CN111861787A - Substation operation ticket processing method and device, computer equipment and storage medium - Google Patents

Substation operation ticket processing method and device, computer equipment and storage medium Download PDF

Info

Publication number
CN111861787A
CN111861787A CN202010607780.1A CN202010607780A CN111861787A CN 111861787 A CN111861787 A CN 111861787A CN 202010607780 A CN202010607780 A CN 202010607780A CN 111861787 A CN111861787 A CN 111861787A
Authority
CN
China
Prior art keywords
transformation operation
operation ticket
power transformation
ticket
power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010607780.1A
Other languages
Chinese (zh)
Inventor
万华舰
杨振宝
薛志成
崔志文
谢志毅
欧旋
谌志强
李轩
苏再刚
蒋立斌
徐达东
巫伟南
金宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Power Supply Bureau Co Ltd
Original Assignee
Shenzhen Power Supply Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Power Supply Bureau Co Ltd filed Critical Shenzhen Power Supply Bureau Co Ltd
Priority to CN202010607780.1A priority Critical patent/CN111861787A/en
Publication of CN111861787A publication Critical patent/CN111861787A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/30Information retrieval; Database structures therefor; File system structures therefor of unstructured textual data
    • G06F16/33Querying
    • G06F16/332Query formulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F40/00Handling natural language data
    • G06F40/10Text processing
    • G06F40/166Editing, e.g. inserting or deleting
    • G06F40/186Templates
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Strategic Management (AREA)
  • General Physics & Mathematics (AREA)
  • Human Resources & Organizations (AREA)
  • Health & Medical Sciences (AREA)
  • Economics (AREA)
  • General Health & Medical Sciences (AREA)
  • Computational Linguistics (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Data Mining & Analysis (AREA)
  • General Engineering & Computer Science (AREA)
  • Water Supply & Treatment (AREA)
  • Audiology, Speech & Language Pathology (AREA)
  • Artificial Intelligence (AREA)
  • Public Health (AREA)
  • Primary Health Care (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Mathematical Physics (AREA)
  • Databases & Information Systems (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The application relates to a power transformation operation ticket processing method and device, computer equipment and a storage medium. The method comprises the following steps: and acquiring a transformation operation ticket in an electronic document format. And automatically checking the safety standard of the transformer operation ticket according to the standard automatic checking rule generated based on the electric power safety standard file. And automatically checking the attribute of the component associated with the transformer operation ticket based on the equipment component database. And automatically checking the electric power operation state of the transformation operation ticket according to the historical transformation operation ticket corresponding to the transformation operation ticket. And automatically checking the safety measures of the power transformation operation tickets according to the power transformation work tickets related to the power transformation operation tickets. And when at least one item of the automatic examination fails, triggering examination and error reporting, and triggering the transformer operation ticket to be adjusted based on the examination and error reporting contents. And when all the automatic reviews pass, triggering the power transformation operation ticket to take effect. By adopting the method, the checking accuracy of the transformer operation ticket can be improved.

Description

Substation operation ticket processing method and device, computer equipment and storage medium
Technical Field
The application relates to the technical field of electrical safety, in particular to a power transformation operation ticket processing method and device, computer equipment and a storage medium.
Background
A substation is a place in an electric power system where voltage and current are converted, electric energy is received, and electric energy is distributed. The transformer substation comprises a plurality of high-voltage electrical devices, and the high-voltage electrical devices need to be subjected to standard operation based on corresponding transformer operation tickets so as to ensure the operation safety. The substation operation ticket is an organized written control basis designed for changing the application state of electrical equipment and related factors to carry out logical operation and orderly communication. The transformer operation ticket is an important basis for operation, maintenance, test and construction of electrical equipment, and is an important measure for ensuring the safety of personnel, a power grid and electrical equipment in the power production process. In order to ensure the normative of the transformation operation tickets in the transformer substation, the transformation operation tickets need to be examined and processed.
At present, the checking and processing work of the power transformation operation ticket completely depends on manual checking. However, the manual examination of the substation operation tickets often results in unqualified substation operation tickets, which results in low examination accuracy of the substation operation tickets.
Disclosure of Invention
In view of the above, it is necessary to provide a substation operation ticket processing method, a substation operation ticket processing apparatus, a computer device, and a storage medium, which can improve the accuracy of checking a substation operation ticket.
A method of substation operation ticket processing, the method comprising:
acquiring a transformation operation ticket in an electronic document format;
according to a standard automatic inspection rule generated based on the electric power safety standard file, carrying out automatic inspection of safety standards on the power transformation operation ticket;
automatically checking the attribute of the component associated with the transformer operation ticket based on an equipment component database;
according to the historical transformation operation ticket corresponding to the transformation operation ticket, automatically checking the electric power operation state of the transformation operation ticket;
according to the power transformation work ticket related to the power transformation operation ticket, automatically checking the safety measures of the power transformation operation ticket;
when at least one item of the automatic examination fails, triggering examination and error reporting, and triggering to adjust the power transformation operation ticket based on the content of the examination and error reporting;
and when all the automatic examination passes, triggering the power transformation operation ticket to take effect.
In one embodiment, the automatically reviewing the safety regulations of the transformer operation ticket according to the automatic reviewing rules of the regulations generated based on the power safety regulations file includes:
according to a standard automatic examination rule generated based on an electric power safety standard file, searching a first preset component name at a preset position of the power transformation operation ticket;
When the name of the first preset component is not found at the preset position of the power transformation operation ticket, judging that the automatic examination of the safety standard of the power transformation operation ticket does not pass;
when the first preset component name is found at the preset position of the power transformation operation ticket, judging whether the statement of the operation step corresponding to the first preset component name meets a preset grammar rule or not; if the safety standard is met, the safety standard of the power transformation operation ticket is judged to be automatically checked; otherwise, judging that the safety standard automatic examination of the power transformation operation ticket is not passed.
In one embodiment, the automatically reviewing component attributes of the components associated with the substation operation ticket based on the equipment component database includes:
extracting attributes of components associated with the power transformation operation tickets from the power transformation operation tickets;
searching the extracted attributes of the components associated with the power transformation operation ticket in the equipment component database;
when the extracted attributes of the components associated with the substation operation tickets are found in the equipment component database, determining that the automatic examination of the component attributes of the components associated with the substation operation tickets is passed; otherwise, determining that the automatic component attribute examination of the attributes of the components associated with the substation operation ticket is not passed.
In one embodiment, the automatically checking the power transformation operation ticket according to the historical power transformation operation ticket corresponding to the power transformation operation ticket of the power transformation operation ticket includes:
respectively extracting the associated component names from the power transformation operation tickets and the historical power transformation operation tickets corresponding to the power transformation operation tickets;
judging whether the corresponding power operation states are opposite or not aiming at the extracted same component name;
when the power operation states are opposite, judging that the power operation states of the power transformation operation tickets are automatically checked to pass; otherwise, judging that the automatic examination of the electric power operation state of the transformation operation ticket is not passed.
In one embodiment, the automatically reviewing the security measures of the substation operation tickets according to the substation work tickets related to the substation operation tickets includes:
respectively extracting electric power operation states corresponding to second preset component names from the power transformation operation tickets and power transformation work tickets related to the power transformation operation tickets;
when the extracted electric power operation states corresponding to the second preset component names are consistent, judging that the safety measures performed on the power transformation operation tickets are automatically checked; otherwise, judging that the safety measures performed on the power transformation operation ticket are automatically checked and failed.
In one embodiment, before the obtaining the substation operation ticket in the electronic document format, the method further includes:
acquiring power transformation operation task information;
determining equipment to be transformed and the names of components to be operated corresponding to the equipment to be transformed according to the transformation operation task information;
and generating a power transformation operation ticket in an electronic document format according to the equipment to be transformed and the part name to be operated corresponding to the equipment to be transformed and a preset power transformation operation ticket template.
A substation operation ticket processing apparatus, the apparatus comprising:
the acquisition module is used for acquiring a power transformation operation ticket in an electronic document format;
the examination module is used for automatically examining the safety specifications of the power transformation operation ticket according to the automatic specification examination rule generated based on the power safety specification file; automatically checking the attribute of the component associated with the transformer operation ticket based on an equipment component database; according to the historical transformation operation ticket corresponding to the transformation operation ticket, automatically checking the electric power operation state of the transformation operation ticket; according to the power transformation work ticket related to the power transformation operation ticket, automatically checking the safety measures of the power transformation operation ticket; when at least one item of the automatic examination fails, triggering examination and error reporting, and triggering to adjust the power transformation operation ticket based on the content of the examination and error reporting; and when all the automatic examination passes, triggering the power transformation operation ticket to take effect.
In one embodiment, the apparatus further comprises:
the generating module is used for acquiring the power transformation operation task information; determining equipment to be transformed and the names of components to be operated corresponding to the equipment to be transformed according to the transformation operation task information; and generating a power transformation operation ticket in an electronic document format according to the equipment to be transformed and the part name to be operated corresponding to the equipment to be transformed and a preset power transformation operation ticket template.
A computer device comprising a memory, a processor and a computer program stored on the memory and executable on the processor, the processor implementing the following steps when executing the computer program:
acquiring a transformation operation ticket in an electronic document format;
according to a standard automatic inspection rule generated based on the electric power safety standard file, carrying out automatic inspection of safety standards on the power transformation operation ticket;
automatically checking the attribute of the component associated with the transformer operation ticket based on an equipment component database;
according to the historical transformation operation ticket corresponding to the transformation operation ticket, automatically checking the electric power operation state of the transformation operation ticket;
according to the power transformation work ticket related to the power transformation operation ticket, automatically checking the safety measures of the power transformation operation ticket;
When at least one item of the automatic examination fails, triggering examination and error reporting, and triggering to adjust the power transformation operation ticket based on the content of the examination and error reporting;
and when all the automatic examination passes, triggering the power transformation operation ticket to take effect.
A computer-readable storage medium, on which a computer program is stored which, when executed by a processor, carries out the steps of:
acquiring a transformation operation ticket in an electronic document format;
according to a standard automatic inspection rule generated based on the electric power safety standard file, carrying out automatic inspection of safety standards on the power transformation operation ticket;
automatically checking the attribute of the component associated with the transformer operation ticket based on an equipment component database;
according to the historical transformation operation ticket corresponding to the transformation operation ticket, automatically checking the electric power operation state of the transformation operation ticket;
according to the power transformation work ticket related to the power transformation operation ticket, automatically checking the safety measures of the power transformation operation ticket;
when at least one item of the automatic examination fails, triggering examination and error reporting, and triggering to adjust the power transformation operation ticket based on the content of the examination and error reporting;
and when all the automatic examination passes, triggering the power transformation operation ticket to take effect.
According to the power transformation operation ticket processing method, the device, the computer equipment and the storage medium, the power transformation operation ticket in the electronic document format is obtained, and the safety standard automatic examination is performed on the power transformation operation ticket according to the standard automatic examination rule generated based on the power safety standard file, so that the power transformation operation ticket is ensured to meet the requirements of the power safety standard file. And automatically checking the attributes of the components associated with the substation operation tickets on the basis of the equipment component database so as to ensure that the attributes of the components associated with the substation operation tickets are correct. And automatically checking the electric power operation state of the transformation operation ticket according to the historical transformation operation ticket corresponding to the transformation operation ticket so as to ensure that the electric power operation state of the transformation operation ticket is accurate. And automatically checking the safety measures of the power transformation operation tickets according to the power transformation work tickets related to the power transformation operation tickets so as to ensure that the power transformation operation tickets meet the requirements of safety measure specifications. And when at least one item of the automatic examination fails, triggering examination and error reporting, and triggering the transformer operation ticket to be adjusted based on the examination and error reporting contents. And when all the automatic reviews pass, triggering the power transformation operation ticket to take effect. Therefore, the probability of unqualified transformer operation tickets is reduced by carrying out automatic safety standard examination, automatic component attribute examination, automatic electric power operation state examination and automatic safety measure examination on the transformer operation tickets, and the examination accuracy of the transformer operation tickets is improved.
Drawings
FIG. 1 is a diagram illustrating an exemplary scenario of a substation operation order processing method;
FIG. 2 is a schematic flow chart of a substation operation order processing method according to an embodiment;
FIG. 3 is a schematic view of an examination flow of operational terms of a component "switch" in one embodiment;
FIG. 4 is a schematic diagram illustrating an exemplary review process of the names of components "cabinets" in one embodiment;
FIG. 5 is a schematic diagram illustrating an exemplary process for reviewing a power-on ticket via a power-off ticket;
FIG. 6 is a schematic diagram illustrating a process for reviewing substation operation tickets via substation work tickets in one embodiment;
FIG. 7 is a block diagram of a substation operation order processing apparatus according to an embodiment;
fig. 8 is a block diagram showing the structure of a substation operation order processing apparatus according to another embodiment;
FIG. 9 is a diagram illustrating an internal structure of a computer device according to an embodiment.
Detailed Description
In order to make the objects, technical solutions and advantages of the present application more apparent, the present application is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the present application and are not intended to limit the present application.
The substation operation ticket processing method provided by the application can be applied to the application environment shown in fig. 1. The application environment includes a terminal 102 and a server 104. The terminal 102 and the server 104 communicate via a network. The terminal 102 may specifically include a desktop terminal or a mobile terminal. The mobile terminal may specifically include at least one of a mobile phone, a tablet computer, a notebook computer, and the like. The server 104 may be implemented as a stand-alone server or as a server cluster comprised of multiple servers. Those skilled in the art will understand that the application environment shown in fig. 1 is only a part of the scenario related to the present application, and does not constitute a limitation to the application environment of the present application.
The terminal 102 acquires the substation operation ticket in the electronic document format from the server 104. The terminal 102 automatically inspects the safety standard of the transformer operation ticket according to the standard automatic inspection rule generated based on the power safety standard file. The terminal 102 automatically reviews the component attributes of the components associated with the substation operation ticket based on the equipment component database. And the terminal 102 automatically checks the power operation state of the power transformation operation ticket according to the historical power transformation operation ticket corresponding to the power transformation operation ticket. And the terminal 102 automatically checks the safety measures of the power transformation operation tickets according to the power transformation work tickets related to the power transformation operation tickets. When at least one item of the automatic examination fails, the terminal 102 triggers examination error reporting and triggers the transformer operation ticket to be adjusted based on the examination error reporting content. When all the automatic reviews pass, the terminal 102 triggers the power transformation operation ticket to take effect.
In one embodiment, as shown in fig. 2, a substation operation ticket processing method is provided, which is described by taking the method as an example applied to the terminal 102 in fig. 1, and includes the following steps:
s202, obtaining a transformation operation ticket in an electronic document format.
Specifically, the terminal may locally generate the substation operation ticket in an electronic document format. Furthermore, the terminal can obtain the transformation operation ticket in the electronic document format generated locally.
In one embodiment, the transformation operation ticket in the electronic document format is stored in the server. The terminal may communicate with the server. Furthermore, the terminal can acquire the transformation operation ticket in the electronic document format from the server.
And S204, automatically checking the safety standard of the transformer operation ticket according to the standard automatic checking rule generated based on the electric power safety standard file.
Wherein the power safety specification file is a file that specifies operational requirements of equipment in the substation. The standard automatic examination rule is a rule for automatically carrying out standard examination on the transformation operation ticket.
Specifically, the terminal may obtain a power safety specification file and generate a specification automatic review rule based on the power safety specification file. Furthermore, the terminal can automatically check the safety standard of the transformer operation ticket according to the standard automatic checking rule generated based on the electric power safety standard file.
In one embodiment, the power safety specification document may include the southern Power grid, Inc. Power safety work rules, China. The terminal can acquire the electric power safety work regulations of the south China electric network Limited liability company, and automatically inspect the safety regulations of the operation terms, the position terms, the operation principles and the like of the transformer operation tickets according to the standard automatic inspection rules generated based on the electric power safety work regulations of the south China electric network Limited liability company.
And S206, automatically checking the component attribute of the component associated with the transformer operation ticket based on the equipment component database.
The equipment component database is a database in which information on equipment components related to equipment in the power system is stored.
Specifically, the terminal may determine a related equipment component database and may obtain attributes of components associated with the substation operation ticket. Furthermore, the terminal can automatically check the component attribute of the component related to the substation operation ticket based on the equipment component database.
In one embodiment, the components associated with the substation operation ticket may specifically include at least one of a pressure plate, a pressure plate meter, a screen cabinet, an air switch, a handle, and the like. The attribute of the component may specifically include at least one of a component name, a component number, a component position, a component state, and the like.
And S208, automatically checking the electric power operation state of the transformation operation ticket according to the historical transformation operation ticket corresponding to the transformation operation ticket.
The historical transformation operation ticket is generated before the generation time of the transformation operation ticket processed at this time.
Specifically, the terminal may obtain a historical substation operation ticket corresponding to the substation operation ticket. The terminal can respectively determine the corresponding component operation states in the historical transformation operation tickets corresponding to the transformation operation tickets and the transformation operation tickets, and compares the corresponding component operation states of the historical transformation operation tickets corresponding to the transformation operation tickets and the transformation operation tickets so as to automatically check the electric power operation states of the transformation operation tickets.
And S210, automatically checking the safety measures of the power transformation operation tickets according to the power transformation work tickets related to the power transformation operation tickets.
The power transformation work ticket is a work ticket generated when equipment corresponding to the power transformation operation ticket is overhauled.
Specifically, the terminal may generate a substation work ticket associated with the substation operation ticket. Further, the terminal may obtain a transformation work order associated with the transformation operation order. The terminal can automatically check the safety measures of the power transformation operation tickets according to the power transformation work tickets related to the power transformation operation tickets.
And S212, when at least one item of the automatic examination fails, triggering examination and error reporting, and triggering the transformer operation ticket to be adjusted based on the examination and error reporting content.
Specifically, the terminal may acquire respective inspection results of automatic inspection of security specifications, automatic inspection of component attributes, automatic inspection of power operation state, and automatic inspection of security measures. When at least one item in the examination results is not passed, the terminal can trigger examination error reporting. And the terminal can trigger the transformer operation ticket to be adjusted based on the content of examination and error reporting.
In one embodiment, the terminal can automatically adjust the substation operation ticket based on the content of the error report of the examination.
In one embodiment, the user may modify the substation operation ticket based on the content of the error report. The terminal can obtain the electric operation ticket modified by the user, and replace the power transformation operation ticket with the modified electric operation ticket.
And S214, when all the automatic checks pass, triggering the power transformation operation ticket to take effect.
Specifically, the terminal may trigger the power transformation operation ticket to take effect when all of the safety specification automatic review, the component attribute automatic review, the power operation state automatic review, and the safety measure automatic review pass. It can be understood that the validated transformation operation ticket can be used as a basis for a user to operate the transformation equipment in the transformer substation on site.
According to the power transformation operation ticket processing method, the power transformation operation ticket in the electronic document format is obtained, and the safety standard automatic inspection is performed on the power transformation operation ticket according to the standard automatic inspection rule generated based on the power safety standard file, so that the power transformation operation ticket is ensured to meet the requirements of the power safety standard file. And automatically checking the attributes of the components associated with the substation operation tickets on the basis of the equipment component database so as to ensure that the attributes of the components associated with the substation operation tickets are correct. And automatically checking the electric power operation state of the transformation operation ticket according to the historical transformation operation ticket corresponding to the transformation operation ticket so as to ensure that the electric power operation state of the transformation operation ticket is accurate. And automatically checking the safety measures of the power transformation operation tickets according to the power transformation work tickets related to the power transformation operation tickets so as to ensure that the power transformation operation tickets meet the requirements of safety measure specifications. And when at least one item of the automatic examination fails, triggering examination and error reporting, and triggering the transformer operation ticket to be adjusted based on the examination and error reporting contents. And when all the automatic reviews pass, triggering the power transformation operation ticket to take effect. Therefore, the probability of unqualified transformer operation tickets is reduced by carrying out automatic safety standard examination, automatic component attribute examination, automatic electric power operation state examination and automatic safety measure examination on the transformer operation tickets, and the examination accuracy of the transformer operation tickets is improved.
In an embodiment, in step S204, that is, the step of performing automatic safety standard review on the substation operation ticket according to the standard automatic review rule generated based on the power safety specification file specifically includes: according to a standard automatic examination rule generated based on the electric power safety standard file, searching a first preset component name at a preset position of a power transformation operation ticket; when the name of the first preset component is not found at the preset position of the power transformation operation ticket, judging that the automatic examination of the safety standard of the power transformation operation ticket does not pass; when the first preset component name is found at the preset position of the power transformation operation ticket, judging whether the statement of the operation step corresponding to the first preset component name meets a preset grammar rule or not; if the safety standard is met, the safety standard of the power transformation operation ticket is judged to be automatically checked; otherwise, judging that the safety standard automatic examination of the transformer operation ticket is not passed.
The first preset component name is the name of a preset component corresponding to the automatic safety standard examination of the transformer operation ticket.
Specifically, the terminal may obtain a first preset component name, and search the first preset component name at a preset position of the substation operation ticket according to a standard automatic review rule generated based on the power safety specification file. The terminal can monitor the searching state of the first preset component name in real time. When the terminal monitors that the name of the first preset component is not found at the preset position of the power transformation operation ticket, the terminal can directly judge that the safety standard automatic examination of the power transformation operation ticket is not passed. When the terminal monitors that the first preset component name is found at the preset position of the power transformation operation ticket, the terminal can obtain the corresponding preset grammar rule. Furthermore, the terminal can determine whether the statement of the operation step corresponding to the first preset component name meets the preset grammar rule. If the sentence of the operation step corresponding to the first preset component name accords with the preset grammar rule, the terminal can judge that the safety standard of the transformer operation ticket is automatically checked to pass. If the statement of the operation step corresponding to the first preset component name does not accord with the preset grammar rule, the terminal can judge that the safety standard automatic examination of the transformer operation ticket does not pass.
In one embodiment, as shown in fig. 3, the terminal may determine whether a "switch" is included in the operation step of the substation operation ticket, and the operation step is a main item in the operation step (for example, the main item is step 1, and the corresponding sub items are steps 1.1, 1.2, and 1.3, etc.). When the terminal judges that the operation steps of the power transformation operation ticket comprise the switch and are main items in the operation steps, the terminal can continuously judge whether the operation steps in the power transformation operation ticket end with the switch and do not start with the switch. When the terminal judges that the operation steps in the transformation operation ticket end in the 'switch' and do not start in the 'on' or 'off', the terminal can trigger the generation of error report information 'switch operation term error'.
In the above embodiment, the accuracy of the automatic safety standard examination of the substation operation ticket is further ensured by judging whether the first preset component name can be found at the preset position of the substation operation ticket and judging whether the statement of the operation step corresponding to the first preset component name meets the double-level examination processing of the preset grammar rule.
In an embodiment, in step S206, that is, the step of performing automatic component attribute review on the attribute of the component associated with the substation operation ticket based on the equipment component database specifically includes: extracting attributes of components related to the substation operation tickets from the substation operation tickets; searching the attribute of the component associated with the extracted substation operation ticket in an equipment component database; when the attribute of the component associated with the extracted substation operation ticket is found in the equipment component database, judging that the component attribute of the component associated with the substation operation ticket is automatically checked to be passed; otherwise, the automatic examination of the component attribute of the component associated with the substation operation ticket is judged not to pass.
Specifically, the attributes of the components associated with the substation operation ticket may be included in the substation operation ticket. The terminal may extract attributes of components associated with the substation operation ticket from the substation operation ticket. The terminal can determine a corresponding equipment component database, and search the extracted attributes of the components associated with the substation operation ticket in the equipment component database. The terminal can monitor the searching state of the attributes of the components associated with the power transformation operation tickets in real time. When the terminal monitors that the attributes of the parts associated with the extracted transformer operation tickets are found in the equipment part database, the terminal can directly judge that the parts attributes of the parts associated with the transformer operation tickets are automatically checked. When the terminal monitors that the attribute of the component associated with the extracted substation operation ticket is not found in the equipment component database, the terminal can judge that the automatic component attribute examination of the component associated with the substation operation ticket is not passed.
In one embodiment, as shown in fig. 4, the terminal may determine whether the statement of the operation step in the substation operation ticket is "in the screen cabinet". When the terminal judges that the sentence of the operation step in the substation operation ticket is 'screen cabinet', the terminal can extract the name of the screen cabinet and search the name of the screen cabinet in a database corresponding to the account. When the name of the screen cabinet is not searched in the database corresponding to the account, the terminal can generate error report information, namely screen cabinet name error.
In the above embodiment, the component attributes of the components associated with the substation operation tickets are automatically checked by determining whether the extracted attributes of the components associated with the substation operation tickets can be found in the equipment component database. In this way, the accuracy of automatic checking of the component attributes of the transformer operation ticket is further ensured.
In an embodiment, in step S208, that is, the step of automatically checking the power operation state of the substation operation ticket according to the historical substation operation ticket corresponding to the substation operation ticket specifically includes: respectively extracting the names of the components associated with the transformation operation tickets from the historical transformation operation tickets corresponding to the transformation operation tickets; judging whether the corresponding power operation states are opposite or not aiming at the extracted same component name; when the power operation states are opposite, the automatic examination of the power operation states of the power transformation operation tickets is judged to be passed; otherwise, the automatic examination of the electric power operation state of the transformation operation ticket is judged not to pass.
Specifically, the transformation operation ticket is associated with a component name, and a historical transformation operation ticket corresponding to the transformation operation ticket is also associated with a corresponding component name. The terminal can respectively extract the name of the associated component from the power transformation operation ticket and the historical power transformation operation ticket corresponding to the power transformation operation ticket. Each component name may correspond to a respective power operating state. The terminal may determine whether the respective corresponding power operation states are opposite for the extracted identical component names. The terminal can monitor the judgment condition of the electric power operation state in real time. When the terminal monitors that the electric power operation states corresponding to the same component names are opposite, the terminal can judge that the electric power operation states of the transformer operation tickets are automatically checked to pass. When the terminal monitors that the electric power operation states corresponding to the same component names are the same, the terminal can judge that the automatic examination of the electric power operation states of the transformer operation tickets does not pass.
In one embodiment, as shown in fig. 5, the substation operation tickets may include power transmission operation tickets and power outage operation tickets. The terminal can determine whether the operation steps of the power transmission operation ticket end with a "switch" and start with an "on" or not. When the terminal determines that the operation procedure of the power transmission operation ticket ends with the "switch" and starts with the "on" name, the terminal may extract the name of the switch, and determine whether the operation procedure of the power failure operation ticket ends with the "switch" and starts with the "off" name, and the switch names are consistent. When the terminal judges that any one of the conditions of ending with the switch and beginning with the disconnection in the operation steps of the power failure operation ticket and the condition of being consistent with the switch name is not qualified, the terminal can generate error report information 'unclosed loop'.
In the above embodiment, the power transformation operation tickets are automatically checked for the power operation states by determining whether the power operation states corresponding to the same component names in the power transformation operation tickets and the historical power transformation operation tickets corresponding to the power transformation operation tickets are opposite. In this way, the accuracy of the automatic checking of the electric power operation state of the transformation operation ticket is further ensured.
In an embodiment, in step S210, that is, the step of automatically checking the safety measure of the substation operation ticket according to the substation work ticket associated with the substation operation ticket specifically includes: respectively extracting electric power operation states corresponding to the names of the second preset components from the power transformation operation tickets and the power transformation operation tickets related to the power transformation operation tickets; when the extracted electric power operation states corresponding to the second preset component names are consistent, judging that the safety measures of the power transformation operation ticket are automatically checked; otherwise, judging that the safety measures performed on the substation operation ticket are automatically checked and failed.
And the second preset component name is a preset component name corresponding to the automatic examination of the safety measures of the transformer operation ticket.
Specifically, the transformation operation ticket and a transformation work ticket associated with the transformation operation ticket have a second preset component name. And the second preset component names in the transformation operation tickets and the transformation operation ticket related transformation operation tickets correspond to respective electric power operation states. The terminal can respectively extract the electric power operation states corresponding to the second preset component names from the power transformation operation tickets and the power transformation operation tickets related to the power transformation operation tickets. The terminal can compare the power operation states corresponding to the names of the second preset components in the power transformation operation tickets and the power transformation operation tickets related to the power transformation operation tickets. When the power transformation operation ticket and the power transformation operation ticket related to the power transformation operation ticket have the same corresponding power operation states of the second preset component name, the terminal can judge that the safety measures performed on the power transformation operation ticket are automatically checked. When the power transformation operation ticket and the power transformation operation ticket related to the power transformation operation ticket have inconsistent corresponding power operation states of the second preset component name, the terminal can judge that the safety measures performed on the power transformation operation ticket are automatically checked and not passed.
In one embodiment, as shown in fig. 6, the terminal may determine whether there is a requirement to turn off the "switch" in the safety measures specified by the substation work ticket corresponding to the substation operation ticket. When the terminal judges that the safety measures specified by the transformer work ticket require to turn off the switch, the terminal can extract the name of the switch and judge whether the operation steps of the transformer work ticket are ended by the switch and started by the switch, and the names of the switches are consistent. When the terminal judges that the operation steps of the power failure operation ticket are ended by the switch and started by the disconnection, and any one of the conditions of consistent switch names does not meet the requirement, the terminal can generate error reporting information that the safety measure is not met.
In the above embodiment, the safety measures of the substation operation tickets are automatically checked by judging whether the power operation states corresponding to the names of the second preset components in the substation operation tickets and the substation operation tickets related to the substation operation tickets are consistent or not. Therefore, the accuracy of automatic examination of the safety measures of the transformer operation tickets is further ensured.
In one embodiment, before the obtaining of the substation operation ticket in the electronic document format, the method for processing the electrical operation ticket further includes: acquiring power transformation operation task information; determining equipment to be transformed and names of parts to be operated corresponding to the equipment to be transformed according to the transformation operation task information; and generating a power transformation operation ticket in an electronic document format according to the equipment to be transformed and the name of the part to be operated corresponding to the equipment to be transformed and a preset power transformation operation ticket template.
The power transformation operation task information is information corresponding to a power transformation operation task corresponding to an actual power transformation service requirement.
Specifically, the terminal can obtain the transformer operation task information and a preset transformer operation ticket template. The power transformation operation task information may include a device to be transformed and a name of a component to be operated corresponding to the device to be transformed. The terminal can determine the equipment to be transformed and the names of the parts to be operated corresponding to the equipment to be transformed according to the transformation operation task information. And generating a transformation operation ticket in an electronic document format according to the determined equipment to be transformed and the name of the part to be operated corresponding to the equipment to be transformed and the obtained preset transformation operation ticket template.
In the embodiment, the transformation operation order in the electronic document format is generated through the transformation operation task information determined by the transformation operation task information, the device to be transformed, the name of the part to be operated corresponding to the device to be transformed, and the preset transformation operation order template, so that the generation time of the transformation operation order can be shortened, and the generation efficiency of the transformation operation order is improved.
It should be understood that although the various steps of fig. 2 are shown in order, the steps are not necessarily performed in order. The steps are not performed in the exact order shown and described, and may be performed in other orders, unless explicitly stated otherwise. Moreover, at least a portion of the steps in fig. 2 may include multiple sub-steps or multiple stages, which are not necessarily performed at the same time, but may be performed at different times, and the order of performing the sub-steps or stages is not necessarily sequential, but may be performed alternately or alternately with other steps or at least a portion of the sub-steps or stages of other steps.
In one embodiment, as shown in fig. 7, there is provided a substation operation ticket processing apparatus 700 including: an acquisition module 701 and an inspection module 702, wherein:
the obtaining module 701 is configured to obtain a substation operation ticket in an electronic document format.
The examination module 702 is configured to perform automatic examination of safety regulations on the substation operation tickets according to the automatic examination rules of the regulations generated based on the power safety regulation file; automatically checking the attribute of the component associated with the transformer operation ticket based on the equipment component database; according to the historical transformation operation tickets corresponding to the transformation operation tickets, automatically checking the electric power operation states of the transformation operation tickets; according to the power transformation work ticket related to the power transformation operation ticket, automatically checking the safety measures of the power transformation operation ticket; when at least one item of the automatic examination fails, triggering examination and error reporting, and triggering the transformer operation ticket adjusted based on the examination and error reporting contents; and when all the automatic reviews pass, triggering the power transformation operation ticket to take effect.
In one embodiment, the review module 702 is further configured to search for a first preset component name at a preset position of the substation operation ticket according to a specification automatic review rule generated based on the power safety specification file; when the name of the first preset component is not found at the preset position of the power transformation operation ticket, judging that the automatic examination of the safety standard of the power transformation operation ticket does not pass; when the first preset component name is found at the preset position of the power transformation operation ticket, judging whether the statement of the operation step corresponding to the first preset component name meets a preset grammar rule or not; if the safety standard is met, the safety standard of the power transformation operation ticket is judged to be automatically checked; otherwise, judging that the safety standard automatic examination of the transformer operation ticket is not passed.
In one embodiment, the review module 702 is further configured to extract, from the substation operation ticket, attributes of the component associated with the substation operation ticket; searching the attribute of the component associated with the extracted substation operation ticket in an equipment component database; when the attribute of the component associated with the extracted substation operation ticket is found in the equipment component database, judging that the component attribute of the component associated with the substation operation ticket is automatically checked to be passed; otherwise, the automatic examination of the component attribute of the component associated with the substation operation ticket is judged not to pass.
In one embodiment, the review module 702 is further configured to extract the associated component names from the substation operation tickets and the historical substation operation tickets corresponding to the substation operation tickets; judging whether the corresponding power operation states are opposite or not aiming at the extracted same component name; when the power operation states are opposite, the automatic examination of the power operation states of the power transformation operation tickets is judged to be passed; otherwise, the automatic examination of the electric power operation state of the transformation operation ticket is judged not to pass.
In one embodiment, the examination module 702 is further configured to extract the power operation states corresponding to the second preset component names from the power transformation operation tickets and the power transformation operation tickets related to the power transformation operation tickets, respectively; when the extracted electric power operation states corresponding to the second preset component names are consistent, judging that the safety measures of the power transformation operation ticket are automatically checked; otherwise, judging that the safety measures performed on the substation operation ticket are automatically checked and failed.
Referring to fig. 8, in one embodiment, the substation operation ticket processing apparatus 700 further includes: a generating module 703, wherein:
the generating module 703 is configured to obtain substation operation task information; determining equipment to be transformed and names of parts to be operated corresponding to the equipment to be transformed according to the transformation operation task information; and generating a power transformation operation ticket in an electronic document format according to the equipment to be transformed and the name of the part to be operated corresponding to the equipment to be transformed and a preset power transformation operation ticket template.
According to the power transformation operation ticket processing device, the power transformation operation ticket in the electronic document format is obtained, and the safety standard automatic inspection is performed on the power transformation operation ticket according to the standard automatic inspection rule generated based on the power safety standard file, so that the power transformation operation ticket is ensured to meet the requirements of the power safety standard file. And automatically checking the attributes of the components associated with the substation operation tickets on the basis of the equipment component database so as to ensure that the attributes of the components associated with the substation operation tickets are correct. And automatically checking the electric power operation state of the transformation operation ticket according to the historical transformation operation ticket corresponding to the transformation operation ticket so as to ensure that the electric power operation state of the transformation operation ticket is accurate. And automatically checking the safety measures of the power transformation operation tickets according to the power transformation work tickets related to the power transformation operation tickets so as to ensure that the power transformation operation tickets meet the requirements of safety measure specifications. And when at least one item of the automatic examination fails, triggering examination and error reporting, and triggering the transformer operation ticket to be adjusted based on the examination and error reporting contents. And when all the automatic reviews pass, triggering the power transformation operation ticket to take effect. Therefore, the probability of unqualified transformer operation tickets is reduced by carrying out automatic safety standard examination, automatic component attribute examination, automatic electric power operation state examination and automatic safety measure examination on the transformer operation tickets, and the examination accuracy of the transformer operation tickets is improved.
For specific limitations of the substation operation ticket processing device, reference may be made to the above limitations on the substation operation ticket processing method, which are not described herein again. All or part of the modules in the substation operation ticket processing device can be realized by software, hardware and a combination thereof. The modules can be embedded in a hardware form or independent from a processor in the computer device, and can also be stored in a memory in the computer device in a software form, so that the processor can call and execute operations corresponding to the modules.
In one embodiment, a computer device is provided, which may be the terminal 102 in fig. 1, and its internal structure diagram may be as shown in fig. 9. The computer device includes a processor, a memory, a network interface, a display screen, and an input device connected by a system bus. Wherein the processor of the computer device is configured to provide computing and control capabilities. The memory of the computer device comprises a nonvolatile storage medium and an internal memory. The non-volatile storage medium stores an operating system and a computer program. The internal memory provides an environment for the operation of an operating system and computer programs in the non-volatile storage medium. The network interface of the computer device is used for communicating with an external terminal through a network connection. The computer program is executed by a processor to implement a substation operation ticket processing method. The display screen of the computer equipment can be a liquid crystal display screen or an electronic ink display screen, and the input device of the computer equipment can be a touch layer covered on the display screen, a key, a track ball or a touch pad arranged on the shell of the computer equipment, an external keyboard, a touch pad or a mouse and the like.
Those skilled in the art will appreciate that the architecture shown in fig. 9 is merely a block diagram of some of the structures associated with the disclosed aspects and is not intended to limit the computing devices to which the disclosed aspects apply, as particular computing devices may include more or less components than those shown, or may combine certain components, or have a different arrangement of components.
In one embodiment, a computer device is provided, which includes a memory and a processor, the memory stores a computer program, and the computer program, when executed by the processor, causes the processor to execute the steps of the above-mentioned substation operation ticket processing method. Here, the steps of the substation operation ticket processing method may be steps in the substation operation ticket processing method of each of the above embodiments.
In one embodiment, a computer-readable storage medium is provided, which stores a computer program, and when the computer program is executed by a processor, the computer program causes the processor to execute the steps of the above-mentioned substation operation ticket processing method. Here, the steps of the substation operation ticket processing method may be steps in the substation operation ticket processing method of each of the above embodiments.
It will be understood by those skilled in the art that all or part of the processes of the methods of the embodiments described above can be implemented by hardware instructions of a computer program, which can be stored in a non-volatile computer-readable storage medium, and when executed, can include the processes of the embodiments of the methods described above. Any reference to memory, storage, database, or other medium used in the embodiments provided herein may include non-volatile and/or volatile memory, among others. Non-volatile memory can include read-only memory (ROM), Programmable ROM (PROM), Electrically Programmable ROM (EPROM), Electrically Erasable Programmable ROM (EEPROM), or flash memory. Volatile memory can include Random Access Memory (RAM) or external cache memory. By way of illustration and not limitation, RAM is available in a variety of forms such as Static RAM (SRAM), Dynamic RAM (DRAM), Synchronous DRAM (SDRAM), Double Data Rate SDRAM (DDRSDRAM), Enhanced SDRAM (ESDRAM), Synchronous Link DRAM (SLDRAM), Rambus Direct RAM (RDRAM), direct bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM).
The technical features of the above embodiments can be arbitrarily combined, and for the sake of brevity, all possible combinations of the technical features in the above embodiments are not described, but should be considered as the scope of the present specification as long as there is no contradiction between the combinations of the technical features.
The above-mentioned embodiments only express several embodiments of the present application, and the description thereof is more specific and detailed, but not construed as limiting the scope of the invention. It should be noted that, for a person skilled in the art, several variations and modifications can be made without departing from the concept of the present application, which falls within the scope of protection of the present application. Therefore, the protection scope of the present patent shall be subject to the appended claims.

Claims (10)

1. A power transformation operation ticket processing method is characterized by comprising the following steps:
acquiring a transformation operation ticket in an electronic document format;
according to a standard automatic inspection rule generated based on the electric power safety standard file, carrying out automatic inspection of safety standards on the power transformation operation ticket;
automatically checking the attribute of the component associated with the transformer operation ticket based on an equipment component database;
According to the historical transformation operation ticket corresponding to the transformation operation ticket, automatically checking the electric power operation state of the transformation operation ticket;
according to the power transformation work ticket related to the power transformation operation ticket, automatically checking the safety measures of the power transformation operation ticket;
when at least one item of the automatic examination fails, triggering examination and error reporting, and triggering to adjust the power transformation operation ticket based on the content of the examination and error reporting;
and when all the automatic examination passes, triggering the power transformation operation ticket to take effect.
2. The method according to claim 1, wherein the performing automatic safety code review on the substation operation ticket according to a code automatic review rule generated based on a power safety code file comprises:
according to a standard automatic examination rule generated based on an electric power safety standard file, searching a first preset component name at a preset position of the power transformation operation ticket;
when the name of the first preset component is not found at the preset position of the power transformation operation ticket, judging that the automatic examination of the safety standard of the power transformation operation ticket does not pass;
when the first preset component name is found at the preset position of the power transformation operation ticket, judging whether the statement of the operation step corresponding to the first preset component name meets a preset grammar rule or not; if the safety standard is met, the safety standard of the power transformation operation ticket is judged to be automatically checked; otherwise, judging that the safety standard automatic examination of the power transformation operation ticket is not passed.
3. The method of claim 1, wherein automatically reviewing component attributes of components associated with the substation operation ticket based on an equipment component database comprises:
extracting attributes of components associated with the power transformation operation tickets from the power transformation operation tickets;
searching the extracted attributes of the components associated with the power transformation operation ticket in the equipment component database;
when the extracted attributes of the components associated with the substation operation tickets are found in the equipment component database, determining that the automatic examination of the component attributes of the components associated with the substation operation tickets is passed; otherwise, determining that the automatic component attribute examination of the attributes of the components associated with the substation operation ticket is not passed.
4. The method of claim 1, wherein the automatically reviewing the power transformation operation tickets for the power operation status according to the historical power transformation operation tickets corresponding to the power transformation operation tickets comprises:
respectively extracting the associated component names from the power transformation operation tickets and the historical power transformation operation tickets corresponding to the power transformation operation tickets;
judging whether the corresponding power operation states are opposite or not aiming at the extracted same component name;
When the power operation states are opposite, judging that the power operation states of the power transformation operation tickets are automatically checked to pass; otherwise, judging that the automatic examination of the electric power operation state of the transformation operation ticket is not passed.
5. The method of claim 1, wherein the automatically reviewing the substation operation tickets for safety measures based on the substation work tickets associated with the substation operation tickets comprises:
respectively extracting electric power operation states corresponding to second preset component names from the power transformation operation tickets and power transformation work tickets related to the power transformation operation tickets;
when the extracted electric power operation states corresponding to the second preset component names are consistent, judging that the safety measures performed on the power transformation operation tickets are automatically checked; otherwise, judging that the safety measures performed on the power transformation operation ticket are automatically checked and failed.
6. The method according to any one of claims 1 to 5, wherein before the obtaining of the transformation operation ticket in the electronic document format, the method further comprises:
acquiring power transformation operation task information;
determining equipment to be transformed and the names of components to be operated corresponding to the equipment to be transformed according to the transformation operation task information;
And generating a power transformation operation ticket in an electronic document format according to the equipment to be transformed and the part name to be operated corresponding to the equipment to be transformed and a preset power transformation operation ticket template.
7. A substation operation ticket processing apparatus, comprising:
the acquisition module is used for acquiring a power transformation operation ticket in an electronic document format;
the examination module is used for automatically examining the safety specifications of the power transformation operation ticket according to the automatic specification examination rule generated based on the power safety specification file; automatically checking the attribute of the component associated with the transformer operation ticket based on an equipment component database; according to the historical transformation operation ticket corresponding to the transformation operation ticket, automatically checking the electric power operation state of the transformation operation ticket; according to the power transformation work ticket related to the power transformation operation ticket, automatically checking the safety measures of the power transformation operation ticket; when at least one item of the automatic examination fails, triggering examination and error reporting, and triggering to adjust the power transformation operation ticket based on the content of the examination and error reporting; and when all the automatic examination passes, triggering the power transformation operation ticket to take effect.
8. The apparatus of claim 7, further comprising:
the generating module is used for acquiring the power transformation operation task information; determining equipment to be transformed and the names of components to be operated corresponding to the equipment to be transformed according to the transformation operation task information; and generating a power transformation operation ticket in an electronic document format according to the equipment to be transformed and the part name to be operated corresponding to the equipment to be transformed and a preset power transformation operation ticket template.
9. A computer device comprising a memory, a processor and a computer program stored on the memory and executable on the processor, characterized in that the steps of the method of any of claims 1 to 6 are implemented by the processor when executing the computer program.
10. A computer-readable storage medium, on which a computer program is stored, which, when being executed by a processor, carries out the steps of the method of any one of claims 1 to 6.
CN202010607780.1A 2020-06-30 2020-06-30 Substation operation ticket processing method and device, computer equipment and storage medium Pending CN111861787A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010607780.1A CN111861787A (en) 2020-06-30 2020-06-30 Substation operation ticket processing method and device, computer equipment and storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010607780.1A CN111861787A (en) 2020-06-30 2020-06-30 Substation operation ticket processing method and device, computer equipment and storage medium

Publications (1)

Publication Number Publication Date
CN111861787A true CN111861787A (en) 2020-10-30

Family

ID=72988701

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010607780.1A Pending CN111861787A (en) 2020-06-30 2020-06-30 Substation operation ticket processing method and device, computer equipment and storage medium

Country Status (1)

Country Link
CN (1) CN111861787A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113377746A (en) * 2021-07-02 2021-09-10 贵州电网有限责任公司 Test report database construction and intelligent diagnosis analysis system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104036348A (en) * 2014-05-30 2014-09-10 段君寨 Electronic mobile operation order system
CN106202541A (en) * 2016-07-26 2016-12-07 国网山东省电力公司东营供电公司 A kind of grid maintenance comprehensive inspection method of application ticket
CN107767122A (en) * 2017-11-09 2018-03-06 广东电网有限责任公司珠海供电局 A kind of electric operation ticket method of calibration
CN108879661A (en) * 2018-06-27 2018-11-23 中国南方电网有限责任公司 The method and apparatus of grid switching operation is checked by association history ticket
CN109633319A (en) * 2018-12-21 2019-04-16 国网福建省电力有限公司检修分公司 A kind of logic verify method for substation sequence control operation
CN109782724A (en) * 2019-02-25 2019-05-21 国家电网有限公司 The control method and terminal device of anti-misoperation locking

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104036348A (en) * 2014-05-30 2014-09-10 段君寨 Electronic mobile operation order system
CN106202541A (en) * 2016-07-26 2016-12-07 国网山东省电力公司东营供电公司 A kind of grid maintenance comprehensive inspection method of application ticket
CN107767122A (en) * 2017-11-09 2018-03-06 广东电网有限责任公司珠海供电局 A kind of electric operation ticket method of calibration
CN108879661A (en) * 2018-06-27 2018-11-23 中国南方电网有限责任公司 The method and apparatus of grid switching operation is checked by association history ticket
CN109633319A (en) * 2018-12-21 2019-04-16 国网福建省电力有限公司检修分公司 A kind of logic verify method for substation sequence control operation
CN109782724A (en) * 2019-02-25 2019-05-21 国家电网有限公司 The control method and terminal device of anti-misoperation locking

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113377746A (en) * 2021-07-02 2021-09-10 贵州电网有限责任公司 Test report database construction and intelligent diagnosis analysis system
CN113377746B (en) * 2021-07-02 2023-08-18 贵州电网有限责任公司 Test report database construction and intelligent diagnosis analysis system

Similar Documents

Publication Publication Date Title
US11327114B2 (en) Fully-automatic closed-loop detection method and device for intelligent substation
CN109684847B (en) Automatic repairing method, device, equipment and storage medium for script loopholes
CN111475370A (en) Operation and maintenance monitoring method, device and equipment based on data center and storage medium
CN109784502B (en) On-site maintenance processing method and system based on fault equipment
CN109948276B (en) Failure analysis method, device, equipment and storage medium
CN113963457B (en) Inspection task processing method and device, computer equipment and storage medium
CN111797026A (en) Test case generation method and device, computer equipment and storage medium
CN109325058B (en) Rule batch comparison method, device, computer equipment and storage medium
CN104579748A (en) SCD (substation configuration description) online checking network analysis method and system
CN110930075B (en) Power equipment fault positioning method, device, computer equipment and storage medium
CN108563708B (en) equipment information retrieval method and device and computer equipment
CN111259791A (en) Nuclear power station material acceptance method and device, computer equipment and storage medium
CN112506757A (en) Automatic test method, system, computer device and medium thereof
CN111861787A (en) Substation operation ticket processing method and device, computer equipment and storage medium
CN112163211B (en) Distribution network box management method and device, computer equipment and storage medium
CN112596651B (en) Acceptance method, device, equipment and storage medium for power distribution terminal debugging
CN112508404A (en) Automatic checking and accepting method, device and equipment for operation of power distribution network equipment and storage medium
CN111709484A (en) New energy station grid-connected acceptance method and device, computer equipment and storage medium
CN111026826A (en) Power grid map updating method and device, computer equipment and storage medium
CN112883728B (en) Nuclear power test-based test procedure information display method and device
CN112363848A (en) Mobile terminal remote control method and device, computer equipment and storage medium
CN112363929B (en) System online method and device, computer equipment and storage medium
CN114218188A (en) Data migration method, device, equipment and storage medium
CN112686010A (en) Resource data report generation method and device, computer equipment and storage medium
CN112463630A (en) Version difference testing method and device, computer equipment and storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination