Scheme 9: The structure of the elevator itself avoids the wires along the door:

该方案通过电梯自身结构调整,避开现状架空导线,电力设施无需移位,不产生费用。结合楼道布置加装电梯,推荐为首选方案。This scheme avoids the current overhead wires through the adjustment of the structure of the elevator itself, and the power facilities do not need to be displaced, and no costs are incurred. It is recommended to install an elevator in combination with the corridor layout, which is the first choice.

2、方案三:通过电梯结构加装横担改接导线供电:2. Scheme 3: Install a crossarm through the elevator structure and change the wire power supply:

通过电梯结构预制满足电业要求的横担装置,施工时仅需安装绝缘子,架设导线,施工简单,投资费用较低,适用于所有加装电梯楼宇,是值得广泛推广的也是最容易让老百姓接受的方案。The cross-arm device that meets the requirements of the electrical industry is prefabricated through the elevator structure. During construction, only insulators and wires need to be installed. The construction is simple and the investment cost is low. It is suitable for all buildings with elevators. It is worthy of widespread promotion and is the easiest for ordinary people to accept. scheme.

3、方案二:通过新立电杆新放导线避让电梯结构供电:3. Scheme 2: Use the newly installed wires on the new poles to avoid the power supply of the elevator structure:

本方案虽然经济性一版,但通过新立电杆,导线完全避开电梯结构,使居民公共设施与电力设施有效隔离,确保较高的供电可靠性。Although this scheme is economical, the wires completely avoid the elevator structure through the newly erected electric poles, so that residents' public facilities and electric facilities are effectively isolated, ensuring high power supply reliability.

4、方案七:全小区电网配套优化采用低压分支箱供电:4. Scheme 7: Optimizing the support of the power grid in the whole community and using low-voltage branch boxes for power supply:

本方案有效结合区域低压电网配套优化,通过优化电源配置和供电方式,全面提高居民供电可靠性,安全性。供电线路入地,美化了社区环境,充分体现了环境友好型供电设计原则,是配合电网配套优化和整个小区供电改造的首选方案。This scheme effectively combines the supporting optimization of the regional low-voltage power grid, and comprehensively improves the reliability and safety of residents' power supply by optimizing the power supply configuration and power supply mode. The power supply line goes into the ground, which beautifies the community environment and fully embodies the design principles of environment-friendly power supply.

本发明的技术方案遵循“物料更精简、典设更精细、技术更先进、方案更适用”的原则,坚持“安全可靠、技术先进、投资合理、标准统一、协调环境、因地制宜、科学设计”的原则,采用模块化设计手段,努力做到统一性与可靠性、先进性、经济性、适应性和灵活性的协调统一。The technical solution of the present invention follows the principle of "more streamlined materials, more refined design, more advanced technology, and more applicable solutions", and adheres to the principle of "safety and reliability, advanced technology, reasonable investment, unified standards, coordinated environment, adapting measures to local conditions, and scientific design" Principles, adopt modular design means, and strive to achieve the coordination and unity of unity and reliability, advancement, economy, adaptability and flexibility.

该技术方案的实施,有利于统一建设标准、统一设备规范,有利于减少资源消耗和土地占用,有利于提高工作效益,有利于降低建设和运营成本,为电网规划、成本控制、资金管理、招标采购等工作奠定坚实的基础。The implementation of this technical solution is conducive to the unification of construction standards and equipment specifications, the reduction of resource consumption and land occupation, the improvement of work efficiency, and the reduction of construction and operation costs. Procurement and other work to lay a solid foundation.

本发明可广泛用于现有住宅加装电梯工程的设计和施工领域。The invention can be widely used in the field of design and construction of elevator installation projects in existing houses.

Claims (1)

1. A method for shifting along a household power conductor by matching with an existing house and additionally installing an elevator is characterized by comprising the following steps:
for the unit building with low-voltage power supply lines for reconnection adjacent to the building on two sides of the building, the original single-side serial overhead power supply mode is changed into a two-side parallel power supply mode;
for a unit building with a vertical rod space in front of an additionally installed elevator building, a new wire is placed on a new vertical rod to avoid an elevator structure;
for the condition that the cross arm can be installed and the wires are erected on the elevator structure, the way of connecting the prefabricated cross arm of the elevator structure with the wires for power supply is adopted;
for a unit building with a condition excavated road surface, connecting wires at two sides of an elevator for power supply through a crossing cable;
for the condition that the space of a unit building is narrow and a cross arm can be installed on an elevator structure to erect a cable, the cable is laid overhead, the elevator structure is bypassed, and wires on two sides are connected to supply power;
elevators are additionally arranged in batches in the whole building, the building has a community with excavation conditions, and the whole house adopts a low-voltage branch box power supply mode;
for the cells matched with power grid matching optimization and whole cell power supply transformation, the power grid matching optimization of the whole cell adopts a low-voltage branch box power supply mode;
for a unit building at the tail end of a line, power is supplied in a mode of improving the position of a user point;
for the condition that the 2-layer elevator structure has no corridor, the power supply is carried out in a mode that the elevator structure avoids the wires along the house;
the method for moving the elevator along the power lead of the house is matched with the existing house, and a typical design suitable for power lead moving engineering reference under various working conditions is provided by combining the needs of power operation maintenance departments and performing comparative analysis, cost measurement and three-dimensional modeling aiming at the environmental characteristics, power supply point configuration and elevator installation positions of different house houses.
CN202010815070.8A 2020-08-13 2020-08-13 Method for shifting along household power conductor by matching with existing house and additionally installing elevator Active CN112027827B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010815070.8A CN112027827B (en) 2020-08-13 2020-08-13 Method for shifting along household power conductor by matching with existing house and additionally installing elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010815070.8A CN112027827B (en) 2020-08-13 2020-08-13 Method for shifting along household power conductor by matching with existing house and additionally installing elevator

Publications (2)

Publication Number Publication Date
CN112027827A CN112027827A (en) 2020-12-04
CN112027827B true CN112027827B (en) 2023-03-28

Family

ID=73577276

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010815070.8A Active CN112027827B (en) 2020-08-13 2020-08-13 Method for shifting along household power conductor by matching with existing house and additionally installing elevator

Country Status (1)

Country Link
CN (1) CN112027827B (en)

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030213652A1 (en) * 2002-05-15 2003-11-20 Waupaca Elevator Company, Inc. Residential elevator
CN104310163A (en) * 2014-08-21 2015-01-28 罗阿波 Rebuilding structure for high-rise building
CN105401776B (en) * 2015-11-20 2018-09-28 国家电网公司 A kind of device being used to support transmission pressure in electric pole replacement process
CN108343257B (en) * 2018-03-16 2020-08-07 杭州市建筑设计研究院有限公司 Construction method for additionally installing elevator in existing multi-storey house
CN111350372A (en) * 2020-03-23 2020-06-30 河北省建筑科学研究院有限公司 Assembly type rapid reconstruction method for existing house with additionally-installed elevator

Also Published As

Publication number Publication date
CN112027827A (en) 2020-12-04

Similar Documents

Publication Publication Date Title
CN101299517B (en) Centralized remote electric power system
CN204927913U (en) a substation
Duan et al. Study on the voltage level sequence of future urban DC distribution network in China: A Review
CN106301203A (en) Solar energy power generating accesses the method for magnetic floating traffic electric power system
CN112027827B (en) Method for shifting along household power conductor by matching with existing house and additionally installing elevator
CN102361241A (en) Box type transformer station
CN104778552A (en) Village-level power grid configuring and implementing method
CN102561748B (en) Multifunctional large plant structure for plume satellite test
CN202866322U (en) Underground upper cover property complex grounding system
CN209200948U (en) Valve hall and converter station
CN110017051A (en) A kind of novel T of double-circuit line connects tower
CN104834346A (en) High-voltage alternating-current overhead line electromagnetic field control design scheme screening and optimization method
CN104141405A (en) Overhead junction pole for two-circuit overhead transmission line and line junction structure of overhead junction pole
CN201312071Y (en) Direct-current traction substation
CN210224761U (en) A compact 220kV all-indoor substation
CN207651821U (en) First and second unit equipment prefabricated cabins of 35kV with additional maintenance cabin
CN108736362B (en) Highly integrated distribution type booster station
CN101824930B (en) Operation method of live iron tower for 10kV double circuit line on the same tower
CN112348393A (en) A method for analyzing technical and economic indicators of power transmission and transformation project cost
CN210380150U (en) Power distribution wiring structure in vertical shaft of multi-storey and high-rise residential building
CN110752533A (en) Cylindrical and ellipsoidal micro-transformer substation and manufacturing and mounting method thereof
CN205976631U (en) But sled dressization mobility control room
Yao et al. A brief analysis of the power cable planning and design of the utility tunnel
CN204615229U (en) Square radial GIS substation structure
CN117791882B (en) AC excitation system equipment installation process of double-feed variable-speed pumped storage unit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant