CN111737875B - Active power unbalance rate analysis and diagnosis method, system and computer equipment - Google Patents

Active power unbalance rate analysis and diagnosis method, system and computer equipment Download PDF

Info

Publication number
CN111737875B
CN111737875B CN202010602847.2A CN202010602847A CN111737875B CN 111737875 B CN111737875 B CN 111737875B CN 202010602847 A CN202010602847 A CN 202010602847A CN 111737875 B CN111737875 B CN 111737875B
Authority
CN
China
Prior art keywords
active power
transformer
voltage
information
measurement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010602847.2A
Other languages
Chinese (zh)
Other versions
CN111737875A (en
Inventor
林波
王大兴
石涛
刘学文
李�荣
赵珍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electric Power Research Institute of State Grid Sichuan Electric Power Co Ltd
Original Assignee
Electric Power Research Institute of State Grid Sichuan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Research Institute of State Grid Sichuan Electric Power Co Ltd filed Critical Electric Power Research Institute of State Grid Sichuan Electric Power Co Ltd
Priority to CN202010602847.2A priority Critical patent/CN111737875B/en
Publication of CN111737875A publication Critical patent/CN111737875A/en
Application granted granted Critical
Publication of CN111737875B publication Critical patent/CN111737875B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for AC mains or AC distribution networks
    • H02J3/04Circuit arrangements for AC mains or AC distribution networks for connecting networks of the same frequency but supplied from different sources
    • H02J3/06Controlling transfer of power between connected networks; Controlling sharing of load between connected networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for AC mains or AC distribution networks
    • H02J3/26Arrangements for eliminating or reducing asymmetry in polyphase networks
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2113/00Details relating to the application field
    • G06F2113/04Power grid distribution networks
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2119/00Details relating to the type or aim of the analysis or the optimisation
    • G06F2119/06Power analysis or power optimisation
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/10Power transmission or distribution systems management focussing at grid-level, e.g. load flow analysis, node profile computation, meshed network optimisation, active network management or spinning reserve management
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/50Arrangements for eliminating or reducing asymmetry in polyphase networks

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Power Engineering (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The application discloses an active power unbalance analysis and diagnosis method, a system and computer equipment, wherein the method comprises the following steps: s10: establishing a primary equipment element model, and configuring element model parameters according to voltage levels; s20: importing and identifying measurement and control device information in the SCD file; s30: matching the measurement and control device information with a primary equipment element model to generate a primary main wiring system; s40: sampling data information of the measurement and control device is extracted, and a corresponding primary equipment element model in a primary main wiring system is displayed to form active power flow information; s50: calculating the total active power unbalance rate of the total station; s60: dividing voltage class areas to calculate active power unbalance rate; s70: and (5) carrying out regional diagnosis analysis on the grade voltage. According to the application, through carrying out voltage class area calculation and analysis and diagnosis on the active power, the analysis and diagnosis range is reduced, the active power unbalance reason is rapidly found out, and the intelligent transformer station is prevented from operating in an unbalance alarm state for a long time.

Description

有功功率不平衡率分析诊断方法、系统及计算机设备Active power imbalance rate analysis and diagnosis method, system and computer equipment

技术领域Technical field

本发明涉及电力系统保护调试技术领域,具体涉及一种有功功率不平衡率分析诊断方法、系统及计算机设备。The invention relates to the technical field of power system protection and debugging, and in particular to an active power imbalance rate analysis and diagnosis method, system and computer equipment.

背景技术Background technique

伴随智能电网的快速发展,智能变电站的建设规模不断扩大,然而近几年智能变电站经常出现变电站有功功率不平衡率长期偏大的现象,变电站被调度考核的同时对电网安全稳定运行造成极大的威胁,而智能变电站有功功率不平衡率满足调度运行要求是智能变电站及大电网安全稳定运行的前提,同时在智能变电站出现有功功率不平衡率大时,往往不能快速找出原因,得不到解决,使得智能变电站长期运行在不平衡告警状态。With the rapid development of smart grids, the construction scale of smart substations has continued to expand. However, in recent years, smart substations have often experienced a long-term high unbalanced rate of active power in the substations. When substations are dispatched and assessed, they also have a great impact on the safe and stable operation of the power grid. Threat, and the active power imbalance rate of smart substations meeting the dispatching and operation requirements is a prerequisite for the safe and stable operation of smart substations and large power grids. At the same time, when the active power imbalance rate is large in smart substations, the cause cannot be quickly found out and cannot be solved. , causing the smart substation to run in an unbalanced alarm state for a long time.

发明内容Contents of the invention

针对上述现有技术,本发明所要解决的技术问题是现有智能变电站出现有功功率不平衡率偏大时,不能快速找出原因,使得智能变电站长期运行在不平衡告警状态。因此,提供一种有功功率不平衡率分析诊断方法、系统及计算机设备。In view of the above-mentioned prior art, the technical problem to be solved by the present invention is that when the active power imbalance rate in the existing smart substation is too large, the cause cannot be quickly found, causing the smart substation to run in an imbalance alarm state for a long time. Therefore, an active power imbalance rate analysis and diagnosis method, system and computer equipment are provided.

本发明通过下述技术方案实现:The present invention is realized through the following technical solutions:

S10:建立智能变电站一次设备元件模型,根据电压等级配置所述元件模型参数;S10: Establish a smart substation primary equipment component model, and configure the component model parameters according to the voltage level;

S20:导入所述智能变电站的SCD文件,识别所述SCD文件中的测控装置信息;S20: Import the SCD file of the smart substation, and identify the measurement and control device information in the SCD file;

S30:将所述测控装置信息与所述一次设备元件模型匹配,生成一次主接线系统;S30: Match the measurement and control device information with the primary equipment component model to generate a primary main wiring system;

S40:提取所述测控装置的采样数据信息,并在所述一次主接线系统中对应的所述一次设备元件模型显示,形成有功功率潮流信息;S40: Extract the sampling data information of the measurement and control device, and display the corresponding primary equipment component model in the primary main wiring system to form active power flow information;

S50:全站总有功功率不平衡率计算:根据所述有功功率潮流信息和所述采样数据信息计算所述智能变电站的总有功功率不平衡率;S50: Calculation of the total active power imbalance rate of the entire station: Calculate the total active power imbalance rate of the smart substation based on the active power flow information and the sampling data information;

S60:电压等级区域有功功率不平衡率计算:若所述总有功功率不平衡率超过阈值范围,根据所述电压等级进行区域划分计算各区域的有功功率不平衡率;S60: Calculation of active power imbalance rate in voltage level regions: If the total active power imbalance rate exceeds the threshold range, divide the regions according to the voltage level to calculate the active power imbalance rate in each region;

S70:电压等级区域诊断分析:对计算出的所述有功功率不平衡率不等于0的所述电压等级区域进行不平衡诊断分析并得出诊断结果。S70: Voltage level area diagnostic analysis: perform imbalance diagnosis analysis on the voltage level area where the calculated active power imbalance rate is not equal to 0 and obtain a diagnosis result.

可选地,所述智能变电站一次设备包括母线、线路、母联、变压器、CT互感器、PT互感器和断路器。Optionally, the primary equipment of the smart substation includes busbars, lines, bus ties, transformers, CT transformers, PT transformers and circuit breakers.

进一步地,所述步骤S10包括对所述元件模型根据220kv、110kv、35kv和10kv四种电压等级进行配置参数,具体包括:Further, the step S10 includes configuring parameters of the component model according to four voltage levels of 220kv, 110kv, 35kv and 10kv, specifically including:

对CT互感器和PT互感器进行变比配置;Configure CT transformers and PT transformers with variable ratio;

对所述线路进行线路长度、感抗、阻抗、容抗和补偿系数进行参数配置;Configure parameters for the line length, inductive reactance, impedance, capacitive reactance and compensation coefficient;

对主变阻抗、变比特性、负载损耗、空载损耗进行参数配置。Configure parameters for main transformer impedance, transformer ratio characteristics, load loss, and no-load loss.

可选地,所述采样数据信息包括电压采样信息、电流采样信息、有功功率信息、功率因素信息、断路器位置信息和刀闸位置信息。Optionally, the sampling data information includes voltage sampling information, current sampling information, active power information, power factor information, circuit breaker position information and knife switch position information.

可选地,所述测控装置信息包括线路测控装置信息、母线测控装置信息、变压器测控装置信息和母联测控装置信息。Optionally, the measurement and control device information includes line measurement and control device information, busbar measurement and control device information, transformer measurement and control device information and bus tie measurement and control device information.

进一步地,所述步骤S30,具体包括以下步骤:Further, step S30 specifically includes the following steps:

S31:将220kv、110kv、35kv和10kv的所述线路测控装置信息与对应电压等级的线路元件模型进行匹配;S31: Match the line measurement and control device information of 220kv, 110kv, 35kv and 10kv with the line element model of the corresponding voltage level;

S32:将220kv、110kv、35kv和10kv的所述母线测控装置信息与对应电压等级的母线元件模型进行匹配;S32: Match the bus measurement and control device information of 220kv, 110kv, 35kv and 10kv with the bus component model of the corresponding voltage level;

S33:将220kv、110kv、35kv和10kv的所述变压器测控装置信息与对应电压等级的变压器元件模型进行匹配;S33: Match the transformer measurement and control device information of 220kv, 110kv, 35kv and 10kv with the transformer component model of the corresponding voltage level;

S34:将220kv、110kv、35kv和10kv的所述母联测控装置信息与对应电压等级的母联元件模型进行匹配;S34: Match the bus link measurement and control device information of 220kv, 110kv, 35kv and 10kv with the bus link component model of the corresponding voltage level;

S35:将所述测控装置信息全部匹配一次设备元件模型后,生成一次主接线系统。S35: After all the measurement and control device information is matched to the primary equipment component model, a primary main wiring system is generated.

可选地,所述步骤S70具体包括:Optionally, the step S70 specifically includes:

对比220kv、110kv、35kv和10kv各电压等级区域线路、主变侧、母联电压及电流信息与对应电压等级的母线电压信息,得出有功功率不平衡因素为电压采集异常、三相电流不平衡、CT电流互感器精度或CT电流互感器故障、PT互感器精度或PT互感器故障;Comparing the regional line, main transformer side, bus voltage and current information of 220kv, 110kv, 35kv and 10kv with the bus voltage information of the corresponding voltage levels, it is concluded that the active power imbalance factors are abnormal voltage acquisition and three-phase current imbalance. , CT current transformer accuracy or CT current transformer failure, PT transformer accuracy or PT transformer failure;

结合配置变压器负载损耗率分析变压器220kv、110kv、35kv和10kv侧的电流、电压、有功功率和无功率信息,得出有功功率不平衡因素为变压器负荷损耗异常。Combined with the configuration of the transformer load loss rate, the current, voltage, active power and reactive power information of the 220kv, 110kv, 35kv and 10kv sides of the transformer were analyzed, and it was concluded that the active power imbalance factor was the abnormal load loss of the transformer.

结合配置变压器阻抗、变比特性分析变压器220kv、110kv、35kv和10kv侧的电流、电压、有功功率和无功功率信息,得出有功功率不平衡因素为变压器系统电压异常和出口电压异常。By analyzing the current, voltage, active power and reactive power information of the 220kv, 110kv, 35kv and 10kv sides of the transformer based on the impedance and ratio characteristics of the configured transformer, it is concluded that the active power imbalance factors are abnormal voltage of the transformer system and abnormal outlet voltage.

一种有功功率不平衡分析诊断系统,包括:An active power imbalance analysis and diagnosis system, including:

模型建立模块,用于对智能变电站一次设备建立一次设备元件模型;The model building module is used to establish primary equipment component models for primary equipment in smart substations;

参数配置模块,用于对所述一次设备元件模型进行参数配置;Parameter configuration module, used to configure parameters for the primary equipment component model;

导入识别模块,用于导入所述智能变电站的SCD文件和识别所述SCD文件中的测控装置信息;Import the identification module, used to import the SCD file of the smart substation and identify the measurement and control device information in the SCD file;

匹配生成模块,用于将所述测控装置信息与所述一次设备元件模型匹配和生成一次主接线系统Matching generation module, used to match the measurement and control device information with the primary equipment component model and generate a primary main wiring system

提取形成模块,用于提取所述测控装置的采样数据信息并在所述一次主接线系统中对应的所述一次设备元件模型显示和形成有功功率潮流信息;An extraction and formation module, used to extract the sampling data information of the measurement and control device and display and form the active power flow information on the corresponding primary equipment component model in the primary main wiring system;

计算模块,用于计算所述智能变电站的总有功功率不平衡率和计算各电压等级区域的有功功率不平衡率;A calculation module used to calculate the total active power imbalance rate of the smart substation and calculate the active power imbalance rate in each voltage level area;

判断模块,用于判断总有功功率不平衡率是否超过阈值范围和判断各电压等级区域的有功功率不平衡率是否为0;A judgment module used to judge whether the total active power imbalance rate exceeds the threshold range and whether the active power imbalance rate in each voltage level area is 0;

分析诊断模块,用于分析有功功率不平衡率不为0的电压等级区域和诊断有功功率不平衡因素。The analysis and diagnosis module is used to analyze the voltage level area where the active power imbalance rate is not 0 and diagnose the active power imbalance factors.

进一步地,所述分析诊断模块包括:Further, the analysis and diagnosis module includes:

第一诊断分析单元,用于计算全站220kv、110kv、35kv和10kv侧的电流、电压、有功功率信息,综合诊断全站有功功率是否平衡,全站有功功率不平衡时,按电压等级确定有功不平衡区域;The first diagnostic analysis unit is used to calculate the current, voltage and active power information of the 220kv, 110kv, 35kv and 10kv sides of the entire station, and comprehensively diagnose whether the active power of the entire station is balanced. When the active power of the entire station is unbalanced, the active power is determined according to the voltage level. Unbalanced area;

第二诊断分析单元,当全站有功功率不平衡时,用于对比220kv电压等级区域线路、220kV主变侧、母联电压及电流信息与对应电压等级的母线电压信息,综合计算220kV电压等级区域有功功率是否平衡,若不平衡,得出有功功率不平衡因素为220kV电压采集异常、三相电流不平衡、CT电流互感器精度或CT电流互感器故障、PT互感器精度或PT互感器故障;The second diagnostic analysis unit, when the active power of the whole station is unbalanced, is used to compare the 220kV voltage level area lines, 220kV main transformer side, bus voltage and current information with the bus voltage information of the corresponding voltage level, and comprehensively calculate the 220kV voltage level area. Is the active power balanced? If not, it can be concluded that the active power imbalance factors are 220kV voltage acquisition abnormality, three-phase current imbalance, CT current transformer accuracy or CT current transformer failure, PT transformer accuracy or PT transformer failure;

第三诊断分析单元,当全站有功功率不平衡时,用于对比110kv电压等级区域线路、110kV主变侧、母联电压及电流信息与对应电压等级的母线电压信息,综合计算110kV电压等级区域有功功率是否平衡,若不平衡,得出有功功率不平衡因素为110kV电压采集异常、三相电流不平衡、CT电流互感器精度或CT电流互感器故障、PT互感器精度或PT互感器故障;The third diagnostic analysis unit, when the active power of the whole station is unbalanced, is used to compare the 110kV voltage level area lines, 110kV main transformer side, bus voltage and current information with the bus voltage information of the corresponding voltage level, and comprehensively calculate the 110kV voltage level area. Is the active power balanced? If not, it can be concluded that the active power imbalance factors are 110kV voltage acquisition abnormality, three-phase current imbalance, CT current transformer accuracy or CT current transformer failure, PT transformer accuracy or PT transformer failure;

第四诊断分析单元,当全站有功功率不平衡时,用于对比35kv电压等级区域线路、22035kV主变侧、母联电压及电流信息与对应电压等级的母线电压信息,综合计算35kV电压等级区域有功功率是否平衡,若不平衡,得出有功功率不平衡因素为35kV电压采集异常、三相电流不平衡、CT电流互感器精度或CT电流互感器故障、PT互感器精度或PT互感器故障;The fourth diagnostic analysis unit, when the active power of the whole station is unbalanced, is used to compare the 35kV voltage level area lines, 22035kV main transformer side, bus voltage and current information with the bus voltage information of the corresponding voltage level, and comprehensively calculate the 35kV voltage level area Is the active power balanced? If not, it can be concluded that the active power imbalance factors are 35kV voltage acquisition abnormality, three-phase current imbalance, CT current transformer accuracy or CT current transformer failure, PT transformer accuracy or PT transformer failure;

第五诊断分析单元,当全站有功功率不平衡时,用于对比10kv电压等级区域线路、10kV主变侧、母联电压及电流信息与对应电压等级的母线电压信息,综合计算10kV电压等级区域有功功率是否平衡,若不平衡,得出有功功率不平衡因素为10kV电压采集异常、三相电流不平衡、CT电流互感器精度或CT电流互感器故障、PT互感器精度或PT互感器故障;The fifth diagnostic analysis unit, when the active power of the whole station is unbalanced, is used to compare the 10kV voltage level area line, 10kV main transformer side, bus voltage and current information with the bus voltage information of the corresponding voltage level, and comprehensively calculate the 10kV voltage level area Is the active power balanced? If not, it can be concluded that the active power imbalance factors are 10kV voltage acquisition abnormality, three-phase current imbalance, CT current transformer accuracy or CT current transformer failure, PT transformer accuracy or PT transformer failure;

第六诊断分析单元,用于结合配置变压器负载损耗率分析变压器220kv、110kv、35kv和10kv侧的电流、电压、有功功率和无功功率信息,得出有功功率不平衡因素为变压器负荷损耗;The sixth diagnostic analysis unit is used to analyze the current, voltage, active power and reactive power information of the 220kv, 110kv, 35kv and 10kv sides of the transformer in combination with the configured transformer load loss rate, and conclude that the active power imbalance factor is the transformer load loss;

第七诊断分析单元,用于结合配置变压器阻抗、变比特性分析变压器220kv、110kv、35kv和10kv侧的电流、电压、有功功率和无功功率信息,得出有功功率不平衡因素为变压器系统电压异常和出口电压异常。The seventh diagnostic analysis unit is used to analyze the current, voltage, active power and reactive power information of the 220kv, 110kv, 35kv and 10kv sides of the transformer in combination with the configured transformer impedance and transformation ratio characteristics, and conclude that the active power imbalance factor is the transformer system voltage Abnormality and outlet voltage abnormality.

一种计算机设备,包括存储器、处理器以及存储在所述存储器中并可在所述处理器上运行的计算机程序,所述处理器执行所述计算机程序时实现如上述有功功率不平衡分析诊断方法。A computer device, including a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the computer program, it implements the above active power imbalance analysis and diagnosis method. .

本发明与现有技术相比,具有如下的优点和有益效果:Compared with the prior art, the present invention has the following advantages and beneficial effects:

本发明提供了一种有功功率不平衡率分析诊断方法、系统及计算机设备,通过对智能变电站一次设备建立一次设备元件模型,并按照电压等级进行参数配置,然后导入并识别SCD文件中的测控装置信息,匹配生成一次主接线系统,通过先计算全站总有功功率不平衡率来判断是否超过阈值范围,当超过阈值范围时,再根据电压等级分区域计算有功功率不平衡率,并对出现有功功率不平衡率不为0的电压区域分析诊断出原因,这样按照电压等级进行分区域诊断分析,缩小了分析诊断范围,能够快速找出有功功率不平衡原因,避免智能变电站长期运行在不平衡警告状态。The invention provides an active power imbalance rate analysis and diagnosis method, system and computer equipment. By establishing a primary equipment component model for the primary equipment of the smart substation, configuring parameters according to the voltage level, and then importing and identifying the measurement and control device in the SCD file information, match and generate a primary main wiring system, and determine whether it exceeds the threshold range by first calculating the total active power unbalance rate of the entire station. When the threshold range is exceeded, the active power unbalance rate is calculated by region according to the voltage level, and the active power unbalance rate is calculated accordingly. Analyze and diagnose the cause of the voltage area where the power imbalance rate is not 0. In this way, regional diagnostic analysis is performed according to the voltage level, which narrows the scope of analysis and diagnosis. It can quickly find out the cause of active power imbalance and avoid long-term operation of smart substations with imbalance warnings. state.

附图说明Description of the drawings

此处所说明的附图用来提供对本发明实施例的进一步理解,构成本申请的一部分,并不构成对本发明实施例的限定。在附图中:The drawings described here are used to provide a further understanding of the embodiments of the present invention, constitute a part of this application, and do not constitute a limitation to the embodiments of the present invention. In the attached picture:

图1为本发明实施例一提供的一种有功功率不平衡率分析诊断方法的流程示意图;Figure 1 is a schematic flow chart of an active power imbalance rate analysis and diagnosis method provided by Embodiment 1 of the present invention;

图2为图1中步骤S30的一具体流程示意图;Figure 2 is a specific flow diagram of step S30 in Figure 1;

图3为本发明实施例一提供的一次主接线系统示意图;Figure 3 is a schematic diagram of the primary main wiring system provided by Embodiment 1 of the present invention;

图4为本发明实施例一提供的各电压等级的有功功率不平衡分析诊断示意图;Figure 4 is a schematic diagram of active power imbalance analysis and diagnosis of each voltage level provided by Embodiment 1 of the present invention;

图5为本发明实施例二提供的一种有功功率不平衡率分析诊断系统的功能模块示意图。Figure 5 is a schematic diagram of the functional modules of an active power imbalance rate analysis and diagnosis system provided in Embodiment 2 of the present invention.

具体实施方式Detailed ways

为使本发明的目的、技术方案和优点更加清楚明白,下面结合实施例和附图,对本发明作进一步的详细说明,本发明的示意性实施方式及其说明仅用于解释本发明,并不作为对本发明的限定。In order to make the purpose, technical solutions and advantages of the present invention more clear, the present invention will be further described in detail below in conjunction with the examples and drawings. The schematic embodiments of the present invention and their descriptions are only used to explain the present invention and do not as a limitation of the invention.

目前国内有对大电网潮流有功功率计算仿真以及控制调节,没有针对变电站出现有功功率不平衡诊断分析原因的研究,然而近几年智能变电站经常出现电站有功功率不平衡率长期偏大的现象,这对电网安全稳定运行造成极大威胁,但目前还不能快速找出导致有功功率不平衡的原因,使得智能变电站长期运行在不平衡告警状态。At present, there is no research on the calculation, simulation and control regulation of large power grid active power in the country, but there is no research on the diagnosis and analysis of the causes of active power imbalance in substations. However, in recent years, smart substations often have the phenomenon that the active power imbalance rate of the power station is relatively large for a long time. It poses a great threat to the safe and stable operation of the power grid. However, it is currently not possible to quickly find out the cause of active power imbalance, causing smart substations to run in an imbalance alarm state for a long time.

因此,本发明基于智能变电站提出了一种有功功率不平衡分析诊断方法、系统和计算机设备,主要为了解决现有技术在出现有功功率不平衡率大时,往往不能快速找到有功功率不平衡原因的问题,需要说明的是本发明提供的一种有功功率不平衡分析诊断方法、系统和计算机设备不限于应用于智能变电站中,还可适用于其它大型电网中。Therefore, the present invention proposes an active power imbalance analysis and diagnosis method, system and computer equipment based on a smart substation, mainly to solve the problem that the existing technology often cannot quickly find the cause of the active power imbalance when the active power imbalance rate is large. question, it should be noted that the active power imbalance analysis and diagnosis method, system and computer equipment provided by the present invention are not limited to application in smart substations, but can also be applied to other large power grids.

实施例一Embodiment 1

如图1所示,本发明提供一种变电站有功功率不平衡分析诊断方法,包括以下步骤:As shown in Figure 1, the present invention provides a substation active power imbalance analysis and diagnosis method, which includes the following steps:

S10:建立智能变电站一次设备元件模型,根据电压等级配置一次设备元件模型参数;S10: Establish a primary equipment component model of the smart substation, and configure the primary equipment component model parameters according to the voltage level;

其中,智能变电站的一次设备包括但不限于母线、线路、母联、变压器、CT互感器、PT互感器和断路器,元件模型是指根据上述一次设备建立相应的母线元件模型、线路元件模型、母联元件模型、变压器元件模型等。Among them, the primary equipment of the smart substation includes but is not limited to busbars, lines, bus ties, transformers, CT transformers, PT transformers and circuit breakers. The component model refers to establishing the corresponding busbar component model, line component model, Bus tie component model, transformer component model, etc.

其中,电压等级包括220kv、110kv、35kv和10kv四种电压等级,具体包括对CT互感器和PT互感器进行变比配置;对线路进行线路长度、感抗、阻抗、容抗和补偿系数进行参数配置;对主变阻抗、变比特性、负载损耗、空载损耗进行参数配置。Among them, the voltage levels include four voltage levels: 220kv, 110kv, 35kv and 10kv. Specifically, they include variable ratio configuration of CT transformers and PT transformers; parameterization of line length, inductive reactance, impedance, capacitive reactance and compensation coefficient of the line. Configuration; configure parameters for main transformer impedance, transformation ratio characteristics, load loss, and no-load loss.

S20:导入智能变电站的SCD文件,识别SCD文件中的测控装置信息;S20: Import the SCD file of the smart substation and identify the measurement and control device information in the SCD file;

其中,SCD文件是全站系统配置信息文件,包括整个智能变电站的系统配置信息。测控装置信息包括但不限于线路测控装置信息、母线测控装置信息、变压器测控装置信息和母联测控装置信息。Among them, the SCD file is the whole station system configuration information file, including the system configuration information of the entire smart substation. The measurement and control device information includes but is not limited to line measurement and control device information, busbar measurement and control device information, transformer measurement and control device information and bus tie measurement and control device information.

S30:将测控装置信息与一次设备元件模型匹配,生成一次主接线系统;S30: Match the measurement and control device information with the primary equipment component model to generate the primary main wiring system;

其中,通过测控装置信息中各元件参数与一次设备元件模型按电压等级配置的参数进行匹配,生成一次接线系统,一次接线系统可体现智能变电站全站的数据信息,能够直观地对整个智能变电站进行分析,为后续进行有功功率计算和分析诊断提供基础。Among them, by matching the parameters of each component in the measurement and control device information with the parameters configured according to the voltage level of the primary equipment component model, a primary wiring system is generated. The primary wiring system can reflect the data information of the entire smart substation and can intuitively conduct operations on the entire smart substation. Analysis provides a basis for subsequent active power calculation and analysis and diagnosis.

S40:提取测控装置的采样数据信息,并在一次主接线系统中对应的一次设备元件模型显示,形成有功功率潮流信息;S40: Extract the sampling data information of the measurement and control device and display it on the corresponding primary equipment component model in the primary main wiring system to form active power flow information;

具体的,通过自动读取智能变电站SCD文件中的测控装置的IP地址,然后在智能变电站站控层提取测控装置的采样数据信息,并将采样数据信息显示在一次主接线系统的对应的一次设备元件模型中,根据在一次设备元件模型显示中的采样数据信息形成有功功率潮流信息。Specifically, the IP address of the measurement and control device in the SCD file of the smart substation is automatically read, and then the sampling data information of the measurement and control device is extracted at the station control layer of the smart substation, and the sampling data information is displayed on the corresponding primary equipment of the primary main wiring system. In the component model, active power flow information is formed based on the sampled data information displayed in the primary equipment component model.

其中,采样数据信息包括电压采样信息、电流采样信息、有功功率信息、功率因素信息、断路器位置信息和刀闸位置信息。Among them, the sampling data information includes voltage sampling information, current sampling information, active power information, power factor information, circuit breaker position information and knife switch position information.

S50:第一次全站式计算:根据有功功率潮流信息和采样数据信息计算智能变电站的总有功功率不平衡率;S50: The first full-station calculation: calculate the total active power imbalance rate of the smart substation based on the active power flow information and sampling data information;

S60:第二次电压等级区域计算:若总有功功率不平衡率超过阈值范围,根据电压等级进行区域划分计算各区域的有功功率不平衡率;S60: The second voltage level area calculation: If the total active power imbalance rate exceeds the threshold range, the area is divided according to the voltage level to calculate the active power imbalance rate in each area;

其中,有功功率不平衡率的计算公式为:P为有功功率输入,P为有功功率输出;根据有功功率潮流信息和采样数据信息结合判断有功功率输入和有功功率输出,便于计算出全站有功功率不平衡率和各电压等级区域的有功功率不平衡率。Among them, the calculation formula of the active power unbalance rate is: P input is the active power input, and P output is the active power output; the active power input and active power output are determined based on the active power flow information and sampling data information, which facilitates the calculation of the active power unbalance rate of the entire station and the active power in each voltage level area. Power imbalance rate.

其中,阈值范围为±1%,当计算得出的全站有功功率不平衡率超过了±1%,则对有功功率不平衡率按照电压等级(即220kv、110kv、35kv和10kv)进行区域划分计算,先对全站总有功功率不平衡率进行计算并判断是否偏大,然后再进一步进行电压等级区域计算及判断,这样能够缩小分析诊断范围,实现快速找出有功功率不平衡原因。Among them, the threshold range is ±1%. When the calculated active power imbalance rate of the whole station exceeds ±1%, the active power imbalance rate will be divided into regions according to the voltage level (i.e. 220kv, 110kv, 35kv and 10kv). For calculation, first calculate the total active power imbalance rate of the entire station and determine whether it is too large, and then further calculate and determine the voltage level area. This can narrow the scope of analysis and diagnosis and quickly find out the cause of the active power imbalance.

S70:对计算出的有功功率不平衡率不等于0的电压等级区域进行不平衡诊断分析并得出诊断结果。S70: Perform imbalance diagnosis analysis on the voltage level area where the calculated active power imbalance rate is not equal to 0 and obtain the diagnosis result.

其中,对有功功率不平衡率不等于0的电压等级区域进行定位分析诊断,缩小分析诊断范围,实现快速找出有功功率不平衡原因。Among them, the voltage level area where the active power imbalance rate is not equal to 0 is located, analyzed and diagnosed, and the scope of analysis and diagnosis is narrowed to quickly find out the cause of the active power imbalance.

本发明提供的一种有功功率不平衡分析诊断方法,通过对智能变电站一次设备建立一次设备元件模型,并根据电压等级对一次设备元件模型进行参数配置,然后再导入智能变电站SCD文件并识别SCD文件中的测控装置信息,生成一次主接线系统;通过智能变电站站控层通讯接入,提取测控装置的采样数据信息,将其显示在一次主接线系统中相应的一次设备模型,形成有功功率潮流信息;根据有功功率潮流信息和采样数据信息计算智能变电站的总有功功率不平衡率,判断有功功率是否超过±1%,若超过,则根据电压等级进行区域划分计算各区域的有功功率不平衡率;最后对计算出的有功功率不平衡率不等于0的电压等级区域进行不平衡诊断分析并得出诊断结果。通过电压等级区域划分计算有功功率不平衡率,缩小分析诊断范围,能够快速找出有功功率不平衡原因,避免智能变电站长期运行在不平衡告警状态。The present invention provides an active power imbalance analysis and diagnosis method by establishing a primary equipment component model for the primary equipment of a smart substation, configuring the parameters of the primary equipment component model according to the voltage level, and then importing the SCD file of the smart substation and identifying the SCD file. The measurement and control device information in the system is used to generate a primary main wiring system; through the smart substation station control layer communication access, the sampling data information of the measurement and control device is extracted and displayed on the corresponding primary equipment model in the primary main wiring system to form active power flow information ;Calculate the total active power imbalance rate of the smart substation based on the active power flow information and sampling data information, and determine whether the active power exceeds ±1%. If it exceeds, divide the regions according to the voltage level to calculate the active power imbalance rate in each region; Finally, the imbalance diagnosis analysis is performed on the voltage level area where the calculated active power imbalance rate is not equal to 0 and the diagnosis results are obtained. Calculating the active power imbalance rate by dividing voltage level areas and narrowing the scope of analysis and diagnosis can quickly find out the cause of active power imbalance and avoid long-term operation of smart substations in an imbalance alarm state.

如图2所示,步骤30,将测控装置信息与所述元件模型匹配,生成一次主接线系统,具体包括以下步骤:As shown in Figure 2, step 30 matches the measurement and control device information with the component model to generate a primary wiring system, which specifically includes the following steps:

S31:将220kv、110kv、35kv和10kv的线路测控装置信息与对应电压等级的线路元件模型进行匹配;S31: Match the line measurement and control device information of 220kv, 110kv, 35kv and 10kv with the line component model of the corresponding voltage level;

S32:将220kv、110kv、35kv和10kv的母线测控装置信息与对应电压等级的母线元件模型进行匹配;S32: Match the bus measurement and control device information of 220kv, 110kv, 35kv and 10kv with the bus component model of the corresponding voltage level;

S33:将220kv、110kv、35kv和10kv的变压器测控装置信息与对应电压等级的变压器元件模型进行匹配;S33: Match the 220kv, 110kv, 35kv and 10kv transformer measurement and control device information with the transformer component model of the corresponding voltage level;

S34:将220kv、110kv、35kv和10kv的母联测控装置信息与对应电压等级的母联元件模型进行匹配;S34: Match the bus link measurement and control device information of 220kv, 110kv, 35kv and 10kv with the bus link component model of the corresponding voltage level;

S35:将测控装置信息全部匹配一次设备元件模型后,生成一次主接线系统。S35: After all the measurement and control device information is matched to the primary equipment component model, a primary main wiring system is generated.

通过将线路测控装置信息、母线测控装置信息、变压器测控装置信息和母联测控装置信息与对应等级的对应一次元件模型进行匹配,匹配完成后,自动生成一次主接线系统,并关联测控装置信息,为后续计算有功功率不平衡率和分析诊断提供基础。By matching the line measurement and control device information, busbar measurement and control device information, transformer measurement and control device information and bus tie measurement and control device information with the corresponding primary component model of the corresponding level, after the matching is completed, the primary main wiring system is automatically generated and associated with the measurement and control device information. It provides a basis for subsequent calculation of active power imbalance rate and analysis and diagnosis.

如图3所示,若智能变电站全站均处于有功功率平衡状态,即全站有功功率:As shown in Figure 3, if the entire smart substation is in an active power balance state, that is, the active power of the entire station is:

P1+P2+P9+P10+P13+P14+P15+P16=0。P1+P2+P9+P10+P13+P14+P15+P16=0.

220kV区域:P1+P2+P4+P5=0;220kV area: P1+P2+P4+P5=0;

220kV I母区域:P1+P3+P4=0;220kV I mother area: P1+P3+P4=0;

220kV II母区域:P2+(-p3)+p5=0。220kV II mother area: P2+(-p3)+p5=0.

1#主变区域:P4+P6+P11=0;1# main transformer area: P4+P6+P11=0;

2#主变区域:P5+P7+P12=0。2# main transformer area: P5+P7+P12=0.

110kV区域:P6+P7+P9+P10=0;110kV area: P6+P7+P9+P10=0;

110kV I母区域:P6+P8+P9=0;110kV I mother area: P6+P8+P9=0;

110kV II母区域:P7+(-p8)+p10=0。110kV II mother area: P7+(-p8)+p10=0.

10kV区域:P11+P12+P13+P14+P15+P16=0;10kV area: P11+P12+P13+P14+P15+P16=0;

10kV I母区域:P11+P13+P4+P17=0;10kV I mother area: P11+P13+P4+P17=0;

10kV II母区域:P12+P15+p16+P17=0。10kV II mother area: P12+P15+p16+P17=0.

在实际应用中,全站有功功率不为0,且各电压等级区域的有功功率不全为0,因此,本发明先通过对全站有功功率不平衡率进行计算判断,然后再对各电压等级区域的有功功率不平衡率进行计算判断,定位到有功功率不平衡的电压等级区域,实现缩小分析诊断范围,达到快速找出有功功率不平衡原因。In practical applications, the active power of the entire station is not 0, and the active power in each voltage level area is not all 0. Therefore, the present invention first calculates and determines the active power imbalance rate of the entire station, and then calculates the active power in each voltage level area. The active power imbalance rate is calculated and judged, and the voltage level area of the active power imbalance is located, so as to narrow the scope of analysis and diagnosis and quickly find out the cause of the active power imbalance.

如图4所示,步骤70,对计算出的有功功率不平衡率不等于0的电压等级区域进行不平衡诊断分析并得出诊断结果,具体包括以下步骤:As shown in Figure 4, step 70 is to perform imbalance diagnosis analysis on the voltage level area where the calculated active power imbalance rate is not equal to 0 and obtain the diagnosis result, which specifically includes the following steps:

对比220kv、110kv、35kv和10kv各电压等级区域线路、主变侧、母联电压及电流信息与对应电压等级的母线电压信息,得出有功功率不平衡因素为电压采集异常、三相电流不平衡、CT电流互感器精度或CT电流互感器故障、PT互感器精度或PT互感器故障;Comparing the regional line, main transformer side, bus voltage and current information of 220kv, 110kv, 35kv and 10kv with the bus voltage information of the corresponding voltage levels, it is concluded that the active power imbalance factors are abnormal voltage acquisition and three-phase current imbalance. , CT current transformer accuracy or CT current transformer failure, PT transformer accuracy or PT transformer failure;

结合配置变压器负载损耗率分析变压器220kv、110kv、35kv和10kv侧的电流、电压、有功功率和无功率信息,得出有功功率不平衡因素为变压器负荷损耗异常。Combined with the configuration of the transformer load loss rate, the current, voltage, active power and reactive power information of the 220kv, 110kv, 35kv and 10kv sides of the transformer were analyzed, and it was concluded that the active power imbalance factor was the abnormal load loss of the transformer.

结合配置变压器阻抗、变比特性分析变压器220kv、110kv、35kv和10kv侧的电流、电压、有功功率和无功功率信息,得出有功功率不平衡因素为变压器系统电压异常和出口电压异常。By analyzing the current, voltage, active power and reactive power information of the 220kv, 110kv, 35kv and 10kv sides of the transformer based on the impedance and ratio characteristics of the configured transformer, it is concluded that the active power imbalance factors are abnormal voltage of the transformer system and abnormal outlet voltage.

通过定位到对有功功率不平衡的电压等级区域内的测控装置进行分析,并对其得出相应的诊断结果,即有功功率不平衡因素为CT异常、PT异常、电流采集异常、电压采集异常、采集精度异常、功率因素异常、合并单元异常、主变电压比异常、有载负荷损耗异常和主变输出系统电压异常中的一种或多种,这样能够快速找出有功功率不平衡原因,便于后续采取相应措施解决,维护智能变电站的稳定运行。By locating and analyzing the measurement and control device in the voltage level area where the active power is unbalanced, the corresponding diagnosis results are obtained, that is, the active power unbalance factors are CT abnormality, PT abnormality, current acquisition abnormality, voltage acquisition abnormality, Collect one or more of abnormal accuracy, abnormal power factor, abnormal merging unit, abnormal main transformer voltage ratio, abnormal on-load load loss and abnormal main transformer output system voltage, so as to quickly find out the cause of active power imbalance and facilitate Corresponding measures will be taken to solve the problem and maintain the stable operation of the smart substation.

将本发明提供的一种有功功率不平衡分析诊断方法应用于智能变电站中,通过对智能变电站一次设备建立一次设备元件模型,并根据电压等级对一次设备元件模型进行参数配置,然后再导入智能变电站SCD文件并识别SCD文件中的测控装置信息,生成一次主接线系统;通过智能变电站站控层通讯接入,提取测控装置的采样数据信息,将其显示在一次主接线系统中相应的一次设备模型,形成有功功率潮流信息;根据有功功率潮流信息和采样数据信息计算智能变电站的总有功功率不平衡率,判断有功功率是否超过±1%,若超过,则根据电压等级进行区域划分计算各区域的有功功率不平衡率;最后对计算出的有功功率不平衡率不等于0的电压等级区域进行不平衡诊断分析并得出诊断结果。通过电压等级区域划分计算有功功率不平衡率,缩小分析诊断范围,能够快速找出有功功率不平衡原因。An active power imbalance analysis and diagnosis method provided by the present invention is applied to a smart substation by establishing a primary equipment component model for the primary equipment of the smart substation, configuring the parameters of the primary equipment component model according to the voltage level, and then importing it into the smart substation. SCD file and identify the measurement and control device information in the SCD file to generate a primary main wiring system; through smart substation station control layer communication access, extract the sampling data information of the measurement and control device and display it in the corresponding primary equipment model in the primary main wiring system , to form active power flow information; calculate the total active power unbalance rate of the smart substation based on the active power flow information and sampling data information, and determine whether the active power exceeds ±1%. If it exceeds, divide the regions according to the voltage level and calculate the Active power imbalance rate; finally, perform imbalance diagnosis analysis on the voltage level area where the calculated active power imbalance rate is not equal to 0 and obtain the diagnosis results. Calculate the active power imbalance rate by dividing the voltage level area, narrow the scope of analysis and diagnosis, and quickly find out the cause of the active power imbalance.

实施例二Embodiment 2

如图5所示,本实施例提供一种有功功率不平衡分析诊断系统,包括:As shown in Figure 5, this embodiment provides an active power imbalance analysis and diagnosis system, including:

模型建立模块,用于对智能变电站的一次设备建立一次设备元件模型;The model building module is used to establish primary equipment component models for primary equipment in smart substations;

参数配置模块,用于对一次元件模型进行参数配置;Parameter configuration module, used to configure parameters for the primary component model;

导入识别模块,用于导入智能变电站的SCD文件和识别SCD文件中的测控装置信息;Import identification module, used to import SCD files of smart substations and identify measurement and control device information in SCD files;

匹配生成模块,用于将测控装置信息与所述一次设备元件模型匹配和生成一次主接线系统Matching generation module, used to match the measurement and control device information with the primary equipment component model and generate a primary main wiring system

提取形成模块,用于提取测控装置的采样数据信息并在一次主接线系统中对应的一次设备元件模型显示和形成有功功率潮流信息;The extraction and formation module is used to extract the sampling data information of the measurement and control device and display and form the active power flow information in the corresponding primary equipment component model in the primary main wiring system;

计算模块,用于计算智能变电站的总有功功率不平衡率和计算各电压等级区域的有功功率不平衡率;The calculation module is used to calculate the total active power imbalance rate of the smart substation and calculate the active power imbalance rate in each voltage level area;

判断模块,用于判断总有功功率不平衡率和判断各电压等级区域的有功功率不平衡率,The judgment module is used to judge the total active power imbalance rate and the active power imbalance rate in each voltage level area.

分析诊断模块,用于分析各电压等级区域的有功功率不平衡率和诊断有功功率不平衡因素。The analysis and diagnosis module is used to analyze the active power imbalance rate in each voltage level area and diagnose the active power imbalance factors.

其中,分析诊断模块包括第一诊断分析单元、第二诊断分析单元、第三诊断分析单元、第四诊断单元、第五诊断单元、第六诊断单元和第七诊断分析单元,Wherein, the analysis and diagnosis module includes a first diagnosis and analysis unit, a second diagnosis and analysis unit, a third diagnosis and analysis unit, a fourth diagnosis unit, a fifth diagnosis unit, a sixth diagnosis unit and a seventh diagnosis and analysis unit,

第一诊断分析单元,用于计算全站220kv、110kv、35kv和10kv侧的电流、电压、有功功率信息,综合诊断全站有功功率是否平衡,全站有功功率不平衡时,按电压等级确定有功不平衡区域;The first diagnostic analysis unit is used to calculate the current, voltage and active power information of the 220kv, 110kv, 35kv and 10kv sides of the entire station, and comprehensively diagnose whether the active power of the entire station is balanced. When the active power of the entire station is unbalanced, the active power is determined according to the voltage level. Imbalanced area;

第二诊断分析单元,当全站有功功率不平衡时,用于对比220kv电压等级区域线路、220kV主变侧、母联电压及电流信息与对应电压等级的母线电压信息,综合计算220kV电压等级区域有功功率是否平衡,若不平衡,得出有功功率不平衡因素为220kV电压采集异常、三相电流不平衡、CT电流互感器精度或CT电流互感器故障、PT互感器精度或PT互感器故障;The second diagnostic analysis unit, when the active power of the whole station is unbalanced, is used to compare the 220kV voltage level area lines, 220kV main transformer side, bus voltage and current information with the bus voltage information of the corresponding voltage level, and comprehensively calculate the 220kV voltage level area. Is the active power balanced? If not, it can be concluded that the active power imbalance factors are 220kV voltage acquisition abnormality, three-phase current imbalance, CT current transformer accuracy or CT current transformer failure, PT transformer accuracy or PT transformer failure;

第三诊断分析单元,当全站有功功率不平衡时,用于对比110kv电压等级区域线路、110kV主变侧、母联电压及电流信息与对应电压等级的母线电压信息,综合计算110kV电压等级区域有功功率是否平衡,若不平衡,得出有功功率不平衡因素为110kV电压采集异常、三相电流不平衡、CT电流互感器精度或CT电流互感器故障、PT互感器精度或PT互感器故障;The third diagnostic analysis unit, when the active power of the whole station is unbalanced, is used to compare the 110kV voltage level area lines, 110kV main transformer side, bus voltage and current information with the bus voltage information of the corresponding voltage level, and comprehensively calculate the 110kV voltage level area. Is the active power balanced? If not, it can be concluded that the active power imbalance factors are 110kV voltage acquisition abnormality, three-phase current imbalance, CT current transformer accuracy or CT current transformer failure, PT transformer accuracy or PT transformer failure;

第四诊断分析单元,当全站有功功率不平衡时,用于对比35kv电压等级区域线路、22035kV主变侧、母联电压及电流信息与对应电压等级的母线电压信息,综合计算35kV电压等级区域有功功率是否平衡,若不平衡,得出有功功率不平衡因素为35kV电压采集异常、三相电流不平衡、CT电流互感器精度或CT电流互感器故障、PT互感器精度或PT互感器故障;The fourth diagnostic analysis unit, when the active power of the whole station is unbalanced, is used to compare the 35kV voltage level area lines, 22035kV main transformer side, bus voltage and current information with the bus voltage information of the corresponding voltage level, and comprehensively calculate the 35kV voltage level area Is the active power balanced? If not, it can be concluded that the active power imbalance factors are 35kV voltage acquisition abnormality, three-phase current imbalance, CT current transformer accuracy or CT current transformer failure, PT transformer accuracy or PT transformer failure;

第五诊断分析单元,当全站有功功率不平衡时,用于对比10kv电压等级区域线路、10kV主变侧、母联电压及电流信息与对应电压等级的母线电压信息,综合计算10kV电压等级区域有功功率是否平衡,若不平衡,得出有功功率不平衡因素为10kV电压采集异常、三相电流不平衡、CT电流互感器精度或CT电流互感器故障、PT互感器精度或PT互感器故障;The fifth diagnostic analysis unit, when the active power of the whole station is unbalanced, is used to compare the 10kV voltage level area line, 10kV main transformer side, bus voltage and current information with the bus voltage information of the corresponding voltage level, and comprehensively calculate the 10kV voltage level area Is the active power balanced? If not, it can be concluded that the active power imbalance factors are 10kV voltage acquisition abnormality, three-phase current imbalance, CT current transformer accuracy or CT current transformer failure, PT transformer accuracy or PT transformer failure;

第六诊断分析单元,用于结合配置变压器负载损耗率分析变压器220kv、110kv、35kv和10kv侧的电流、电压、有功功率和无功功率信息,得出有功功率不平衡因素为变压器负荷损耗;The sixth diagnostic analysis unit is used to analyze the current, voltage, active power and reactive power information of the 220kv, 110kv, 35kv and 10kv sides of the transformer in combination with the configured transformer load loss rate, and conclude that the active power imbalance factor is the transformer load loss;

第七诊断分析单元,用于结合配置变压器阻抗、变比特性分析变压器220kv、110kv、35kv和10kv侧的电流、电压、有功功率和无功功率信息,得出有功功率不平衡因素为变压器系统电压异常和出口电压异常。The seventh diagnostic analysis unit is used to analyze the current, voltage, active power and reactive power information of the 220kv, 110kv, 35kv and 10kv sides of the transformer in combination with the configured transformer impedance and transformation ratio characteristics, and conclude that the active power imbalance factor is the transformer system voltage Abnormality and outlet voltage abnormality.

关于有功功率不平衡分析诊断系统的具体限定可以参见实施例一中对于有功功率不平衡分析诊断方法的限定,在此不再赘述。上述有功功率不平衡分析诊断系统中的各个模块可全部或部分通过软件、硬件及其组合来实现。上述各模块可以硬件形式内嵌于或独立于计算机设备中的处理器中,也可以以软件形式存储于计算机设备中的存储器中,以便于处理器调用执行以上各个模块对应的操作。For specific limitations on the active power imbalance analysis and diagnosis system, please refer to the limitations on the active power imbalance analysis and diagnosis method in Embodiment 1, which will not be described again here. Each module in the above-mentioned active power imbalance analysis and diagnosis system can be realized in whole or in part by software, hardware and their combination. Each of the above modules may be embedded in or independent of the processor of the computer device in the form of hardware, or may be stored in the memory of the computer device in the form of software, so that the processor can call and execute the operations corresponding to the above modules.

实施例三Embodiment 3

本实施例提供了一种计算机设备,包括存储器、处理器以及存储在所述存储器中并可在所述处理器上运行的计算机程序,其特征在于,所述处理器执行所述计算机程序时实现如上述有功功率不平衡分析诊断方法,例如图1所示的步骤S10至步骤S70。或者,处理器执行计算机程序时实现上述实施例中有功功率不平衡分析诊断系统的各模块/单元的功能,例如图4所示中各模块的功能。为避免重复,这里不再赘述。This embodiment provides a computer device, including a memory, a processor, and a computer program stored in the memory and executable on the processor. The feature is that when the processor executes the computer program, The above-mentioned active power imbalance analysis and diagnosis method, for example, steps S10 to S70 shown in Figure 1 . Alternatively, when the processor executes the computer program, the functions of each module/unit of the active power imbalance analysis and diagnosis system in the above embodiment are implemented, such as the functions of each module shown in Figure 4 . To avoid repetition, they will not be repeated here.

以上所述的具体实施方式,对本发明的目的、技术方案和有益效果进行了进一步详细说明,所应理解的是,以上所述仅为本发明的具体实施方式而已,并不用于限定本发明的保护范围,凡在本发明的精神和原则之内,所做的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above-described specific embodiments further describe the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above-mentioned are only specific embodiments of the present invention and are not intended to limit the scope of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention shall be included in the protection scope of the present invention.

Claims (8)

1. An active power imbalance analysis and diagnosis method is characterized by comprising the following steps:
s10: establishing an intelligent substation primary equipment element model, and configuring parameters of the primary equipment element model according to voltage levels;
s20: importing an SCD file of the intelligent substation, and identifying measurement and control device information in the SCD file;
s30: matching the measurement and control device information with the primary equipment element model to generate a primary main wiring system;
s40: extracting sampling data information of the measurement and control device, and displaying the sampling data information in the primary equipment element model corresponding to the primary main wiring system to form active power flow information;
s50: total active power unbalance rate calculation of the total station: calculating the total active power unbalance rate of the intelligent substation according to the active power flow information and the sampling data information;
s60: calculating the active power unbalance rate of the voltage class area: if the total active power unbalance rate exceeds a threshold range, dividing the area according to the voltage grade to calculate the active power unbalance rate of each area;
s70: hierarchical voltage region diagnostic analysis: carrying out unbalance diagnosis analysis on the calculated voltage class area with the active power unbalance rate not equal to 0 and obtaining a diagnosis result;
the step S70 specifically includes:
comparing the line, main transformer side, bus voltage and current information of each voltage class area of 220kv, 110kv, 35kv and 10kv with the bus voltage information of the corresponding voltage class to obtain active power unbalance factors which are abnormal voltage acquisition, three-phase current unbalance, CT current transformer precision or CT current transformer fault, PT transformer precision or PT transformer fault;
analyzing current, voltage, active power and non-power information of the transformer at 220kv, 110kv, 35kv and 10kv sides by combining with the load loss rate of the configured transformer to obtain an active power unbalanced factor which is abnormal load loss of the transformer;
and combining the configuration transformer impedance, the variable bit characteristic analysis transformers 220kv, 110kv, 35kv and 10kv side currents, voltages and active power to obtain the active power unbalance factors which are abnormal voltage of the transformer system and abnormal voltage of an outlet.
2. The active power unbalance analysis and diagnosis method according to claim 1, wherein the primary equipment of the intelligent substation comprises a bus bar, a line, a bus bar, a transformer, a CT transformer, a PT transformer and a circuit breaker.
3. The active power unbalance analysis and diagnosis method according to claim 2, wherein the step S10 includes configuring parameters of the element model according to four voltage levels of 220kv, 110kv, 35kv and 10kv, and specifically includes:
performing transformation ratio configuration on a CT transformer and a PT transformer;
carrying out parameter configuration on the line length, the inductive reactance, the impedance, the capacitive reactance and the compensation coefficient of the line;
and carrying out parameter configuration on the main transformer impedance, the transformation ratio characteristic, the load loss and the no-load loss.
4. The active power imbalance analysis and diagnosis method of claim 1, wherein the sampling data information includes voltage sampling information, current sampling information, active power information, power factor information, breaker position information, and knife switch position information.
5. The active power unbalance analysis and diagnosis method according to claim 2, wherein the measurement and control device information includes line measurement and control device information, bus measurement and control device information, transformer measurement and control device information and bus joint measurement and control device information.
6. The active power unbalance analysis and diagnosis method according to claim 5, wherein the step S30 specifically comprises the steps of:
s31: matching the information of the line measurement and control devices with the voltage levels of 220kv, 110kv, 35kv and 10kv with line element models with corresponding voltage levels;
s32: matching the bus measurement and control device information of 220kv, 110kv, 35kv and 10kv with bus element models of corresponding voltage grades;
s33: matching the information of the transformer measurement and control devices of 220kv, 110kv, 35kv and 10kv with transformer element models of corresponding voltage grades;
s34: matching the information of the bus-tie measurement and control device with 220kv, 110kv, 35kv and 10kv with a bus-tie element model with corresponding voltage level;
s35: and after the measurement and control device information is completely matched with the primary equipment element model, a primary main wiring system is generated.
7. An active power imbalance analysis and diagnosis system, comprising:
the model building module is used for building a primary equipment element model for primary equipment of the intelligent substation;
the parameter configuration module is used for carrying out parameter configuration on the primary equipment element model;
the importing identification module is used for importing the SCD file of the intelligent substation and identifying the measurement and control device information in the SCD file;
the matching generation module is used for matching the measurement and control device information with the primary equipment element model and generating a primary main wiring system
The extraction and formation module is used for extracting sampling data information of the measurement and control device and displaying and forming active power flow information in the primary equipment element model corresponding to the primary main wiring system;
the analysis and diagnosis module is used for analyzing and diagnosing the active power of the total station and the active power of each voltage class area;
the analytical diagnostic module includes:
the first diagnosis and analysis unit is used for calculating current, voltage and active power information of 220kv, 110kv, 35kv and 10kv sides of the total station, comprehensively diagnosing whether the active power of the total station is balanced, and determining an active imbalance area according to voltage levels when the active power of the total station is unbalanced;
the second diagnosis and analysis unit is used for comparing the 220kV voltage level region line, the 220kV main transformer side, the bus voltage and current information with bus voltage information of corresponding voltage levels when the total station active power is unbalanced, comprehensively calculating whether the active power in the 220kV voltage level region is balanced or not, and obtaining that the active power unbalance factors are abnormal 220kV voltage acquisition, three-phase current unbalance, CT current transformer precision or CT current transformer fault, PT transformer precision or PT transformer fault if the active power unbalance factors are unbalanced;
the third diagnosis and analysis unit is used for comparing the 110kV voltage level area line, the 110kV main transformer side, the bus voltage and current information with the bus voltage information of the corresponding voltage level when the total station active power is unbalanced, comprehensively calculating whether the active power in the 110kV voltage level area is balanced or not, and obtaining that the active power unbalance factor is 110kV voltage acquisition abnormality, three-phase current unbalance, CT current transformer precision or CT current transformer fault, PT transformer precision or PT transformer fault if the active power unbalance factor is unbalanced;
the fourth diagnosis analysis unit is used for comparing the 35kV voltage class area line, the 22035kV main transformer side, the bus voltage and current information with bus voltage information of corresponding voltage classes when the total station active power is unbalanced, comprehensively calculating whether the active power in the 35kV voltage class area is balanced or not, and obtaining that the active power unbalance factors are abnormal 35kV voltage acquisition, three-phase current unbalance, CT current transformer precision or CT current transformer fault, PT transformer precision or PT transformer fault if the active power unbalance factors are unbalanced;
the fifth diagnosis and analysis unit is used for comparing the line, the 10kV main transformer side, the bus voltage and current information of the 10kV voltage class area with the bus voltage information of the corresponding voltage class when the total station active power is unbalanced, comprehensively calculating whether the active power of the 10kV voltage class area is balanced or not, and obtaining that the active power unbalance factors are 10kV voltage acquisition abnormality, three-phase current unbalance, CT current transformer precision or CT current transformer fault, PT transformer precision or PT transformer fault if the active power unbalance factors are unbalanced;
the sixth diagnostic analysis unit is used for analyzing current, voltage, active power and reactive power information of the 220kv, 110kv, 35kv and 10kv sides of the transformer in combination with the configured transformer load loss rate to obtain an active power unbalance factor as transformer load loss;
and a seventh diagnosis and analysis unit, which is used for analyzing the current, voltage, active power and reactive power information of the transformer 220kv, 110kv, 35kv and 10kv sides in combination with the configuration transformer impedance and the variable bit property to obtain the active power unbalance factors which are the abnormal voltage of the transformer system and the abnormal voltage of the outlet.
8. A computer device comprising a memory, a processor and a computer program stored in the memory and executable on the processor, characterized in that the processor implements the active power imbalance analysis diagnostic method according to any one of claims 1 to 6 when executing the computer program.
CN202010602847.2A 2020-06-29 2020-06-29 Active power unbalance rate analysis and diagnosis method, system and computer equipment Active CN111737875B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010602847.2A CN111737875B (en) 2020-06-29 2020-06-29 Active power unbalance rate analysis and diagnosis method, system and computer equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010602847.2A CN111737875B (en) 2020-06-29 2020-06-29 Active power unbalance rate analysis and diagnosis method, system and computer equipment

Publications (2)

Publication Number Publication Date
CN111737875A CN111737875A (en) 2020-10-02
CN111737875B true CN111737875B (en) 2023-09-26

Family

ID=72651677

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010602847.2A Active CN111737875B (en) 2020-06-29 2020-06-29 Active power unbalance rate analysis and diagnosis method, system and computer equipment

Country Status (1)

Country Link
CN (1) CN111737875B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112199367B (en) * 2020-12-04 2021-03-09 中国电力科学研究院有限公司 A method and system for long-term power balance verification and big data analysis

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103701116A (en) * 2013-12-11 2014-04-02 云南电力试验研究院(集团)有限公司电力研究院 Novel intelligent electric quantity balance method adopting power real-time operation
CN104502691A (en) * 2014-12-24 2015-04-08 镇江长河电力技术有限公司 Online monitoring and analysis device for energy efficiency of distribution transformer
CN107748954A (en) * 2017-10-17 2018-03-02 国网江苏省电力公司盐城供电公司 A kind of transformer station's balancing monitor and control system
CN107944680A (en) * 2017-11-16 2018-04-20 国网江苏省电力有限公司 A kind of substation's electric energy balance monitoring method based on intelligent electric energy meter
CN108879654A (en) * 2018-06-04 2018-11-23 国网浙江省电力有限公司 Based on telemetering unusual fluctuation unit exception remote diagnostic method

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101924364B (en) * 2010-07-23 2013-05-01 清华大学 Method for estimating nonlinear state of substation-dispatching center two-stage distributed power grid
EP2485358B2 (en) * 2011-02-07 2021-12-22 Siemens Gamesa Renewable Energy A/S System and method for mitigating an electric unbalance of a three-phase current at a Point of Common Coupling between a wind farm and a power grid

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103701116A (en) * 2013-12-11 2014-04-02 云南电力试验研究院(集团)有限公司电力研究院 Novel intelligent electric quantity balance method adopting power real-time operation
CN104502691A (en) * 2014-12-24 2015-04-08 镇江长河电力技术有限公司 Online monitoring and analysis device for energy efficiency of distribution transformer
CN107748954A (en) * 2017-10-17 2018-03-02 国网江苏省电力公司盐城供电公司 A kind of transformer station's balancing monitor and control system
CN107944680A (en) * 2017-11-16 2018-04-20 国网江苏省电力有限公司 A kind of substation's electric energy balance monitoring method based on intelligent electric energy meter
CN108879654A (en) * 2018-06-04 2018-11-23 国网浙江省电力有限公司 Based on telemetering unusual fluctuation unit exception remote diagnostic method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
Yan Xu等.Yan Xu等.《2008 40th North American Power Symposium》.2009,第1-7页. *
洪训山.一起变电站母线电量不平衡问题查处和分析.《中国电业(技术版)》.2015,第56-59页. *

Also Published As

Publication number Publication date
CN111737875A (en) 2020-10-02

Similar Documents

Publication Publication Date Title
US8805666B2 (en) Method for calculating primary time constant of power grid
CN102332709B (en) A digital simulation method and system for equivalent HVDC transmission DC protection
CN110441641A (en) A kind of small current earthing wire-selecting method and system based on Zero sequence DC component
CN108733928B (en) SCD file virtual circuit automatic checking method based on intermediate model file
CN112883592B (en) Full-electromagnetic transient modeling method for power grid
CN203276027U (en) Digital dynamic closed-loop test system of electricity smooth and steady supply device
CN104142448A (en) Method for automatically checking protection functions of microcomputer main-transformer differential protection device
Li et al. An integrated online dynamic security assessment system for improved situational awareness and economic operation
CN106528968A (en) Intelligent substation automatic dynamic simulation test method based on SSD file
Al-bayaty et al. Electrical distribution grid of Kirkuk City: A case study of load flow and short circuit valuation using ETAP
CN111737875B (en) Active power unbalance rate analysis and diagnosis method, system and computer equipment
CN103064054B (en) The matrix majorization method of electric power meter analogue system and wiring thereof
Jedrzejczak et al. Transition rates assessment of protective relay reliability models with incomplete data
KR101243216B1 (en) Control system for detecting a electric power chain in wide area
CN117390700B (en) Method, device and computer equipment for determining verification data of relay protection system
CN104317987A (en) Error analysis method for simulating calculation of short-circuit current
Tuhin et al. Integrative Fault Analysis of Transmission Lines using MATLAB and ETAP
CN117271788A (en) Intelligent monitoring method and system for electric power secondary system based on knowledge graph
CN105391058A (en) A network topology analysis method for error prevention in regional power grid
Huang et al. Extracting substation cyber-physical architecture through intelligent electronic devices' data
Platero et al. Novel adaptive 100% stator ground fault protection based on the third harmonic measurement
CN109446722B (en) PSD-based transformer substation main transformer zero-sequence parameter batch processing calculation method
CN114527327A (en) Voltage disturbance quantity-based transformer leakage reactance measuring method and system
CN114200354A (en) Zero sequence CT polarity online detection method, system and equipment
CN107968387B (en) Means of relay controlling based on impedance plane analysis positive sequence polarization voltage

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant