CN111851462A - 软土地基处理方法 - Google Patents
软土地基处理方法 Download PDFInfo
- Publication number
- CN111851462A CN111851462A CN202010760126.4A CN202010760126A CN111851462A CN 111851462 A CN111851462 A CN 111851462A CN 202010760126 A CN202010760126 A CN 202010760126A CN 111851462 A CN111851462 A CN 111851462A
- Authority
- CN
- China
- Prior art keywords
- soft soil
- soil foundation
- sand
- cushion layer
- layer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
- E02D3/10—Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/005—Soil-conditioning by mixing with fibrous materials, filaments, open mesh or the like
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0053—Production methods using suction or vacuum techniques
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
本发明公开了一种软土地基处理方法,本方法包括如下步骤:在软土地基中喷砂;在泥面上铺设砂垫层;铺设排水通道,排水通道贯穿喷砂层将软土地基中含水排出;沿砂垫层周缘挖设压膜沟,并在砂垫层外铺设密封膜,密封膜的边角折入压膜沟内以保证与砂垫层之间呈密封态;在排水管外连真空泵,真空泵对软土地基内抽真空,预压地基至满足卸载标准。通过气压填充砂粒,提高软土地基的透水能力,再真空预压,加快真空预压时软土地基的排水效率,极大的缩短施工时间。
Description
技术领域
本发明属于软土地基处理领域,特别是涉及一种软土地基处理方法。
背景技术
软土地基主要以淤泥质粘土、淤泥质粉质粘土和淤泥为主,近几年来随着临港经济蓬勃发展,沿海吹填造成大量的软土地基,施工过程中采用真空预压处理技术,能够避免大规模堆载土方的运输,解决堆载料原材料,土源寻找困难,堆载料及运输成本高等问题。通过真空预压技术能够避免堆载完成后大方量的土方外运存在困难,外运堆放点难寻找,造成大量的机械及运输费用等问题。然而在软土地基中,主要以淤泥质粘土、淤泥质粉质粘土和淤泥为主,这些土的透水能力差,排水效率差,影响真空预压的施工效率,拖延软土地基的处理工期。
发明内容
本发明的目的在于针对现有技术的不足之处,提供一种提高排水效率、缩短施工时间的软土地基处理方法。
本发明提供的这种软土地基处理方法,包括如下步骤:
步骤一、在软土地基中气压喷砂;
步骤二、在软土地基上铺设砂垫层;
步骤三、铺设排水通道,排水通道贯穿喷砂层将软土地基中含水排出;
步骤四、沿砂垫层周缘挖设压膜沟,并在砂垫层外铺设密封膜,密封膜的边角折入压膜沟内以保证与砂垫层之间呈密封态;
步骤五、在排水管外连真空泵,真空泵对软土地基内抽真空,预压地基至满足卸载标准。
在所述步骤一中:
a、选定初喷点,通过钻机将喷嘴自初喷点钻至最大设计深度土层中旋转气压喷射砂粒,完成底层喷砂后停止喷砂;
b、上提设备0.3m-0.5m后喷嘴继续旋转喷射砂粒,完成该层喷砂;
c、重复b,直至将设备带出土层;
d、距初喷点30—50米外沿同一方向选定其它喷砂点,重复步骤a—c,完成软土地基的喷砂。
所述砂垫层包括依次铺设于泥面上的编织布层、荆芭垫层和土工布层,以及依次堆填于土工布层上的粉砂垫层与中粗砂垫层。
所述排水通道包括排水管和滤管,滤管埋于砂垫层内、端部与压膜沟连通,各排水管纵向布置、底端伸至原泥底层、顶端与滤管连通。
所述排水管之间的间距为30—50米。
所述密封膜的层数为2—5层。
所述步骤五中,在密封膜外连监测仪器,抽真空前通过监测仪器检测气密性,无漏气后再抽真空,并记录真空度。
本发明利用钻机把喷嘴钻到不同的设计深度的土层,再通过喷嘴喷出高压气体携带砂粒完成喷射,喷砂过程中,喷气切割软土,在软土内形成若干气孔,提高软土的排水性能也利于排水管网的布置;在泥面上铺设砂垫层,并在砂垫层上铺设排水通道;沿砂垫层周围挖设压膜沟,并铺设密封膜;安装监测仪器与真空泵,并通过真空泵对密封膜内抽气预压地基即可。通过气压填充砂粒,提高软土地基的透水能力,再真空预压,加快真空预压时软土地基的排水效率,极大的缩短施工时间。
附图说明
图1为本发明一个优选实施的流程框图。
图2为本优选实施例的施工状态示意图。
图示序号:
1—喷砂;
2—砂垫层,21—编织布层,22—荆芭垫层,23—土工布层,24—粉砂垫层,25—中粗砂垫层;
3—排水通道,31—排水管,32—滤管;
4—压膜沟;5—密封膜;6—监测仪器;7—真空泵。
具体实施方式
如图1、图2所示,本实施例公开的这种软土地基处理方法,按如下步骤进行:
步骤一、在软土地基中气压喷砂1。
喷砂时,先在软土地基中选定第一钻孔点,通过钻机将喷嘴自该钻孔点送至最大设计深度土层中,在该深度位置通过喷嘴喷出高压气体,高压气体携带砂粒实现,旋转喷砂,喷砂完成后上提喷嘴。喷砂过程中,高压气体切割软土,在软土中形成若干气孔,这些气孔一方面能够提高软土的透水效果,另一方面也便于布置排水网管。上提喷嘴0.3—0.5米后,喷嘴继续喷砂,重复该动作直至喷嘴带出土层。
然后以第一钻孔点为原点,沿同一方向隔30—50米间距选定若干钻孔点覆盖整个软土地基。按第一钻孔点处理方法,在各钻孔点处气压旋转喷砂。完成整个软土地基的喷砂。通过高压气体切割软土,以及喷射的砂粒协同作用,提高软土地基的透水能力。
步骤二、在泥面上铺设砂垫层2。
砂垫层自内向外依次有五层,分别为编织布层21、荆芭垫层22、土工布层23、粉砂垫层24与中粗砂垫层25。
铺设时,先在泥面上依次铺设编织布层、荆芭垫层和土工布层,然后在土工布层上堆填粉砂垫层与中粗砂垫层。
步骤三、铺设排水通道3。
排水通道3包括排水管31和滤管32,滤管埋于砂垫层内,各排水管自钻孔点处埋入,呈纵向布置、底端伸至原泥底层、顶端与滤管连通,相邻两排水管之间的间距在30—50米间,从而将软土地基中的水由排水通道排出。
步骤四、沿砂垫层周缘挖设压膜沟4,挖设压膜沟4时保证滤管的外端外露,以便通过压膜沟配合作用保证排水效果;并在砂垫层外铺设2—5层密封膜5,密封膜的边角折入压膜沟内以保证与砂垫层之间呈密封态。
步骤五、在密封膜外连监测仪器6,在滤管外连真空泵7。检测仪器可选用真空表。本步中先通过真空泵试抽真空,通过监测仪器检测气密性,无漏气后再正式抽真空,并记录真空度。满足卸载标准后,停止抽气,卸载,进行相应的效果检验。
本发明通过气压旋喷砂填充与真空预压联合处理软土地基,利用钻机把喷嘴钻到不同的设计深度的土层,再通过喷嘴喷出高压气体旋转喷射砂粒,喷砂过程中,高压气体切割软土,在软土中形成若干气孔,这些气孔一方面能够提高软土的透水效果,另一方面也便于布置排水网管。喷砂完成后;在泥面上铺设砂垫层,并在砂垫层上铺设排水通道;沿砂垫层周围挖设压膜沟,并铺设密封膜;安装监测仪器与真空泵,并通过真空泵对密封膜内抽气预压地基即可。通过气压填充砂粒,提高软土地基的透水能力,再真空预压,加快真空预压时软土地基的排水效率,极大的缩短施工时间。
Claims (7)
1.一种软土地基处理方法,其特征在于,本方法包括如下步骤:
步骤一、在软土地基中气压喷砂;
步骤二、在软土地基上铺设砂垫层;
步骤三、铺设排水通道,排水通道贯穿喷砂层将软土地基中含水排出;
步骤四、沿砂垫层周缘挖设压膜沟,并在砂垫层外铺设密封膜,密封膜的边角折入压膜沟内以保证与砂垫层之间呈密封态;
步骤五、在排水管外连真空泵,真空泵对软土地基内抽真空,预压地基至满足卸载标准。
2.如权利要求1所述的软土地基处理方法,其特征在于,在所述步骤一中:
a、选定初喷点,通过钻机将喷嘴自初喷点钻至最大设计深度土层中旋转气压喷射砂粒,完成底层喷砂后停止喷砂;
b、上提设备0.3m-0.5m后喷嘴继续旋转喷射砂粒,完成该层喷砂;
c、重复b,直至将设备带出土层;
d、距初喷点30—50米外沿同一方向选定其它喷砂点,重复步骤a—c,完成软土地基的喷砂。
3.如权利要求1所述的软土地基处理方法,其特征在于:所述砂垫层包括依次铺设于泥面上的编织布层、荆芭垫层和土工布层,以及依次堆填于土工布层上的粉砂垫层与中粗砂垫层。
4.如权利要求1所述的软土地基处理方法,其特征在于:所述排水通道包括排水管和滤管,滤管埋于砂垫层内、端部与压膜沟连通,各排水管纵向布置、底端伸至原泥底层、顶端与滤管连通。
5.如权利要求4所述的软土地基处理方法,其特征在于:所述排水管之间的间距为30—50米。
6.如权利要求1所述的软土地基处理方法,其特征在于:所述密封膜的层数为2—5层。
7.如权利要求1所述的软土地基处理方法,其特征在于:所述步骤五中,在密封膜外连监测仪器,抽真空前通过监测仪器检测气密性,无漏气后再抽真空,并记录真空度。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010760126.4A CN111851462A (zh) | 2020-07-31 | 2020-07-31 | 软土地基处理方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010760126.4A CN111851462A (zh) | 2020-07-31 | 2020-07-31 | 软土地基处理方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111851462A true CN111851462A (zh) | 2020-10-30 |
Family
ID=72953944
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010760126.4A Pending CN111851462A (zh) | 2020-07-31 | 2020-07-31 | 软土地基处理方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111851462A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113047263A (zh) * | 2021-04-06 | 2021-06-29 | 合肥工业大学 | 联合竖向排水体施工系统及其施工方法 |
CN113737773A (zh) * | 2021-09-26 | 2021-12-03 | 同济大学 | 一种淤泥质土疏干降水系统及施工方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS58185820A (ja) * | 1982-04-23 | 1983-10-29 | Fudo Constr Co Ltd | 軟弱地盤の改良工法 |
CN1664245A (zh) * | 2005-04-01 | 2005-09-07 | 东南大学 | 气压劈裂真空预压法加固软土地基操作方法 |
CN105672241A (zh) * | 2016-01-29 | 2016-06-15 | 太原理工大学 | 喷气破土联合气囊挤土处理深厚震陷性黄土的装置及方法 |
CN106939591A (zh) * | 2017-04-01 | 2017-07-11 | 温州浙南地质工程有限公司 | 强排式可控砂板复合构造及施工砂板的喷射设备和软基处理方法 |
CN108265697A (zh) * | 2016-12-30 | 2018-07-10 | 北京市第五建筑工程集团有限公司 | 真空预压地基处理方法 |
CN110847150A (zh) * | 2019-12-09 | 2020-02-28 | 冯清波 | 一种软土地基处理装置及方法 |
CN111305185A (zh) * | 2019-09-29 | 2020-06-19 | 中交天津港湾工程研究院有限公司 | 基于软土地基的联合排水装置及其加固方法 |
-
2020
- 2020-07-31 CN CN202010760126.4A patent/CN111851462A/zh active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS58185820A (ja) * | 1982-04-23 | 1983-10-29 | Fudo Constr Co Ltd | 軟弱地盤の改良工法 |
CN1664245A (zh) * | 2005-04-01 | 2005-09-07 | 东南大学 | 气压劈裂真空预压法加固软土地基操作方法 |
CN105672241A (zh) * | 2016-01-29 | 2016-06-15 | 太原理工大学 | 喷气破土联合气囊挤土处理深厚震陷性黄土的装置及方法 |
CN108265697A (zh) * | 2016-12-30 | 2018-07-10 | 北京市第五建筑工程集团有限公司 | 真空预压地基处理方法 |
CN106939591A (zh) * | 2017-04-01 | 2017-07-11 | 温州浙南地质工程有限公司 | 强排式可控砂板复合构造及施工砂板的喷射设备和软基处理方法 |
CN111305185A (zh) * | 2019-09-29 | 2020-06-19 | 中交天津港湾工程研究院有限公司 | 基于软土地基的联合排水装置及其加固方法 |
CN110847150A (zh) * | 2019-12-09 | 2020-02-28 | 冯清波 | 一种软土地基处理装置及方法 |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113047263A (zh) * | 2021-04-06 | 2021-06-29 | 合肥工业大学 | 联合竖向排水体施工系统及其施工方法 |
CN113737773A (zh) * | 2021-09-26 | 2021-12-03 | 同济大学 | 一种淤泥质土疏干降水系统及施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102220755B (zh) | 超压真空降水联合强夯地基处理方法 | |
CN111851462A (zh) | 软土地基处理方法 | |
CN102628273B (zh) | 利用疏浚土充灌筑堤的大型充灌袋筑堤方法及其设备 | |
CN101130952A (zh) | 一种无密封快速真空预压强夯法 | |
CN112411518A (zh) | 软基地段真空联合堆载预压施工方法 | |
CN102220757A (zh) | 超软弱土浅表层空间排水固结快速处理方法 | |
CN103374900B (zh) | 建设于淤泥质地基上的重力式码头及其施工方法 | |
CN111305185A (zh) | 基于软土地基的联合排水装置及其加固方法 | |
CN111206564A (zh) | 真空排水联合水载预压固结地基施工方法 | |
CN110984200B (zh) | 二元地质结构层的基坑降排水的方法 | |
CN104711968B (zh) | 一种负压立体导流扰动冲击固结吹填土方法 | |
CN106930304A (zh) | 流沙基坑降水施工方法 | |
CN112144503A (zh) | 一种真空预压处理系统及工艺 | |
CN105484229B (zh) | 适用于水域软基的上覆泥层密封真空预压方法 | |
CN104612128B (zh) | 适用于水下淤泥环境的真空预压加固施工方法 | |
CN107313421A (zh) | 一种吹填土快速固结装置及施工方法 | |
CN109139057B (zh) | 一种采煤巷道底板吸水底鼓治理方法 | |
CN213709481U (zh) | 一种真空预压处理系统 | |
CN109944263B (zh) | 双真空疏干降水系统及方法 | |
CN109610465B (zh) | 超大面积深基坑开挖施工方法 | |
CN113605361A (zh) | 一种高真空击密深厚淤土地基加固结构及其施工方法 | |
CN106869107A (zh) | 一种加固软土地基的新型立体排水系统及其降水施工方法 | |
CN112267452A (zh) | 一种利用土工合成材料修复过度开采矿山的方法 | |
CN111535293A (zh) | 一种低位降水真空联合堆载预压加固深厚软基方法及系统 | |
CN113605362B (zh) | 一种微劈裂多层面高真空分层预压击密施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20201030 |