CN111980165A - Large-span net rack external-expanding splicing integral jacking construction method - Google Patents

Large-span net rack external-expanding splicing integral jacking construction method Download PDF

Info

Publication number
CN111980165A
CN111980165A CN202010785410.7A CN202010785410A CN111980165A CN 111980165 A CN111980165 A CN 111980165A CN 202010785410 A CN202010785410 A CN 202010785410A CN 111980165 A CN111980165 A CN 111980165A
Authority
CN
China
Prior art keywords
jacking
net rack
assembling
grid
expanding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010785410.7A
Other languages
Chinese (zh)
Inventor
于景民
徐超
马海龙
赵宝重
张�浩
高磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN202010785410.7A priority Critical patent/CN111980165A/en
Publication of CN111980165A publication Critical patent/CN111980165A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35—Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B1/3511—Lift-slab; characterised by a purely vertical lifting of floors or roofs or parts thereof
    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14—Conveying or assembling building elements
    • E04G21/16—Tools or apparatus
    • E04G21/163—Jacks specially adapted for working-up building elements
    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35—Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B2001/3577—Extraordinary methods of construction, e.g. lift-slab, jack-block prefabricating a building and moving it as a whole to the erection site
    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35—Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B2001/3588—Extraordinary methods of construction, e.g. lift-slab, jack-block using special lifting or handling devices, e.g. gantries, overhead conveying rails

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a construction method for externally expanding, splicing and integrally jacking a large-span net rack, which belongs to the field of building construction, and aims to solve the technical problems of reducing the construction difficulty of a spherical shell, a cylindrical shell, a flat plate and various special-shaped stadium large-span net rack structures under complex conditions, reducing high-construction operation, improving safety and simultaneously ensuring construction quality, wherein the technical scheme is as follows: the construction method comprises the following specific steps: assembling and jacking: assembling the net rack on the ground, installing a jacking bracket when the net rack is assembled to the position of the stand, and stopping jacking when the net rack is jacked by the jacking bracket to a set height to meet the assembly of the next grid; symmetrically expanding and assembling: after the jacking operation is stopped, symmetrically expanding and assembling the completed space rigidity units from the center of the net rack, so that the net rack continuously extends to the periphery; adjusting the number and the positions of jacking points: when the net rack is expanded and spliced outwards, the number and the positions of the jacking points of the net rack are adjusted according to the calculation result; and (4) unloading and dismantling.

Description

大跨度网架外扩拼装整体顶升施工方法Construction method of overall jacking of large-span grid frame with external expansion and assembly

技术领域technical field

本发明涉及建筑施工领域,尤其适用于球壳、筒壳、平板及各种异形网架下弦标高25m及以下的工程,特别针对焊接节点、螺栓球节点与焊接球节点混装的网架结构,具体地说是一种大跨度网架外扩拼装整体顶升施工方法。The invention relates to the field of building construction, and is especially suitable for spherical shells, cylindrical shells, flat plates and projects with a lower chord elevation of 25m and below of various special-shaped grid frames, especially for grid structures in which welded joints, bolted ball joints and welded ball joints are mixed. Specifically, it is a large-span grid frame external expansion and assembly overall jacking construction method.

背景技术Background technique

随着各地大型体育场馆、剧院、文体中心的兴建,各类大跨度钢结构网架越来越多的应用到建筑屋盖中。此类工程的钢结构网架一方面跨度大、体量多且高度高,另一方面由于网架往往架立在场馆中心,施工中往往存在着起重机械外围吊装难度、成本较高的情况。With the construction of large-scale stadiums, theaters, and cultural and sports centers in various places, various types of large-span steel structure grids are more and more applied to building roofs. On the one hand, the steel structure grids of such projects have large spans, large volumes and high heights. On the other hand, because the grids are often erected in the center of the venue, there are often difficulties in hoisting the periphery of the hoisting machinery and high costs during construction. .

故如何减少球壳、筒壳、平板及各种异形场馆类大跨度网架结构复杂条件下的施工难度,减少高工作业,提高安全性的同时确保施工质量是目前亟待解决的技术问题。Therefore, how to reduce the construction difficulty of spherical shells, cylinder shells, flat plates and various special-shaped stadiums and large-span grid structures under complex conditions, reduce high-level work, improve safety and ensure construction quality is a technical problem that needs to be solved urgently.

发明内容SUMMARY OF THE INVENTION

本发明的技术任务是提供一种大跨度网架外扩拼装整体顶升施工方法,来解决如何减少球壳、筒壳、平板及各种异形场馆类大跨度网架结构复杂条件下的施工难度,减少高工作业,提高安全性的同时确保施工质量的问题。The technical task of the present invention is to provide a large-span grid frame external expansion and assembly integral jacking construction method to solve how to reduce the construction difficulty of spherical shells, cylinder shells, flat plates and various special-shaped venues under the complex structure of large-span grid frames , reduce high-level work, improve safety while ensuring construction quality.

本发明的技术任务是按以下方式实现的,大跨度网架外扩拼装整体顶升施工方法,该施工方法具体如下:The technical task of the present invention is achieved in the following manner, the construction method for the overall jacking of the large-span grid frame is expanded and assembled, and the construction method is as follows:

拼装及顶升:网架在地面进行拼装,拼装到看台位置时安装顶升支架,利用顶升支架把网架顶升设定高度(每次顶升高度不同,根据土建情况确定)满足下一网格拼装时,停止顶升工作;Assembling and jacking: The grid is assembled on the ground, and the jacking bracket is installed when it is assembled to the stand position, and the grid frame is lifted to a set height by the jacking bracket (the jacking height is different for each time, determined according to the civil construction) to meet the next requirements. When the grid is assembled, stop the lifting work;

对称外扩拼装:顶升工作停止后,由网架中心开始对称外扩拼装已完成的空间刚度单元,使网架不断向四周延伸;Symmetrical expansion and assembly: After the lifting work is stopped, the completed spatial rigidity unit will be symmetrically expanded and assembled from the center of the grid frame, so that the grid frame will continue to extend around;

调整顶升点数量及位置:向外扩展拼接时,根据计算结果对网架顶升点的数量和位置进行调整;Adjust the number and position of jacking points: when expanding and splicing outward, adjust the number and position of jacking points of the grid according to the calculation results;

卸载及拆除:重复拼装及顶升、对称外扩拼装及调整顶升点数量及位置,直至网架升至结构标高以上位置后,网架完成后嵌补柱顶杆件、卸载并拆除顶升装置,网架施工完成。Unloading and dismantling: Repeat assembly and jacking, symmetrically expand and assemble and adjust the number and position of jacking points until the net frame is raised to a position above the structural level. After the net frame is completed, the column top members are inserted, unloaded and removed for jacking. Installation, grid construction is completed.

作为优选,该施工方法的工艺流程具体如下:As preferably, the technological process of this construction method is as follows:

S1、施工前准备;S1. Preparation before construction;

S2、网架拼装;S2, grid assembly;

S3、顶升点布置,安装顶升装置;S3, jacking point arrangement, install jacking device;

S4、质量与安全检查;S4, quality and safety inspection;

S5、试顶升;S5, try jacking;

S6、正式顶升;S6, official jacking up;

S7、外扩拼装及循环提升;S7. External expansion and assembly and circulation improvement;

S8、提升到位及对接支座;S8. Lift in place and dock the support;

S9、同步卸载;S9, synchronous uninstall;

S10、拆除顶升装置,安装完成。S10, remove the jacking device, and the installation is completed.

更优地,所述步骤S1中施工前准备具体如下:More preferably, the preparation before construction in the step S1 is as follows:

S101、对已进场的网架材料进行清点,球、杆分别分类堆放,并对球、杆的加工尺寸进行校核,以保证安装精度,否则不得使用;S101. Inventory the grid materials that have entered the site, classify and stack the balls and rods separately, and check the processing dimensions of the balls and rods to ensure the installation accuracy, otherwise they cannot be used;

S102、现场堆放的杂物必须清理干净,以保证工程施工的顺利进行;S102. The sundries stacked on the site must be cleaned up to ensure the smooth progress of the project construction;

S103、根据场地情况和结构外形采用MIDAS计算顶升架数量和位置,进行应力和变形核算;网架经过验算后,若发现有超应力杆,则进行临时加固,即在杆件外侧用夹具加固;S103. Use MIDAS to calculate the number and position of the jacking frame according to the site conditions and structural shape, and perform stress and deformation calculation; after the grid frame is checked and calculated, if it is found that there is an overstressed rod, temporary reinforcement is performed, that is, the outer side of the rod is reinforced with a clamp ;

S104、按照方案位置放出顶升架安装位置及部分下弦球的投影位置,对于下方有混凝土结构的其位置定位应放在柱梁部位;S104. Release the installation position of the jacking frame and the projection position of part of the lower chord ball according to the planned position. The position of the concrete structure below should be placed on the column beam position;

S105、检查顶升设备,确保顶升过程中设备运转正常;S105. Check the jacking equipment to ensure that the equipment operates normally during the jacking process;

S106、检查顶升设备的基础,基础应有足够的强度,否则应事先进行处理。S106. Check the foundation of the jacking equipment, the foundation should have sufficient strength, otherwise it should be dealt with in advance.

更优地,所述步骤S2中网架拼装具体如下:More preferably, the grid assembling in the step S2 is as follows:

S201、安装下弦平面网架,具体包括:S201. Install the lower chord plane grid, specifically including:

S20101、柱轴线及中心线对中,用水平仪复核标高,有误差应予修正;S20101. Align the axis and center line of the column, check the elevation with a spirit level, and correct any errors;

S20102、安装网架中心区域下弦球及杆组成纵向平面网格;排好临时支点,保证下弦球的平等度;当有起拱要求时,在临时支点上找出坡底;S20102. Install the lower string ball and rod in the central area of the grid frame to form a longitudinal plane grid; arrange the temporary fulcrum to ensure the equality of the lower string ball; when there is a requirement for arching, find the bottom of the slope on the temporary fulcrum;

S20103、安装第一单元间的腹杆与上弦球,第一个锥为一球四腹杆的小单元,就位后与下弦球拧入并固定;S20103. Install the web rod and the upper string ball between the first units. The first cone is a small unit with one ball and four web rods. After it is in place, it is screwed into and fixed with the bottom string ball;

S20104、第二个锥起为先装一球一弦杆二腹杆的三角锥,再填入另外两根腹杆,逐步循环安装完第一单元的网架;S20104. The second cone is a triangular cone with a ball, a chord, and two webs first, and then the other two webs are filled, and the grid frame of the first unit is installed in a cycle step by step;

S20105、检查网架、网格尺寸及网架纵向尺寸与矢高;同时检查网架位置,若有出入,则调整临时支点的位置和高低,以校准网架定位尺寸;S20105. Check the grid frame, grid size, longitudinal dimension and sag height of the grid frame; at the same time, check the position of the grid frame. If there is any discrepancy, adjust the position and height of the temporary fulcrum to calibrate the positioning size of the grid frame;

S202、安装上弦倒三角网格,具体包括:S202, install the upper chord inverted triangular mesh, specifically including:

S20201、从边跨开始先将一球一上弦二腹杆的三角锥,之后为一球二上弦二腹杆的四角锥;S20201, starting from the side span, firstly make a triangular cone with one ball, one winding and two belly rods, and then a quadrangular pyramid with one ball, two windings and two belly rods;

S20202、将二斜腹杆支撑在下弦球上,在上方拉紧上弦杆,使上弦杆逐步靠近已安装好的上弦球(推锥)拧入、调整并紧固;S20202. Support the second inclined web bar on the lower chord ball, and tighten the upper chord bar above, so that the upper chord bar is gradually approached to the installed upper chord ball (push cone), screwed in, adjusted and tightened;

S20203、网架安装过程中,随时检查网架轴线与建筑基础轴线是否偏离,并随时调整;S20203. During the installation of the grid, check whether the axis of the grid is deviated from the axis of the building foundation at any time, and adjust it at any time;

S20204、检查网架整体挠度,严格控制网架上下弦尺寸,确保每个螺栓均旋紧到位;S20204. Check the overall deflection of the grid frame, strictly control the size of the upper and lower chords of the grid frame, and ensure that each bolt is tightened in place;

S20205、网架在安装过程中随时检查各临时支点的下沉情况,若有下降情况,则及时加固。S20205. Check the subsidence of each temporary fulcrum at any time during the installation process of the grid frame. If there is a drop, reinforce it in time.

更优地,所述网架采用钢网架,钢网架的拼装过程具体如下:More preferably, the mesh frame adopts a steel mesh frame, and the assembling process of the steel mesh frame is as follows:

(1)、在地面上将第一个下弦网格临时支撑点定位;(1) Position the temporary support point of the first lower chord grid on the ground;

(2)、在临时支撑点上完成第一个网格下弦杆件的组装;(2) Complete the assembly of the first mesh lower chord on the temporary support point;

(3)、将一个上弦球以及与之相连的网架腹杆组装成整体与安装就位的下弦单元拼装成整体结构;(3) Assemble a top chord ball and the web frame web bar connected to it into a whole and assemble the lower chord unit installed in place into an integral structure;

(4)、组装下一单元格网架下弦构件;(4), assemble the lower chord member of the next cell grid;

(5)、将一个上弦球以及与之相连的网架腹杆以及一侧的一根上弦杆组装成整体与安装就位的下弦单元拼装成整体结构;(5), assemble a top chord ball and the web frame web rod connected to it and a top chord rod on one side into a whole and the installed bottom chord unit into an overall structure;

(6)、重复步骤步骤(4)和步骤(5)继续进行其余网格构件的拼装;(6), repeat steps (4) and step (5) to continue the assembling of the remaining grid members;

(7)、直至完成整个结构拼装。(7), until the entire structure is assembled.

更优地,所述步骤S3中顶升装置的位置确定过程中,确保在顶升过程中每个节点球儿受力均匀,顶升装置底部设置钢板支座,避免顶升装置对支撑面的压强过大;More preferably, in the process of determining the position of the jacking device in the step S3, it is ensured that each node ball is uniformly stressed during the jacking process, and the bottom of the jacking device is provided with a steel plate support to avoid the jacking device. Excessive pressure;

当顶升装置在混凝土结构面上时,将支撑点设在混凝土柱子及梁的部位,并通过验算确定是否需要加固;When the jacking device is on the concrete structure surface, set the support point at the position of the concrete column and beam, and determine whether it needs to be reinforced by checking calculation;

当支撑点未放置在主梁处,在楼板上提前做好预留洞并对地面进行处理,同时对地面的承载力进行验算,确保地面沉降量不能影响施工质量和安全,再将顶升装置穿过预留洞立在地面上。When the supporting point is not placed at the main beam, make a reserved hole in the floor in advance and deal with the ground, and at the same time, check the bearing capacity of the ground to ensure that the ground subsidence does not affect the construction quality and safety, and then install the jacking device. Go through the reserved hole and stand on the ground.

更优地,所述步骤S6中正式顶升具体如下:More preferably, the formal jacking in the step S6 is as follows:

S601、利用全站仪复核网架不同方位点的标高和变形情况,各标高点的允许偏差根据网架的施工验算确定;S601. Use a total station to review the elevation and deformation of different azimuth points of the grid frame, and the allowable deviation of each elevation point is determined according to the construction check calculation of the grid frame;

S602、每次顶升1.5m左右暂停,对网架各点偏差进行检查,分次将网架顶升到预定标高后固定;S602. Pause for about 1.5m each time of jacking up, check the deviation of each point of the grid frame, and lift the grid frame to the predetermined elevation in stages and fix it;

S603、待顶升到预定标高固定后,检查网架整体位移和扭转偏差;当存在较大偏差,利用混凝土结构为拉结点,通过倒链调;S603. After being jacked up to a predetermined elevation and fixed, check the overall displacement and torsional deviation of the grid frame; when there is a large deviation, use the concrete structure as the tension point, and adjust the grid through the reverse chain;

S604、增高时下托架受力,当活塞杆完全伸出时增加一节支撑架,相关螺栓拧紧后活塞杆回缩,上托架受力,当活塞杆完全收回时,下托架收至上一个可受力处,上挪横杆(受力杆),横杆要与下托架受力梁位置对应;S604. When the height is increased, the lower bracket is stressed. When the piston rod is fully extended, a support bracket is added. After the relevant bolts are tightened, the piston rod is retracted, and the upper bracket is stressed. When the piston rod is fully retracted, the lower bracket is retracted to the previous one. Move the cross bar (stressed bar) upward at the place where it can bear the force, and the horizontal bar should correspond to the position of the stress beam of the lower bracket;

S605、拆除时上托架受力,活塞杆回缩至不受力,下挪横杆(受力杆),横杆要与下托架受力梁位置对应,活塞杆伸出,将下托架移到下一支撑架处,使下托架受力,上托架不受力,拆除一节支撑架。S605. When dismantling, the upper bracket is stressed, the piston rod is retracted to no force, and the horizontal rod (stressed rod) is moved down. The horizontal rod should correspond to the position of the stressed beam of the lower bracket. Move the frame to the next support frame, so that the lower bracket is stressed, the upper bracket is not stressed, and a section of the support frame is removed.

更优地,所述步骤S7中外扩拼装及循环提升具体如下:More preferably, the step S7 is as follows:

S701、待网架顶升到设定高度,能够满足网架外扩拼装要求时,停止顶升;S701. When the grid frame is lifted to the set height and can meet the requirements of the grid frame's expansion and assembly, stop lifting;

S702、把已经组装完成的微型网架单元通过吊装进行外扩拼装;同时根据外扩尺寸,及时按计算确定位置增加顶升装置;S702, expand and assemble the assembled micro-grid unit by hoisting; at the same time, according to the expansion size, add a lifting device according to the position determined by calculation in time;

S703、外扩拼装、顶升装置安装完成后,再次进行试顶升,以确保前后安装的顶升装置同步;S703. After the external expansion assembly and the installation of the jacking device are completed, try jacking again to ensure that the jacking devices installed in the front and rear are synchronized;

S704、在外扩拼装、循环顶升的过程中,注意缆风绳、拉结钢丝绳的安装和调整应用;当顶升到3米高度时,为确保整体稳定,给顶升设备增加斜支撑;当顶升到10米高度时采用缆风绳,缆风绳斜拉角度不小于30度,布置位置为顶升桁架四角。S704. During the process of expanding and assembling and cyclic jacking, pay attention to the installation and adjustment of cable wind ropes and knotted wire ropes; when jacking up to a height of 3 meters, in order to ensure the overall stability, add inclined supports to the jacking equipment; When jacking up to a height of 10 meters, the cable wind rope is used, and the cable wind rope cantilever angle is not less than 30 degrees, and the arrangement position is the four corners of the jacking truss.

更优地,所述步骤S8中提升到位及对接支座具体如下:More preferably, the lifting in place and the docking support in the step S8 are as follows:

S801、网架外扩拼装到预定范围,顶升到支座标高后,停止顶升;S801. The grid frame is expanded and assembled to a predetermined range, and the jacking is stopped after it is jacked up to the support height;

S802、对网架标高、位移及扭转偏差进行复核及调整,调整到位后完成支座杆件嵌补工作;同时进行支座的安装和标高调整,确保网架、支座对接质量;S802. Review and adjust the height, displacement and torsional deviation of the grid frame, and complete the embedding work of the support rods after the adjustment is in place; at the same time, carry out the installation and elevation adjustment of the support to ensure the quality of the connection between the grid frame and the support;

S803、待网架下落,支座受力后,再进行剩余悬挑节点球和杆件的拼装工作,直至网架拼装全部完成。S803 , after the grid frame is dropped and the support is stressed, the remaining cantilever node balls and rods are assembled until the grid frame is completely assembled.

更优地,所述步骤S9中同步卸载具体如下:More preferably, the synchronous unloading in the step S9 is as follows:

S901、卸载前测量网架中部节点的标高;S901. Measure the elevation of the node in the middle of the grid before unloading;

S902、在电脑的控制下顶升装置每次同步下降10mm,观察顶升装置与网架是否脱离,同时测量网架中部节点标高变化情况,直至顶升装置与网架完全脱离;S902. Under the control of the computer, the jacking device is lowered synchronously by 10mm each time, observe whether the jacking device is separated from the grid frame, and measure the elevation change of the middle node of the grid frame until the jacking device is completely separated from the grid frame;

所述步骤S10中拆除顶升装置,安装完成具体如下:In the step S10, the lifting device is removed, and the installation is completed as follows:

S1001、顶升装置拆除两节后,用吊车将剩余支撑架整体吊平放到在地面上;S1001. After removing the two sections of the jacking device, use a crane to hoist the remaining support frame as a whole and place it on the ground;

S1002、在地面拆除,码放整齐,运至场外。S1002. Dismantle on the ground, stack them neatly, and transport them off-site.

本发明的大跨度网架外扩拼装整体顶升施工方法具有以下优点:The large-span grid frame externally expanded and assembled integral jacking construction method of the present invention has the following advantages:

(一)本发明成功解决了场馆类大跨度网架结构复杂条件下的施工难题,通过本发明的应用,工程在工期、质量、成本以及安全方面均得以很好的控制,取得了良好的社会效益和经济效益;(1) The present invention successfully solves the construction problem under complex conditions of the large-span grid structure of venues. Through the application of the present invention, the project can be well controlled in terms of construction period, quality, cost and safety, and a good social benefits and economic benefits;

(二)本发明采用800*800mm标准节作为承载装置,便于安装、拆卸,标准节采用圆管与法兰焊接,便于安装;(2) The present invention adopts the 800*800mm standard section as the bearing device, which is convenient for installation and disassembly, and the standard section is welded with a round pipe and a flange, which is convenient for installation;

(三)液压同步提升技术的核心设备采用计算机控制,全自动完成同步升降、负载平衡、姿态校正、应力控制、操作闭锁、过程显示和故障报警等多种功能,是集机、电、液、传感器、计算机于一体的现代化先进设备;(3) The core equipment of hydraulic synchronous lifting technology is controlled by computer, which can automatically complete various functions such as synchronous lifting, load balancing, attitude correction, stress control, operation locking, process display and fault alarm. Modern advanced equipment integrating sensors and computers;

(四)本发明的实施能够保证网架在地面或较低空间内拼装,高空作业少,降低了安全风险,同时方便质量监控,可以具体到每一个点、面,减少隐患,保证质量;(4) The implementation of the present invention can ensure that the grid frame is assembled on the ground or in a lower space, with less high-altitude operations, reducing safety risks, and at the same time facilitating quality monitoring, which can be specific to each point and surface, reducing hidden dangers and ensuring quality;

(五)本发明采用顶升法安装,避免了搭设脚手架对工期的影响,降低了措施费,同时大部分工作在地面完成,几乎不受风、雨等气候影响,提高了工作效率,缩短了工期;(5) The present invention adopts the jacking method for installation, which avoids the influence of erecting scaffolds on the construction period, reduces the cost of measures, and at the same time, most of the work is done on the ground, which is almost not affected by weather such as wind and rain, which improves the work efficiency and shortens the time. construction period;

(六)对于设有看台、辅房或设置地下室的体育场馆、多层建筑上置的网架,解决了结构造型无法一次性整体顶升的困难;(6) For stadiums with grandstands, auxiliary rooms or basements, and grids placed on multi-storey buildings, the difficulty that the structural shape cannot be lifted as a whole at one time has been solved;

(七)本发明降低了工程成本,缩短了工期,为工程的按期交付创造了条件。顶升工艺不产生噪音和各种垃圾,所有顶升装置均可周转使用,符合环保理念;网架顶升做法的应用获得了业界较高关注,多次迎接外部单位的观摩和交流,对企业起到了很好的宣传作用。(7) The present invention reduces the cost of the project, shortens the construction period, and creates conditions for the on-time delivery of the project. The jacking process does not produce noise and all kinds of garbage, and all jacking devices can be used in a turnaround, which is in line with the concept of environmental protection; the application of the grid jacking method has received high attention in the industry, and has welcomed the observation and exchange of external units for many times. Played a good publicity role.

附图说明Description of drawings

下面结合附图对本发明进一步说明。The present invention will be further described below with reference to the accompanying drawings.

附图1为大跨度网架外扩拼装整体顶升施工方法的流程框图;Accompanying drawing 1 is the flow chart of the construction method of large-span grid frame external expansion and assembling integral jacking;

附图2为节点加固的结构示意图;Accompanying drawing 2 is the structural schematic diagram of node reinforcement;

附图3为钢网架拼装过程中支撑垫定位的示意图;Accompanying drawing 3 is the schematic diagram of support pad positioning in the steel grid assembling process;

附图4为钢网架拼装过程中第一个网格下弦杆件的组装的示意图;Accompanying drawing 4 is the schematic diagram of the assembly of the first grid lower chord member in the steel grid assembling process;

附图5为钢网架拼装过程中整体与安装就位的下弦单元拼装成整体结构的示意图;Accompanying drawing 5 is the schematic diagram of the overall structure assembled with the lower chord unit installed in place in the steel mesh frame assembly process;

附图6为钢网架拼装过程中组装下一单元格网架下弦构件的示意图;Accompanying drawing 6 is the schematic diagram of assembling the lower chord member of the next cell grid frame in the steel grid frame assembling process;

附图7为钢网架拼装过程中整体与安装就位的下弦单元拼装成整体结构的示意图;Accompanying drawing 7 is the schematic diagram of the overall structure assembled with the lower chord unit installed in place in the steel mesh frame assembly process;

附图8为钢网架拼装过程中其余网格构件的拼装的示意图;Accompanying drawing 8 is the schematic diagram of the assembling of the remaining grid members in the steel grid assembling process;

附图9为整个结构拼装完成的示意图;Accompanying drawing 9 is the schematic diagram that the whole structure is assembled;

附图10为顶升装置钢板底座得到示意图;Figure 10 is a schematic diagram of the steel plate base of the jacking device;

附图11为顶升装置基础处理的示意图;Figure 11 is a schematic diagram of the basic treatment of the jacking device;

附图12为顶升架安装过程的示意图;12 is a schematic diagram of the installation process of the jacking frame;

附图13为油缸安装过程的示意图;13 is a schematic diagram of the installation process of the oil cylinder;

附图14为缆风绳拉设示意图。Figure 14 is a schematic diagram of the cable wind rope pulling.

具体实施方式Detailed ways

参照说明书附图和具体实施例对本发明的大跨度网架外扩拼装整体顶升施工方法作以下详细地说明。With reference to the accompanying drawings and specific embodiments of the description, the construction method of the large-span grid frame outwardly expanding and assembling integral jacking of the present invention will be described in detail below.

实施例1:Example 1:

本发明的大跨度网架外扩拼装整体顶升施工方法,该施工方法具体如下:The construction method of the large-span grid frame of the present invention is as follows:

(一)拼装及顶升:网架在地面进行拼装,拼装到看台位置时安装顶升支架,利用顶升支架把网架顶升设定高度(每次顶升高度不同,根据土建情况确定)满足下一网格拼装时,停止顶升工作;(1) Assembling and jacking: The grid is assembled on the ground, and the jacking bracket is installed when it is assembled to the position of the stand, and the jacking bracket is used to lift the grid to a set height (the height of each jacking is different, and it is determined according to the civil construction) When the next grid assembly is satisfied, stop the lifting work;

(二)对称外扩拼装:顶升工作停止后,由网架中心开始对称外扩拼装已完成的空间刚度单元,使网架不断向四周延伸;(2) Symmetrical expansion and assembly: After the lifting work is stopped, the completed spatial rigidity unit will be symmetrically expanded and assembled from the center of the grid frame, so that the grid frame will continue to extend around;

(三)调整顶升点数量及位置:向外扩展拼接时,根据计算结果对网架顶升点的数量和位置进行调整;(3) Adjust the number and position of jacking points: when expanding and splicing outward, adjust the number and position of jacking points of the grid according to the calculation results;

(四)卸载及拆除:重复拼装及顶升、对称外扩拼装及调整顶升点数量及位置,直至网架升至结构标高以上位置后,网架完成后嵌补柱顶杆件、卸载并拆除顶升装置,网架施工完成。(4) Unloading and dismantling: Repeat assembly and jacking, symmetrical outward expansion assembly, and adjust the number and position of jacking points until the grid is raised to a position above the structural elevation, and the grid is completed. The lifting device is removed, and the grid construction is completed.

实施例2:Example 2:

如附图1所示,本发明的大跨度网架外扩拼装整体顶升施工方法,该施工方法的工艺流程具体如下:As shown in accompanying drawing 1, the large-span grid frame of the present invention expands and assembles the overall jacking construction method, and the technological process of this construction method is as follows:

S1、施工前准备;具体如下:S1. Preparation before construction; the details are as follows:

S101、对已进场的网架材料进行清点,球、杆分别分类堆放,并对球、杆的加工尺寸进行校核,以保证安装精度,否则不得使用;S101. Inventory the grid materials that have entered the site, classify and stack the balls and rods separately, and check the processing dimensions of the balls and rods to ensure the installation accuracy, otherwise they cannot be used;

S102、现场堆放的杂物必须清理干净,以保证工程施工的顺利进行;S102. The sundries stacked on the site must be cleaned up to ensure the smooth progress of the project construction;

S103、根据场地情况和结构外形采用MIDAS计算顶升架数量和位置,进行应力和变形核算;网架经过验算后,若发现有超应力杆,则进行临时加固,即在杆件外侧用夹具加固,如附图2所示;S103. Use MIDAS to calculate the number and position of the jacking frame according to the site conditions and structural shape, and perform stress and deformation calculation; after the grid frame is checked and calculated, if it is found that there is an overstressed rod, temporary reinforcement is performed, that is, the outer side of the rod is reinforced with a clamp , as shown in Figure 2;

S104、按照方案位置放出顶升架安装位置及部分下弦球的投影位置,对于下方有混凝土结构的其位置定位应放在柱梁部位;S104. Release the installation position of the jacking frame and the projection position of part of the lower chord ball according to the planned position. The position of the concrete structure below should be placed on the column beam position;

S105、检查顶升设备,确保顶升过程中设备运转正常;S105. Check the jacking equipment to ensure that the equipment operates normally during the jacking process;

S106、检查顶升设备的基础,基础应有足够的强度,否则应事先进行处理。S106. Check the foundation of the jacking equipment, the foundation should have sufficient strength, otherwise it should be dealt with in advance.

S2、网架拼装;网架拼装具体如下:S2, grid assembly; grid assembly is as follows:

S201、安装下弦平面网架,具体包括:S201. Install the lower chord plane grid, specifically including:

S20101、柱轴线及中心线对中,用水平仪复核标高,有误差应予修正;S20101. Align the axis and center line of the column, check the elevation with a spirit level, and correct any errors;

S20102、安装网架中心区域下弦球及杆组成纵向平面网格;排好临时支点,保证下弦球的平等度;当有起拱要求时,在临时支点上找出坡底;S20102. Install the lower string ball and rod in the central area of the grid frame to form a longitudinal plane grid; arrange the temporary fulcrum to ensure the equality of the lower string ball; when there is a requirement for arching, find the bottom of the slope on the temporary fulcrum;

S20103、安装第一单元间的腹杆与上弦球,第一个锥为一球四腹杆的小单元,就位后与下弦球拧入并固定;S20103. Install the web rod and the upper string ball between the first units. The first cone is a small unit with one ball and four web rods. After it is in place, it is screwed into and fixed with the bottom string ball;

S20104、第二个锥起为先装一球一弦杆二腹杆的三角锥,再填入另外两根腹杆,逐步循环安装完第一单元的网架;S20104. The second cone is a triangular cone with a ball, a chord, and two webs first, and then the other two webs are filled, and the grid frame of the first unit is installed in a cycle step by step;

S20105、检查网架、网格尺寸及网架纵向尺寸与矢高;同时检查网架位置,若有出入,则调整临时支点的位置和高低,以校准网架定位尺寸;S20105. Check the grid frame, grid size, longitudinal dimension and sag height of the grid frame; at the same time, check the position of the grid frame. If there is any discrepancy, adjust the position and height of the temporary fulcrum to calibrate the positioning size of the grid frame;

S202、安装上弦倒三角网格,具体包括:S202, install the upper chord inverted triangular mesh, specifically including:

S20201、从边跨开始先将一球一上弦二腹杆的三角锥,之后为一球二上弦二腹杆的四角锥;S20201. Starting from the side span, firstly make a triangular cone with one ball, one winding and two abdominal rods, and then a quadrangular pyramid with one ball, two windings and two abdominal rods;

S20202、将二斜腹杆支撑在下弦球上,在上方拉紧上弦杆,使上弦杆逐步靠近已安装好的上弦球(推锥)拧入、调整并紧固;S20202. Support the two inclined web bars on the lower chord ball, and tighten the upper chord rod above, so that the upper chord rod is gradually approached to the installed upper chord ball (push cone), screwed in, adjusted and tightened;

S20203、网架安装过程中,随时检查网架轴线与建筑基础轴线是否偏离,并随时调整;S20203. During the installation of the grid, check whether the axis of the grid is deviated from the axis of the building foundation at any time, and adjust it at any time;

S20204、检查网架整体挠度,严格控制网架上下弦尺寸,确保每个螺栓均旋紧到位;S20204. Check the overall deflection of the grid frame, strictly control the size of the upper and lower chords of the grid frame, and ensure that each bolt is tightened in place;

S20205、网架在安装过程中随时检查各临时支点的下沉情况,若有下降情况,则及时加固。S20205. Check the subsidence of each temporary fulcrum at any time during the installation process of the grid frame. If there is a drop, reinforce it in time.

其中,网架采用钢网架,如附图3-9所示,钢网架的拼装过程具体如下:Among them, the mesh frame adopts the steel mesh frame, as shown in the attached drawings 3-9, the assembly process of the steel mesh frame is as follows:

(1)、在地面上将第一个下弦网格临时支撑点定位;(1) Position the temporary support point of the first lower chord grid on the ground;

(2)、在临时支撑点上完成第一个网格下弦杆件的组装;(2) Complete the assembly of the first mesh lower chord on the temporary support point;

(3)、将一个上弦球以及与之相连的网架腹杆组装成整体与安装就位的下弦单元拼装成整体结构;(3) Assemble a top chord ball and the web frame web bar connected to it into a whole and assemble the lower chord unit installed in place into an integral structure;

(4)、组装下一单元格网架下弦构件;(4), assemble the lower chord member of the next cell grid;

(5)、将一个上弦球以及与之相连的网架腹杆以及一侧的一根上弦杆组装成整体与安装就位的下弦单元拼装成整体结构;(5), assemble a top chord ball and the web frame web rod connected to it and a top chord rod on one side into a whole and the installed bottom chord unit into an overall structure;

(6)、重复步骤步骤(4)和步骤(5)继续进行其余网格构件的拼装;(6), repeat steps (4) and step (5) to continue the assembling of the remaining grid members;

(7)、直至完成整个结构拼装。(7), until the entire structure is assembled.

S3、顶升点布置,安装顶升装置;顶升装置的位置确定过程中,确保在顶升过程中每个节点球儿受力均匀,顶升装置底部设置钢板支座,避免顶升装置对支撑面的压强过大,如附图10所示;S3. Arrange the jacking point and install the jacking device; in the process of determining the position of the jacking device, ensure that the force of each node ball is uniform during the jacking process, and set the steel plate support at the bottom of the jacking device to avoid the jacking device. The pressure on the support surface is too large, as shown in Figure 10;

当顶升装置在混凝土结构面上时,将支撑点设在混凝土柱子及梁的部位,并通过验算确定是否需要加固;When the jacking device is on the concrete structure surface, set the support point at the position of the concrete column and beam, and determine whether it needs to be reinforced by checking calculation;

当支撑点未放置在主梁处,在楼板上提前做好预留洞并对地面进行处理,如附图11所示,同时对地面的承载力进行验算,确保地面沉降量不能影响施工质量和安全,再将顶升装置穿过预留洞立在地面上。When the support point is not placed at the main beam, make a reserved hole in the floor in advance and deal with the ground, as shown in Figure 11. At the same time, check the bearing capacity of the ground to ensure that the ground subsidence does not affect the construction quality and Safety, and then put the jacking device on the ground through the reserved hole.

S4、质量与安全检查;具体如下:网架顶升前,需要对已经拼装完成的网架进行质量与安全检查,质量方面重点对已拼装节点球、杆件、焊缝及轴线等进行检验、复核。安全方面重点检查顶升装置的就位情况,如千斤顶、缆风绳、电脑监测控制系统等,另外,还需注意其他设施是否妨碍网架顶升、网架是否与其他结构脱离等情况。S4, quality and safety inspection; the details are as follows: before the grid frame is lifted, the quality and safety inspection of the assembled grid needs to be carried out. Review. In terms of safety, focus on checking the position of the jacking devices, such as jacks, cable wind ropes, computer monitoring and control systems, etc. In addition, it is also necessary to pay attention to whether other facilities hinder the lifting of the grid frame and whether the grid frame is separated from other structures.

S5、试顶升;具体如下:网架顶升前,对所有施工人员进行详细的技术、安全交底,对现场设备检查无误后开始第一次顶升。各个顶升动力装置在统一指挥下开始同步顶升,顶升控制由有线网络电脑协同进行。试顶升的高度控制在500mm左右,使已经拼装完成的网架脱离支撑点,处于悬空状态即可。S5. Test jacking; the details are as follows: Before the grid frame is jacked up, detailed technical and safety disclosures shall be made to all construction personnel, and the first jacking shall be started after the on-site equipment is checked correctly. Each jacking power unit starts to lift synchronously under the unified command, and the jacking control is coordinated by the wired network computer. The height of the test jacking is controlled at about 500mm, so that the assembled grid can be separated from the support point and be in a suspended state.

S6、正式顶升:试顶升完成后,及时进行检查确定是否存在问题,如各项指标正常可直接进行正式顶升,正式顶升同试顶升操作方法;具体如下:S6. Formal jacking: After the test jacking is completed, check in time to determine whether there is any problem. If the indicators are normal, the formal jacking can be directly carried out. The formal jacking is the same as the test jacking operation method; the details are as follows:

S601、利用全站仪复核网架不同方位点的标高和变形情况,各标高点的允许偏差根据网架的施工验算确定;S601. Use a total station to review the elevation and deformation of different azimuth points of the grid frame, and the allowable deviation of each elevation point is determined according to the construction check calculation of the grid frame;

S602、每次顶升1.5m左右暂停,对网架各点偏差进行检查,分次将网架顶升到预定标高后固定;S602. Pause for about 1.5m each time of jacking up, check the deviation of each point of the grid frame, and lift the grid frame to the predetermined elevation in stages and fix it;

S603、待顶升到预定标高固定后,检查网架整体位移和扭转偏差;当存在较大偏差,利用混凝土结构为拉结点,通过倒链调;S603. After being jacked up to a predetermined elevation and fixed, check the overall displacement and torsional deviation of the grid frame; when there is a large deviation, use the concrete structure as the tension point, and adjust the grid through the reverse chain;

S604、增高时下托架受力,当活塞杆完全伸出时增加一节支撑架,相关螺栓拧紧后活塞杆回缩,上托架受力,当活塞杆完全收回时,下托架收至上一个可受力处,上挪横杆(受力杆),横杆要与下托架受力梁位置对应;S604. When the height is increased, the lower bracket is stressed. When the piston rod is fully extended, a support bracket is added. After the relevant bolts are tightened, the piston rod is retracted, and the upper bracket is stressed. When the piston rod is fully retracted, the lower bracket is retracted to the previous one. Move the cross bar (stressed bar) upward at the place where it can bear the force, and the horizontal bar should correspond to the position of the stress beam of the lower bracket;

S605、拆除时上托架受力,活塞杆回缩至不受力,下挪横杆(受力杆),横杆要与下托架受力梁位置对应,活塞杆伸出,将下托架移到下一支撑架处,使下托架受力,上托架不受力,拆除一节支撑架。顶升架提升及安装安装、转换过程如附图12和13所示。S605. When dismantling, the upper bracket is stressed, the piston rod is retracted to no force, and the horizontal rod (stressed rod) is moved down. The horizontal rod should correspond to the position of the stressed beam of the lower bracket. Move the frame to the next support frame, so that the lower bracket is stressed, the upper bracket is not stressed, and a section of the support frame is removed. The lifting, installation, installation and conversion process of the jacking frame are shown in Figures 12 and 13.

其中,顶升过程具体如下:Among them, the lifting process is as follows:

①、混凝土结构施工完成后,按照顶升点平面位置安装顶升支架;①. After the construction of the concrete structure is completed, install the jacking bracket according to the plane position of the jacking point;

②、地面拼装看台内部网架,网架整体拼装完成后,须对网架进行的尺寸、焊接质量进行自检。无误后便可进行顶升工作当高度满足下一个网格组对时,停止顶升,组对、焊接网架;②. The internal grid of the stand is assembled on the ground. After the overall assembly of the grid is completed, the size and welding quality of the grid must be self-checked. After it is correct, the lifting work can be carried out. When the height meets the next grid pairing, the lifting is stopped, and the grids are assembled and welded;

③、开始顶升,顶升至3.5m,往外延伸杆件;③. Start to lift, lift to 3.5m, and extend the rod outward;

④、安装杆件完成后,继续顶升7.1m,向外延伸杆件;④. After the installation of the rod is completed, continue to lift 7.1m and extend the rod outward;

⑤、安装杆件完成后,继续顶升9.4m,向外延伸杆件。同时,顶升点数量和位置进行调整;⑤ After the installation of the rod is completed, continue to lift 9.4m and extend the rod outward. At the same time, the number and position of jacking points are adjusted;

⑥、重复步骤①-⑤,待顶升至支座标高20.6m以上位置后,安装支座,下落顶升架使支座受力;支座受力,结构稳定后,,利用汽车吊补装悬挑部分网架,直至将网架全部完成。⑥. Repeat steps ①-⑤. After jacking up to the position above 20.6m of the support, install the support, and drop the jacking frame to make the support stress; after the support is stressed and the structure is stable, use a car to hoist. Overhang part of the mesh frame until the mesh frame is complete.

S7、外扩拼装及循环提升;具体如下:S7. External expansion assembly and cyclic promotion; the details are as follows:

S701、待网架顶升到设定高度,能够满足网架外扩拼装要求时,停止顶升;S701. When the grid frame is lifted to the set height and can meet the requirements of the grid frame's expansion and assembly, stop lifting;

S702、把已经组装完成的微型网架单元通过吊装进行外扩拼装;同时根据外扩尺寸,及时按计算确定位置增加顶升装置;S702, expand and assemble the assembled micro-grid unit by hoisting; at the same time, according to the expansion size, add a lifting device according to the position determined by calculation in time;

S703、外扩拼装、顶升装置安装完成后,再次进行试顶升,以确保前后安装的顶升装置同步;S703. After the external expansion assembly and the installation of the jacking device are completed, try jacking again to ensure that the jacking devices installed in the front and rear are synchronized;

S704、在外扩拼装、循环顶升的过程中,注意缆风绳、拉结钢丝绳的安装和调整应用;当顶升到3米高度时,为确保整体稳定,给顶升设备增加斜支撑;当顶升到10米高度时采用缆风绳,缆风绳斜拉角度不小于30度,布置位置为顶升桁架四角,顶升架标准节上有连接板来连接钢支撑或缆风绳,如附图14所示。S704. During the process of expanding and assembling and cyclic jacking, pay attention to the installation and adjustment of cable wind ropes and knotted wire ropes; when jacking up to a height of 3 meters, in order to ensure the overall stability, add inclined supports to the jacking equipment; When jacking up to a height of 10 meters, the cable wind rope is used. The angle of the cable wind rope is not less than 30 degrees. The arrangement position is the four corners of the jacking truss. There are connecting plates on the standard section of the jacking frame to connect the steel support or the cable wind rope. Figure 14 shows.

S8、提升到位及对接支座;具体如下:S8. Lift in place and dock the support; the details are as follows:

S801、网架外扩拼装到预定范围,顶升到支座标高后,停止顶升;S801. The grid frame is expanded and assembled to a predetermined range, and the jacking is stopped after it is jacked up to the support height;

S802、对网架标高、位移及扭转偏差进行复核及调整,调整到位后完成支座杆件嵌补工作;同时进行支座的安装和标高调整,确保网架、支座对接质量;S802. Review and adjust the height, displacement and torsional deviation of the grid frame, and complete the embedding work of the support rods after the adjustment is in place; at the same time, carry out the installation and elevation adjustment of the support to ensure the quality of the connection between the grid frame and the support;

S803、待网架下落,支座受力后,再进行剩余悬挑节点球和杆件的拼装工作,直至网架拼装全部完成。S803 , after the grid frame is dropped and the support is stressed, the remaining cantilever node balls and rods are assembled until the grid frame is completely assembled.

S9、同步卸载;具体如下:S9. Uninstall synchronously; the details are as follows:

S901、卸载前测量网架中部节点的标高;S901. Measure the elevation of the node in the middle of the grid before unloading;

S902、在电脑的控制下顶升装置每次同步下降10mm,观察顶升装置与网架是否脱离,同时测量网架中部节点标高变化情况,直至顶升装置与网架完全脱离;S902. Under the control of the computer, the jacking device is lowered synchronously by 10mm each time, observe whether the jacking device is separated from the grid frame, and measure the elevation change of the middle node of the grid frame until the jacking device is completely separated from the grid frame;

S10、拆除顶升装置,安装完成。具体如下:S10, remove the jacking device, and the installation is completed. details as follows:

S1001、顶升装置拆除两节后,用吊车将剩余支撑架整体吊平放到在地面上;S1001. After removing the two sections of the jacking device, use a crane to hoist the remaining support frame as a whole and place it on the ground;

S1002、在地面拆除,码放整齐,运至场外。S1002. Dismantle on the ground, stack them neatly, and transport them off-site.

环保措施具体如下:The environmental protection measures are as follows:

1)、网架拼装过程中,焊接作业面保持良好的通风换浆,防止烟尘对作业人员的伤害;1) During the assembling process of the grid frame, the welding operation surface should be well ventilated and replaced to prevent the harm of smoke and dust to the operators;

2)、网架喷涂用油漆时应进行封闭式、容器式管理,防止造成空气污染。油漆稀料要严格控制发放量,对剩余部分及时回收,防止造成二次污染;2) Closed and container management should be carried out when spraying paint on the grid to prevent air pollution. The amount of paint thinner should be strictly controlled, and the remaining part should be recycled in time to prevent secondary pollution;

3)、进出工地道路及时清扫、洒水,运输车辆出场前应清扫轮胎和车身;3) The roads entering and leaving the construction site should be cleaned and sprinkled in time, and the tires and body of the transport vehicle should be cleaned before leaving the site;

4)、构件应按种类、安装顺序分区存放,并需平整、垫实、干燥、无积水处,防止材料生锈。4) The components should be stored in partitions according to the type and installation order, and should be flat, padded, dry, and free of water to prevent the material from rusting.

具体实施案例:Specific implementation cases:

1)、北京化工大学体育馆工程中采用顶升工艺避免了满堂脚手架的搭设,节约了措施费,经测算节约费用95万元。顶升工艺安装可减少大型履带吊的投入,本工程现场仅投入1台25t履带吊,减少机械台班费用经测算为25万元。1) The jacking process was adopted in the Beijing University of Chemical Technology Gymnasium project to avoid the erection of full-scale scaffolding and save the cost of measures. It is estimated that the cost is saved by 950,000 yuan. The installation of the jacking process can reduce the investment of large crawler cranes. Only one 25t crawler crane is put into the project site, and the cost of reducing the mechanical shift is estimated to be 250,000 yuan.

2)、南宁市房产服务大厦工程避免了满堂脚手架的搭设,节约脚手架钢管租赁费8万元,搭拆费用1万元,合计节约脚手架措施9万元。缩短工期25天,每台机械台班费用0.2万元,每日3台,合计减少机械台班费用15万元。并取得了较好的社会效益。2) The Nanning Real Estate Service Building project avoids the erection of full-scale scaffolding, saving 80,000 yuan in the rental fee of scaffolding steel pipes, and 10,000 yuan in erection and dismantling costs. The total saving of scaffolding measures is 90,000 yuan. The construction period is shortened by 25 days, the cost of each machine shift is 2,000 yuan, and there are 3 machines per day, reducing the total cost of mechanical shifts by 150,000 yuan. And achieved good social benefits.

最后应说明的是:以上各实施例仅用以说明本发明的技术方案,而非对其限制;尽管参照前述各实施例对本发明进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分或者全部技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本发明各实施例技术方案的范围。Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, but not to limit them; although the present invention has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that: The technical solutions described in the foregoing embodiments can still be modified, or some or all of the technical features thereof can be equivalently replaced; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the technical solutions of the embodiments of the present invention. scope.

Claims (10)

1. The construction method for externally expanding, splicing and integrally jacking the large-span net rack is characterized by comprising the following steps of:
assembling and jacking: assembling the net rack on the ground, installing a jacking bracket when the net rack is assembled to the position of the stand, and stopping jacking when the net rack is jacked by the jacking bracket to a set height to meet the assembly of the next grid;
symmetrically expanding and assembling: after the jacking operation is stopped, symmetrically expanding and assembling the completed space rigidity units from the center of the net rack, so that the net rack continuously extends to the periphery;
adjusting the number and the positions of jacking points: when the net rack is expanded and spliced outwards, the number and the positions of the jacking points of the net rack are adjusted according to the calculation result;
unloading and dismantling: repeatedly assemble and jacking, the symmetry expands outward and assembles and adjust jacking point quantity and position, after the rack rises to above the position of structure elevation, the rack is accomplished the back and is inlayed the post top member, uninstallation and demolish jacking device, and the rack construction is accomplished.
2. The large-span net rack outward-expanding splicing integral jacking construction method according to claim 1, characterized in that the construction method comprises the following specific process flows:
s1, preparation before construction;
s2, assembling net racks;
s3, arranging jacking points, and installing a jacking device;
s4, quality and safety inspection;
s5, trial jacking;
s6, formally jacking;
s7, outward expanding assembly and circular lifting;
s8, lifting to the right and butting the support;
s9, synchronous unloading;
and S10, removing the jacking device, and finishing the installation.
3. The large-span net rack externally-expanding, assembling and integral jacking construction method according to claim 2, wherein the preparation before construction in the step S1 is as follows:
s101, counting the net rack materials which have entered the field, respectively stacking balls and rods in a classified manner, and checking the processing sizes of the balls and the rods;
s102, cleaning up sundries stacked on site to ensure smooth construction;
s103, calculating the number and the positions of the jacking frames by using MIDAS according to the site condition and the structure appearance, and performing stress and deformation accounting; after the net rack is checked and calculated, if the super-stress rod is found, temporary reinforcement is carried out, namely, the outer side of the rod piece is reinforced by a clamp;
s104, releasing the mounting position of the jacking frame and the projection position of part of the lower chord ball according to the position of the scheme, and positioning the position of the lower chord ball with the concrete structure at the position of the column beam;
s105, checking jacking equipment to ensure that the equipment runs normally in the jacking process;
s106, checking the foundation of the jacking equipment, wherein the foundation should have enough strength.
4. The large-span net rack outward-expanding assembling integral jacking construction method according to claim 2, wherein the net rack assembling in the step S2 is as follows:
s201, installing a lower chord plane net rack, and specifically comprising:
s20101, centering a column axis and a center line, rechecking elevation by using a level gauge, and correcting errors;
s20102, forming a longitudinal plane grid by a lower chord ball and a rod in the central area of the installation net rack; arranging temporary supporting points to ensure the equality of the lower string ball; finding out the slope bottom on the temporary pivot when an arching requirement exists;
s20103, mounting web members and an upper chord ball between first units, wherein a first cone is a small unit with one ball and four web members, and is screwed and fixed with a lower chord ball after being in place;
s20104, starting the second cone to be a triangular cone which is firstly provided with a ball, a chord and two web members, then filling the other two web members, and gradually circularly installing the net rack of the first unit;
s20105, checking the net rack, the grid size and the longitudinal size and rise of the net rack; meanwhile, the position of the net rack is checked, and if the net rack is in and out, the position and the height of the temporary fulcrum are adjusted to calibrate the positioning size of the net rack;
s202, installing an upper chord inverted triangular grid, and specifically comprising:
s20201, starting from the side span, firstly forming a triangular pyramid of the first sphere-first upper chord second web member, and then forming a quadrangular pyramid of the first sphere-second upper chord second web member;
s20202, supporting the two diagonal web members on the lower chord ball, and tensioning the upper chord member above to enable the upper chord member to be gradually close to the mounted upper chord ball to be screwed, adjusted and fastened;
s20203, in the installation process of the net rack, whether the axis of the net rack deviates from the axis of the building foundation is checked at any time, and the adjustment is carried out at any time;
s20204, checking the integral deflection of the net rack, strictly controlling the sizes of the upper chord and the lower chord of the net rack, and ensuring that each bolt is screwed in place;
s20205, the net rack is inspected at any time in the installation process for the sinking condition of each temporary supporting point, and if the sinking condition exists, the net rack is reinforced in time.
5. The large-span net rack outward-expanding assembling integral jacking construction method according to claim 4, wherein the net rack is a steel net rack, and the assembling process of the steel net rack is as follows:
(1) positioning a first lower chord grid temporary supporting point on the ground;
(2) assembling the first grid lower chord member on the temporary supporting point;
(3) assembling an upper chord ball and a net rack web member connected with the upper chord ball into a whole and assembling a lower chord unit in place into an integral structure;
(4) assembling a lower chord member of the next unit grid frame;
(5) assembling an upper chord ball, a net rack web member connected with the upper chord ball and an upper chord member on one side into a whole and assembling a lower chord unit in place into an integral structure;
(6) repeating the step (4) and the step (5) to continue assembling the other grid components;
(7) and assembling the whole structure.
6. The construction method for the outward-expanding, assembling and integral jacking of the large-span net rack according to claim 2, wherein in the step of determining the position of the jacking device in the step S3, each node ball is uniformly stressed in the jacking process, and a steel plate support is arranged at the bottom of the jacking device;
when the jacking device is arranged on the concrete structure surface, the supporting points are arranged at the concrete columns and the concrete beams, and whether reinforcement is needed or not is determined through checking calculation;
when the supporting point is not placed at the main beam, a reserved hole is made before the floor slab is lifted, the ground is processed, meanwhile, the bearing capacity of the ground is checked, it is ensured that the ground settlement can not affect the construction quality and safety, and then the jacking device penetrates through the reserved hole to stand on the ground.
7. The construction method for the outward-expanding, splicing and integral jacking of the large-span net rack according to claim 1, wherein the formal jacking in the step S6 is as follows:
s601, rechecking the elevations and deformation conditions of different square points of the net rack by using a total station, and determining the allowable deviation of each elevation point according to the construction check calculation of the net rack;
s602, pausing each time of jacking for about 1.5m, checking the deviation of each point of the net rack, jacking the net rack to a preset elevation in times and then fixing;
s603, after the net rack is jacked to a preset elevation and fixed, checking the integral displacement and torsion deviation of the net rack; when large deviation exists, a concrete structure is used as a pulling node, and chain inversion adjustment is carried out;
s604, the lower bracket is stressed when the piston rod is heightened, a section of support frame is added when the piston rod is completely extended out, the piston rod retracts after the related bolt is screwed, the upper bracket is stressed, when the piston rod retracts completely, the lower bracket retracts to a position capable of being stressed, the cross rod is moved upwards, and the position of the cross rod corresponds to that of a stress beam of the lower bracket;
s605, when the upper bracket is stressed during dismantling, the piston rod retracts to be not stressed, the cross rod is moved downwards, the position of the cross rod is corresponding to that of the stress beam of the lower bracket, the piston rod extends out, the lower bracket is moved to the next support frame, the lower bracket is stressed, the upper bracket is not stressed, and a section of support frame is dismantled.
8. The large-span net rack externally-expanding assembling integral jacking construction method according to claim 2, wherein the externally-expanding assembling and cyclic lifting in the step S7 are as follows:
s701, stopping jacking when the net rack is jacked to a set height and the requirement of outward expansion and assembly of the net rack can be met;
s702, carrying out outward expansion assembly on the assembled miniature grid units through hoisting; meanwhile, according to the external expansion size, a jacking device is added at a determined position in time according to calculation;
s703, after the external expansion assembling and jacking devices are installed, performing trial jacking again to ensure that the jacking devices installed front and back are synchronous;
s704, paying attention to installation, adjustment and application of the guy rope and the tied steel wire rope in the processes of outward expanding assembly and circulating jacking; when the lifting device is lifted to the height of 3 m, the inclined support is added to the lifting device to ensure the integral stability; when the lifting is carried out to the height of 10 meters, the guy cables are adopted, the cable-stayed angle of the guy cables is not less than 30 degrees, and the arrangement positions are four corners of the lifting truss.
9. The construction method for the outward-expanding, assembling and integral jacking of the large-span net rack according to claim 2, wherein the lifting in place and the butt joint of the support in the step S8 are as follows:
s801, expanding and assembling the net rack to a preset range, and stopping jacking after jacking to the elevation of the support;
s802, rechecking and adjusting the elevation, the displacement and the torsional deviation of the net rack, and completing the support rod piece embedding work after the adjustment is in place; simultaneously, the installation and elevation adjustment of the support are carried out, so that the butt joint quality of the net rack and the support is ensured;
and S803, after the net rack falls down and the support is stressed, assembling the residual overhanging node balls and the rod pieces until the net rack is completely assembled.
10. The construction method for the outward-expanding, splicing and integral jacking of the large-span net rack according to claim 2, wherein the synchronous unloading in the step S9 is as follows:
s901, measuring the elevation of the middle node of the net rack before unloading;
s902, synchronously descending the jacking device by 10mm each time under the control of a computer, observing whether the jacking device is separated from the net rack, and measuring the elevation change condition of the middle node of the net rack until the jacking device is completely separated from the net rack;
and (S10) removing the jacking device, wherein the installation is completed as follows:
s1001, after the two sections of the jacking devices are disassembled, integrally and horizontally hanging the rest support frames on the ground by using a crane;
s1002, dismantling the steel pipe from the ground, stacking the steel pipe neatly and transporting the steel pipe to the outside of the field.
CN202010785410.7A 2020-08-07 2020-08-07 Large-span net rack external-expanding splicing integral jacking construction method Pending CN111980165A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010785410.7A CN111980165A (en) 2020-08-07 2020-08-07 Large-span net rack external-expanding splicing integral jacking construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010785410.7A CN111980165A (en) 2020-08-07 2020-08-07 Large-span net rack external-expanding splicing integral jacking construction method

Publications (1)

Publication Number Publication Date
CN111980165A true CN111980165A (en) 2020-11-24

Family

ID=73445861

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010785410.7A Pending CN111980165A (en) 2020-08-07 2020-08-07 Large-span net rack external-expanding splicing integral jacking construction method

Country Status (1)

Country Link
CN (1) CN111980165A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114575601A (en) * 2022-03-16 2022-06-03 中铁二十局集团第一工程有限公司 Method for installing net rack
CN114809310A (en) * 2022-06-24 2022-07-29 天津医科大学 Construction method of high-altitude integral variable-angle jacking of large-span steel grid
CN115233831A (en) * 2022-08-19 2022-10-25 湖南建工集团有限公司 Integral continuous lifting method of multi-point large-span space steel structure with free deflection control
CN116254920A (en) * 2023-02-14 2023-06-13 中建三局集团有限公司 A cumulative lifting construction method for multi-system steel structure composites
CN116971490A (en) * 2023-10-07 2023-10-31 北京城建六建设集团有限公司 Grid jacking construction process and electromechanical cooperation installation method thereof
CN118128183A (en) * 2024-04-30 2024-06-04 山西四建集团有限公司 Large-span reticulated shell structure and space vertical swivel mounting method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE7505744L (en) * 1975-05-20 1976-11-21 Intezet Epitestudomanyi SET AND DEVICE FOR VERTICAL MOVEMENT OF ASSISTANT ELEMENTS FOR CONSTRUCTION WORK, DIFFERENT SHELL FORMS AND SPACE TRACKS
CN105220769A (en) * 2014-06-24 2016-01-06 中国二十冶集团有限公司 Large area bolt-ball net frame integral top lifting construction method
CN106906911A (en) * 2017-05-02 2017-06-30 中建城市建设发展有限公司 A kind of Elements of Space Grid Truss jacking ball point Integral rotating device and jack-up system and construction method
CN107489199A (en) * 2017-08-31 2017-12-19 中建七局安装工程有限公司 Space Reticulated dome expands lifting construction method by ring
CN110284600A (en) * 2019-07-10 2019-09-27 贵州建工集团第二建筑工程有限责任公司 A kind of longspan structure rack hydraulic lifting construction method of installation
CN110805138A (en) * 2019-11-29 2020-02-18 中国二十冶集团有限公司 Construction method for jacking two sides of large-span net rack

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE7505744L (en) * 1975-05-20 1976-11-21 Intezet Epitestudomanyi SET AND DEVICE FOR VERTICAL MOVEMENT OF ASSISTANT ELEMENTS FOR CONSTRUCTION WORK, DIFFERENT SHELL FORMS AND SPACE TRACKS
CN105220769A (en) * 2014-06-24 2016-01-06 中国二十冶集团有限公司 Large area bolt-ball net frame integral top lifting construction method
CN106906911A (en) * 2017-05-02 2017-06-30 中建城市建设发展有限公司 A kind of Elements of Space Grid Truss jacking ball point Integral rotating device and jack-up system and construction method
CN107489199A (en) * 2017-08-31 2017-12-19 中建七局安装工程有限公司 Space Reticulated dome expands lifting construction method by ring
CN110284600A (en) * 2019-07-10 2019-09-27 贵州建工集团第二建筑工程有限责任公司 A kind of longspan structure rack hydraulic lifting construction method of installation
CN110805138A (en) * 2019-11-29 2020-02-18 中国二十冶集团有限公司 Construction method for jacking two sides of large-span net rack

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
于景民: "整体顶升法在体育馆大跨度网架中的研究与应用", 《工程质量》 *
朱国平: "浅谈网架整体顶升法在工程中的应用", 《山西建筑》 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114575601A (en) * 2022-03-16 2022-06-03 中铁二十局集团第一工程有限公司 Method for installing net rack
CN114809310A (en) * 2022-06-24 2022-07-29 天津医科大学 Construction method of high-altitude integral variable-angle jacking of large-span steel grid
CN114809310B (en) * 2022-06-24 2022-09-27 天津医科大学 Construction method of high-altitude integral variable-angle jacking of large-span steel grid
CN115233831A (en) * 2022-08-19 2022-10-25 湖南建工集团有限公司 Integral continuous lifting method of multi-point large-span space steel structure with free deflection control
CN115233831B (en) * 2022-08-19 2023-09-15 湖南建工集团有限公司 Overall continuous lifting method of multi-point large-span space steel structure with free deflection control
CN116254920A (en) * 2023-02-14 2023-06-13 中建三局集团有限公司 A cumulative lifting construction method for multi-system steel structure composites
CN116254920B (en) * 2023-02-14 2025-11-25 中建三局集团有限公司 A method for cumulative lifting of multi-system steel structure assemblies
CN116971490A (en) * 2023-10-07 2023-10-31 北京城建六建设集团有限公司 Grid jacking construction process and electromechanical cooperation installation method thereof
CN118128183A (en) * 2024-04-30 2024-06-04 山西四建集团有限公司 Large-span reticulated shell structure and space vertical swivel mounting method
CN118128183B (en) * 2024-04-30 2024-08-20 山西四建集团有限公司 Large-span reticulated shell structure and space vertical swivel mounting method

Similar Documents

Publication Publication Date Title
CN114086669B (en) A modular rapid construction method for large space special-shaped curved surface steel grids
CN112343233B (en) Circular roof space tube truss structure and its construction method
CN114718325B (en) Construction method of hyperboloid overhanging space pipe truss of stadium
CN107090932B (en) Construction method of large-span thin-wall plane arch truss based on stiff ring beam
CN102345393B (en) High-altitude bulk process of bolt ball net frame
CN114232805B (en) Construction method of ultrahigh-height large-span steel concrete beam hanging structure
CN113123469A (en) Method for constructing complex curved surface modeling roof grid structure
CN111270852A (en) Construction method of a new formwork support system for reinforced concrete silo domes
CN106836498A (en) A kind of super-span Stadium roof system steel truss lifting construction engineering method
CN205558304U (en) Hoist and mount system of large -scale steel gallery truss
CN113401815B (en) High-altitude conversion system of core tube tower crane of super high-rise building and construction method thereof
CN209941511U (en) Supporting device for high-altitude folding of bridge steel box girder by section hoisting
CN111927111B (en) Construction method of ultrahigh special-shaped outer frame steel structure
CN106638960A (en) Super-span cylindrical latticed shell construction method
CN205558306U (en) Big profiled steel structure vestibule hoist and mount hoisting frame
CN110820950A (en) Integral synchronous jacking construction method for large-span combined type overweight eccentric slope angle steel structure
CN110318344B (en) Novel steel box girder No. 0 block support and No. 0 block erection construction method
CN115749298A (en) Construction method for steel structure of main body of high-speed rail station house
CN118007799A (en) A method for assembling and lifting a large-span grid dome in circles and stages
CN109653517B (en) Multidirectional unloading system and construction method for assembling steel corridor by using same
CN116856723A (en) Multi-layer steel structure slope-returning type installation method
CN111561050A (en) Ellipsoidal single-layer grid bulk construction method
CN115787996A (en) Overhung construction method and overhung frame for super-high building
CN113931661A (en) Secondary lining template device suitable for large-span cavity dome and construction method
CN116427723B (en) A construction method for a shell-shaped large-span space frame

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201124

RJ01 Rejection of invention patent application after publication