CN111575438A - Mounting method of full-suspension four-point meshing type super-large converter - Google Patents

Mounting method of full-suspension four-point meshing type super-large converter Download PDF

Info

Publication number
CN111575438A
CN111575438A CN202010244251.XA CN202010244251A CN111575438A CN 111575438 A CN111575438 A CN 111575438A CN 202010244251 A CN202010244251 A CN 202010244251A CN 111575438 A CN111575438 A CN 111575438A
Authority
CN
China
Prior art keywords
bearing
trunnion
converter
ring
hoisting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010244251.XA
Other languages
Chinese (zh)
Other versions
CN111575438B (en
Inventor
王敏
杨俊�
石席龙
程权民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN202010244251.XA priority Critical patent/CN111575438B/en
Publication of CN111575438A publication Critical patent/CN111575438A/en
Application granted granted Critical
Publication of CN111575438B publication Critical patent/CN111575438B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21CPROCESSING OF PIG-IRON, e.g. REFINING, MANUFACTURE OF WROUGHT-IRON OR STEEL; TREATMENT IN MOLTEN STATE OF FERROUS ALLOYS
    • C21C5/00Manufacture of carbon-steel, e.g. plain mild steel, medium carbon steel or cast steel or stainless steel
    • C21C5/28Manufacture of steel in the converter
    • C21C5/42Constructional features of converters

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Manufacturing & Machinery (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Carbon Steel Or Casting Steel Manufacturing (AREA)

Abstract

The invention relates to the field of installation of large metallurgical equipment, in particular to a method for installing a full-suspension four-point meshing type super-large converter; it is characterized in that; mounting a converter bearing support base plate; finishing the installation of the main beam of the structural frame of the operation platform in front of the furnace; mounting a bearing support; assembling a trunnion bearing and a bearing seat of the trunnion ring; hoisting a backing ring; hoisting a furnace shell; the transmission mechanism of the tilting device is arranged in the trunnion; the converter integrally slides; the furnace body installation is completed; assembling a tangential key; and (5) polishing by using a cutting machine, and confirming that the gap between the end cover and the key is zero. The invention is optimized and improved on the original pushing installation method of large-scale converter equipment, and has the advantages of reducing the potential safety and quality hazards in the process of turning over the upper and lower furnace shells in the traditional 'pushing installation method' of the oversize converter, and ensuring that the converter is installed more scientifically, safely and economically.

Description

Mounting method of full-suspension four-point meshing type super-large converter
Technical Field
The invention relates to the field of installation of large metallurgical equipment, in particular to a method for installing a full-suspension four-point meshing type super-large converter.
Background
In-process, reinforced metallurgical bridge crane strides hoists alone to the trunnion ring in to last furnace shell, set up anti-tilt device, recycle reinforced metallurgical bridge crane strides and carries out whole 180 stands up to trunnion ring and last furnace shell, it is fixed, at last the lower stove outer covering of hoist and mount again, group is right on the trunnion ring, the alignment is upper, lower stove outer covering, control welding seam misalignment deviation, utilize sliding beam and synchronous hydraulic jack to carry out the whole slip to the trunnion ring at last, the stove outer covering, tilting device, whole process of sliding, the operation is fairly simple, but also has the shortcoming: 1. the whole furnace shell turning process is relatively complex, and the furnace shell turning process is frequently used for a charging cross-metallurgy bridge crane; 2. the upper furnace shell and the lower furnace shell are assembled in the high altitude, and a temporary safety measure platform is required to be built to ensure the safe welding of the furnace shells; 3. in the aspect of quality, the upper furnace shell and the lower furnace shell are assembled at high altitude, the deviation of the staggered joints is difficult to control, and the welding quality of the furnace shells is higher in requirement and needs 100% detection by an air gouging back chipping and an ultrasonic pen, so that the assembling and welding quality of the high altitude furnace shells is difficult to control.
Disclosure of Invention
The invention aims to overcome the defects and provide a safe, reliable and efficient mounting method of a full-suspension four-point meshing type super-large converter.
In order to achieve the above object, the present invention is realized by:
a method for installing a full-suspension four-point meshing type super-large converter comprises
Step 1, early preparation;
step 1.1, basic handover acceptance, center target plate and elevation datum point burying and measuring;
step 1.2, checking and retesting the center distance, the verticality and the elevation of the foundation bolt;
step 1.3, mounting a converter bearing support base plate;
step 1.4, the special inspection and acceptance of the charging cross 450/80t metallurgical bridge crane are completed, and the plant is closed;
step 1.5, dismantling a charging cross 450/80t metallurgical bridge crane hook, and designing and manufacturing a support;
step 1.6, finishing the installation of a main beam of a structural frame of a furnace front operation platform with a charging span of +11.35 m;
step 2, mounting a bearing support;
step 2.1, hoisting the bearing support to a converter foundation by using a truck crane, and adjusting the elevation of the upper surface of the equipment base, the longitudinal and transverse center line A, B, the levelness D, E, the support intervals L1 and L2 and the deviation of the diagonals L3 and L4 of the two bases according to the requirements of installation specifications so as to enable the bearing support to meet the installation requirements;
step 2.2, 11.35m furnace front platform installation and sliding beam support foundation construction
The main beam of the structural frame of the operating platform in front of the furnace with the charging span of +11.35m is completely installed, and partial secondary beams and structures are not installed first, and no area is installed; the converter integrally moves on the sliding beam in a traversing way, the supporting structure for installing the sliding beam has strong stability, the stand column is arranged to increase the rigidity of the beam, the design of civil engineering and steel structure of a platform in front of the converter is combined to carry out individual deepened design and optimization, the civil engineering cushion cap foundation widening and thickening measures and the steel structure are utilized to increase the sliding beam sliding stand column, and the sliding tracks are arranged at the driving end and the moving end, so that the integral sliding of the converter is ensured; throwing parallel lines of a longitudinal central line and a transverse central line of the converter on the sliding beam by using a theodolite;
step 2.3, assembling a trunnion bearing and a bearing seat of the backing ring: the assembly is carried out by heating the bearing. The principle is that the diameter of the bearing hole is expanded to a certain value by heating the bearing, and the bearing is installed in a trunnion matched with the bearing hole.
Step 2.3.1, calculating the heating temperature of the bearing: after the trunnion and the bearing reach the site, firstly measuring the interference magnitude of the trunnion and the bearing, wherein in order to ensure that the hot-charging operation is convenient and reliable, the heating temperature is required to ensure that the expansion magnitude of the hole reaches about 2-3 times of the actually measured interference magnitude or the interference magnitude is added with a gap of 0.2-0.4 mm, and the highest temperature of the heating oil is not more than 110 ℃;
heating calculation formula:
Figure 760311DEST_PATH_IMAGE002
in the formula: t- -heating temperature; i-actually measuring interference magnitude mm; k- -coefficient of expansion of the heating material 1/deg.C; d-the matching diameter is mm; t0- -ambient temperature
Step 2.3.2, assembling the bearing and the trunnion: before heating the bearing, firstly installing components such as a bearing spacer ring, a dust ring, a sealing gasket and the like on the inner side of the trunnion, carefully checking a drawing, confirming the qualification and heating the bearing after no leakage exists; respectively manufacturing a tool for hot-mounting a bearing on a transmission side and a bearing on a non-transmission side by using [14 channel steel, clamping and fixing the bearing, taking the heated bearing out of an oil tank by using an 450/80t bridge crane, turning the bearing by 90 degrees by using a manual hoist to enable the end surface of the bearing to be vertical to the ground, then stably moving the 450/80t bridge crane to enable an inner hole of the bearing to be aligned with a trunnion, respectively mounting the bearing on the trunnion on the rotation side and the trunnion on the free side, mounting a spacer ring, a sealing gasket and a dust ring on the inner side of the trunnion before mounting the bearing, and finally assembling a bearing support, a sealing ring, a sealing cover, a spacer ring and a bearing fixer;
step 2.4, lifting the backing ring
(1) After the trunnion ring is on site, placing the trunnion ring on a ground steel pier, and assembling the trunnion bearing;
(2) assembling bearing seats on the transmission side and the non-transmission side in place on the ground;
(3) hoisting the trunnion ring with the installed bearing seat to the sliding beam;
(4) turning the backing ring for 180 degrees, and installing the hanging device on the backing ring according to the correct installation position;
(5) welding and fixing the trunnion ring and the bearing seat by using an auxiliary support measure so as to prevent the trunnion ring from tipping;
hoisting the steel wire rope by using 4 fiber core steel wire rope lifting lugs with the diameter of phi 90mm (6 x 37), wherein the tensile strength is 1770 MPa, and the length is 16 m;
step 2.5, hoisting the furnace shell
(1) Dismantling a plate hook of a 480t/80t heavy metallurgy bridge crane, and installing a converter shell hoisting support on a balance beam shaft sleeve of the 480t/80t heavy metallurgy bridge crane;
(2) the other end of the converter shell hoisting support is fixed at a water-cooled furnace mouth of the converter shell by using an M80 large hexagon bolt;
(3) a balancing beam shaft sleeve of a 480t/80t heavy metallurgy bridge crane is matched with a hoisting support, and the converter is integrally sleeved in a backing ring;
step 2.6, the tilting device transmission mechanism is installed into the trunnion
The hoisting steel wire rope adopts a phi 90mm (6 x 37) fiber core steel wire rope, the tensile strength is 1770 MPa, the hoisting is carried out at 4 points, and the length is 8 m;
2.7, sliding the converter integrally;
(1) the furnace body slides, two sliding beams are respectively provided with an electric hydraulic jack push top and a chain block traction bearing seat, and the two bearing seats synchronously and stably slide in the sliding process;
(2) after the furnace body slides in place, arranging hydraulic jacks on two sides of the two bearing supports respectively, synchronously jacking the two bearing supports, stably lifting the whole furnace body, removing the sliding plate, cleaning the joint surface of the bearing supports and the bearing supports, installing a positioning pin, synchronously and stably descending the jacks, aligning the assembly marks of the bearing supports and the bearing supports, checking the installation quality, fastening a connecting bolt, and finishing the installation of the furnace body;
step 2.8, assembling the tangential key; the sizes of two key groove wide edges B are measured and checked by an inside micrometer and a dial indicator and a gauge stand respectively, and it is confirmed that B2 and B1 are equal, namely, the working surfaces of the hole grooves are parallel, and the non-parallel holes can cause the variation of interference; the processed movable key and the inclined plane of the static key are subjected to painting inspection outside the hole again to prevent the inclined plane of the movable key from being scratched in the processing and cutting process, otherwise, the movable key and the inclined plane of the static key are subjected to coping. And hoisting the tangential key by a crane, loading the key into the key groove, impacting by a heavy traveling hammer of about 0.2t, cutting off redundant parts at a specified position, polishing by a cutting machine, and confirming that the gap between the end cover and the key is zero.
The invention is optimized and improved on the original pushing installation method of large-scale converter equipment, and has the advantages of reducing the potential safety and quality hazards in the process of turning over the upper and lower furnace shells in the traditional 'pushing installation method' of the oversize converter, and ensuring that the converter is installed more scientifically, safely and economically.
Detailed Description
The invention is further illustrated by the following specific examples.
A method for installing a full-suspension four-point meshing type super-large converter comprises
Step 1, early preparation;
step 1.1, basic handover acceptance, center target plate and elevation datum point burying and measuring;
step 1.2, checking and retesting the center distance, the verticality and the elevation of the foundation bolt;
step 1.3, mounting a converter bearing support base plate;
step 1.4, the special inspection and acceptance of the charging cross 450/80t metallurgical bridge crane are completed, and the plant is closed;
step 1.5, dismantling a charging cross 450/80t metallurgical bridge crane hook, and designing and manufacturing a support;
step 1.6, finishing the installation of a main beam of a structural frame of a furnace front operation platform with a charging span of +11.35 m;
step 2, mounting a bearing support;
step 2.1, hoisting the bearing support to a converter foundation by using a truck crane, and adjusting the elevation of the upper surface of the equipment base, the longitudinal and transverse center line A, B, the levelness D, E, the support intervals L1 and L2 and the deviation of the diagonals L3 and L4 of the two bases according to the requirements of installation specifications so as to enable the bearing support to meet the installation requirements;
step 2.2, 11.35m furnace front platform installation and sliding beam support foundation construction
The main beam of the structural frame of the operating platform in front of the furnace with the charging span of +11.35m is completely installed, and partial secondary beams and structures are not installed first, and no area is installed; the converter integrally moves on the sliding beam in a traversing way, the supporting structure for installing the sliding beam has strong stability, the stand column is arranged to increase the rigidity of the beam, the design of civil engineering and steel structure of a platform in front of the converter is combined to carry out individual deepened design and optimization, the civil engineering cushion cap foundation widening and thickening measures and the steel structure are utilized to increase the sliding beam sliding stand column, and the sliding tracks are arranged at the driving end and the moving end, so that the integral sliding of the converter is ensured; throwing parallel lines of a longitudinal central line and a transverse central line of the converter on the sliding beam by using a theodolite;
step 2.3, assembling a trunnion bearing and a bearing seat of the backing ring: the assembly is carried out by heating the bearing. The principle is that the diameter of the bearing hole is expanded to a certain value by heating the bearing, and the bearing is installed in a trunnion matched with the bearing hole.
Step 2.3.1, calculating the heating temperature of the bearing: after the trunnion and the bearing reach the site, firstly measuring the interference magnitude of the trunnion and the bearing, wherein in order to ensure that the hot-charging operation is convenient and reliable, the heating temperature is required to ensure that the expansion magnitude of the hole reaches about 2-3 times of the actually measured interference magnitude or the interference magnitude is added with a gap of 0.2-0.4 mm, and the highest temperature of the heating oil is not more than 110 ℃;
heating calculation formula:
Figure 739769DEST_PATH_IMAGE002
in the formula: t- -heating temperature; i-actually measuring interference magnitude mm; k- -coefficient of expansion of the heating material 1/deg.C; d-the matching diameter is mm; t0- -ambient temperature
Step 2.3.2, assembling the bearing and the trunnion: before heating the bearing, firstly installing components such as a bearing spacer ring, a dust ring, a sealing gasket and the like on the inner side of the trunnion, carefully checking a drawing, confirming the qualification and heating the bearing after no leakage exists; respectively manufacturing a tool for hot-mounting a bearing on a transmission side and a bearing on a non-transmission side by using [14 channel steel, clamping and fixing the bearing, taking the heated bearing out of an oil tank by using an 450/80t bridge crane, turning the bearing by 90 degrees by using a manual hoist to enable the end surface of the bearing to be vertical to the ground, then stably moving the 450/80t bridge crane to enable an inner hole of the bearing to be aligned with a trunnion, respectively mounting the bearing on the trunnion on the rotation side and the trunnion on the free side, mounting a spacer ring, a sealing gasket and a dust ring on the inner side of the trunnion before mounting the bearing, and finally assembling a bearing support, a sealing ring, a sealing cover, a spacer ring and a bearing fixer;
step 2.4, lifting the backing ring
(1) After the trunnion ring is on site, placing the trunnion ring on a ground steel pier, and assembling the trunnion bearing;
(2) assembling bearing seats on the transmission side and the non-transmission side in place on the ground;
(3) hoisting the trunnion ring with the installed bearing seat to the sliding beam;
(4) turning the backing ring for 180 degrees, and installing the hanging device on the backing ring according to the correct installation position;
(5) welding and fixing the trunnion ring and the bearing seat by using an auxiliary support measure so as to prevent the trunnion ring from tipping;
hoisting the steel wire rope by using 4 fiber core steel wire rope lifting lugs with the diameter of phi 90mm (6 x 37), wherein the tensile strength is 1770 MPa, and the length is 16 m;
step 2.5, hoisting the furnace shell
(1) Dismantling a plate hook of a 480t/80t heavy metallurgy bridge crane, and installing a converter shell hoisting support on a balance beam shaft sleeve of the 480t/80t heavy metallurgy bridge crane;
(2) the other end of the converter shell hoisting support is fixed at a water-cooled furnace mouth of the converter shell by using an M80 large hexagon bolt;
(3) a balancing beam shaft sleeve of a 480t/80t heavy metallurgy bridge crane is matched with a hoisting support, and the converter is integrally sleeved in a backing ring;
step 2.6, the tilting device transmission mechanism is installed into the trunnion
The hoisting steel wire rope adopts a phi 90mm (6 x 37) fiber core steel wire rope, the tensile strength is 1770 MPa, the hoisting is carried out at 4 points, and the length is 8 m;
2.7, sliding the converter integrally;
(1) the furnace body slides, two sliding beams are respectively provided with an electric hydraulic jack push top and a chain block traction bearing seat, and the two bearing seats synchronously and stably slide in the sliding process;
(2) after the furnace body slides in place, arranging hydraulic jacks on two sides of the two bearing supports respectively, synchronously jacking the two bearing supports, stably lifting the whole furnace body, removing the sliding plate, cleaning the joint surface of the bearing supports and the bearing supports, installing a positioning pin, synchronously and stably descending the jacks, aligning the assembly marks of the bearing supports and the bearing supports, checking the installation quality, fastening a connecting bolt, and finishing the installation of the furnace body;
step 2.8, assembling the tangential key; the sizes of two key groove wide edges B are measured and checked by an inside micrometer and a dial indicator and a gauge stand respectively, and it is confirmed that B2 and B1 are equal, namely, the working surfaces of the hole grooves are parallel, and the non-parallel holes can cause the variation of interference; the processed movable key and the inclined plane of the static key are subjected to painting inspection outside the hole again to prevent the inclined plane of the movable key from being scratched in the processing and cutting process, otherwise, the movable key and the inclined plane of the static key are subjected to coping. And hoisting the tangential key by a crane, loading the key into the key groove, impacting by a heavy traveling hammer of about 0.2t, cutting off redundant parts at a specified position, polishing by a cutting machine, and confirming that the gap between the end cover and the key is zero.
The invention is optimized and improved on the original pushing installation method of large-scale converter equipment, and has the advantages of reducing the potential safety and quality hazards in the process of turning over the upper and lower furnace shells in the traditional 'pushing installation method' of the oversize converter, and ensuring that the converter is installed more scientifically, safely and economically.

Claims (1)

1. A mounting method of a full-suspension four-point meshing type super-huge converter is characterized in that; comprises that
Step 1, early preparation;
step 1.1, basic handover acceptance, center target plate and elevation datum point burying and measuring;
step 1.2, checking and retesting the center distance, the verticality and the elevation of the foundation bolt;
step 1.3, mounting a converter bearing support base plate;
step 1.4, the special inspection and acceptance of the charging cross 450/80t metallurgical bridge crane are completed, and the plant is closed;
step 1.5, dismantling a charging cross 450/80t metallurgical bridge crane hook, and designing and manufacturing a support;
step 1.6, finishing the installation of a main beam of a structural frame of a furnace front operation platform with a charging span of +11.35 m;
step 2, mounting a bearing support;
step 2.1, hoisting the bearing support to a converter foundation by using a truck crane, and adjusting the elevation of the upper surface of the equipment base, the longitudinal and transverse center line A, B, the levelness D, E, the support intervals L1 and L2 and the deviation of the diagonals L3 and L4 of the two bases according to the requirements of installation specifications so as to enable the bearing support to meet the installation requirements;
step 2.2, 11.35m furnace front platform installation and sliding beam support foundation construction
The main beam of the structural frame of the operating platform in front of the furnace with the charging span of +11.35m is completely installed, and partial secondary beams and structures are not installed first, and no area is installed; the converter integrally moves on the sliding beam in a traversing way, the supporting structure for installing the sliding beam has strong stability, the stand column is arranged to increase the rigidity of the beam, the design of civil engineering and steel structure of a platform in front of the converter is combined to carry out individual deepened design and optimization, the civil engineering cushion cap foundation widening and thickening measures and the steel structure are utilized to increase the sliding beam sliding stand column, and the sliding tracks are arranged at the driving end and the moving end, so that the integral sliding of the converter is ensured; throwing parallel lines of a longitudinal central line and a transverse central line of the converter on the sliding beam by using a theodolite;
step 2.3, assembling a trunnion bearing and a bearing seat of the backing ring: assembling by heating the bearing;
the principle is that the diameter of a bearing hole is expanded to a certain value by heating the bearing, and the bearing is arranged in a trunnion matched with the bearing hole;
step 2.3.1, calculating the heating temperature of the bearing: after the trunnion and the bearing reach the site, firstly measuring the interference magnitude of the trunnion and the bearing, wherein in order to ensure that the hot-charging operation is convenient and reliable, the heating temperature is required to ensure that the expansion magnitude of the hole reaches about 2-3 times of the actually measured interference magnitude or the interference magnitude is added with a gap of 0.2-0.4 mm, and the highest temperature of the heating oil is not more than 110 ℃;
heating calculation formula:
Figure RE-RE-DEST_PATH_IMAGE002
in the formula: t- -heating temperature; i-actually measuring interference magnitude mm; k- -coefficient of expansion of the heating material 1/deg.C; d-the matching diameter is mm; t0- -ambient temperature
Step 2.3.2, assembling the bearing and the trunnion: before heating the bearing, firstly installing components such as a bearing spacer ring, a dust ring, a sealing gasket and the like on the inner side of the trunnion, carefully checking a drawing, confirming the qualification and heating the bearing after no leakage exists; respectively manufacturing a tool for hot-mounting a bearing on a transmission side and a bearing on a non-transmission side by using [14 channel steel, clamping and fixing the bearing, taking the heated bearing out of an oil tank by using an 450/80t bridge crane, turning the bearing by 90 degrees by using a manual hoist to enable the end surface of the bearing to be vertical to the ground, then stably moving the 450/80t bridge crane to enable an inner hole of the bearing to be aligned with a trunnion, respectively mounting the bearing on the trunnion on the rotation side and the trunnion on the free side, mounting a spacer ring, a sealing gasket and a dust ring on the inner side of the trunnion before mounting the bearing, and finally assembling a bearing support, a sealing ring, a sealing cover, a spacer ring and a bearing fixer;
step 2.4, lifting the backing ring
(1) After the trunnion ring is on site, placing the trunnion ring on a ground steel pier, and assembling the trunnion bearing;
(2) assembling bearing seats on the transmission side and the non-transmission side in place on the ground;
(3) hoisting the trunnion ring with the installed bearing seat to the sliding beam;
(4) turning the backing ring for 180 degrees, and installing the hanging device on the backing ring according to the correct installation position;
(5) welding and fixing the trunnion ring and the bearing seat by using an auxiliary support measure so as to prevent the trunnion ring from tipping;
hoisting the steel wire rope by using 4 fiber core steel wire rope lifting lugs with the diameter of phi 90mm (6 x 37), wherein the tensile strength is 1770 MPa, and the length is 16 m;
step 2.5, hoisting the furnace shell
(1) Dismantling a plate hook of a 480t/80t heavy metallurgy bridge crane, and installing a converter shell hoisting support on a balance beam shaft sleeve of the 480t/80t heavy metallurgy bridge crane;
(2) the other end of the converter shell hoisting support is fixed at a water-cooled furnace mouth of the converter shell by using an M80 large hexagon bolt;
(3) a balancing beam shaft sleeve of a 480t/80t heavy metallurgy bridge crane is matched with a hoisting support, and the converter is integrally sleeved in a backing ring;
step 2.6, the tilting device transmission mechanism is installed into the trunnion
The hoisting steel wire rope adopts a phi 90mm (6 x 37) fiber core steel wire rope, the tensile strength is 1770 MPa, the hoisting is carried out at 4 points, and the length is 8 m;
2.7, sliding the converter integrally;
(1) the furnace body slides, two sliding beams are respectively provided with an electric hydraulic jack push top and a chain block traction bearing seat, and the two bearing seats synchronously and stably slide in the sliding process;
(2) after the furnace body slides in place, arranging hydraulic jacks on two sides of the two bearing supports respectively, synchronously jacking the two bearing supports, stably lifting the whole furnace body, removing the sliding plate, cleaning the joint surface of the bearing supports and the bearing supports, installing a positioning pin, synchronously and stably descending the jacks, aligning the assembly marks of the bearing supports and the bearing supports, checking the installation quality, fastening a connecting bolt, and finishing the installation of the furnace body;
step 2.8, assembling the tangential key; the sizes of two key groove wide edges B are measured and checked by an inside micrometer and a dial indicator and a gauge stand respectively, and it is confirmed that B2 and B1 are equal, namely, the working surfaces of the hole grooves are parallel, and the non-parallel holes can cause the variation of interference; the processed movable key and the inclined plane of the static key are subjected to painting inspection outside the hole again to prevent the inclined plane of the movable key from being scratched in the processing and cutting process, otherwise, the movable key and the inclined plane of the static key are subjected to coping;
and hoisting the tangential key by a crane, loading the key into the key groove, impacting by a heavy traveling hammer of about 0.2t, cutting off redundant parts at a specified position, polishing by a cutting machine, and confirming that the gap between the end cover and the key is zero.
CN202010244251.XA 2020-03-31 2020-03-31 Mounting method of full-suspension four-point meshing type super-large converter Active CN111575438B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010244251.XA CN111575438B (en) 2020-03-31 2020-03-31 Mounting method of full-suspension four-point meshing type super-large converter

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010244251.XA CN111575438B (en) 2020-03-31 2020-03-31 Mounting method of full-suspension four-point meshing type super-large converter

Publications (2)

Publication Number Publication Date
CN111575438A true CN111575438A (en) 2020-08-25
CN111575438B CN111575438B (en) 2022-03-15

Family

ID=72089725

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010244251.XA Active CN111575438B (en) 2020-03-31 2020-03-31 Mounting method of full-suspension four-point meshing type super-large converter

Country Status (1)

Country Link
CN (1) CN111575438B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101063177A (en) * 2006-04-29 2007-10-31 上海宝冶建设有限公司 Integral installation method for mammoth steel converter outer assemblage
CN102094106A (en) * 2011-03-21 2011-06-15 中国十九冶集团有限公司南京分公司 Quick installation method for large four-point suspended type converter
CN202543243U (en) * 2011-12-15 2012-11-21 中国十九冶集团有限公司南京分公司 Special assembling platform for hanging backing ring of four-point suspension type mammoth converter
CN104762438A (en) * 2015-03-23 2015-07-08 莱芜钢铁集团有限公司 A converter device replacing and installing method
CN110846463A (en) * 2019-11-04 2020-02-28 上海宝冶集团有限公司 Integral hoisting method for super-huge converter shell

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101063177A (en) * 2006-04-29 2007-10-31 上海宝冶建设有限公司 Integral installation method for mammoth steel converter outer assemblage
CN102094106A (en) * 2011-03-21 2011-06-15 中国十九冶集团有限公司南京分公司 Quick installation method for large four-point suspended type converter
CN202543243U (en) * 2011-12-15 2012-11-21 中国十九冶集团有限公司南京分公司 Special assembling platform for hanging backing ring of four-point suspension type mammoth converter
CN104762438A (en) * 2015-03-23 2015-07-08 莱芜钢铁集团有限公司 A converter device replacing and installing method
CN110846463A (en) * 2019-11-04 2020-02-28 上海宝冶集团有限公司 Integral hoisting method for super-huge converter shell

Also Published As

Publication number Publication date
CN111575438B (en) 2022-03-15

Similar Documents

Publication Publication Date Title
CN109231007B (en) Electric furnace body hoisting and mounting process
CN103801921B (en) Vertical sleeve kiln kiln shell installation method
CN105755205A (en) Combination-method mounting method of ultra-large converter
CN115162182B (en) Cantilever type steel box girder high-precision cable hoisting construction method
CN114183000A (en) Manufacturing and mounting construction method for outer tank steel dome of large-scale low-temperature storage tank
CN101367116A (en) Mounting technique of vertical conticaster for smelting copper
CN111827125A (en) Accurate adjustment method and device for installation line shape of steel upright post of arch bridge
CN103205526A (en) Pushing installation method for large converter
CN111235333A (en) Method for replacing furnace shell of blast furnace body part
CN107303941B (en) Derrick of marine drilling ship and centering installation method thereof
CN111575438B (en) Mounting method of full-suspension four-point meshing type super-large converter
CN101846450A (en) Installation method of big gear ring of rotary kiln
CN105773138B (en) O-shaped four-tipping car dumper mounting process
CN110963408B (en) Hoisting method for replacing high-altitude vertical equipment
CN202023298U (en) Roof truss-sectioned roof girder structure capable of being hoisted by cross type tower crane
CN101831916B (en) Method for mounting large-size sleeve bolt framework in combined type
CN114988309B (en) Installation and construction method of chlorination reaction kettle enamel equipment
CN105823329B (en) A kind of Rotary kiln installation construction method
CN109000483B (en) Electric furnace bottom insulation and furnace shell flip-chip process
CN113996882A (en) Large-scale tower equipment and tower-attached pipeline installation method
CN109266869B (en) Furnace cover upside-down mounting and furnace cover mounting process
CN110306420B (en) Pipe transportation device in pipe bridge and construction method thereof
CN112523111A (en) Steel box girder hoisting and splicing process
CN103510712A (en) Right-angled-Z-shaped aerial butt-joint construction method of multi-layer H-shaped steel columns
CN111826490B (en) Device and method for measuring and adjusting roundness of furnace shell wall of hot blast furnace

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant