CN111794075A - Ballastless track steel truss girder bridge - Google Patents

Ballastless track steel truss girder bridge Download PDF

Info

Publication number
CN111794075A
CN111794075A CN202010702424.8A CN202010702424A CN111794075A CN 111794075 A CN111794075 A CN 111794075A CN 202010702424 A CN202010702424 A CN 202010702424A CN 111794075 A CN111794075 A CN 111794075A
Authority
CN
China
Prior art keywords
bridge
truss girder
steel truss
track
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010702424.8A
Other languages
Chinese (zh)
Other versions
CN111794075B (en
Inventor
徐升桥
金令
任为东
杨永明
高静青
简方梁
焦亚萌
魏峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China State Railway Group Co Ltd
China Railway Engineering Consulting Group Co Ltd
Original Assignee
China State Railway Group Co Ltd
China Railway Engineering Consulting Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China State Railway Group Co Ltd, China Railway Engineering Consulting Group Co Ltd filed Critical China State Railway Group Co Ltd
Priority to CN202010702424.8A priority Critical patent/CN111794075B/en
Publication of CN111794075A publication Critical patent/CN111794075A/en
Application granted granted Critical
Publication of CN111794075B publication Critical patent/CN111794075B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D6/00Truss-type bridges
    • E01D6/02Truss-type bridges of bowstring type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B1/00Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
    • E01B1/002Ballastless track, e.g. concrete slab trackway, or with asphalt layers
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/30Adapting or protecting infrastructure or their operation in transportation, e.g. on roads, waterways or railways

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to the technical field of bridge construction, in particular to a ballastless track steel truss girder bridge. The ballastless track steel truss girder bridge comprises a bridge pier, a girder body and a stiffening chord. The rigidity of the steel truss girder bridge can be effectively improved by arranging the bridge deck slab of the highway bridge deck into the concrete slab of the highway bridge deck; the arrangement of the stiffening chord further improves the overall strength of the steel truss girder bridge, reduces the vertical vibration amplitude of the bridge when a train passes through the steel truss girder bridge, and simultaneously increases the span of the bridge; by organically combining the ballastless track and the steel truss girder bridge, the deformation of the track is dynamically controlled, so that the design speed of the high-speed railway on the bridge reaches 350km/h, the kilometer-level long-span steel bridge is not a restriction point of the operation speed of the high-speed railway, the running efficiency of the line is improved, and the difficulty of driving control is reduced. The invention is very suitable for crossing over the large rivers with high flood control standard and lower navigation requirement, such as yellow river.

Description

Ballastless track steel truss girder bridge
Technical Field
The invention relates to the technical field of bridge construction, in particular to a ballastless track steel truss girder bridge.
Background
Compared with a ballast track, the ballastless track has good stability, smoothness and durability, and the ballastless track structure has light dead weight and less maintenance workload. By introducing technology and digestion and absorption, the experiences of structural design, dynamic analysis, construction and operation management of ballastless track application are successfully mastered in China, and the ballastless track is generally applied to concrete bridges, but breakthrough progress is not always obtained in long-connection large-span steel structure bridges spanning large rivers. At present, large-scale steel structure bridge engineering at home and abroad adopts a ballast track structure. After the train operation speed reaches 300km/h, railway ballasts can be splashed, pulverization of a railway bed is accelerated, aging of vehicles is accelerated, maintenance workload is increased, and the design speed of a steel bridge with a ballast track is not more than 250km/h, so that the train operation speed in a high-speed railway interval is limited.
Disclosure of Invention
The invention aims to provide a ballastless track steel truss girder bridge to improve the problems. In order to achieve the purpose, the technical scheme adopted by the invention is as follows:
the embodiment of the application provides a ballastless track steel truss girder bridge, which comprises piers, a girder body and stiffening strings, wherein the girder body is arranged above the piers, the girder body comprises a highway bridge floor and a railway bridge floor, the highway bridge floor is arranged above the railway bridge floor, a bridge deck of the highway bridge floor is a highway bridge floor concrete slab, and ballastless tracks are laid above the railway bridge floor; the stiffening chord is arranged between the beam body and the bridge pier, and the bottoms of flanges on two sides of the stiffening chord are arc-shaped.
The ballastless track steel truss girder bridge can comprise a plurality of main hole spans with equal span in the middle, and the two ends of the main hole spans are provided with side hole spans smaller than the main hole spans to form a long-connection multi-span steel truss girder bridge. By adopting the structural form of the ballastless track steel truss girder bridge, the joint length and the total length can exceed the level of thousands of meters.
Optionally, the ballastless track is arranged on the railway bridge deck through a track mounting mechanism, and the track mounting mechanism comprises a reinforced concrete bridge deck, a reinforced concrete base and a track slab; the reinforced concrete bridge deck is characterized in that the reinforced concrete base is arranged at the top of the reinforced concrete bridge deck, the reinforced concrete base is fixedly connected with the reinforced concrete bridge deck, the track plate is arranged above the reinforced concrete base, a sleeper is arranged above the track plate, and a railway track is arranged above the sleeper.
Optionally, the reinforced concrete bridge deck is disposed above the lower truss girder of the girder, a shear nail is disposed in the reinforced concrete bridge deck, and the bottom of the shear nail is fixedly connected to the lower truss girder.
Optionally, a shock absorbing pad is arranged between the reinforced concrete base and the track plate.
Optionally, a groove is formed in the top of the reinforced concrete base, a protruding block corresponding to the groove is arranged at the bottom of the track slab, a first pattern formed by the cross section of the protruding block and a second pattern formed by the cross section of the groove are similar patterns, and the protruding block is arranged in the groove.
Optionally, the sleeper is a short sleeper, the track plate is further provided with a positioning element, the positioning element is buried in the track plate, and the positioning element is provided with a pair of sleepers.
Optionally, the two sides of the beam body are respectively provided with an edge girder, the middle part of the beam body is provided with a middle girder, and the height of the middle girder is higher than that of the edge girders; the side purlin includes first side purlin and second side purlin, the middle part of highway bridge face concrete slab with the top of well purlin links to each other, the both sides of highway bridge face concrete slab respectively with the top of first side purlin with the top of second side purlin links to each other.
Optionally, the top of the middle truss and the top of the side truss are both provided with a cluster type shear nail, the highway bridge deck concrete slab is provided with a concrete pouring hole matched with the cluster type shear nail, the cluster type shear nail is arranged in the concrete pouring hole, and concrete is poured in the concrete pouring hole.
Optionally, a cross-link is arranged above the railway deck, the cross-link comprises a first cross-link and a second cross-link, one end of the first cross-link is connected with the first side truss, the other end of the first cross-link is connected with the middle truss, one end of the second cross-link is connected with the middle truss, and the other end of the second cross-link is connected with the second side truss.
Optionally, a seismic isolation and reduction support is further arranged between the stiffening chord and the pier; the shock absorption and isolation support comprises an upper connecting plate, an upper support plate, a spherical crown, a lower support plate and a lower connecting plate; the upper part of the upper connecting plate is connected with the stiffening chord, the lower part of the upper connecting plate is connected with the upper support plate, the bottom of the lower connecting plate is connected with the pier, the top of the lower connecting plate is provided with a sliding groove, and the lower support plate is arranged in the sliding groove; the upper surface and the lower surface of spherical crown are the sphere, the lower terminal surface of upper bracket board be provided with the upper surface matched with sphere of spherical crown, the up end of bottom suspension bedplate be provided with the lower surface matched with sphere of spherical crown.
The invention has the beneficial effects that:
the rigidity of the steel truss girder bridge can be effectively improved by arranging the bridge deck slab of the highway bridge deck into the concrete slab of the highway bridge deck; the arrangement of the stiffening chord further improves the overall strength of the steel truss girder bridge, reduces the vertical vibration amplitude of the bridge when a train passes through the steel truss girder bridge, and simultaneously increases the span of the bridge; by organically combining the ballastless track and the steel truss girder bridge, the deformation of the track is dynamically controlled, so that the design speed of the high-speed railway on the bridge reaches 350km/h, the kilometer-level long-span steel bridge is not a restriction point of the operation speed of the high-speed railway, the running efficiency of the line is improved, and the difficulty of driving control is reduced. The invention is very suitable for crossing over the large rivers with high flood control standard and lower navigation requirement, such as yellow river.
Additional features and advantages of the invention will be set forth in the description which follows, and in part will be obvious from the description, or may be learned by the practice of the embodiments of the invention. The objectives and other advantages of the invention will be realized and attained by the structure particularly pointed out in the written description and claims hereof as well as the appended drawings.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings needed to be used in the embodiments will be briefly described below, it should be understood that the following drawings only illustrate some embodiments of the present invention and therefore should not be considered as limiting the scope, and for those skilled in the art, other related drawings can be obtained according to the drawings without inventive efforts.
Fig. 1 is a schematic structural view of a ballastless track steel truss girder bridge according to an embodiment of the invention;
FIG. 2 is a schematic sectional view of a seismic mitigation and isolation bearing structure according to an embodiment of the invention;
FIG. 3 is a schematic cross-sectional view of a beam structure according to an embodiment of the present invention;
fig. 4 is a schematic structural diagram of a rail mounting mechanism according to an embodiment of the present invention.
The labels in the figure are: 1. a bridge pier; 2. a beam body; 21. a highway deck; 22. a railway deck; 23. transverse connection; 24. an upper truss beam; 25. a lower truss beam; 26. a side rail; 27. a middle truss; 28. concrete slab of highway bridge deck; 29. a rail mounting mechanism; 291. shear nails; 292. a reinforced concrete deck slab; 293. a reinforced concrete base; 294. a shock pad; 295. a track plate; 296. a positioning member; 297. a sleeper; 3. a seismic isolation and reduction support; 301. an upper connecting plate; 302. an upper support plate; 303. a first wear plate; 304. a spherical cap; 305. a first dust ring; 306. a baffle plate; 307. a second wear plate; 308. a lower support plate; 309. a third wear plate; 310. a lower connecting plate; 311. a second dust ring; 312. a shear pin; 4. and (6) stiffening the chord.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all, embodiments of the present invention. The components of embodiments of the present invention generally described and illustrated in the figures herein may be arranged and designed in a wide variety of different configurations. Thus, the following detailed description of the embodiments of the present invention, presented in the figures, is not intended to limit the scope of the invention, as claimed, but is merely representative of selected embodiments of the invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
It should be noted that: like reference numbers and letters refer to like items in the following figures, and thus, once an item is defined in one figure, it need not be further defined and explained in subsequent figures. Meanwhile, in the description of the present invention, the terms "first", "second", and the like are used only for distinguishing the description, and are not to be construed as indicating or implying relative importance.
As shown in fig. 1 to 4, the present embodiment provides a ballastless track steel truss girder bridge, which includes piers 1, girder bodies 2 and stiffening strings 4, wherein the girder bodies 2 are arranged above the piers 1, the girder bodies 2 include highway bridge floors 21 and railway bridge floors 22, the highway bridge floors 21 are arranged above the railway bridge floors 22, bridge decks of the highway bridge floors 21 are highway bridge deck concrete slabs 28, and ballastless tracks are laid above the railway bridge floors 22; the stiffening chord 4 is arranged between the beam body 2 and the bridge pier 1, the bottom of the flange at two sides of the stiffening chord 4 is arc-shaped, and the vertical plate shape of the stiffening chord 4 is adjusted to enable the vertical surface of the bridge to be in an arch-shaped structure, so that the rigidity of the bridge is increased. The height of the stiffening chord 4 is the same as that of the beam body 2. The stiffening chord 4 and the beam body 2 form a whole, the thickness of the beam body 2 is increased, and the shearing force of the top of the beam body 2 right above the pier 1 can be effectively reduced when the height of the stiffening chord 4 is the same as that of the beam body 2, so that the rigidity of the bridge is improved. The ballastless track steel truss girder bridge can comprise a plurality of main hole spans with equal span in the middle, and the two ends of the main hole spans are provided with side hole spans smaller than the main hole spans to form a long-connection multi-span steel truss girder bridge. By adopting the structural form of the ballastless track steel truss girder bridge, the joint length and the total length can exceed the level of thousands of meters.
Optionally, the ballastless track is disposed on the railway deck 22 through a track mounting mechanism 29, where the track mounting mechanism 29 includes a reinforced concrete deck 292, a reinforced concrete base 293, and a track plate 295; the reinforced concrete base 293 is arranged at the top of the reinforced concrete bridge deck 292, the reinforced concrete base 293 is fixedly connected with the reinforced concrete bridge deck 292, the track plate 295 is arranged above the reinforced concrete base 293, a sleeper 297 is arranged above the track plate 295, and a railway track is arranged above the sleeper 297.
Optionally, the reinforced concrete bridge deck 292 is disposed above the lower truss girder 25 of the girder 2, a shear pin 291 is disposed in the reinforced concrete bridge deck 292, and a bottom of the shear pin 291 is fixedly connected to the lower truss girder 25.
Optionally, a shock absorbing pad 294 is disposed between the reinforced concrete base 293 and the track plate 295. The shock absorbing pad 294 may be an ethylene propylene diene monomer strip.
Optionally, a groove is formed in the top of the reinforced concrete base 293, a protrusion corresponding to the groove is formed at the bottom of the track plate 295, a first pattern formed by a cross section of the protrusion and a second pattern formed by a cross section of the groove are similar patterns, and the protrusion is disposed in the groove. The arrangement of the grooves and the projections can effectively limit the positions of the reinforced concrete base 293 and the track plate 295, so that the reinforced concrete base 293 and the track plate 295 cannot be displaced laterally.
Optionally, the sleepers 297 are short sleepers, the track plate 295 is further provided with a positioning member 296, the positioning member 296 is embedded in the track plate 295, and the positioning member 296 is provided with a pair of sleepers 297.
Optionally, the two sides of the beam body 2 are respectively provided with an edge girder 26, the middle part of the beam body 2 is provided with a middle girder 27, and the height of the middle girder 27 is higher than that of the edge girder 26; the side girders 26 comprise first side girders and second side girders, the middle parts of the highway bridge deck concrete slabs 28 are connected with the top parts of the middle girders 27, and the two sides of the highway bridge deck concrete slabs 28 are respectively connected with the top parts of the first side girders and the second side girders. The height of middle purlin 27 is higher than the height of side purlin 26, can make the height that highly is less than the middle part of the both sides of highway bridge face concrete slab 28, makes highway bridge face concrete slab 28 form certain slope, makes things convenient for highway bridge face concrete slab 28 drainage.
Optionally, the top of the middle truss 27 and the top of the side truss 26 are both provided with cluster shear nails, the highway bridge deck concrete slab 28 is provided with concrete pouring holes matched with the cluster shear nails, the cluster shear nails are arranged in the concrete pouring holes, and concrete is poured in the concrete pouring holes.
Optionally, a cross-link 23 is arranged above the railway deck 22, the cross-link 23 includes a first cross-link and a second cross-link, one end of the first cross-link is connected to the first side girder, the other end of the first cross-link is connected to the middle girder 27, one end of the second cross-link is connected to the middle girder 27, and the other end of the second cross-link is connected to the second side girder. Above the cross beam 23 is an upper truss beam 24.
Optionally, an earthquake reduction and isolation support 3 is further arranged between the stiffening chord 4 and the pier 1; the seismic isolation and reduction support 3 comprises an upper connecting plate 301, an upper support plate 302, a spherical crown 304, a lower support plate 308 and a lower connecting plate 310; the upper part of the upper connecting plate 301 is connected with the stiffening chord 4, the lower part of the upper connecting plate 301 is connected with the upper support plate 302, the bottom of the lower connecting plate 310 is connected with the pier 1, the top of the lower connecting plate 310 is provided with a sliding groove, and the lower support plate 308 is arranged in the sliding groove; the upper surface and the lower surface of the spherical crown 304 are both spherical surfaces, the lower end surface of the upper support plate 302 is provided with a spherical surface matched with the upper surface of the spherical crown 304, and the upper end surface of the lower support plate 308 is provided with a spherical surface matched with the lower surface of the spherical crown 304.
Optionally, a first dust ring 305 is arranged above the lower support plate 308, the first dust ring 305 is arranged around the outer side of the spherical crown 304, the upper end of the first dust ring 305 is connected with the upper side of the side wall of the spherical crown 304, and the lower end of the first dust ring 305 is connected with the upper end face of the lower support plate 308.
Optionally, the sliding groove is circular, the lower support plate 308 is circular, and the diameter of the lower support plate 308 is smaller than that of the sliding groove.
Optionally, a first wear plate 303 is disposed above the spherical crown 304, the first wear plate 303 is arc-shaped, and the arc degree of the first wear plate 303 is equal to the arc degree of the upper surface of the spherical crown 304; a second wear-resisting plate 307 is arranged below the spherical crown 304, the second wear-resisting plate 307 is arc-shaped, and the radian of the second wear-resisting plate 307 is equal to that of the lower surface of the spherical crown 304; the lower end of the lower seat plate 308 is provided with a third wear plate 309. The first wear plate 303, the second wear plate 307 and the third wear plate 309 are all non-metallic wear plates.
Optionally, a baffle 306 is disposed around the outer side of the lower support plate 308, the baffle 306 is fixedly disposed on the lower section of the upper support plate 302, and a shear pin 312 is disposed in the baffle 306; a second dust ring 311 is arranged between the upper support plate 302 and the lower connecting plate 310 in a surrounding manner, the upper end of the second dust ring 311 is connected with the outer side wall of the upper support plate 302, and the lower end of the second dust ring is connected with the outer side wall of the lower connecting plate 310. Through first dust ring 305 and second dust ring 311, can constitute twice dustproof construction, can effectively improve dustproof effect.
The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
The above description is only for the specific embodiments of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art can easily conceive of the changes or substitutions within the technical scope of the present invention, and all the changes or substitutions should be covered within the scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.

Claims (10)

1. The utility model provides a ballastless track steel truss girder bridge which characterized in that includes:
a bridge pier (1);
the bridge body (2) is arranged above the pier (1), the bridge body (2) comprises a highway bridge floor (21) and a railway bridge floor (22), the highway bridge floor (21) is arranged above the railway bridge floor (22), a bridge deck of the highway bridge floor (21) is a highway bridge floor concrete slab (28), and ballastless tracks are laid above the railway bridge floor (22); and
and the stiffening chord (4) is arranged between the beam body (2) and the bridge piers (1), and the bottoms of flanges on two sides of the stiffening chord (4) are arc-shaped.
2. The ballastless track steel truss girder bridge of claim 1, wherein: the ballastless track is arranged on the railway bridge deck (22) through a track mounting mechanism (29), and the track mounting mechanism (29) comprises a reinforced concrete bridge deck (292), a reinforced concrete base (293) and a track plate (295); the reinforced concrete bridge deck is characterized in that the reinforced concrete base (293) is arranged at the top of the reinforced concrete bridge deck (292), the reinforced concrete base (293) is fixedly connected with the reinforced concrete bridge deck (292), the track plate (295) is arranged above the reinforced concrete base (293), a sleeper (297) is arranged above the track plate (295), and a railway track is arranged above the sleeper (297).
3. The ballastless track steel truss girder bridge of claim 2, wherein: the reinforced concrete bridge deck (292) is arranged above the lower truss girder (25) of the girder body (2), a shear nail (291) is arranged in the reinforced concrete bridge deck (292), and the bottom of the shear nail (291) is fixedly connected with the lower truss girder (25).
4. The ballastless track steel truss girder bridge of claim 2, wherein: and a damping pad (294) is arranged between the reinforced concrete base (293) and the track plate (295).
5. The ballastless track steel truss girder bridge of claim 2, wherein: the reinforced concrete base (293) is provided with a groove at the top, the bottom of the track plate (295) is provided with a convex block corresponding to the groove, a first pattern formed by the cross section of the convex block and a second pattern formed by the cross section of the groove are similar patterns, and the convex block is arranged in the groove.
6. The ballastless track steel truss girder bridge of claim 2, wherein: the sleeper (297) is a short sleeper, the track plate (295) is further provided with a positioning piece (296), the positioning piece (296) is embedded in the track plate (295), and the positioning piece (296) is provided with a pair of sleepers (297).
7. The ballastless track steel truss girder bridge of claim 1, wherein: the two sides of the beam body (2) are respectively provided with an edge truss (26), the middle part of the beam body (2) is provided with a middle truss (27), and the height of the middle truss (27) is higher than that of the edge truss (26); the side girders (26) comprise first side girders and second side girders, the middle parts of the highway bridge deck concrete slabs (28) are connected with the top parts of the middle girders (27), and the two sides of the highway bridge deck concrete slabs (28) are respectively connected with the top parts of the first side girders and the second side girders.
8. The ballastless track steel truss girder bridge of claim 7, wherein: well purlin (27) with the top of limit purlin (26) all is provided with the cluster formula shear force nail, highway bridge face concrete slab (28) be provided with cluster formula shear force nail matched with concrete pouring hole, the cluster formula shear force nail sets up in the concrete pouring hole, pour into the concrete in the concrete pouring hole.
9. The ballastless track steel truss girder bridge of claim 7, wherein: the top of railway deck (22) is provided with horizontal antithetical couplet (23), horizontal antithetical couplet (23) are including first horizontal antithetical couplet and second horizontal antithetical couplet, the one end of first horizontal antithetical couplet with first limit purlin links to each other, the other end with well purlin (27) link to each other, the one end of second horizontal antithetical couplet with well purlin (27) link to each other, the other end with second limit purlin links to each other.
10. The ballastless track steel truss girder bridge of claim 1, wherein: a seismic isolation and reduction support (3) is arranged between the stiffening chord (4) and the pier (1); the seismic isolation and reduction support (3) comprises an upper connecting plate (301), an upper support plate (302), a spherical crown (304), a lower support plate (308) and a lower connecting plate (310); the upper part of the upper connecting plate (301) is connected with the stiffening chord (4), the lower part of the upper connecting plate (301) is connected with the upper support plate (302), the bottom of the lower connecting plate (310) is connected with the pier (1), the top of the lower connecting plate (310) is provided with a sliding groove, and the lower support plate (308) is arranged in the sliding groove; the upper surface and the lower surface of spherical crown (304) are the sphere, the lower terminal surface of upper bracket board (302) be provided with the upper surface matched with sphere of spherical crown (304), the up end of lower support board (308) be provided with the lower surface matched with sphere of spherical crown (304).
CN202010702424.8A 2020-07-21 2020-07-21 Ballastless track steel truss girder bridge Active CN111794075B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010702424.8A CN111794075B (en) 2020-07-21 2020-07-21 Ballastless track steel truss girder bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010702424.8A CN111794075B (en) 2020-07-21 2020-07-21 Ballastless track steel truss girder bridge

Publications (2)

Publication Number Publication Date
CN111794075A true CN111794075A (en) 2020-10-20
CN111794075B CN111794075B (en) 2022-08-30

Family

ID=72808004

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010702424.8A Active CN111794075B (en) 2020-07-21 2020-07-21 Ballastless track steel truss girder bridge

Country Status (1)

Country Link
CN (1) CN111794075B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007032165A (en) * 2005-07-28 2007-02-08 Railway Technical Res Inst Noise reduction structure of viaduct
CN101603288A (en) * 2009-07-03 2009-12-16 中铁大桥局股份有限公司 A kind of three-truss main girder structure of highway and railway bi-purpose cable-stayed bridge and mounting method thereof
CN102182120A (en) * 2011-03-31 2011-09-14 中铁第四勘察设计院集团有限公司 Precast slab type ballastless track structure
CN203229864U (en) * 2013-04-27 2013-10-09 中铁二院工程集团有限责任公司 Large-span six-line double-layer railway bridge steel truss girder structure
CN203603019U (en) * 2013-11-25 2014-05-21 中铁第四勘察设计院集团有限公司 Highway and railway layering steel box beam
CN105178174A (en) * 2015-08-11 2015-12-23 洛阳双瑞特种装备有限公司 Seismic isolation and reduction support with displacement locking device
CN106522095A (en) * 2016-08-27 2017-03-22 江苏中铁山桥重工有限公司 Truss section intra-site multi-directional transferring method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007032165A (en) * 2005-07-28 2007-02-08 Railway Technical Res Inst Noise reduction structure of viaduct
CN101603288A (en) * 2009-07-03 2009-12-16 中铁大桥局股份有限公司 A kind of three-truss main girder structure of highway and railway bi-purpose cable-stayed bridge and mounting method thereof
CN102182120A (en) * 2011-03-31 2011-09-14 中铁第四勘察设计院集团有限公司 Precast slab type ballastless track structure
CN203229864U (en) * 2013-04-27 2013-10-09 中铁二院工程集团有限责任公司 Large-span six-line double-layer railway bridge steel truss girder structure
CN203603019U (en) * 2013-11-25 2014-05-21 中铁第四勘察设计院集团有限公司 Highway and railway layering steel box beam
CN105178174A (en) * 2015-08-11 2015-12-23 洛阳双瑞特种装备有限公司 Seismic isolation and reduction support with displacement locking device
CN106522095A (en) * 2016-08-27 2017-03-22 江苏中铁山桥重工有限公司 Truss section intra-site multi-directional transferring method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
孟维军等: "《高速铁路桥梁工程施工技术》", 31 August 2014, 中国铁道出版社 *
秦顺全等: "武汉天兴洲公铁两用长江大桥关键技术研究", 《工程力学》 *
项海帆等: "《中国桥梁史纲》", 30 September 2009, 同济大学出版社 *

Also Published As

Publication number Publication date
CN111794075B (en) 2022-08-30

Similar Documents

Publication Publication Date Title
CN201581344U (en) Double track railway steel truss cable-stayed bridge
CN207891661U (en) A kind of medium-and low-speed maglev traffic track beam and rail system
CN110016854B (en) Low tower draws stiffening combination arched bridge structure to one side
CN106567320B (en) The local gravity rigidity and auxiliary suspension cable structure system of large span stayed-cable bridge
CN101200871A (en) Bottom bearing trough girder for rail traffic station
CN109930469B (en) Steel box girder thin-wall pier rigid frame cable-stayed bridge suitable for straddle type monorail
CN111794075B (en) Ballastless track steel truss girder bridge
CN101200872B (en) Bottom bearing box beam for rail traffic station
CN108342980B (en) Railway suspension bridge upper bearing type steel truss bridge deck structure
CN211285229U (en) Full-prefabricated assembled track structure on steel truss girder
CN113174831B (en) Steel truss combined main beam structure of cable-stayed bridge of ballastless track of high-speed railway
CN213507844U (en) Novel vibration reduction track structure for elevated section sleeve track
CN202577061U (en) Prefabricated floating slab
CN205804149U (en) Bridge rigid pulling force is put
CN205012221U (en) Embedded track structure that is fit for medium and small span bridge
CN210482016U (en) Device for controlling deformation of railway bridge beam end
CN209066192U (en) Elastic long sleeper buried-type ballastless track structure on a kind of Railway Steel Truss Girder Bridges
CN210826952U (en) Wide flange beam upper plate type track beam
CN209975275U (en) Elastic support line structure for high-speed magnetic levitation track traffic
CN202945544U (en) Novel ballastless track
CN218932833U (en) Prestressed concrete simply supported box girder
CN111424477A (en) double-H-shaped concrete track beam of rubber-tyred tramcar and construction method thereof
CN207091832U (en) A kind of anchor formula non-fragment orbit
CN215104289U (en) Long sleeper buried ballastless track for upper casing line of railway steel truss girder
CN215104676U (en) Prefabricated bridge deck and long sleeper buried ballastless track

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant