CN111884239B - 储能电站调节方法 - Google Patents
储能电站调节方法 Download PDFInfo
- Publication number
- CN111884239B CN111884239B CN202010768296.7A CN202010768296A CN111884239B CN 111884239 B CN111884239 B CN 111884239B CN 202010768296 A CN202010768296 A CN 202010768296A CN 111884239 B CN111884239 B CN 111884239B
- Authority
- CN
- China
- Prior art keywords
- energy storage
- storage power
- power station
- data
- model
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/28—Arrangements for balancing of the load in a network by storage of energy
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/004—Generation forecast, e.g. methods or systems for forecasting future energy generation
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2203/00—Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
- H02J2203/20—Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
Description
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010768296.7A CN111884239B (zh) | 2020-08-03 | 2020-08-03 | 储能电站调节方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010768296.7A CN111884239B (zh) | 2020-08-03 | 2020-08-03 | 储能电站调节方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN111884239A CN111884239A (zh) | 2020-11-03 |
CN111884239B true CN111884239B (zh) | 2021-08-27 |
Family
ID=73205373
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010768296.7A Active CN111884239B (zh) | 2020-08-03 | 2020-08-03 | 储能电站调节方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111884239B (zh) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0993817A (ja) * | 1995-09-25 | 1997-04-04 | Mitsubishi Heavy Ind Ltd | 超伝導エネルギ貯蔵装置 |
CN102077437A (zh) * | 2008-06-30 | 2011-05-25 | 维斯塔斯风力系统集团公司 | 操作包括多个风力涡轮发电机的风力发电站的方法和系统 |
CN103904682A (zh) * | 2014-03-18 | 2014-07-02 | 许继电气股份有限公司 | 一种基于风光混合模型的功率预测方法 |
CN110472857A (zh) * | 2019-08-09 | 2019-11-19 | 国电南瑞科技股份有限公司 | 一种基于通用模型的大规模能量管理方法 |
CN111446920A (zh) * | 2020-04-02 | 2020-07-24 | 合肥阳光新能源科技有限公司 | 光伏电站监控方法、装置及系统 |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201898345U (zh) * | 2010-12-20 | 2011-07-13 | 上海市电力公司 | 对接入电网的储能电池进行充放电监控的系统 |
CN107742900A (zh) * | 2017-11-10 | 2018-02-27 | 国网四川省电力公司技能培训中心 | 风光储智能微电网经济调度控制方法 |
-
2020
- 2020-08-03 CN CN202010768296.7A patent/CN111884239B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0993817A (ja) * | 1995-09-25 | 1997-04-04 | Mitsubishi Heavy Ind Ltd | 超伝導エネルギ貯蔵装置 |
CN102077437A (zh) * | 2008-06-30 | 2011-05-25 | 维斯塔斯风力系统集团公司 | 操作包括多个风力涡轮发电机的风力发电站的方法和系统 |
CN103904682A (zh) * | 2014-03-18 | 2014-07-02 | 许继电气股份有限公司 | 一种基于风光混合模型的功率预测方法 |
CN110472857A (zh) * | 2019-08-09 | 2019-11-19 | 国电南瑞科技股份有限公司 | 一种基于通用模型的大规模能量管理方法 |
CN111446920A (zh) * | 2020-04-02 | 2020-07-24 | 合肥阳光新能源科技有限公司 | 光伏电站监控方法、装置及系统 |
Non-Patent Citations (3)
Title |
---|
Model to Improve the Forecast of the Content Caching based Time-Series Analysis at the Small Base Station;Khalil Ibrahimi等;《2019 International Conference on Wireless Networks and Mobile Communications (WINCOM)》;20191226;第1-6页 * |
储能参与电网电压调节研究综述;陆立民等;《电器与能效管理技术》;20191030;第10-18页 * |
基于专家库模式的层次化电网项目评审体系构建;陈火焱等;《中国电力企业管理创新实践(2017年)》;20171231;第1030-1033页 * |
Also Published As
Publication number | Publication date |
---|---|
CN111884239A (zh) | 2020-11-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN113655768B (zh) | 装配良率控制方法、设备及计算机可读存储介质 | |
CN110380444B (zh) | 一种基于变结构Copula的多场景下分散式风电有序接入电网的容量规划方法 | |
CN111461922A (zh) | 一种基于极限学习机的变压器热点温度实时预测方法 | |
CN106656669B (zh) | 一种基于阈值自适应设置的设备参数异常检测系统及方法 | |
EP3905424B1 (en) | Data processing device, data processing method and computer program | |
CN110837915B (zh) | 一种基于混合集成深度学习的电力系统低压负荷点预测及概率预测方法 | |
CN109298225A (zh) | 一种电压量测数据异常状态自动识别模型及方法 | |
CN117411189B (zh) | 一种微电网协调控制器的监测数据增强方法 | |
CN116629416A (zh) | 光伏电站功率预测方法及装置 | |
CN115049163A (zh) | 基于禁忌搜索与深度稳定学习的光伏区域预测方法及装置 | |
CN116956203B (zh) | 一种变压器分接开关动作特性测量方法及系统 | |
CN111884239B (zh) | 储能电站调节方法 | |
CN112734141B (zh) | 一种多元化负荷区间预测方法及装置 | |
CN113627755B (zh) | 智能终端工厂的测试方法、装置、设备及存储介质 | |
CN116629406A (zh) | 一种基于改进Prophet模型的用电碳排放预测方法 | |
CN115935261A (zh) | 基于工业互联网的群体设备非绝对正向反馈方法 | |
CN112330009B (zh) | 一种电网负荷预测方法 | |
CN115267586A (zh) | 锂电池soh评估方法 | |
CN114819391A (zh) | 基于历史数据集时间跨度优化的光伏发电功率预测方法 | |
CN108009686B (zh) | 一种光伏发电功率预测方法、装置及系统 | |
CN113283695A (zh) | 一种基于人工智能的电力调度智慧坐席实现方法及系统 | |
CN112257347A (zh) | 一种变电设备的仿真系统 | |
CN116910637B (zh) | 基于改进的iga-rbf神经网络短期负荷预测方法 | |
CN116151491B (zh) | 一种基于电力数据的电力故障智慧预测平台 | |
CN116885703B (zh) | 一种高维多元气象数据融合的短期风光功率预测方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CB03 | Change of inventor or designer information |
Inventor after: Tan Liping Inventor after: Zhang Yuming Inventor after: Zhang Liang Inventor after: Liang Qiuhong Inventor after: Zhou Nianguang Inventor after: Wang Hongliang Inventor after: Chen Zhongwei Inventor after: Huang Jiyuan Inventor after: Zhang Xingwei Inventor after: Shen Xiaoli Inventor after: Xu Zhiqiang Inventor after: Luo Leixin Inventor after: Liu Lihong Inventor after: He Li Inventor after: Liu Yi Inventor after: Liao Yingao Inventor before: Tan Liping Inventor before: Zhang Yuming Inventor before: Zhang Liang Inventor before: Liang Qiuhong Inventor before: Zhang Xingwei Inventor before: Shen Xiaoli Inventor before: Xu Zhiqiang Inventor before: Luo Leixin Inventor before: Liu Lihong Inventor before: He Li Inventor before: Liu Yi Inventor before: Liao Yingao |
|
CB03 | Change of inventor or designer information |