CN111583750A - Standard line construction training frame - Google Patents

Standard line construction training frame Download PDF

Info

Publication number
CN111583750A
CN111583750A CN202010586863.7A CN202010586863A CN111583750A CN 111583750 A CN111583750 A CN 111583750A CN 202010586863 A CN202010586863 A CN 202010586863A CN 111583750 A CN111583750 A CN 111583750A
Authority
CN
China
Prior art keywords
training frame
standard line
arc
standard
line construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010586863.7A
Other languages
Chinese (zh)
Inventor
张琦
张玉
连志纯
朱亚辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Borderless Aviation Technology Co ltd
Original Assignee
Jiangsu Borderless Aviation Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Borderless Aviation Technology Co ltd filed Critical Jiangsu Borderless Aviation Technology Co ltd
Priority to CN202010586863.7A priority Critical patent/CN111583750A/en
Publication of CN111583750A publication Critical patent/CN111583750A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G09EDUCATION; CRYPTOGRAPHY; DISPLAY; ADVERTISING; SEALS
    • G09BEDUCATIONAL OR DEMONSTRATION APPLIANCES; APPLIANCES FOR TEACHING, OR COMMUNICATING WITH, THE BLIND, DEAF OR MUTE; MODELS; PLANETARIA; GLOBES; MAPS; DIAGRAMS
    • G09B9/00Simulators for teaching or training purposes
    • GPHYSICS
    • G09EDUCATION; CRYPTOGRAPHY; DISPLAY; ADVERTISING; SEALS
    • G09BEDUCATIONAL OR DEMONSTRATION APPLIANCES; APPLIANCES FOR TEACHING, OR COMMUNICATING WITH, THE BLIND, DEAF OR MUTE; MODELS; PLANETARIA; GLOBES; MAPS; DIAGRAMS
    • G09B23/00Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes
    • G09B23/06Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes for physics
    • G09B23/18Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes for physics for electricity or magnetism

Landscapes

  • Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Educational Administration (AREA)
  • Educational Technology (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Mathematical Physics (AREA)
  • Pure & Applied Mathematics (AREA)
  • Algebra (AREA)
  • Rehabilitation Tools (AREA)

Abstract

The invention discloses a standard line construction training frame which is composed of an upright post and a bottom supporting plate, wherein the upright post and the bottom supporting plate are vertically installed, the angle formed by the upright post and the bottom supporting plate is ninety degrees, two ends of the bottom supporting plate are grounding areas, the upright post and the bottom supporting plate are fixed through a supporting rod, and an arc-shaped training frame is installed on the upright post. This real standard line construction training frame, all standard line components include the inspection of standard line stranded bundle, the decomposition of plug etc, standard line components contains circuit shielded wire crimping method, the crimping method of dead joint, the bundy piece needs two kinds of fixers, the slidingtype includes two kinds of guide rails, the plug, it has to move forward the formula, moving backward the formula in increasing, wire can not add, the place of installation relay in addition jump switch and pilot lamp can, this real training frame can help the student in understanding aircraft electronic circuit logic, accomplish the training of all kinds of electronic circuits simultaneously.

Description

Standard line construction training frame
Technical Field
The invention relates to the field of practical training frames, in particular to a practical training frame for standard line construction.
Background
The standard line construction training frame is used for teaching and training and simulating an airplane line for training and construction;
in the past, only the training of line construction is carried out, and the training effect cannot be achieved by logically combining the training with a real airplane electronic circuit, so that a standard line construction training frame is provided.
Disclosure of Invention
Aiming at the defects of the prior art, the invention provides the following technical scheme: the utility model provides a real standard frame of standard circuit construction, this real standard frame of construction comprises stand and bottom support plate, the stand is installed with the bottom support plate is perpendicular, and the stand is ninety degrees with bottom support plate institute angle, bottom support plate's both ends are the ground connection region, just it is fixed through the bracing piece between stand and the bottom support plate, install the real standard frame of arc on the stand, the real surface one side of putting up of this arc is installed the panel to the real standard frame of this arc is last to have seted up a plurality of standard tracks.
Preferably, the number of the support rods is three, the three support rods are sequentially arranged at two ends and the inner side of the bottom support plate, and included angles between the three support rods and the stand column are forty-five degrees.
Preferably, the panel is mounted on the outer surface of the arc-shaped training frame through screws and bolts.
Preferably, the base is installed to four corners in bottom of bottom sprag board, the base passes through the screw installation in bottom sprag board lower extreme.
Preferably, the ground area is an arc-shaped structure.
Preferably, the arc training frame has a specification of 2400MM 1200MM 1800 MM.
Preferably, the arc-shaped practical training frame is made of square steel, the angle section is made of a steel plate with the thickness of 6MM, and the two sides of the arc-shaped practical training frame are made of airplane skins.
Compared with the prior art, the invention has the following beneficial effects: this real standard line construction training frame, all standard line components include the inspection of standard line stranded bundle, the decomposition of plug etc, standard line components contains circuit shielded wire crimping method, the crimping method of dead joint, the bundy piece needs two kinds of fixers, the slidingtype includes two kinds of guide rails, the plug, it has to move forward the formula, moving backward the formula in increasing, wire can not add, the place of installation relay in addition jump switch and pilot lamp can, this real training frame can help the student in understanding aircraft electronic circuit logic, accomplish the training of all kinds of electronic circuits simultaneously.
Drawings
FIG. 1 is a schematic overall structure diagram of a standard line construction training frame according to the present invention;
FIG. 2 is a front view of a standard line construction training frame of the present invention;
FIG. 3 is a left side view of a standard line construction training frame of the present invention;
FIG. 4 is a right side view of the standard line construction training frame of the present invention;
in the figure: 1. an arc training frame; 2. a panel; 3. a standard track; 4. a bottom support plate; 5. a column; 6. a support bar; 7. a ground region; 8. a base.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-4, the invention discloses a standard line construction training frame, which is composed of an upright post 5 and a bottom support plate 4, wherein the upright post 5 and the bottom support plate 4 are vertically installed, an angle formed by the upright post 5 and the bottom support plate 4 is ninety degrees, two ends of the bottom support plate 4 are grounding areas 7, the upright post 5 and the bottom support plate 4 are fixed through a support rod 6, an arc-shaped training frame 1 is installed on the upright post 5, a panel 2 is installed on one side of the outer surface of the arc-shaped training frame 1, and a plurality of standard rails 3 are arranged on the arc-shaped training frame 1.
The number of the support rods 6 is three, the three support rods 6 are sequentially arranged at two ends and the inner side of the bottom support plate 4, and included angles between the three support rods 6 and the stand column 5 are forty-five degrees.
The panel 2 is installed on the outer surface of the arc training frame 1 through screws and bolts.
Base 8 is all installed to four corners in bottom of bottom sprag board 4, base 8 passes through the screw installation in bottom sprag board 4 lower extreme.
The ground region 7 is of an arcuate configuration.
The arc training frame 1 has the specification of 2400MM 1200MM 1800 MM.
The arc training frame 1 is made of square steel, angle bars are made of steel plates 6MM thick, and two sides of the arc training frame are made of airplane skins.
It should be noted that, after the standard line construction training frame is connected with electricity, the panel 2 can present a specific circuit power-on condition, so that a trainee can be trained to perform troubleshooting by setting a relevant circuit fault through the logic, and the troubleshooting process can be used for performing the following series of exercises:
a. installing MIL-C-26500 series BACC45FT plug, BACC45FN socket: the plug can be repaired, the plug and the socket can be assembled, and the tail clamp of the plug can be disassembled and adjusted; practice such as plug pin withdrawing and pressing;
b. a ground region 7; the grounding pile can be disassembled and assembled, the grounding resistance can be measured, the BACT12AC series lug part number can be selected, and the crimping can be exercised;
c. mounting a 280W555 series terminal junction block and a standard track 3, and allowing the junction block to be disassembled and assembled, identifying marks, withdrawing a plug pin of the junction block and performing crimping practice;
d. installing a circuit switch and controlling a switch to be used for circuit switch and switch dismounting practice;
e. the crossed wire bundle area is bundled in advance according to the requirements of an SWPM manual and can be used for the protection construction practice of the crossed wire bundle;
f. the grounding plug with the shielding cable is installed, so that the common shielding ground wire can be led out for construction practice and repair of the shielding cable;
g. the single wire bundle laying area can be used for special bundling display and practice of standard wire bundle bundling (pressurization area and high-earthquake area);
k. installing a high-frequency cable, and repairing the cable, repairing a shielding layer and manufacturing a high-frequency joint;
and l, installing a D436-37 standard butt joint splicing pipe for wire splicing repair practice, insulation layer repair practice and thermal shrinkage practice.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a real standard frame of standard line construction, this real standard frame of construction comprises stand (5) and bottom sprag board (4), its characterized in that: the utility model discloses a real standard rail, including stand (5), bottom support plate (4), stand (5) and bottom support plate (4) are installed perpendicularly, and stand (5) and bottom support plate (4) are the angle and are ninety degrees, the both ends of bottom support plate (4) are ground connection region (7), just it is fixed through bracing piece (6) between stand (5) and bottom support plate (4), install real standard frame (1) of arc on stand (5), panel (2) are installed to the surface one side of real standard frame (1) of this arc to a plurality of standard rails (3) have been seted up on real standard frame (1) of this arc.
2. The standard line construction training frame according to claim 1, which is characterized in that: the number of the support rods (6) is three, the three support rods (6) are sequentially arranged at two ends and the inner side of the bottom support plate (4), and included angles between the three support rods (6) and the upright columns (5) are forty-five degrees.
3. The standard line construction training frame according to claim 1, which is characterized in that: the panel (2) is installed on the outer surface of the arc training frame (1) through screws and bolts.
4. The standard line construction training frame according to claim 1, which is characterized in that: base (8) are all installed to four corners in bottom of bottom sprag board (4), base (8) pass through the screw and install in bottom sprag board (4) lower extreme.
5. The standard line construction training frame according to claim 1, which is characterized in that: the grounding area (7) is of an arc-shaped structure.
6. The standard line construction training frame according to claim 1, which is characterized in that: the arc training frame (1) is 2400MM 1200MM 1800MM in specification.
7. The standard line construction training frame according to claim 1, which is characterized in that: the arc-shaped practical training frame (1) is made of square steel, angle bars are made of steel plates 6MM thick, and aircraft skins are adopted on two sides of the arc-shaped practical training frame.
CN202010586863.7A 2020-06-24 2020-06-24 Standard line construction training frame Pending CN111583750A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010586863.7A CN111583750A (en) 2020-06-24 2020-06-24 Standard line construction training frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010586863.7A CN111583750A (en) 2020-06-24 2020-06-24 Standard line construction training frame

Publications (1)

Publication Number Publication Date
CN111583750A true CN111583750A (en) 2020-08-25

Family

ID=72114690

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010586863.7A Pending CN111583750A (en) 2020-06-24 2020-06-24 Standard line construction training frame

Country Status (1)

Country Link
CN (1) CN111583750A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113799863A (en) * 2021-10-28 2021-12-17 西安航空学院 Equipment for carrying airplane skin parts

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113799863A (en) * 2021-10-28 2021-12-17 西安航空学院 Equipment for carrying airplane skin parts

Similar Documents

Publication Publication Date Title
CN111583750A (en) Standard line construction training frame
CN108806383A (en) Distribution training frame and distribution Training Methodology
CN212084427U (en) Standard line construction training frame
CN203932871U (en) A kind of Novel cable fixture
CN201812416U (en) Power distribution training system for electricians
CN201518182U (en) Generic cabling practical training wall apparatus
CN113327476A (en) Installation and maintenance skill training and identification device for comprehensive wiring system
CN114243464A (en) Urban area high-low voltage power distribution system management and control terminal
CN201622762U (en) Module combined car electrical equipment training platform
CN115308570A (en) Aging test equipment and test method for PCBA (printed circuit board assembly)
CN210039205U (en) LED photoelectric technology training platform
CN203520722U (en) Intelligent building comprehensive lightning-protection technology practical training apparatus
CN102296842A (en) Operation shed frame for mounting cable accessory
CN208722423U (en) A kind of teaching building engineering experimental exercising apparatus for checking
CN219916517U (en) Special bench for airplane standard line construction operation competition
CN102376180A (en) Distribution training system for electrician
CN218770721U (en) Splicing piece for electric cabinet and electric cabinet framework using splicing piece
CN217036523U (en) Operating console for assembling ring main unit
CN211923152U (en) Glass curtain wall
CN220336178U (en) A pin-connected panel connection structure for adjacent large-span building cuts off
CN114374165B (en) Split type modularization installation low-voltage distribution cabinet
CN215564998U (en) Detachable noise prevention and control board for construction
CN214847193U (en) Real device frame that instructs of electrician's skill
CN216242937U (en) Special steel structure antidetonation support of warm ventilation pipe in natural gas long distance pipeline compressor room
CN203881805U (en) Multifunctional test stand

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination