CN111997630A - Monitoring and measuring method for high-ground-stress soft rock tunnel - Google Patents

Monitoring and measuring method for high-ground-stress soft rock tunnel Download PDF

Info

Publication number
CN111997630A
CN111997630A CN202011041888.5A CN202011041888A CN111997630A CN 111997630 A CN111997630 A CN 111997630A CN 202011041888 A CN202011041888 A CN 202011041888A CN 111997630 A CN111997630 A CN 111997630A
Authority
CN
China
Prior art keywords
tunnel
deformation
monitoring
construction
measuring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011041888.5A
Other languages
Chinese (zh)
Inventor
张生
袁松
王元
王希宝
许白杨
韩根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Jiaotou Construction Engineering Co ltd
Sichuan Communication Surveying and Design Institute Co Ltd
Original Assignee
Sichuan Jiaotou Construction Engineering Co ltd
Sichuan Communication Surveying and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Jiaotou Construction Engineering Co ltd, Sichuan Communication Surveying and Design Institute Co Ltd filed Critical Sichuan Jiaotou Construction Engineering Co ltd
Priority to CN202011041888.5A priority Critical patent/CN111997630A/en
Publication of CN111997630A publication Critical patent/CN111997630A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/003Arrangement of measuring or indicating devices for use during driving of tunnels, e.g. for guiding machines
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention provides a monitoring and measuring method for a high ground stress soft rock tunnel, which comprises the steps of formulating a special monitoring and measuring scheme for the high ground stress soft rock tunnel according to the design of the tunnel; at the moment, the tunnel starts to be constructed, and the tunnel is excavated and is used as primary support; monitoring and measuring the construction process by using a measuring instrument to obtain monitoring and measuring data; performing regression analysis on the monitoring measurement data to determine the construction time of the inverted arch and the secondary lining; determining the deformation grade of the tunnel according to the tunnel face sketch condition and the regression analysis of the monitoring measurement data; determining a tunnel management reference according to the tunnel deformation grade; evaluating the stability of the tunnel, and if the safety requirement is met, constructing a secondary lining; and if the safety requirement is not met, repeating the steps according to the construction condition. By adopting the scheme, monitoring measurement can be correctly carried out, real data of monitoring measurement can be effectively fed back, and supporting parameters and construction management levels can be adjusted by utilizing the monitoring measurement data, so that the safety of tunnel construction is improved, and the capital cost pressure is reduced.

Description

Monitoring and measuring method for high-ground-stress soft rock tunnel
Technical Field
The invention relates to the field of highway tunnels, in particular to a monitoring and measuring method for a high-ground-stress soft rock tunnel.
Background
In recent years, more and more mountain roads are planned and constructed, more and more tunnels are also planned and constructed, particularly in southwest mountainous areas, the earthquake intensity is high, the broken zones are accompanied by faults, the burial depth is large, the ground stress is high, the tunnels in water-rich soft rock strata bring great difficulty to the tunnel construction, the primary support is deformed for a long time, the soft rock strength is low, the weathering is easy, great deformation is easy to generate in the construction and construction process, and great hidden dangers are brought to the tunnel construction safety and the structural safety. The observation data of long-term monitoring and measurement are not timely and can not be effectively judged, large deformation is often caused, primary support cracking, damage, limit invasion and the like are caused, great hidden dangers are brought to the safety and the quality of the tunnel, and meanwhile, serious pressure is brought to the construction period and the capital cost.
Disclosure of Invention
The invention aims to solve the problems and provides a monitoring and measuring method for a high-ground-stress soft rock tunnel.
The technical scheme adopted by the invention is as follows: a monitoring and measuring method for a high-ground-stress soft rock tunnel comprises the following steps:
s1: making a special monitoring and measuring scheme for the high-ground-stress soft rock tunnel according to the design of the tunnel;
s2: at the moment, the tunnel starts to be constructed, and the tunnel is excavated and is used as primary support;
s3: in the primary supporting process, monitoring and measuring the construction process by using a measuring instrument to obtain monitoring and measuring data;
s4: performing regression analysis on the monitoring measurement data to determine the construction time of the inverted arch and the secondary lining;
s5: determining the deformation grade of the tunnel according to the tunnel face sketch condition and the regression analysis of the monitoring measurement data;
s6: determining a tunnel management reference according to the tunnel deformation grade;
s7: establishing an evaluation standard according to the past experience analogy, theoretical analysis and special requirements of projects, evaluating the stability of the tunnel by combining the evaluation standard with a tunnel management standard, and if the safety requirement is met, performing secondary lining to complete the construction of the section of the tunnel; if the safety requirements are not met, dynamic design and construction are required according to the deformation condition, and the steps from S2 to S7 are repeated according to the construction condition.
During the concrete operation of the scheme, in order to early warn the deformation amount of soft rock in the construction process and increase the safety of the tunnel construction process, before the tunnel construction, the concrete flow and the used tools of the scheme are made according to the tunnel design, then the tunnel construction is started, the tunnel is excavated and initially supported in the initial construction stage, in the construction process, a measuring instrument is adopted for monitoring and measuring, and monitoring and measuring data are obtained, the monitoring and measuring data comprise the soft rock deformation rate, the displacement distance when the tunnel wall deforms, the equivalent radius of the tunnel and other data, then regression analysis is carried out on the monitoring and measuring data, the change of daily data is analyzed to determine the making time of the inverted arch and the secondary lining, then the tunnel deformation grade is determined according to the combination of the tunnel face sketch condition and the regression analysis of the monitoring and measuring data, the tunnel deformation conditions reflected by different tunnel deformation grades are different, determining a tunnel management standard according to the total deformation of the tunnel deformation level, finally establishing an evaluation standard according to the past experience analogy, theoretical analysis and special requirements of projects, evaluating the stability of the tunnel by combining the evaluation standard with the tunnel management standard, and performing secondary lining if the safety requirement is met, so that the tunnel construction of the section is completed; if the safety requirements are not met, dynamic design and construction are required according to the deformation condition, and the steps from S2 to S7 are repeated according to the construction condition.
Further, the tunnel design needs to be designed according to tunnel detailed data, site survey data, relevant tunnel data collection and specification requirements.
Furthermore, the measuring instrument adopts three-dimensional laser scanning and total station instrument to combine measurement.
Furthermore, regression analysis is carried out on the monitoring measurement data, and the construction and construction time of the inverted arch and the secondary lining is determined according to the combination of deformation effect evaluation and deformation rate judgment.
Further, regression analysis is carried out on the monitored and measured data, and if the deformation control effect meets the requirement and the deformation tends to be stable, secondary lining and inverted arch construction are carried out;
and if the deformation control effect does not meet the requirement, the deformation rate is too high, and the deformation is not converged, taking treatment measures.
Further, the tunnel deformation grades can be divided into three grades of mild, moderate and severe;
mild: ua is 20-35 cm, and Ua/a is 3-6%; the failure of the primary support is shown as follows: the sprayed concrete layer is cracked, and the steel frame is partially separated from the sprayed layer
Medium: ua is 35-60 cm, and Ua/a is 6-10%; the failure of the primary support is shown as follows: the sprayed concrete layer is seriously cracked, blocks fall off, a local steel frame is deformed, and the anchor rod base plate is sunken.
Severe: ua is more than 60cm, and Ua/a is more than 10 percent; the failure of the primary support is shown as follows: the sprayed concrete layer is seriously cracked, the block falls, the local steel frame is deformed, the anchor rod base plate is sunken, but the large-area occurrence is realized, and the phenomena of anchor rod breakage and steel frame deformation and distortion are generated.
Ua is the displacement of the hole wall, and a is the equivalent radius of the tunnel.
Further, the tunnel management reference comprises three section deformation levels according to the accumulated deformation: u is less than 30 percent of U0、30%U0≤U<70U0And 70% U0≤U<100U0The deformation rate is divided into four interval deformation rate grades: 2 to 10mm/d, 10 to 30mm/d30-50 mm/d and more than 50 mm/d;
determining a tunnel management level according to 4 different interval deformation rate levels when the accumulated deformation is in each interval deformation level;
u is the total amount of deformation, U0And reserving deformation for design.
Furthermore, the tunnel management level is divided into four management levels, and each management level correspondingly adopts construction treatment measures;
a first stage: normal construction;
and a second stage: warning, strengthening detection and preparing a plan;
and a third stage: early warning, reason analysis and plan implementation;
fourth stage: alarming, checking the implementation condition of a plan, analyzing reasons, perfecting and strengthening measures, carrying out safety evaluation, and considering the suspension of construction when necessary.
The invention has the following beneficial effects:
according to the scheme, tunnel deformation is divided into three levels according to tunnel displacement, tunnel deformation management is divided into four levels according to deformation rate, construction measures are provided for the four levels respectively, and support parameters of surrounding rocks in front of a tunnel face can be selected reasonably according to tunnel face sketch and constructed paragraph primary support deformation levels in the implementation process. And reasonable construction measures are taken for the excavated paragraphs according to the deformation management level.
Therefore, the monitoring and measuring method for the high-ground-stress soft rock tunnel can widely guide the excavation of the high-ground-stress soft rock tunnel, is clear in flow arrangement, reasonable in large deformation grade division, clear in management grade, clear in construction measure corresponding to each management grade and convenient to guide construction. The invention is not only suitable for the high ground stress soft rock tunnel, but also suitable for the fault fracture zone.
Drawings
Fig. 1 is a flowchart of a monitoring and measuring method for a high ground stress soft rock tunnel according to the present invention.
Detailed Description
The present invention will be described in further detail with reference to examples.
Example (b): fig. 1 is a flowchart of a monitoring and measuring method for a high ground stress soft rock tunnel according to the present invention. A monitoring and measuring method for a high-ground-stress soft rock tunnel comprises the following steps:
s1: making a special monitoring and measuring scheme for the high-ground-stress soft rock tunnel according to the design of the tunnel;
s2: at the moment, the tunnel starts to be constructed, and the tunnel is excavated and is used as primary support;
s3: in the primary supporting process, monitoring and measuring the construction process by using a measuring instrument to obtain monitoring and measuring data;
s4: performing regression analysis on the monitoring measurement data to determine the construction time of the inverted arch and the secondary lining;
s5: determining the deformation grade of the tunnel according to the tunnel face sketch condition and the regression analysis of the monitoring measurement data;
s6: determining a tunnel management reference according to the tunnel deformation grade;
s7: establishing an evaluation standard according to the past experience analogy, theoretical analysis and special requirements of projects, evaluating the stability of the tunnel by combining the evaluation standard with a tunnel management standard, and if the safety requirement is met, performing secondary lining to complete the construction of the section of the tunnel; if the safety requirements are not met, dynamic design and construction are required according to the deformation condition, and the steps from S2 to S7 are repeated according to the construction condition.
In the embodiment, in order to early warn the deformation of soft rock in the construction process and increase the safety of the tunnel construction process, before the tunnel construction, the specific flow and the used tools of the scheme are made according to the tunnel design, then the tunnel construction is started, the tunnel is excavated and initially supported in the initial construction stage, in the construction process, a measuring instrument is adopted to carry out monitoring measurement and obtain monitoring measurement data, the monitoring measurement data comprises the data of soft rock deformation rate, displacement distance when the tunnel wall deforms, equivalent radius of the tunnel and the like, regression analysis is carried out on the monitoring measurement data, the change of daily data is analyzed to determine the construction time of the inverted arch and the secondary lining, then the tunnel deformation grade is determined according to the combination of the tunnel face sketch condition and the monitoring measurement data regression analysis, the tunnel deformation conditions reflected by different tunnel deformation grades are different, determining a tunnel management standard according to the total deformation of the tunnel deformation level, finally establishing an evaluation standard according to the past experience analogy, theoretical analysis and special requirements of projects, evaluating the stability of the tunnel by combining the evaluation standard with the tunnel management standard, and performing secondary lining if the safety requirement is met, so that the tunnel construction of the section is completed; if the safety requirements are not met, dynamic design and construction are required according to the deformation condition, and the steps from S2 to S7 are repeated according to the construction condition.
In this embodiment, the tunnel design needs to be designed according to the detailed tunnel survey data, the site survey data, the collection of the relevant tunnel data and the specification requirements.
In this embodiment, the measuring instrument adopts three-dimensional laser scanning and total station instrument to combine measurement.
In this embodiment, regression analysis of the monitored and measured data is performed to determine the timing of constructing the inverted arch and the secondary lining according to a combination of deformation effect evaluation and deformation rate judgment.
In the embodiment, regression analysis is performed on the monitored and measured data, and if the deformation control effect meets the requirement and the deformation tends to be stable, secondary lining and inverted arch construction are performed;
and if the deformation control effect does not meet the requirement, the deformation rate is too high, and the deformation is not converged, taking treatment measures.
In this embodiment, the tunnel deformation grades may be classified into mild, moderate and severe grades;
Figure BDA0002706886280000041
in the table, Ua is the displacement of the tunnel wall, and a is the equivalent radius of the tunnel; in the table, deformation and displacement are generated under the condition that preliminary bracing is constructed, and the bracing is conventional standard bracing.
Mild: ua is 20-35 cm, and Ua/a is 3-6%; the failure of the primary support is shown as follows: the sprayed concrete layer is cracked, and the steel frame is partially separated from the sprayed layer
Medium: ua is 35-60 cm, and Ua/a is 6-10%; the failure of the primary support is shown as follows: the sprayed concrete layer is seriously cracked, blocks fall off, a local steel frame is deformed, and the anchor rod base plate is sunken.
Severe: ua is more than 60cm, and Ua/a is more than 10 percent; the failure of the primary support is shown as follows: the sprayed concrete layer is seriously cracked, the block falls, the local steel frame is deformed, the anchor rod base plate is sunken, but the large-area occurrence is realized, and the phenomena of anchor rod breakage and steel frame deformation and distortion are generated.
In this embodiment, the tunnel management reference includes three section deformation levels according to the accumulated deformation: u is less than 30 percent of U0、30%U0≤U<70U0And 70% U0≤U<100U0The deformation rate is divided into four interval deformation rate grades: 2-10 mm/d, 10-30 mm/d, 30-50 mm/d and more than 50 mm/d;
determining a tunnel management level according to 4 different interval deformation rate levels when the accumulated deformation is in each interval deformation level;
Figure BDA0002706886280000051
note that in the table, U0 is the amount of deformation reserved for the design, and U is the total amount of deformation.
In the embodiment, the tunnel management level is divided into four management levels, and each management level correspondingly adopts construction treatment measures;
Figure BDA0002706886280000052
a first stage: normal construction;
and a second stage: warning, strengthening detection and preparing a plan;
and a third stage: early warning, reason analysis and plan implementation;
fourth stage: alarming, checking the implementation condition of a plan, analyzing reasons, perfecting and strengthening measures, carrying out safety evaluation, and considering the suspension of construction when necessary.
The above-mentioned embodiments are intended to illustrate the objects, technical solutions and advantages of the present invention in further detail, and it should be understood that the above-mentioned embodiments are merely exemplary embodiments of the present invention, and are not intended to limit the scope of the present invention, and any modifications, equivalent substitutions, improvements and the like made within the spirit and principle of the present invention should be included in the scope of the present invention.

Claims (8)

1. A monitoring and measuring method for a high-ground-stress soft rock tunnel is characterized by comprising the following steps:
s1: making a special monitoring and measuring scheme for the high-ground-stress soft rock tunnel according to the design of the tunnel;
s2: at the moment, the tunnel starts to be constructed, and the tunnel is excavated and is used as primary support;
s3: in the primary supporting process, monitoring and measuring the construction process by using a measuring instrument to obtain monitoring and measuring data;
s4: performing regression analysis on the monitoring measurement data to determine the construction time of the inverted arch and the secondary lining;
s5: determining the deformation grade of the tunnel according to the tunnel face sketch condition and the regression analysis of the monitoring measurement data;
s6: determining a tunnel management reference according to the tunnel deformation grade;
s7: establishing an evaluation standard according to the past experience analogy, theoretical analysis and special requirements of projects, evaluating the stability of the tunnel by combining the evaluation standard with a tunnel management standard, and if the safety requirement is met, performing secondary lining to complete the construction of the section of the tunnel; if the safety requirements are not met, dynamic design and construction are required according to the deformation condition, and the steps from S2 to S7 are repeated according to the construction condition.
2. The method as claimed in claim 1, wherein the design of the tunnel is based on the detailed survey data, the site survey data, the collection of the relevant tunnel data and the specification requirements.
3. The method as claimed in claim 1, wherein the measuring instrument is used for measuring by combination of three-dimensional laser scanning and total station.
4. The method as claimed in claim 1, wherein the regression analysis of the monitored data is determined according to the deformation effect evaluation and deformation rate.
5. The method for monitoring and measuring the high-ground-stress soft rock tunnel according to claim 4, wherein regression analysis is performed on the monitored and measured data, and if the deformation control effect meets the requirement and the deformation tends to be stable, secondary lining and inverted arch construction are performed;
and if the deformation control effect does not meet the requirement, the deformation rate is too high, and the deformation is not converged, taking treatment measures.
6. The method as claimed in claim 1, wherein the tunnel deformation is classified into mild, moderate and severe;
mild: ua is 20-35 cm, and Ua/a is 3-6%;
medium: ua is 35-60 cm, and Ua/a is 6-10%;
severe: ua is more than 60cm, and Ua/a is more than 10 percent;
ua is the displacement of the hole wall, and a is the equivalent radius of the tunnel.
7. The method as claimed in claim 6, wherein the tunnel management criteria includes three deformation levels according to the accumulated deformation: u is less than 30 percent of U0、30%U0≤U<70U0And 70% U0≤U<100U0The deformation rate is divided into four interval deformation rate grades: 2 to 10mm/d,10-30 mm/d, 30-50 mm/d and more than 50 mm/d;
determining a tunnel management level according to 4 different interval deformation rate levels when the accumulated deformation is in each interval deformation level;
u is the total amount of deformation, U0And reserving deformation for design.
8. The method as claimed in claim 7, wherein the tunnel management level is divided into four management levels, each management level corresponding to a construction treatment;
a first stage: normal construction;
and a second stage: warning, strengthening detection and preparing a plan;
and a third stage: early warning, reason analysis and plan implementation;
fourth stage: alarming, checking the implementation condition of a plan, analyzing reasons, perfecting and strengthening measures, carrying out safety evaluation, and considering the suspension of construction when necessary.
CN202011041888.5A 2020-09-28 2020-09-28 Monitoring and measuring method for high-ground-stress soft rock tunnel Pending CN111997630A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011041888.5A CN111997630A (en) 2020-09-28 2020-09-28 Monitoring and measuring method for high-ground-stress soft rock tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011041888.5A CN111997630A (en) 2020-09-28 2020-09-28 Monitoring and measuring method for high-ground-stress soft rock tunnel

Publications (1)

Publication Number Publication Date
CN111997630A true CN111997630A (en) 2020-11-27

Family

ID=73475443

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011041888.5A Pending CN111997630A (en) 2020-09-28 2020-09-28 Monitoring and measuring method for high-ground-stress soft rock tunnel

Country Status (1)

Country Link
CN (1) CN111997630A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112727469A (en) * 2020-12-28 2021-04-30 中铁十九局集团第六工程有限公司 Monitoring and measuring method for tunnel of tillite layer
CN113266364A (en) * 2021-05-29 2021-08-17 贵州铁建工程质量检测咨询有限公司 Tunnel construction monitoring measurement and super-undermining measurement control technology
CN113360998A (en) * 2021-07-14 2021-09-07 四川绵九高速公路有限责任公司 Large deformation trend dynamic judgment and construction decision method for large deformation tunnel
CN115900635A (en) * 2023-03-09 2023-04-04 四川省交通勘察设计研究院有限公司 Tunnel deformation data monitoring method, device and system
CN117993088A (en) * 2024-04-07 2024-05-07 中交天津港湾工程研究院有限公司 Method for predicting stress of second lining of soft rock large-deformation tunnel

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102900441A (en) * 2012-09-18 2013-01-30 铁道部经济规划研究院 China tunnel construction method based on complete deformation control of surrounding rocks
CN103837125A (en) * 2014-03-19 2014-06-04 中铁隧道集团有限公司 Convergence monitoring system for tunnel construction
CN105401947A (en) * 2015-10-26 2016-03-16 中铁二十局集团有限公司 Large-deformation control construction method for high ground stress weak surrounding rock tunnel
CN105937408A (en) * 2016-06-15 2016-09-14 中国铁道科学研究院电子计算技术研究所 Tunnel surrounding rock deformation early-warning method and system
US20200018164A1 (en) * 2018-07-12 2020-01-16 China Institute Of Water Resources And Hydropower Research Advanced monitoring device for whole-process deformation curve of surrounding rock of tunnel excavation and implementation method thereof
CN111058855A (en) * 2019-11-11 2020-04-24 北京住总集团有限责任公司 Deformation control method and evaluation system for shield underpassing structure
WO2020119018A1 (en) * 2018-12-14 2020-06-18 山东科技大学 Device for monitoring horizontal extrusion force of top rock and use method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102900441A (en) * 2012-09-18 2013-01-30 铁道部经济规划研究院 China tunnel construction method based on complete deformation control of surrounding rocks
CN103837125A (en) * 2014-03-19 2014-06-04 中铁隧道集团有限公司 Convergence monitoring system for tunnel construction
CN105401947A (en) * 2015-10-26 2016-03-16 中铁二十局集团有限公司 Large-deformation control construction method for high ground stress weak surrounding rock tunnel
CN105937408A (en) * 2016-06-15 2016-09-14 中国铁道科学研究院电子计算技术研究所 Tunnel surrounding rock deformation early-warning method and system
US20200018164A1 (en) * 2018-07-12 2020-01-16 China Institute Of Water Resources And Hydropower Research Advanced monitoring device for whole-process deformation curve of surrounding rock of tunnel excavation and implementation method thereof
WO2020119018A1 (en) * 2018-12-14 2020-06-18 山东科技大学 Device for monitoring horizontal extrusion force of top rock and use method
CN111058855A (en) * 2019-11-11 2020-04-24 北京住总集团有限责任公司 Deformation control method and evaluation system for shield underpassing structure

Non-Patent Citations (8)

* Cited by examiner, † Cited by third party
Title
侯永生等: "《隧道施工技术问答》", 31 January 2014, 中国铁道出版社 *
巫晨笛: "隧道施工监测与塌方动态分析预警系统研发及应用", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 *
李天斌等: "隧道坍方动态分析与综合预警方法研究", 《隧道与地下工程灾害防治》 *
李春林等: "龙溪隧道初期支护监控量测技术初步研究", 《地质灾害与环境保护》 *
杨秀飞: "监控量测技术在隧道施工中的应用", 《中国新技术新产品》 *
汪耀等: "鹧鸪山高地应力软岩隧道大变形预测与施工技术研究", 《路基工程》 *
胡荣明: "《工程测量学》", 30 April 2013, 中国矿业大学出版社 *
霍明: "《山区高速公路勘察设计指南》", 31 July 2003, 人民交通出版社 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112727469A (en) * 2020-12-28 2021-04-30 中铁十九局集团第六工程有限公司 Monitoring and measuring method for tunnel of tillite layer
CN113266364A (en) * 2021-05-29 2021-08-17 贵州铁建工程质量检测咨询有限公司 Tunnel construction monitoring measurement and super-undermining measurement control technology
CN113266364B (en) * 2021-05-29 2022-10-04 贵州铁建工程质量检测咨询有限公司 Tunnel construction monitoring measurement and overbreak and undermining measurement control method
CN113360998A (en) * 2021-07-14 2021-09-07 四川绵九高速公路有限责任公司 Large deformation trend dynamic judgment and construction decision method for large deformation tunnel
CN115900635A (en) * 2023-03-09 2023-04-04 四川省交通勘察设计研究院有限公司 Tunnel deformation data monitoring method, device and system
CN117993088A (en) * 2024-04-07 2024-05-07 中交天津港湾工程研究院有限公司 Method for predicting stress of second lining of soft rock large-deformation tunnel
CN117993088B (en) * 2024-04-07 2024-07-26 中交天津港湾工程研究院有限公司 Method for predicting stress of second lining of soft rock large-deformation tunnel

Similar Documents

Publication Publication Date Title
CN111997630A (en) Monitoring and measuring method for high-ground-stress soft rock tunnel
Cheng et al. A zoning model for coal mining-induced strata movement based on microseismic monitoring
CN105257339A (en) Multi-parameter integrated monitoring and early-warning method for excavation working face
CN104390537A (en) Method for controlling damage of slope pre-splitting blasting digging based on blast vibration test
CN109506614B (en) Method for judging large deformation of layered surrounding rock
CN105672371A (en) Existing engineering pile body completeness and defect type judging method
CN114251103B (en) Directional joint-cutting fracturing roof main roadway scour-prevention roadway-protecting method and safe mining method
US20240110479A1 (en) Multi-factor quantitative analysis method for deformation of neighborhood tunnel
Yu et al. Multivariate early warning method for rockburst monitoring based on microseismic activity characteristics
Sun et al. Analysis of roof deformation mechanism and control measures with roof cutting and pressure releasing in gob‐side entry retaining
CN108868777B (en) Comprehensive detection and treatment construction method for tunnel unfavorable geological surrounding rock
CN103244185A (en) Early warning method for instability of bolt-supported roadway roof separation
Zhou et al. Research on reasonable reserved deformation and height-span ratio of a large deformation tunnel section in high geo-stress soft rock near a fault zone: a case study
CN110502794B (en) Prediction method for high-ground stress concentration zone damage mode of surrounding rock at lower part of large-scale slow-dip angle weak structural surface
Qin et al. Stability and control of retracement channels in thin seam working faces with soft roof
CN110579194A (en) On-site testing method and application of fracture position of lateral basic roof rock beam of gob-side roadway
CN115655362A (en) Construction comprehensive monitoring method for optimizing shallow-buried large-section underground excavation tunnel construction method
CN114320268B (en) Major diameter drilling pressure relief effect evaluation method based on drilling stress monitoring
CN115288607A (en) Large-diameter drilling pressure relief method for high horizontal stress area of regional structure
CN115929408A (en) System and method for monitoring coal mine roof cracks in real time in roadway driving process
CN115288704A (en) Safety risk assessment and construction method for pile foundation settlement caused by shield tunneling
CN114526073A (en) Design method and mining method for two-side fully mining area going up hill and preventing coal pillar from rushing
CN115374611A (en) Method for judging tunnel soft rock large deformation disaster risk level under complex geological condition
CN109766628A (en) A kind of prominent hidden danger degree tri-layer that gushes in great burying tunnel recycles progressive quantization method
CN115560723B (en) Advanced measurement method for instantaneous deformation of surrounding rock of large-span tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20201127