data
cost
project
construction
unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202010570529.2A
Other languages
Chinese (zh)
Inventor
张新姣
李永鹏
海明聪
任伟伟
詹海强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202010570529.2A priority Critical patent/CN111798204A/en
Publication of CN111798204A publication Critical patent/CN111798204A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q40/00Finance; Insurance; Tax strategies; Processing of corporate or income taxes
    • G06Q40/12Accounting
    • G06Q40/125Finance or payroll
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Human Resources & Organizations (AREA)
  • General Business, Economics & Management (AREA)
  • Accounting & Taxation (AREA)
  • Marketing (AREA)
  • Economics (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Finance (AREA)
  • General Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Tourism & Hospitality (AREA)
  • Technology Law (AREA)
  • Development Economics (AREA)
  • Data Mining & Analysis (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a design method of a construction engineering cost information management system, which comprises the following steps: s1, setting a data storage unit to store the project cost data table in the historical building project; s2, setting a cost information acquisition unit to acquire engineering data and account information of the construction engineering to obtain cost calculation data; s3, setting a construction cost calculation unit to perform classified calculation on the construction cost calculation data collected by the construction cost information collection unit, and obtaining a construction cost data table after summary statistics; s4, setting a data inspection unit to compare and inspect various data in the project cost data sheet with the project cost data sheet in the historical building project; and S5, setting a warning unit to perform system alarm on the project cost data sheet which is not qualified in the data inspection unit inspection, and reminding workers to perform manual inspection operation.

Description

Design method of building engineering cost information management system
Technical Field
The invention relates to the field of construction cost, in particular to a design method of a construction cost information management system.
Background
At present, under the background of an information era, the background of engineering cost management also changes greatly, along with the gradual perfection and scale expansion of the market of construction engineering, the engineering cost management industry is competitive day by day, and in order to manage the engineering cost information, people use an informatization technology to manufacture an engineering cost information management system, but the existing engineering cost information management system only has the function of recording data information and cannot check the accuracy of the cost data information, the data volume of the engineering cost information is overlarge, the error of each piece of calculation information influences the accuracy of the subsequent cost information, the possibility of calculation error is higher, and certain obstruction is caused to the information management work of the engineering cost.
Disclosure of Invention
The invention aims to provide a design method of a construction project cost information management system capable of checking the accuracy of cost information.
In order to achieve the purpose, the technical scheme of the invention is as follows:
a design method of a construction cost information management system comprises the following steps:
s1, setting a data storage unit to store the project cost data table in the historical building project;
s2, setting a cost information acquisition unit to acquire engineering data and account information of the construction engineering to obtain cost calculation data;
s3, setting a construction cost calculation unit to perform classified calculation on the construction cost calculation data collected by the construction cost information collection unit, and obtaining a construction cost data table after summary statistics;
s4, setting a data inspection unit to compare and inspect various data in the project cost data sheet with the project cost data sheet in the historical building project; when the comparison result does not exceed the preset threshold value of the data inspection unit, the data is inspected to be qualified, and the engineering cost data table which is inspected to be qualified is stored in the data storage unit; when the comparison result exceeds a preset threshold value of the data inspection unit, the data inspection unit is unqualified;
and S5, setting a warning unit to perform system alarm on the project cost data sheet which is not qualified in the data inspection unit inspection, and reminding workers to perform manual inspection operation.
Further, when the data storage unit stores the construction cost data table in the historical construction project in step S1, the construction area, the construction time, the construction area, and the construction material of the construction cost data table are marked.
Furthermore, a data classification module and a data extraction module are arranged in the cost information acquisition unit;
the data classification module is used for classifying the engineering data and the account information of the constructional engineering according to categories;
and the data extraction module is used for extracting bidding price data from the divided constructional engineering data and the account information, summarizing the price data and transmitting the summarized price data to the engineering cost calculation unit.
Furthermore, a data screening module, a data analysis module and a comparison module are arranged in the data inspection unit;
the data screening module is used for screening a project cost data table of the historical building project similar to the project construction area, the project construction time, the project construction area and the project construction material in the project cost data table from the data storage unit;
the data analysis module is used for extracting various data in the project cost data sheet and transmitting the data to the comparison module;
the comparison module is used for comparing various data in the existing project cost data table with various data in the screened project cost data table and judging whether the difference value of various data exceeds a preset threshold value or not; when the difference value of each item of data does not exceed a preset threshold value, storing the existing project cost data table into a data storage unit; and when the difference value of each item of data exceeds a preset threshold value, controlling the warning unit to perform system warning operation.
Further, the preset threshold is arranged in the comparison module and can be adjusted according to requirements.
Compared with the prior art, the invention has the advantages and positive effects that:
according to the invention, through the design of comparing and checking various data in the project cost data table with the project cost data table in historical building projects by adopting the data checking unit, whether the difference value between the existing building project cost information and the similar building project cost information exceeds a preset threshold value can be compared, namely, the building projects with two similar project construction areas, project construction time, project construction area and project construction materials are compared, whether the difference value of the cost information is overlarge is judged, when the difference value is overlarge, the existing building project cost information is judged to have a calculation error possibly, a warning is given by the warning unit, and after receiving the warning of the warning unit, people can calculate and check the building project cost information manually, so that the accuracy of the building project cost information is ensured; the method is simple and quick to operate, and brings convenience to information management work of engineering cost.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
FIG. 1 is a logical framework diagram of the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived from the embodiments of the present invention by a person skilled in the art without any creative effort, should be included in the protection scope of the present invention.
As shown in fig. 1, the method for designing a construction cost information management system in the present embodiment includes the following steps:
s1, setting a data storage unit to store the project cost data table in the historical building project;
when the data are stored, the engineering construction area, the engineering construction time, the engineering construction area and the engineering construction material of the engineering cost data sheet are respectively marked so as to facilitate the screening operation of the data inspection unit;
s2, setting a cost information acquisition unit to acquire engineering data and account information of the construction engineering to obtain cost calculation data;
the cost information acquisition unit is internally provided with a data classification module and a data extraction module;
the data classification module is used for classifying the engineering data and the account information of the constructional engineering according to categories;
and the data extraction module is used for extracting bidding price data from the divided constructional engineering data and the account information, summarizing the price data and transmitting the summarized price data to the engineering cost calculation unit.
S3, setting a construction cost calculation unit to perform classified calculation on the construction cost calculation data collected by the construction cost information collection unit, and obtaining a construction cost data table after summary statistics;
s4, setting a data inspection unit to compare and inspect various data in the project cost data sheet with the project cost data sheet in the historical building project;
when the comparison result does not exceed the preset threshold value of the data inspection unit, the data is inspected to be qualified, and the engineering cost data table which is inspected to be qualified is stored in the data storage unit; when the comparison result exceeds a preset threshold value of the data inspection unit, the data inspection unit is unqualified;
a data screening module, a data analysis module and a comparison module are arranged in the data inspection unit;
the data screening module is used for screening a project cost data table of the historical building project similar to the project construction area, the project construction time, the project construction area and the project construction material in the project cost data table from the data storage unit;
the data analysis module is used for extracting various data in the project cost data sheet and transmitting the data to the comparison module;
the comparison module is used for comparing various data in the existing project cost data table with various data in the screened project cost data table and judging whether the difference value of various data exceeds a preset threshold value or not; when the difference value of each item of data does not exceed a preset threshold value, storing the existing project cost data table into a data storage unit; when the difference value of each item of data exceeds a preset threshold value, controlling a warning unit to perform system warning operation;
the preset threshold is arranged in the comparison module and can be adjusted according to requirements;
and S5, setting a warning unit to perform system alarm on the project cost data sheet which is not qualified in the data inspection unit inspection, and reminding workers to perform manual inspection operation.
According to the invention, through the design of comparing and checking various data in the project cost data table with the project cost data table in historical building projects by adopting the data checking unit, whether the difference value between the existing building project cost information and the similar building project cost information exceeds a preset threshold value can be compared, namely, the building projects with two similar project construction areas, project construction time, project construction area and project construction materials are compared, whether the difference value of the cost information is overlarge is judged, when the difference value is overlarge, the existing building project cost information is judged to have a calculation error possibly, a warning is given by the warning unit, and after receiving the warning of the warning unit, people can calculate and check the building project cost information manually, so that the accuracy of the building project cost information is ensured; the method is simple and quick to operate, and brings convenience to information management work of engineering cost.

Claims (5)

1. A design method of a construction cost information management system is characterized in that: the method comprises the following steps:
s1, setting a data storage unit to store the project cost data table in the historical building project;
s2, setting a cost information acquisition unit to acquire engineering data and account information of the construction engineering to obtain cost calculation data;
s3, setting a construction cost calculation unit to perform classified calculation on the construction cost calculation data collected by the construction cost information collection unit, and obtaining a construction cost data table after summary statistics;
s4, setting a data inspection unit to compare and inspect various data in the project cost data sheet with the project cost data sheet in the historical building project; when the comparison result does not exceed the preset threshold value of the data inspection unit, the data is inspected to be qualified, and the engineering cost data table which is inspected to be qualified is stored in the data storage unit; when the comparison result exceeds a preset threshold value of the data inspection unit, the data inspection unit is unqualified;
and S5, setting a warning unit to perform system alarm on the project cost data sheet which is not qualified in the data inspection unit inspection, and reminding workers to perform manual inspection operation.
2. The construction cost information management system design method according to claim 1, characterized in that: when the data storage unit stores the construction cost data table in the historical construction project in step S1, the data storage unit marks the construction area, construction time, construction area, and construction material of the construction cost data table.
3. The construction cost information management system design method according to claim 2, characterized in that: the cost information acquisition unit is internally provided with a data classification module and a data extraction module;
the data classification module is used for classifying the engineering data and the account information of the constructional engineering according to categories;
and the data extraction module is used for extracting bidding price data from the divided constructional engineering data and the account information, summarizing the price data and transmitting the summarized price data to the engineering cost calculation unit.
4. The construction cost information management system design method according to claim 3, characterized in that: a data screening module, a data analysis module and a comparison module are arranged in the data inspection unit;
the data screening module is used for screening a project cost data table of the historical building project similar to the project construction area, the project construction time, the project construction area and the project construction material in the project cost data table from the data storage unit;
the data analysis module is used for extracting various data in the project cost data sheet and transmitting the data to the comparison module;
the comparison module is used for comparing various data in the existing project cost data table with various data in the screened project cost data table and judging whether the difference value of various data exceeds a preset threshold value or not; when the difference value of each item of data does not exceed a preset threshold value, storing the existing project cost data table into a data storage unit; and when the difference value of each item of data exceeds a preset threshold value, controlling the warning unit to perform system warning operation.
5. The construction cost information management system design method according to claim 4, characterized in that: the preset threshold is arranged in the comparison module and can be adjusted according to requirements.
CN202010570529.2A 2020-06-19 2020-06-19 Design method of building engineering cost information management system Withdrawn CN111798204A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010570529.2A CN111798204A (en) 2020-06-19 2020-06-19 Design method of building engineering cost information management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010570529.2A CN111798204A (en) 2020-06-19 2020-06-19 Design method of building engineering cost information management system

Publications (1)

Publication Number Publication Date
CN111798204A true CN111798204A (en) 2020-10-20

Family

ID=72803645

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010570529.2A Withdrawn CN111798204A (en) 2020-06-19 2020-06-19 Design method of building engineering cost information management system

Country Status (1)

Country Link
CN (1) CN111798204A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112699182A (en) * 2020-12-30 2021-04-23 广西信达友邦工程造价咨询有限责任公司 Engineering cost data management system
CN115841306A (en) * 2022-11-30 2023-03-24 中诚智信工程咨询集团股份有限公司 Method and system for checking quality of engineering cost result
CN116860737A (en) * 2023-07-22 2023-10-10 广东至衡工程管理有限公司 Engineering cost data storage method, device, equipment and storage medium

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112699182A (en) * 2020-12-30 2021-04-23 广西信达友邦工程造价咨询有限责任公司 Engineering cost data management system
CN115841306A (en) * 2022-11-30 2023-03-24 中诚智信工程咨询集团股份有限公司 Method and system for checking quality of engineering cost result
CN116860737A (en) * 2023-07-22 2023-10-10 广东至衡工程管理有限公司 Engineering cost data storage method, device, equipment and storage medium

Similar Documents

Publication Publication Date Title
CN111798204A (en) Design method of building engineering cost information management system
TWI706318B (en) Solder paste printing quality detecting method, data processing device and computer storage medium
US8248228B2 (en) Method and device for optimizing the alarm configuration
CN102540944B (en) Embedded multifunctional statistical process control (SPC) device and method
CN115689396B (en) Pollutant emission control method, device, equipment and medium
CN110990393A (en) Big data identification method for abnormal data behaviors of industry enterprises
CN111159272A (en) Data quality monitoring and early warning method and system based on data warehouse and ETL
CN111626626B (en) Project consultation report progress monitoring and evaluating system, method and device
CN111811567B (en) Equipment detection method based on curve inflection point comparison and related device
CN110648085A (en) Operation and maintenance method and system for comprehensive energy park
CN112180230A (en) Chip test parameter abnormity detection method, storage medium and terminal
US20200175847A1 (en) Method and system for determining probability of an alarm generated by an alarm system
CN114880405A (en) Data lake-based data processing method and system
CN113886830A (en) Information security scoring system construction method based on artificial intelligence
CN113836381A (en) System scoring coverage degree tuning method
CN111914315A (en) Material list statistical method and system based on CAD
CN104698004A (en) Intelligent appearance quality detector and operation method thereof
CN110659289B (en) Material quality detection test report management method and system
CN114372311B (en) BIM-based design detection method and device, electronic equipment and storage medium
CN117670256B (en) BIM technology-based engineering cost accurate control system and method
US20150277976A1 (en) System and method for data quality assessment in multi-stage multi-input batch processing scenario
US20170277583A1 (en) System and method for classifying defects occurring in a software environment
CN114021750A (en) Work order processing method and device and storage medium
CN117371992A (en) Reservoir operation and maintenance control system based on GIS
CN112486841A (en) Method and device for checking data collected by buried point

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20201020