CN111877406A - Repairing construction method of integrated pressure-resistant well lid - Google Patents

Repairing construction method of integrated pressure-resistant well lid Download PDF

Info

Publication number
CN111877406A
CN111877406A CN202010787689.2A CN202010787689A CN111877406A CN 111877406 A CN111877406 A CN 111877406A CN 202010787689 A CN202010787689 A CN 202010787689A CN 111877406 A CN111877406 A CN 111877406A
Authority
CN
China
Prior art keywords
well
well lid
cover
resistant
integrated pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010787689.2A
Other languages
Chinese (zh)
Inventor
周伟平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuxi Ailu Technology Co Ltd
Original Assignee
Wuxi Ailu Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuxi Ailu Technology Co Ltd filed Critical Wuxi Ailu Technology Co Ltd
Priority to CN202010787689.2A priority Critical patent/CN111877406A/en
Publication of CN111877406A publication Critical patent/CN111877406A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/14Covers for manholes or the like; Frames for covers
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/005Methods or materials for repairing pavings
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Road Repair (AREA)

Abstract

The invention relates to a restoration construction method of an integrated pressure-resistant well lid, which is characterized by comprising the following steps: (1) cutting by a circular spherical surface cutting machine; (2) crushing the round inner pavement, and removing the original well cover; crushing the periphery of the well lid to form a well ring mounting hole for repairing the well lid; (3) pouring the repairing material into the well ring mounting hole to be filled firmly, and leveling the repairing material to be level with the road surface after pouring; (4) in the integration resistance to compression well lid hoist and mount process, the gap between well lid and the lateral wall is filled to well lid below prosthetic materials, spills over along integration resistance to compression well lid border, wipes off the prosthetic materials that spills over. The manhole cover is quick to install and construct, the periphery of the manhole cover does not need to be subjected to crack pouring operation after the manhole cover is hoisted, the repairing operation is simpler and more convenient, the phenomenon that the periphery of the manhole cover is damaged due to the fact that repairing materials below a manhole ring are separated from a manhole ring installing hole can be effectively prevented, the effect of an integrated compression-resistant manhole cover is fully exerted, and a real integrated structure among the manhole cover, the repairing materials and a road surface is realized.

Description

Repairing construction method of integrated pressure-resistant well lid
Technical Field
The invention relates to a well lid repairing method, in particular to a repairing construction method of an integrated pressure-resistant well lid.
Background
At present, the problem of collapse of the road surface around the manhole cover is 5% of the problem of damage and noise caused by the quality problem of the manhole cover, but 95% of the problem is that the road surface around the manhole cover collapses or the foundation of the manhole cover collapses. The main reasons for the collapse of the road surface around the well lid and the collapse of the well lid foundation are the design defects of the traditional well lid. The traditional method for repairing the damaged pavement around the well cover mainly comprises the steps of digging out and grooving the asphalt pavement in the area range near the well cover for forming, filling the periphery of the well cover with cold-mixed asphalt mixture or hot-mixed asphalt mixture, and then performing construction compaction. Traditional well lid installation construction, need use concrete placement to come unable adjustment base during the maintenance, need seven days before and after the construction just can be under construction and lay pitch, the time limit for a project is longer, influences the normal current of road, and the maintenance that the construction is complicated and the maintenance back road surface needs certain time during the change leads to the fact certain traffic pressure to urban road, especially to the great road of vehicle flow, changes well lid maintenance road surface and becomes more difficult. On the other hand, the upper surface on the peripheral road surface of well lid is restoreed the back and can not guarantee the parallel and level with the road surface, influences the travelling comfort that vehicle and pedestrian passed through.
To current well lid at vehicle roll compaction in-process atress concentrate on the well seat, the atress is uneven, easily causes the problem that the road surface sinks around the well lid, has redesigned the structure of well lid among the prior art, has made the adjustment to the well lid structure from the angle of the atress area and the atress principle of well lid, forms integration resistance to compression well lid (like the well lid of the disclosure of CN201510746411, CN 201510746411). This kind of integration resistance to compression well lid passes through outer walling crib and forms integrated structure with the road surface around the well lid, has improved the compressive strength of well lid. The installation process of present integration resistance to compression well lid when being used for restoreing does: a pit is arranged at the damaged part around the well lid, and a hoisting gap is expanded outside the edge of the pit, so that a gap is reserved between the edge of the pit and the well lid ring body, and the well lid ring is favorably hoisted into the pit; and hoisting the well lid body to the well lid ring body. In the construction method in the prior art, after the ring body is hoisted, a gap exists between the ring body and the pit, a small amount of concrete can be poured in the gap, and the construction efficiency is improved.
However, in the process of repairing and installing the existing integrated pressure-resistant well lid, after the ring body is hoisted into the pit, the gap between the ring body and the pit needs to be additionally subjected to crack pouring operation, the construction steps are not simple enough, and the crack pouring work needs to be performed carefully to ensure that the heights of the well lid, the crack pouring and the road surface are kept consistent after the crack pouring. If the crack is not filled enough, a certain cavity and a loose part exist between the repair material base layer below the well lid and the side wall of the well lid mounting hole, in the vehicle rolling process, the difference exists between the strain generated by the bearing stress of the cavity and the loose part and the strain generated by the bearing stress of the repair material filled part, so that the repair material base layer is separated from the well ring mounting hole, and the periphery of the well lid is damaged. Therefore, although the integrated pressure-resistant well lid can structurally solve the phenomena of peripheral collapse and damage, the seam filling process enables the seam filling and the well lid foundation to be not of an integrated structure, and the unreasonable installation mode can also cause the reduction of the effect of the integrated pressure-resistant well lid.
Disclosure of Invention
The invention aims to overcome the defects in the prior art, and provides a repair construction method of an integrated compression-resistant well lid, which is quick to install and construct, free from crack pouring operation on the periphery of the well lid after the well lid is hoisted, simpler and more convenient in repair operation, capable of effectively preventing the damage phenomenon of the periphery of the well lid caused by the separation of a repair material below a well ring and a well ring installation hole, fully playing the role of the integrated compression-resistant well lid, and realizing the real integrated structure among the well lid, the repair material and a road surface.
According to the technical scheme provided by the invention, the restoration construction method of the integrated pressure-resistant well lid is characterized by comprising the following steps of:
(1) determining a well lid to be repaired, placing a circle center positioning frame on the well lid, enabling the center of the circle center positioning frame to coincide with the center of the well lid, and fixing the circle center positioning frame and the peripheral pavement of the well lid together to realize positioning;
(2) fixing the cutting center of the circular spherical surface cutting machine on the circle center of the circle center positioning frame, and adjusting the cutting radius of the circular spherical surface cutting machine according to the required cutting radius to cut;
(3) after the circular cutting is finished, removing the cutting machine and the positioning frame, clearing accumulated water on the road surface, and sucking sewage; crushing the round inner pavement, and removing the original well cover;
(4) after cleaning, a cross brace rod is installed at the position of a well mouth, a well mouth cover plate and cover cloth are placed on the cross brace rod, and a well ring crushing surface on the periphery of the well cover is crushed to form a well ring installation hole for repairing the well cover;
(5) paving a pavement protection pad at a well mouth, wherein an opening on the pavement protection pad exposes the area of the well curb mounting hole;
(6) disassembling a wellhead cover plate, cover cloth and a cross brace rod, putting a reinforcement cage into a walling crib mounting hole, and inserting a filling mold with a large caliber and a small caliber into a wellhead;
(7) preparing a repairing material, pouring the repairing material into the well ring mounting hole to be filled firmly, and leveling the repairing material to be level with the road surface after pouring; taking out the filling mould;
(8) pasting a circle of adhesive tape on the edge of the integrated pressure-resistant well cover, and hoisting the integrated pressure-resistant well cover to the mounting hole after pouring the repairing material for 5-8 minutes; during installation, details are adjusted according to field conditions, and the surface of the integrated pressure-resistant well cover is knocked to enable the integrated pressure-resistant well cover to be consistent with the pavement evenness;
(9) in the hoisting process of the integrated pressure-resistant well lid, repairing materials below the well lid fill gaps between the well lid and the side walls, overflow along the edge of the integrated pressure-resistant well lid, and the overflowing repairing materials are wiped off;
(10) and screwing down the bolts between the integrated pressure-resistant well cover and the repairing material to complete the installation of the well cover.
Further, the diameter of a circle cut by the asphalt at the periphery of the well lid to be repaired is not more than 0.01 meter relative to the diameter of the well lid and the well ring.
Further, the depth of the walling crib mounting hole of the integrated pressure-resistant manhole cover is not less than the height of the manhole cover.
Further, the side surface of the well lid mounting hole obtained by cutting with the circular spherical surface cutting machine is an inclined surface or an arc surface.
The invention has the following advantages:
(1) the manhole cover is quick to install and construct, the periphery of the manhole cover does not need to be subjected to crack pouring operation after the manhole cover is hoisted, the repairing operation is simpler and more convenient, the phenomenon that the periphery of the manhole cover is damaged due to the fact that repairing materials below a manhole ring are separated from a manhole ring installing hole can be effectively prevented, the function of an integrated compression-resistant manhole cover is fully exerted, and a real integrated structure among the manhole cover, the repairing materials and a road surface is realized;
(2) the invention can realize rapid construction under the condition of not influencing road operation.
Drawings
Fig. 1 is a sectional view of a first well cover mounting hole obtained by cutting.
Fig. 2 is a sectional view of a second well cover mounting hole obtained by cutting.
Fig. 3 is a schematic view of a pour mold.
Detailed Description
The invention is further described below with reference to the accompanying drawings.
Example (b):
the repairing construction method of the integrated pressure-resistant well lid comprises the following steps:
(1) determining a well lid to be repaired, placing a circle center positioning frame on the well lid, enabling the center of the circle center positioning frame to coincide with the center of the well lid, and fixing the circle center positioning frame and the peripheral pavement of the well lid together through iron nails to realize positioning;
(2) fixing the cutting center of the circular spherical surface cutting machine on the circle center of the circle center positioning frame, adjusting the cutting radius of the circular spherical surface cutting machine according to the required cutting radius, and starting cutting; in the embodiment, the diameter of the integrated pressure-resistant well lid is 1.2 meters, and the diameter of a circle cut by asphalt on the periphery of the well lid to be repaired is not more than 1.2+0.01 meter;
the side surface of the well cover mounting hole obtained by cutting with the circular spherical surface cutting machine is an inclined surface or an arc surface (the inclination is generally not more than 10 ̊) (as shown in fig. 1 and fig. 2), the side surface of the well ring mounting hole in the prior art is a vertical surface during cutting, and in this case, only the bonding force of the repairing material exists between the well cover and the road surface; in the embodiment, the side surface of the well lid mounting hole is an inclined surface or an arc surface, after the well lid is mounted, the force of the self weight of the well lid on the side wall of the mounting hole is decomposed in the transverse direction and the vertical direction, and the compression resistance is further enhanced on the basis of the bonding force of the repairing material;
(3) after the circular cutting is finished, removing the cutting machine and the positioning frame, clearing accumulated water on the road surface, and sucking sewage; crushing the round inner pavement, and removing the original well cover;
(4) after cleaning, cleaning the site garbage;
(5) installing a cross brace rod at the position of a wellhead, and placing a wellhead cover plate and cover cloth on the cross brace rod to prevent broken garbage of a well curb from falling into the wellhead; crushing a well ring crushing surface on the periphery of the well lid, and measuring the crushing depth to prevent over-deep crushing; cleaning broken garbage to form a manhole ring mounting hole for repairing a manhole cover;
(6) paving a pavement protection pad at a well mouth, wherein an opening on the pavement protection pad exposes the area of the well curb mounting hole;
(7) disassembling the wellhead cover plate, the cover cloth and the cross brace rod, and cleaning the walling crib mounting hole by using clear water; placing a reinforcement cage in a well ring mounting hole, and inserting a pouring mold with a large upper caliber and a small lower caliber into a well mouth (as shown in figure 3);
(8) preparing a repairing material in a stirring barrel on site, pouring the repairing material into the well ring mounting hole to be filled firmly, and leveling the repairing material to be flush with the road surface after pouring; taking out the filling mould;
(9) pasting a circle of adhesive tape on the edge of the integrated pressure-resistant well cover, hoisting the integrated pressure-resistant well cover to the mounting hole after pouring the repairing material for 5-8 minutes, wherein the repairing material is initially solidified, and compared with the hoisting strength which is carried out after pouring the repairing material, the hoisting strength is increased by about 10 MPa; during installation, details are adjusted according to field conditions, the surface of the integrated pressure-resistant well cover is knocked to enable the integrated pressure-resistant well cover to be consistent with the flatness of the pavement, and if the height difference is large, the well cover needs to be lifted out and leveled again;
(10) in the hoisting process of the integrated pressure-resistant well lid, the repairing material below the well lid overflows along the edge of the integrated pressure-resistant well lid, the overflowing repairing material is wiped off, the repairing material can be ensured to overflow between the well lid and the side wall of the well ring mounting hole, and the overflowing repairing material is directly wiped off without crack pouring operation after the well lid is mounted;
(11) tightening bolts between the integrated compression-resistant well cover and the repairing material to firmly connect the integrated compression-resistant well cover and the pavement repairing material; removing the pavement protection pad, installing an anti-attachment net at the well cover opening, removing the adhesive tape at the edge of the well cover, and cleaning the site; after the well cover is installed, the vehicle can be opened after the traffic is closed for about 1-2 hours.
Before the repairing steps are implemented, conical barrels, guardrails and the like can be adopted to separate the areas of 1.5 square meters on the periphery of the damaged pavement of the well lid to be treated, and traffic sealing is not needed, so that the road operation is not influenced.
In the repairing construction method of the integrated pressure-resistant well lid, after the ring body is hoisted to the area of the well ring mounting hole, the gap between the ring body and the side wall of the well ring mounting hole is small (in a common construction method, the gap between the ring body and the edge of the pit body is more than 5 cm).

Claims (4)

1. A restoration construction method of an integrated pressure-resistant well lid is characterized by comprising the following steps:
(1) placing the circle center positioning frame on the well lid to be repaired, enabling the center of the circle center positioning frame to coincide with the center of the well lid, and fixing the circle center positioning frame and the peripheral pavement of the well lid together to realize positioning;
(2) fixing the cutting center of the circular spherical surface cutting machine on the circle center of the circle center positioning frame, and adjusting the cutting radius of the circular spherical surface cutting machine according to the required cutting radius to cut;
(3) after the circular cutting is finished, removing the cutting machine and the positioning frame, clearing accumulated water on the road surface, and sucking sewage; crushing the round inner pavement, and removing the original well cover;
(4) after cleaning, a cross brace rod is installed at the position of a well mouth, a well mouth cover plate and cover cloth are placed on the cross brace rod, and a well ring crushing surface on the periphery of the well cover is crushed to form a well ring installation hole for repairing the well cover;
(5) paving a pavement protection pad at a well mouth, wherein an opening on the pavement protection pad exposes the area of the well curb mounting hole;
(6) disassembling a wellhead cover plate, cover cloth and a cross brace rod, putting a reinforcement cage into a walling crib mounting hole, and inserting a filling mold with a large caliber and a small caliber into a wellhead;
(7) preparing a repairing material, pouring the repairing material into the well ring mounting hole to be filled firmly, and leveling the repairing material to be level with the road surface after pouring; taking out the filling mould;
(8) pasting a circle of adhesive tape on the edge of the integrated pressure-resistant well cover, and hoisting the integrated pressure-resistant well cover to the mounting hole after pouring the repairing material for 5-8 minutes; during installation, details are adjusted according to field conditions, and the surface of the integrated pressure-resistant well cover is knocked to enable the integrated pressure-resistant well cover to be consistent with the pavement evenness;
(9) in the hoisting process of the integrated pressure-resistant well lid, repairing materials below the well lid fill gaps between the well lid and the side walls, overflow along the edge of the integrated pressure-resistant well lid, and the overflowing repairing materials are wiped off;
(10) and screwing down the bolts between the integrated pressure-resistant well cover and the repairing material to complete the installation of the well cover.
2. The restoration construction method of the integrated pressure-resistant well lid as claimed in claim 1, wherein: the diameter of a circle cut by the asphalt on the periphery of the well lid to be repaired is not more than 0.01 meter relative to the diameter of the well lid and the well ring.
3. The restoration construction method of the integrated pressure-resistant well lid as claimed in claim 1, wherein: the depth of the well ring mounting hole of the integrated pressure-resistant well lid is not less than the height of the well lid.
4. The restoration construction method of the integrated pressure-resistant well lid as claimed in claim 1, wherein: the side surface of the well lid mounting hole obtained by cutting with the circular spherical surface cutting machine is an inclined surface or an arc surface.
CN202010787689.2A 2020-08-07 2020-08-07 Repairing construction method of integrated pressure-resistant well lid Pending CN111877406A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010787689.2A CN111877406A (en) 2020-08-07 2020-08-07 Repairing construction method of integrated pressure-resistant well lid

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010787689.2A CN111877406A (en) 2020-08-07 2020-08-07 Repairing construction method of integrated pressure-resistant well lid

Publications (1)

Publication Number Publication Date
CN111877406A true CN111877406A (en) 2020-11-03

Family

ID=73210311

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010787689.2A Pending CN111877406A (en) 2020-08-07 2020-08-07 Repairing construction method of integrated pressure-resistant well lid

Country Status (1)

Country Link
CN (1) CN111877406A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2555291Y (en) * 2002-07-17 2003-06-11 青岛大门铸造有限公司 Anti-theft manhole cover
CN103866792A (en) * 2014-04-04 2014-06-18 北京百世融通市政工程有限公司 Construction technology for super-early-strength grouting material reinforced inspection well
CN205669215U (en) * 2016-05-04 2016-11-02 无锡爱路建设有限公司 The well lid reparation mould pouring installation foundation
CN107747327A (en) * 2017-12-01 2018-03-02 无锡爱路建设有限公司 Well lid and its installation method are repaired in integrated resistance to compression

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2555291Y (en) * 2002-07-17 2003-06-11 青岛大门铸造有限公司 Anti-theft manhole cover
CN103866792A (en) * 2014-04-04 2014-06-18 北京百世融通市政工程有限公司 Construction technology for super-early-strength grouting material reinforced inspection well
CN205669215U (en) * 2016-05-04 2016-11-02 无锡爱路建设有限公司 The well lid reparation mould pouring installation foundation
CN107747327A (en) * 2017-12-01 2018-03-02 无锡爱路建设有限公司 Well lid and its installation method are repaired in integrated resistance to compression

Similar Documents

Publication Publication Date Title
CN106759496B (en) Anti-settling inspection shaft changes the outfit technique
CN106759792B (en) A kind of inspection shaft construction technique
CN106638696A (en) Installation and construction method for anti-settling manhole cover
CN105133655A (en) Construction method of well lid of road surface inspection well and auxiliary installation device
CN108330764B (en) Shallow layer solidified pile bearing type embankment and construction method
LU501207B1 (en) Structure and method for reinforcing manhole cover anchored with existing road surface foundation by means of dowel bars
CN110409244B (en) Composite bearing prefabricated road slab and prefabricated pavement construction method
CN215253030U (en) Anti-settling inspection well cover
CN108930224A (en) Punching stick method bent cap supports regulating system construction method
JP3522268B2 (en) Frame replacement method including manhole cover
CN110700320A (en) Anti-sedimentation construction process for municipal road inspection well
CN201411713Y (en) Manhole of various kinds of pipe networks for urban roads having hole mouth reinforcing mechanism
CN205662948U (en) Cold area road surface manhole cover
CN111877406A (en) Repairing construction method of integrated pressure-resistant well lid
CN218757610U (en) Cutting leveling type invisible inspection well cover
CN217579581U (en) Bituminous paving inspection shaft reinforced structure
KR100966639B1 (en) Manhole repair method
CN111593722B (en) Building surface settlement repairing method
CN212357904U (en) Inspection well lid mounting tool with adjustable
CN108103937A (en) Utilize the cast-in-place box beam construction method of native loose tool substitution falsework
CN216130156U (en) Building basement bottom plate water-collecting device
CN104480966B (en) Bolt steel cover plate guide-well construction and bolt steel cover plate device used
CN204418216U (en) Bolt steel cover plate guide-well construction bolt steel cover plate device used
CN110777570A (en) Expansive soil large-deformation anti-upwarp foundation structure and construction method of foundation structure
CN116084541A (en) Rain grate, and mounting structure and method for same

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20201103