CN111927512A - 一种隧道初支锚杆的施工方法 - Google Patents

一种隧道初支锚杆的施工方法 Download PDF

Info

Publication number
CN111927512A
CN111927512A CN202010819938.1A CN202010819938A CN111927512A CN 111927512 A CN111927512 A CN 111927512A CN 202010819938 A CN202010819938 A CN 202010819938A CN 111927512 A CN111927512 A CN 111927512A
Authority
CN
China
Prior art keywords
anchor rod
tunnel
construction method
primary support
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010819938.1A
Other languages
English (en)
Inventor
徐来银
王镜越
安航
弋华伟
蔡永洪
徐鹏
胡坤鹏
曹敏
周其富
王志军
张黎明
张立华
郑棚艺
赵嵩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Highway Engineering Group Co Ltd
Original Assignee
Guizhou Highway Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Highway Engineering Group Co Ltd filed Critical Guizhou Highway Engineering Group Co Ltd
Priority to CN202010819938.1A priority Critical patent/CN111927512A/zh
Publication of CN111927512A publication Critical patent/CN111927512A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

本发明提供了一种隧道初支锚杆的施工方法,属于隧道施工技术领域,包括以下步骤:根据不同围岩级别锚杆设计大小,准备PE套管;将锚杆打入岩体内;将PE管套在锚杆上;喷射混凝土完成,并达到初凝时间,拔开PE套管盖子即可;本发明的施工方法,能够保证锚杆露头率,防止锚杆刺穿二衬防水板导致隧道防水板失去作用;锚杆露头率能够达到95%以上,提高隧道施工质量。

Description

一种隧道初支锚杆的施工方法
技术领域
本发明涉及隧道施工技术领域,具体为一种隧道初支锚杆的施工方法。
背景技术
隧道系统锚杆为隧道初支的主要组成部分,在初支施工完成后,将做锚杆拉拔试验和进行防水板安装,传统施工往往由于锚杆露头不足而影响拉拔力试验检测、或者锚杆露头过长出现刺破防水板现象,从而导致隧道防水板失去作用而造成隧道后期营运过程中出现二衬渗水质量病害。
发明内容
针对上述存在的技术不足,本发明的目的是提供一种隧道初支锚杆的施工方法,既能能够保证锚杆露头率达到95%以上,又能防止锚杆刺破二衬防水板,导致隧道防水板失去作用;提高隧道施工质量。
为解决上述技术问题,本发明采用如下技术方案:
一种隧道初支锚杆的施工方法,其特征在于,所述方法包括以下步骤:
1)根据不同围岩级别锚杆设计大小,准备PE套管;
2)将锚杆打入岩体内;
3)将PE套管套在锚杆头上;
4)喷射混凝土完成,并达到初凝时间,拔掉PE套管盖子。
本发明的有益效果在于:本发明的施工方法,既能能够保证锚杆露头率达到95%以上,又能防止锚杆刺破二衬防水板,导致隧道防水板失去作用;提高隧道施工质量。
具体实施方式
下面将结合本发明的实施例,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。
一种隧道初支锚杆的施工方法,包括以下步骤:
1)根据不同围岩级别锚杆设计大小,准备PE变截面套管(由两个不同直径管子变截组成,下半部分直径与锚杆直径相同,长度15cm,变截面上部分由直径5cm管子组成,长度10cm。)
2)将锚杆打入岩体内;
3)将PE管套在锚杆上,管顶与喷射混凝土表面齐平。
4)喷射混凝土完成,并达到初凝时间,PE套管盖子即可。
5)在做锚杆拉拔力试验时,加工一个长30cm的钢制套筒,管径与锚杆直径相同,将钢制套筒伸入PE套管中套住锚杆以便开展锚杆拉拔力试验。
隧道锚杆的作用主要是加固岩土体,控制变形,防止坍塌。
操作注意要点:
1、PE套管管径不能太大,否则喷射混凝土时容易脱落;
2、安装PE套管时管顶与喷射混凝土面齐平,以避免超过混凝土面后花费人工将超出部分PE管割除。
本发明的施工方法,能够保证锚杆露头率,防止锚杆刺破二衬防水板,导致隧道防水板失去作用;锚杆露头率能够达到95%以上,提高隧道施工质量。
显然,本领域的技术人员可以对本发明进行各种改动和变型而不脱离本发明的精神和范围。这样,倘若本发明的这些修改和变型属于本发明权利要求及其等同技术的范围之内,则本发明也意图包含这些改动和变型在内。

Claims (1)

1.一种隧道初支锚杆的施工方法,其特征在于,所述方法包括以下步骤:
1)根据不同围岩级别锚杆设计大小,准备PE套管;
2)将锚杆打入岩体内;
3)将PE套管套在锚杆上;
4)喷射混凝土完成,并达到初凝时间,拔掉PE套管盖子。
CN202010819938.1A 2020-08-14 2020-08-14 一种隧道初支锚杆的施工方法 Pending CN111927512A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010819938.1A CN111927512A (zh) 2020-08-14 2020-08-14 一种隧道初支锚杆的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010819938.1A CN111927512A (zh) 2020-08-14 2020-08-14 一种隧道初支锚杆的施工方法

Publications (1)

Publication Number Publication Date
CN111927512A true CN111927512A (zh) 2020-11-13

Family

ID=73311016

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010819938.1A Pending CN111927512A (zh) 2020-08-14 2020-08-14 一种隧道初支锚杆的施工方法

Country Status (1)

Country Link
CN (1) CN111927512A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113153397A (zh) * 2021-04-28 2021-07-23 中交第二航务工程局有限公司 控制隧道锚杆露头长度的套管装置及其使用方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204080856U (zh) * 2014-09-10 2015-01-07 中国电建集团贵阳勘测设计研究院有限公司 一种锚杆牵拉式混凝土挡土墙结构
CN106593483A (zh) * 2016-12-14 2017-04-26 中铁十局集团第四工程有限公司 一种软弱围岩隧道仰拱长锚杆的施工方法
CN109751066A (zh) * 2019-03-08 2019-05-14 中国水利水电第十四工程局有限公司 一种隧道锚杆过防水板止水施工方法
CN110486067A (zh) * 2019-09-09 2019-11-22 中交路桥建设有限公司 一种瓦斯隧道系统锚杆及锚杆检测的安全施工方法
CN210343394U (zh) * 2019-06-27 2020-04-17 中铁六局集团有限公司交通工程分公司 一种隧道锚杆垫板

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204080856U (zh) * 2014-09-10 2015-01-07 中国电建集团贵阳勘测设计研究院有限公司 一种锚杆牵拉式混凝土挡土墙结构
CN106593483A (zh) * 2016-12-14 2017-04-26 中铁十局集团第四工程有限公司 一种软弱围岩隧道仰拱长锚杆的施工方法
CN109751066A (zh) * 2019-03-08 2019-05-14 中国水利水电第十四工程局有限公司 一种隧道锚杆过防水板止水施工方法
CN210343394U (zh) * 2019-06-27 2020-04-17 中铁六局集团有限公司交通工程分公司 一种隧道锚杆垫板
CN110486067A (zh) * 2019-09-09 2019-11-22 中交路桥建设有限公司 一种瓦斯隧道系统锚杆及锚杆检测的安全施工方法

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113153397A (zh) * 2021-04-28 2021-07-23 中交第二航务工程局有限公司 控制隧道锚杆露头长度的套管装置及其使用方法

Similar Documents

Publication Publication Date Title
CN108203983A (zh) 一种深基坑支护结构和方法
CN104405128A (zh) 填充墙暗装配电箱先期直接安装方法
CN111927512A (zh) 一种隧道初支锚杆的施工方法
CN106088115A (zh) 增加土质高边坡稳定性的方法
CN206028572U (zh) 抗浮锚杆原位弯折装置
CN106284266B (zh) 一种用于水面光伏支撑的抗冰推体系
CN204825887U (zh) 一种预应力锚索
CN105040975A (zh) 一种用于飘窗施工的支撑平台及飘窗施工方法
CN205134781U (zh) 一种应用于屋面排水的坡度排水沟系统
CN208328976U (zh) 风电扩展式空心混凝土承台竖向预应力锚索孔道施作装置
CN203008925U (zh) 一种盾构无障碍始发装置
CN216787088U (zh) 一种露天矿边坡水平排水系统
CN206571135U (zh) 一种不影响施工的外脚手架连墙件
CN205839812U (zh) 一种后浇带预处理装置
CN205013862U (zh) 屋面管道安装支架
CN211849527U (zh) 一种高水压降水井组合封堵装置
CN107740497A (zh) 一种水工建筑物过流面预埋地脚螺栓的施工方法
CN204510147U (zh) 上水库库盆防渗结构
CN209150694U (zh) 一种屋面避雷带安装支架
CN208363089U (zh) 一种桩内抗拔锚杆钢绞线加固结构
CN209959261U (zh) 一种矫正地铁隧道水平变形的实时反馈注浆装置
CN107778029B (zh) 结构内埋管的混凝土养护方法
CN205025098U (zh) 一种地下室可拆卸止水对拉螺杆
CN110173113A (zh) 一种临墙吊洞施工结构和方法
CN205134321U (zh) 锚杆静压桩桩机底座固定锚具

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20201113