CN111851261A - Self-resetting concrete filled steel tube pier structure provided with replaceable steel coupling beams and construction method of self-resetting concrete filled steel tube pier structure - Google Patents

Self-resetting concrete filled steel tube pier structure provided with replaceable steel coupling beams and construction method of self-resetting concrete filled steel tube pier structure Download PDF

Info

Publication number
CN111851261A
CN111851261A CN202010566660.1A CN202010566660A CN111851261A CN 111851261 A CN111851261 A CN 111851261A CN 202010566660 A CN202010566660 A CN 202010566660A CN 111851261 A CN111851261 A CN 111851261A
Authority
CN
China
Prior art keywords
steel tube
node
concrete
filled steel
pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010566660.1A
Other languages
Chinese (zh)
Inventor
程国忠
王宣鼎
刘界鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing University
Original Assignee
Chongqing University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing University filed Critical Chongqing University
Priority to CN202010566660.1A priority Critical patent/CN111851261A/en
Publication of CN111851261A publication Critical patent/CN111851261A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal

Abstract

The invention provides a self-resetting concrete filled steel tube pier structure with replaceable steel coupling beams and a construction method thereof. The pier structure comprises a foundation, a capping beam, a concrete filled steel tube pier and a replaceable steel coupling beam, wherein the upper end and the lower end of the concrete filled steel tube pier are respectively connected with the foundation and the capping beam through self-resetting type nodes, and the left end and the right end of the replaceable steel coupling beam are connected with the concrete filled steel tube pier through penetrating rod type nodes. The bridge structure can realize quick recovery of functions after an earthquake and quick repair of damage, and is convenient to construct, safe and reliable.

Description

Self-resetting concrete filled steel tube pier structure provided with replaceable steel coupling beams and construction method of self-resetting concrete filled steel tube pier structure
Technical Field
The invention relates to the technical field of building structures, in particular to a self-resetting concrete filled steel tube pier structure with replaceable steel coupling beams.
Background
The existing earthquake-proof design concept takes life protection as a primary target, and the structure is prevented from brittle failure and even collapsing under the action of an earthquake through ductile design. The pier designed according to ductility consumes energy through the plastic hinge generated at the bottom of the pier under the condition of heavy earthquake, the residual deformation after the earthquake is often overlarge, and a large amount of time and funds are needed for maintaining and reinforcing the damaged bridge. The bridge is used as an important component of the lifeline project, can not be repaired in time when seriously damaged, and can seriously affect the rescue work after the disaster. With the development and deepening of engineering earthquake-proof design research, the important development trend of the engineering earthquake-proof design research is gradually changed from the prevention of structural collapse to the realization of the quick recovery of the functions or the quick repair of damages of the structure after an earthquake.
The existing self-resetting bridge structure realizes the quick recovery of the functions of the bridge structure after the earthquake through the prestressed tendons, but the existing self-resetting bridge structure cannot effectively dissipate the earthquake energy. The existing bridge structure with the replaceable energy consumption piece has good energy consumption performance and can realize quick repair of damage after an earthquake, but the existing bridge structure lacks certain self-resetting capability and causes interruption of bridge functions.
Therefore, how to realize the rapid recovery of the function and the rapid repair of the damage of the bridge structure after the earthquake is an urgent technical problem to be solved by those skilled in the art.
Disclosure of Invention
The invention aims to provide a self-resetting concrete filled steel tube pier structure provided with replaceable steel coupling beams, and the self-resetting concrete filled steel tube pier structure is used for solving the problems in the prior art.
The technical scheme adopted for achieving the purpose of the invention is that the self-resetting concrete filled steel tube pier structure provided with the replaceable steel coupling beam comprises a foundation, a capping beam, two concrete filled steel tube piers and the replaceable steel coupling beam.
The concrete-filled steel tube bridge pier comprises a rectangular hollow steel tube and concrete poured into an inner cavity of the rectangular hollow steel tube. And the two concrete filled steel tube piers are arranged above the foundation and are used for supporting the bent cap. The lower extreme of steel pipe concrete pier links to each other with the basis through self-resetting formula node I. And the upper end of the concrete-filled steel tube pier is connected with the capping beam through a self-resetting node II.
From restoring to throne node I including pre-buried screw rod I, node connecting plate I and pre-compaction spring I. And a node connecting plate I is welded at the opening of the lower end of the rectangular hollow steel pipe. The embedded section of the embedded screw I is embedded into the foundation, and the extending section extends out of the upper surface of the foundation. The extending section penetrates through the node connecting plate I and then is screwed into the nut. The pre-pressing spring I is sleeved on the extending section of the pre-buried screw rod I. Pre-compaction spring I is located between node connecting plate I and the nut.
The self-resetting node II comprises a pre-buried screw rod II, a node connecting plate II and a pre-pressing spring II. And a joint connecting plate II is welded at an opening at the upper end of the rectangular hollow steel pipe. And the node connecting plate II plugs the opening at the upper end of the rectangular hollow steel pipe. The embedded section of the embedded screw rod II is embedded into the bent cap, and the extending section extends out of the lower surface of the bent cap. And the extending section penetrates through the node connecting plate II and then is screwed into the nut. And the pre-pressing spring II is sleeved on the extending section of the pre-buried screw rod II. And the pre-pressing spring II is positioned between the node connecting plate II and the nut.
The replaceable steel coupling beam is transversely arranged between the two concrete filled steel tube piers. And two ends of the replaceable steel coupling beam are connected with the concrete filled steel tube bridge pier through penetrating rod type nodes. The penetrating rod type node comprises a penetrating screw and a node end plate. The node end plates are arranged on two sides of the concrete filled steel tube bridge pier. And holes for the penetration screw to penetrate through are reserved on the concrete-filled steel tube pier. And after the penetrating screw rod penetrates through the concrete filled steel tube bridge pier and the node end plates on two sides, screw nuts are screwed in two ends of the penetrating screw rod. And two ends of the replaceable steel connecting beam are respectively welded with the node end plates.
Furthermore, a node stiffening rib I is welded between the rectangular hollow steel pipe and the node connecting plate I.
Furthermore, a node stiffening rib II is welded between the rectangular hollow steel pipe and the node connecting plate II.
Furthermore, the replaceable steel connecting beam is an I-shaped steel beam. The web plate surface of the I-shaped steel beam is welded with a web plate stiffening rib.
The present invention also discloses a construction method of the pier structure according to claim 1, comprising the steps of:
1) and pouring a foundation, and embedding the embedded screw I.
2) And prefabricating the concrete-filled steel tube bridge pier, the replaceable steel connecting beam and the capping beam in a factory. A node connecting plate I is welded at the lower end of the concrete filled steel tube pier, and a node connecting plate II is welded at the upper end of the concrete filled steel tube pier. And node end plates are welded at two ends of the replaceable steel connecting beam. And embedding a pre-buried screw rod II in the cover beam.
3) And hoisting the concrete-filled steel tube pier on site. And a pre-pressing spring is sleeved on the pre-buried screw rod I. And the screw nut is screwed in to realize the connection between the concrete-filled steel tube pier and the foundation.
4) And hoisting the replaceable steel coupling beam on site. A through screw is installed and a nut is screwed in. The connection between the replaceable steel coupling beam and the concrete filled steel tube bridge pier is realized.
5) And hoisting the bent cap on site. And a pre-pressing spring II is sleeved on the pre-embedded screw II. And screwing the screw cap to realize the connection between the concrete-filled steel tube pier and the capping beam.
The technical effects of the invention are undoubted:
A. under the working condition of normal use, the self-reset node can realize rigid connection by utilizing the pre-pressure of the pre-pressing spring; under the earthquake working condition, the self-reset node can realize semi-rigid connection by utilizing the compressible characteristic of the pre-pressing spring, so that the energy consumption capacity of the steel connecting beam can be fully utilized;
B. removable even roof beam performance bridge structures power consumption spare and the dual function of fuse, it links to each other with the steel pipe concrete pier through wearing rod formula node, can realize that bridge structures impairs quick replacement after shaking.
Drawings
FIG. 1 is a schematic view of a pier structure;
FIG. 2 is a schematic structural diagram of a self-resetting node I;
FIG. 3 is a sectional view taken along line a-a;
FIG. 4 is a schematic structural diagram of a self-resetting node II;
FIG. 5 is a schematic view of a bar penetrating node structure;
FIG. 6 is a sectional view taken along line b-b;
FIG. 7 is a cross-sectional view taken along line c-c.
In the figure: foundation 1, bent cap 2, steel pipe concrete pier 3, rectangular hollow steel pipe 301, concrete 302, removable steel even roof beam 4, from restoring to the throne formula node I5, pre-buried screw rod I501, node connecting plate I502, node stiffening rib I503, pre-compaction spring I504, from restoring to the throne formula node II 50, pre-buried screw rod II 510, node connecting plate II 520, node stiffening rib II 530, pre-compaction spring II 540, wear pole formula node 6, run through screw rod 601, node end plate 602.
Detailed Description
The present invention is further illustrated by the following examples, but it should not be construed that the scope of the above-described subject matter is limited to the following examples. Various substitutions and alterations can be made without departing from the technical idea of the invention and the scope of the invention is covered by the present invention according to the common technical knowledge and the conventional means in the field.
Example 1:
referring to fig. 1, the embodiment discloses a self-resetting steel pipe concrete pier structure provided with a replaceable steel coupling beam, which comprises a foundation 1, a capping beam 2, two steel pipe concrete piers 3 and a replaceable steel coupling beam 4.
The concrete filled steel tube pier 3 comprises a rectangular hollow steel tube 301 and concrete 302 poured in an inner cavity of the rectangular hollow steel tube. And the two concrete filled steel tube piers 3 are arranged above the foundation 1 and are used for supporting the bent cap 2. The lower end of the concrete filled steel tube pier 3 is connected with the foundation 1 through a self-resetting node I5. The upper end of the concrete filled steel tube pier 3 is connected with the capping beam 2 through a self-resetting node II 50.
Referring to fig. 2 and 3, the self-resetting node i 5 comprises a pre-buried screw rod i 501, a node connecting plate i 502 and a pre-pressing spring i 504. The open welding of the lower extreme of rectangle hollow steel pipe 301 has node connecting plate I502. The node connecting plate I52 seals the lower end opening of the rectangular hollow steel pipe 301. The embedded section of the embedded screw I501 is embedded into the foundation 1, and the extending section extends out of the upper surface of the foundation 1. The extending section penetrates through the node connecting plate I502 and then is screwed into a nut. The pre-pressing spring I504 is sleeved on the extending section of the embedded screw I501. The pre-compression spring I504 is located between the node connecting plate I502 and the nut. A node stiffening rib I503 is further welded between the rectangular hollow steel pipe 301 and the node connecting plate I502.
Referring to fig. 4, the self-resetting joint ii 50 includes a pre-embedded screw ii 510, a joint connection plate ii 520 and a pre-compression spring ii 540. And a joint connecting plate II 520 is welded at an opening at the upper end of the rectangular hollow steel pipe 301. And the node connecting plate II 520 seals the opening at the upper end of the rectangular hollow steel pipe 301. The embedded section of the embedded screw II 510 is embedded into the bent cap 2, and the extending section extends out of the lower surface of the bent cap 2. The extending section penetrates through the node connecting plate II 520 and then is screwed into the nut. And the pre-pressing spring II 540 is sleeved on the extending section of the pre-buried screw II 510. The pre-pressing spring II 540 is positioned between the node connecting plate II 520 and the nut. And a node stiffening rib II 530 is also welded between the rectangular hollow steel pipe 301 and the node connecting plate II 520.
Referring to fig. 5 to 7, the replaceable steel connecting beam 4 is an i-shaped steel beam. The web plate surface of the I-shaped steel beam is welded with a web stiffening rib 401. The replaceable steel coupling beam 4 is transversely arranged between the two concrete filled steel tube piers 3. And two ends of the replaceable steel coupling beam 4 are connected with the concrete filled steel tube pier 3 through the penetrating rod type node 6. The through-rod node 6 comprises a through-screw 601 and a node end plate 602. The node end plates 602 are disposed at both sides of the concrete filled steel tube pier 3. The concrete filled steel tube pier 3 is reserved with a hole for the through screw 601 to penetrate through. After the penetrating screw 601 penetrates through the concrete filled steel tube pier 3 and the node end plates 602 on the two sides, nuts are screwed into the two ends. And two ends of the replaceable steel coupling beam 4 are respectively welded with the node end plates 602.
The pier structure of this embodiment can realize that the function resumes fast and the harm restores fast after the shake. When the earthquake is in a working condition, the self-reset node I5 and the self-reset node II 50 enter a semi-rigid state, and the replaceable steel connecting beam 4 enters a plastic energy consumption stage. The self-reset node I5 and the self-reset node II 50 are always in a non-damage state and can be automatically reset after an earthquake. The replaceable steel coupling beam 4 concentrates damage caused by earthquakes and serves as a fuse of a pier structure.
Example 2:
the embodiment discloses a construction method of a pier structure related to embodiment 1, which includes the following steps:
1) and pouring the foundation 1, and embedding the embedded screw I501 according to the design requirement.
2) The concrete-filled steel tube bridge pier 3, the replaceable steel connecting beam 4 and the cover beam 2 are prefabricated in a factory. A node connecting plate I502 is welded at the lower end of the concrete filled steel tube pier 3, and a node connecting plate II 520 is welded at the upper end of the concrete filled steel tube pier 3. A node stiffening rib I503 is welded at a node connecting plate I502. And welding a node stiffening rib II 53 at the node connecting plate II 520. And node end plates 602 are welded at two ends of the replaceable steel coupling beam 4. Web stiffeners 401 are welded at the web of the replaceable steel link beam 4. And embedding a pre-buried screw II 510 in the cover beam 2.
3) And hoisting the concrete filled steel tube pier 3 on site. The pre-pressing spring 54 is sleeved on the pre-embedded screw I501. And screwing the screw cap to realize the connection between the concrete filled steel tube pier 3 and the foundation 1.
4) And hoisting the replaceable steel coupling beam 4 on site. A through screw 61 is installed and a nut is screwed in. The connection between the replaceable steel coupling beam 4 and the concrete filled steel tube bridge pier 3 is realized.
5) And hoisting the bent cap 2 on site. And a pre-pressing spring II 540 is sleeved on the pre-embedded screw II 510. And screwing the screw cap to realize the connection between the concrete filled steel tube pier 3 and the capping beam 2.

Claims (5)

1. The utility model provides a dispose removable steel coupling beam from restoring to throne concrete filled steel tube pier structure which characterized in that: the bridge comprises a foundation (1), a capping beam (2), two concrete-filled steel tube piers (3) and a replaceable steel connecting beam (4);
the concrete-filled steel tube pier (3) comprises a rectangular hollow steel tube (301) and concrete (302) poured into an inner cavity of the rectangular hollow steel tube. The two concrete filled steel tube piers (3) are arranged above the foundation (1) and are used for supporting the bent cap (2); the lower end of the concrete filled steel tube pier (3) is connected with the foundation (1) through a self-resetting node I (5); the upper end of the concrete filled steel tube pier (3) is connected with the capping beam (2) through a self-resetting node II (50);
the self-resetting node I (5) comprises a pre-buried screw I (501), a node connecting plate I (502) and a pre-pressing spring I (504); a node connecting plate I (502) is welded at an opening at the lower end of the rectangular hollow steel pipe (301); the embedded section of the embedded screw I (501) is embedded into the foundation (1), and the extending section extends out of the upper surface of the foundation (1); the extending section penetrates through the node connecting plate I (502) and then is screwed into the nut; the pre-pressing spring I (504) is sleeved on the extending section of the embedded screw I (501); the pre-pressing spring I (504) is positioned between the node connecting plate I (502) and the nut;
The self-reset node II (50) comprises a pre-buried screw II (510), a node connecting plate II (520) and a pre-pressing spring II (540); a node connecting plate II (520) is welded at an opening at the upper end of the rectangular hollow steel pipe (301); the node connecting plate II (520) plugs the upper end opening of the rectangular hollow steel pipe (301); the embedded section of the embedded screw II (510) is embedded into the bent cap (2), and the extending section extends out of the lower surface of the bent cap (2); the extending section penetrates through the node connecting plate II (520) and then is screwed into the nut; the pre-pressing spring II (540) is sleeved on the extending section of the pre-buried screw II (510); the pre-pressing spring II (540) is positioned between the node connecting plate II (520) and the nut;
the replaceable steel coupling beam (4) is transversely arranged between the two concrete filled steel tube piers (3); two ends of the replaceable steel coupling beam (4) are connected with the concrete filled steel tube pier (3) through a penetrating rod type node (6); the rod penetrating type node (6) comprises a penetrating screw rod (601) and a node end plate (602); the node end plates (602) are arranged on two sides of the concrete-filled steel tube pier (3); holes for the penetration screw rods (601) to penetrate through are reserved in the steel tube concrete pier (3); after the penetrating screw rod (601) penetrates through the concrete filled steel tube pier (3) and the node end plates (602) on the two sides, screw nuts are screwed into the two ends; and two ends of the replaceable steel connecting beam (4) are respectively welded with the node end plate (602).
2. The self-restoring concrete filled steel tube pier structure provided with the replaceable steel coupling beams as claimed in claim 1, wherein: a node stiffening rib I (503) is further welded between the rectangular hollow steel pipe (301) and the node connecting plate I (502).
3. The self-restoration concrete-filled steel tube pier structure provided with replaceable steel coupling beams according to claim 1 or 2, wherein: and a node stiffening rib II (530) is also welded between the rectangular hollow steel pipe (301) and the node connecting plate II (520).
4. The self-restoration concrete-filled steel tube pier structure provided with replaceable steel coupling beams according to claim 1 or 3, wherein: the replaceable steel connecting beam (4) is an I-shaped steel beam; and web stiffening ribs (401) are welded on the web plate surface of the I-shaped steel beam.
5. A construction method for the pier structure according to claim 1, comprising the steps of:
1) pouring a foundation (1), and embedding a pre-buried screw I (501);
2) prefabricating a concrete-filled steel tube pier (3), a replaceable steel connecting beam (4) and a cover beam (2) in a factory; welding a node connecting plate I (502) at the lower end of the concrete-filled steel tube pier (3), and welding a node connecting plate II (520) at the upper end of the concrete-filled steel tube pier (3); the two ends of the replaceable steel connecting beam (4) are welded with node end plates (602); embedding a pre-buried screw II (510) in the cover beam (2);
3) Hoisting the concrete-filled steel tube pier (3) on site; a pre-pressing spring (54) is sleeved on the embedded screw I (501); screwing in the screw cap to realize the connection between the concrete-filled steel tube pier (3) and the foundation (1);
4) hoisting the replaceable steel connecting beam (4) on site; a penetrating screw rod (61) is installed and a screw cap is screwed in; the connection between the replaceable steel coupling beam (4) and the concrete filled steel tube bridge pier (3) is realized;
5) hoisting the bent cap (2) on site; a pre-pressing spring II (540) is sleeved on the pre-buried screw II (510); and screwing the screw cap to realize the connection between the concrete filled steel tube pier (3) and the capping beam (2).
CN202010566660.1A 2020-06-19 2020-06-19 Self-resetting concrete filled steel tube pier structure provided with replaceable steel coupling beams and construction method of self-resetting concrete filled steel tube pier structure Pending CN111851261A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010566660.1A CN111851261A (en) 2020-06-19 2020-06-19 Self-resetting concrete filled steel tube pier structure provided with replaceable steel coupling beams and construction method of self-resetting concrete filled steel tube pier structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010566660.1A CN111851261A (en) 2020-06-19 2020-06-19 Self-resetting concrete filled steel tube pier structure provided with replaceable steel coupling beams and construction method of self-resetting concrete filled steel tube pier structure

Publications (1)

Publication Number Publication Date
CN111851261A true CN111851261A (en) 2020-10-30

Family

ID=72986929

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010566660.1A Pending CN111851261A (en) 2020-06-19 2020-06-19 Self-resetting concrete filled steel tube pier structure provided with replaceable steel coupling beams and construction method of self-resetting concrete filled steel tube pier structure

Country Status (1)

Country Link
CN (1) CN111851261A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113430922A (en) * 2021-08-07 2021-09-24 福州大学 Concrete-filled steel tube pier with corrugated sleeve and resettable double-column pier and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090080016A (en) * 2008-01-19 2009-07-23 주식회사 오케이컨설턴트 Device for bearing the earthquake by a mechanical damper and method of constructing it on the pier
CN105908621A (en) * 2016-06-29 2016-08-31 北京工业大学 Damage-controllable self-resetting section prefabricated assembled steel pipe concrete bridge pier and manufacturing method thereof
CN206538676U (en) * 2017-03-05 2017-10-03 防灾科技学院 A kind of utilization split column technology exempts from seismic Damage high-speed railway bridge pier
CN108035440A (en) * 2017-10-27 2018-05-15 西安建筑科技大学 A kind of assembled Self-resetting Column Joint with Wedge device
CN110067212A (en) * 2019-05-07 2019-07-30 防灾科技学院 Fast repairing method after a kind of shake of reinforced concrete bridge pier
CN110835975A (en) * 2019-11-25 2020-02-25 海南大学 Tough energy-consuming steel column and construction and installation method thereof

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090080016A (en) * 2008-01-19 2009-07-23 주식회사 오케이컨설턴트 Device for bearing the earthquake by a mechanical damper and method of constructing it on the pier
CN105908621A (en) * 2016-06-29 2016-08-31 北京工业大学 Damage-controllable self-resetting section prefabricated assembled steel pipe concrete bridge pier and manufacturing method thereof
CN206538676U (en) * 2017-03-05 2017-10-03 防灾科技学院 A kind of utilization split column technology exempts from seismic Damage high-speed railway bridge pier
CN108035440A (en) * 2017-10-27 2018-05-15 西安建筑科技大学 A kind of assembled Self-resetting Column Joint with Wedge device
CN110067212A (en) * 2019-05-07 2019-07-30 防灾科技学院 Fast repairing method after a kind of shake of reinforced concrete bridge pier
CN110835975A (en) * 2019-11-25 2020-02-25 海南大学 Tough energy-consuming steel column and construction and installation method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113430922A (en) * 2021-08-07 2021-09-24 福州大学 Concrete-filled steel tube pier with corrugated sleeve and resettable double-column pier and construction method thereof

Similar Documents

Publication Publication Date Title
CN104895249B (en) It is a kind of can in-situ immobilization combination suspension column
CN106400954A (en) Steel beam-steel pipe concrete column joint based on damage control concept
CN103696498B (en) Easily steel hetermorphiscal column-center support is repaired after a kind of shake
CN109057144B (en) Multifunctional replaceable coupling beam structure
CN103669650B (en) Easily steel shaped pile frame-steel plate shear force wall is repaired after a kind of shake
CN103669570B (en) A kind of novel shake easily repairs steel hetermorphiscal column-prestressing force center support afterwards
CN105888058B (en) One kind damages recoverable assembled combination suspension column
CN103711215B (en) Easily steel shaped pile frame-accentric support frame is repaired after a kind of shake
CN102304892A (en) External energy-consumption self-resetting bridge pier stud structure system and realization method thereof
CN107354863A (en) A kind of assembled gate-type round steel pipe bridge pier that power consumption binder is set
CN111021232A (en) Double-column type self-resetting concrete filled steel tube pier with replaceable energy-consuming corrugated steel connecting beam
CN108331258B (en) Assembled double-energy-consumption resettable circular steel tube concrete combined column and mounting method thereof
CN103669567B (en) Easily steel hetermorphiscal column-prestressing force accentric support frame is repaired after a kind of shake
CN103696503A (en) Novel post-earthquake easy-to-repair steel irregular column framework
CN111851261A (en) Self-resetting concrete filled steel tube pier structure provided with replaceable steel coupling beams and construction method of self-resetting concrete filled steel tube pier structure
CN216664470U (en) Self-resetting steel frame beam column joint of crawler steel energy dissipation damper
CN111021233A (en) Double-column type concrete-filled steel tube pier with replaceable energy-consuming corrugated steel connecting beam and construction method
CN113481833A (en) Prefabricated assembly type swing pier structure system with additional energy dissipation support or self-resetting energy dissipation support
CN211947909U (en) Double-column type self-resetting concrete filled steel tube pier with replaceable energy-consuming corrugated steel connecting beam
CN209854913U (en) Replaceable energy-consumption connecting node for assembled rectangular steel pipe column and H-shaped steel beam
CN217150662U (en) Replaceable mountain building lateral connection system with early warning system
CN211949048U (en) Section steel concrete shear wall structure
CN211735037U (en) Prevent roof beam expansion joint connecting device that falls
CN103790258A (en) Novel post-earthquake self-reset concrete framework-eccentric supporting structural system
CN110080432B (en) Novel self-resetting frame shear structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201030

RJ01 Rejection of invention patent application after publication