CN111539570A - Tower crane type selection and arrangement optimization method and system for group towers - Google Patents

Tower crane type selection and arrangement optimization method and system for group towers Download PDF

Info

Publication number
CN111539570A
CN111539570A CN202010327982.0A CN202010327982A CN111539570A CN 111539570 A CN111539570 A CN 111539570A CN 202010327982 A CN202010327982 A CN 202010327982A CN 111539570 A CN111539570 A CN 111539570A
Authority
CN
China
Prior art keywords
tower crane
tower
arrangement
checking
hoisting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010327982.0A
Other languages
Chinese (zh)
Other versions
CN111539570B (en
Inventor
车辕
陈蕾
周子淇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
Original Assignee
China Construction First Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN202010327982.0A priority Critical patent/CN111539570B/en
Publication of CN111539570A publication Critical patent/CN111539570A/en
Application granted granted Critical
Publication of CN111539570B publication Critical patent/CN111539570B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06315Needs-based resource requirements planning or analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Physics & Mathematics (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Operations Research (AREA)
  • Development Economics (AREA)
  • Quality & Reliability (AREA)
  • Game Theory and Decision Science (AREA)
  • Educational Administration (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Jib Cranes (AREA)

Abstract

The invention discloses a tower crane model selection and arrangement optimization method aiming at a tower group, which comprises the steps of providing an initial tower crane model selection and arrangement scheme, coverage range checking, material distribution, collision checking, hoisting weight checking, construction period checking, economy checking and economy optimization. The method has strong man-machine interaction degree, gives full play to the experience advantages and subjective initiative of technicians in each link of tower crane type selection and arrangement, and performs refined calculation on the basis of a tower crane hoisting material information base and a tower crane single hoisting operation time calculation formula by means of strong calculation capacity of a computer to obtain an optimal tower crane type selection and arrangement scheme.

Description

Tower crane type selection and arrangement optimization method and system for group towers
Technical Field
The invention relates to the technical field of building construction, in particular to a tower crane type selection and arrangement optimization method and system aiming at tower groups.
Background
The tower crane is used as the most important vertical transportation equipment in building construction, and the selection and the arrangement of the tower crane can obviously influence the progress, the safety, the cost and the like of the project. Factors for determining the arrangement scheme of the tower crane comprise a building form, a total engineering hoisting capacity, a maximum hoisting weight, site conditions and the like, and influence of all factors on the type selection and the arrangement of the tower crane is not independent. For projects with fewer tower cranes, a better tower crane arrangement scheme can be obtained relatively easily in the analysis process; however, for tower group engineering, the relationship among all factors is more complex, the tower crane and the tower crane may influence each other, and an ideal tower crane arrangement scheme is difficult to obtain by experience alone.
The BIM technology is an engineering design and construction management tool with wide application, and a model of the BIM technology contains various information of a building and can be used as a foundation for cooperative work of units in the process of project design, construction and operation. In the process of tower crane model selection and arrangement, certain specific digital information in the BIM model can be extracted, and quantitative analysis such as coverage range check, collision check, hoisting weight check, construction period check, economic analysis and the like in the process of tower crane model selection and arrangement is carried out. The existing BIM-based tower crane arrangement comparison selection system is difficult in man-machine interaction, the experience advantages of technicians cannot be fully exerted, a construction period check module in the system does not give a clear calculation formula, the construction period calculation precision is not high, and the finally determined tower crane arrangement scheme is not the optimal scheme.
Disclosure of Invention
The invention aims to provide a tower crane model selection and arrangement optimization method aiming at a group tower, and aims to solve the technical problems of difficulty in man-machine interaction and low calculation accuracy in the prior art.
In order to achieve the technical purpose, the invention adopts the following technical scheme:
a tower crane model selection and arrangement optimization method aiming at tower groups comprises the following steps:
s1: giving an initial tower crane type selection and arrangement scheme, establishing a material information base of all the required tower cranes for hoisting and a database of each parameter of alternative tower cranes in the project, and giving the initial tower crane type selection and arrangement scheme on the basis;
s2: checking the coverage area, checking whether the proposed building and the material to be hoisted are both in the coverage area of the tower crane, if not, displaying the information of the proposed building or the material to be hoisted which does not fall into the coverage area in the system, adjusting the model, the number and the arrangement position of the tower crane, and checking the coverage area again;
s3: distributing materials, namely distributing all materials in a material information base according to the arrangement positions of the tower cranes, determining the materials to be hoisted by each tower crane respectively, and forming a material list of each tower crane;
s4: performing collision check, simulating the operation process of the tower crane, checking whether the tower crane collides with a building to be built and the tower crane, if so, displaying collision information in the system, adjusting the model and the arrangement position of the tower crane according to the information, and jumping to the step S2;
s5: checking the hoisting weight, checking whether each tower crane can meet the hoisting requirements of each material in the respective material list or not by contrasting the hoisting weight curve of each tower crane, if not, displaying the material information and the tower crane information which do not meet the requirements in the system, adjusting the type and the arrangement position of the tower crane according to the information, and jumping to the step S2;
s6: checking a construction period, respectively fitting a single hoisting operation time calculation formula for completing hoisting of different types of materials by using a statistical method according to operation time data of various types of tower cranes in the previous engineering, sequentially substituting specific material information in respective material lists of the tower cranes into the time calculation formula, summing to obtain the total operation time of the tower cranes, and if the total operation time is longer than the engineering construction period, adjusting the types, the number and the arrangement positions of the tower cranes and jumping to the step S2;
s7: the method comprises the following steps of (1) economy checking, calculating the total cost of each tower crane in the whole service process according to the economy parameter values of each tower crane, comparing the total cost with the budget cost of the tower crane of a proposed project, displaying the excess amount in a system and adjusting the type, quantity and arrangement position of the tower cranes if the budget cost is exceeded, and jumping to the step S2;
s8: and (4) optimizing economy, storing the tower crane arrangement scheme obtained in the step S6 as a candidate scheme by the system, sequentially replacing models of all tower cranes according to the cost reduction direction, replacing only one tower crane each time, skipping to the step S2, and outputting the candidate scheme as a final tower crane arrangement scheme if the requirements cannot be met after all the tower cranes are replaced once.
Preferably, the material information base is obtained on the basis of a Building Information Model (BIM) according to a construction method and construction deployment, and the material information recorded in the material information base comprises the types, the in-position heights, the plane coordinates and the weights of all materials to be hoisted in the project; the tower crane parameter database can be updated in real time, corresponding parameters of various types of tower cranes commonly used in the market are recorded, the parameters comprise technical parameters and economic parameters, the technical parameters comprise the arm length, the hoisting curve, the lifting speed, the rotating speed and the amplitude changing speed of various types of tower cranes, and the economic parameters comprise rent, tower crane foundation cost, operation and maintenance cost and attachment cost.
Preferably, the calculation formula of the single hoisting operation time of each tower crane in the step S6 is as follows,
Figure BDA0002463906540000021
in the formula: t isiThe single hoisting operation time of the tower crane;
t0-static time of tower crane operation process;
omega-tower crane rotation angular velocity;
v1-tower crane amplitude variation speed;
v2-the tower crane lifting speed;
theta is the rotation included angle of the tower crane in the single hoisting process;
r is the amplitude variation distance of the tower crane in the single hoisting process;
h, the lifting height of the tower crane in the single lifting process;
alpha-adjusting coefficients of the rotation time, the amplitude variation time and the lifting time of the tower crane, wherein the adjusting coefficients are obtained by statistical analysis and fitting of the previous engineering operation time data of various types of tower cranes.
Preferably, the material distribution in the step S3 follows a principle of being close, that is, all the materials are distributed to the tower crane closest to the plane where the material is located.
Preferably, the material distribution in step S3 may also follow an average distribution principle, and if the material is only within the coverage of a single tower crane, the material is distributed to the tower crane, and if the material is within the coverage of multiple tower cranes, the material is distributed to a tower crane with fewer hoisting tasks.
Preferably, the steps S4-S7 are sequentially adjustable.
In addition, the invention also provides a system based on the tower crane type selection and arrangement optimization method aiming at the tower group, which comprises an initial tower crane arrangement scheme generation module, a coverage range checking module, a material distribution module, a collision checking module, a hoisting weight checking module, a construction period checking module, an economy checking module and an economy optimization module which are respectively corresponding to the steps S1-S8, wherein the system also comprises a modification module which can be called by the coverage range checking module, the collision checking module, the hoisting weight checking module, the construction period checking module, the economy checking module and the economy optimization module and is used for adjusting the initial type, the number and the arrangement position of the tower crane.
Compared with the prior art, the invention has the beneficial effects that:
1. the invention has strong man-machine interaction degree, and gives full play to the experience advantages and subjective activity of technicians in each link of tower crane type selection and arrangement;
2. the invention applies a statistical analysis method to analyze the operation data of the tower cranes of various models in the prior engineering and fits a calculation formula of the single operation time for completing the hoisting of different types of materials by the tower cranes of various models. By means of the strong computing power of a computer, a series of fine calculations are performed on the basis of a tower crane hoisting material information base and a tower crane operation time calculation formula to obtain a tower crane arrangement scheme meeting various requirements of engineering construction, and then the economy of the tower crane arrangement scheme is further optimized to obtain an optimal tower crane type selection and arrangement scheme.
Drawings
The above and/or other aspects and advantages of the present invention will become more apparent and more readily appreciated from the detailed description taken in conjunction with the following drawings, which are meant to be illustrative, not limiting of the invention, and in which:
fig. 1 is a flowchart of a tower crane model selection and layout optimization method for tower groups according to the present invention.
Detailed Description
Hereinafter, embodiments of a tower crane model selection and arrangement optimization method and system for a group tower according to the present invention will be described with reference to the accompanying drawings. The examples described herein are specific embodiments of the present invention, are intended to be illustrative and exemplary in nature, and are not to be construed as limiting the scope of the invention. In addition to the embodiments described herein, those skilled in the art will be able to employ other technical solutions which are obvious based on the disclosure of the claims and the specification of the present application, and these technical solutions include technical solutions which make any obvious replacement or modification for the embodiments described herein.
The principles and features of this invention are described below in conjunction with the following drawings, which are set forth to illustrate, but are not to be construed to limit the scope of the invention. The preferred embodiment of the present invention is described in further detail below with reference to fig. 1:
as shown in fig. 1, a preferred method for selecting and optimizing tower crane types and layout for tower groups of towers of the present invention includes the following steps:
s1: giving an initial tower crane model selection and arrangement scheme, establishing a material information base needing to be hoisted by a tower crane and each parameter database of an alternative tower crane of the project, and giving the initial tower crane model selection and arrangement scheme by technical personnel on the basis of the initial tower crane model selection and arrangement scheme, wherein the material information base is obtained on the basis of a Building Information Model (BIM) according to a construction method and construction arrangement, and the material information recorded in the material information base comprises the types, the in-position heights, the plane coordinates and the weights of all materials to be hoisted by the project; the tower crane parameter database can be updated in real time, corresponding parameters of various types of tower cranes commonly used in the market are recorded, the parameters comprise technical parameters and economic parameters, the technical parameters comprise the arm length, the hoisting curve, the lifting speed, the rotating speed and the amplitude variation speed of various types of tower cranes, and the economic parameters comprise rent, tower crane foundation cost, operation and maintenance cost and attachment cost;
s2: checking the coverage area, checking whether the proposed building and the material to be hoisted are both in the coverage area of the tower crane, if not, displaying the information of the proposed building or the material to be hoisted which does not fall into the coverage area in the system, adjusting the model, the quantity and the arrangement position of the tower crane by a technician, and checking the coverage area again;
s3: distributing materials, namely distributing all materials in a material information base according to the arrangement positions of the tower cranes, determining the materials to be hoisted by each tower crane respectively, and forming a material list of each tower crane, wherein the material distribution follows the nearby principle or the average distribution principle, and the nearby principle is that all the materials are uniformly distributed to the tower crane closest to the plane position of the tower crane; according to the average distribution principle, if the material is only in the coverage range of a single tower crane, the material is distributed to the tower crane, and if the material is in the coverage ranges of a plurality of tower cranes, the material is distributed to a tower crane with few hoisting tasks;
s4: performing collision check, simulating the operation process of the tower crane, checking whether the tower crane collides with a building to be built and the tower crane, if so, displaying collision information in the system, adjusting the model and the arrangement position of the tower crane according to the information by a technician, and jumping to the step S2;
s5: checking the hoisting weight, checking whether each tower crane can meet the hoisting requirements of each material in the respective material list or not by contrasting the hoisting weight curve of each tower crane, if not, displaying the material information and the tower crane information which do not meet the requirements in the system, adjusting the model and the arrangement position of the tower crane by a technician according to the information, and jumping to the step S2;
s6: checking a construction period, respectively fitting a calculation formula of single hoisting operation time for completing hoisting of different types of materials by using a statistical method according to operation time data of various types of tower cranes in the prior engineering, sequentially substituting specific material information in respective material lists of the tower cranes into the time calculation formula, summing to obtain the total operation time of the tower cranes, adjusting the types, the number and the arrangement positions of the tower cranes by a technician if the total operation time is longer than the engineering construction period, skipping to the step S2, wherein the calculation formula of the single hoisting operation time of the tower cranes is as follows,
Figure BDA0002463906540000051
in the formula: t isiThe single hoisting operation time of the tower crane;
t0-static time of tower crane operation process;
omega-tower crane rotation angular velocity;
v1-tower crane amplitude variation speed;
v2-the tower crane lifting speed;
theta is the rotation included angle of the tower crane in the single hoisting process;
r is the amplitude variation distance of the tower crane in the single hoisting process;
h, the lifting height of the tower crane in the single lifting process;
alpha-adjusting coefficients of the rotation time, amplitude variation time and lifting time of the tower crane, wherein the adjusting coefficients are obtained by statistical analysis and fitting of the previous engineering operation time data of various types of tower cranes;
s7: the method comprises the following steps of (1) economy checking, calculating the total cost of each tower crane in the whole service process according to the economy parameter values of each tower crane, comparing the total cost with the budget cost of the tower crane of a proposed project, displaying the excess amount in a system if the budget cost is exceeded, adjusting the type, the number and the arrangement position of the tower cranes by a technician, and jumping to the step S2;
s8: optimizing economy, wherein the system stores the tower crane arrangement scheme obtained in the step S6 as an alternative scheme, sequentially changes models of all tower cranes according to the cost reduction direction, only changes one tower crane each time, jumps to the step S2, and outputs the alternative scheme as a final tower crane arrangement scheme if the requirements cannot be met after all the tower cranes are changed once;
wherein, the sequence of the steps S4-S7 is adjustable;
in addition, the invention also provides a system based on the tower crane type selection and arrangement optimization method aiming at the tower group, which comprises an initial tower crane arrangement scheme generation module, a coverage range checking module, a material distribution module, a collision checking module, a hoisting weight checking module, a construction period checking module, an economy checking module and an economy optimization module which are respectively corresponding to the steps S1-S8, wherein the system also comprises a modification module which can be called by the coverage range checking module, the collision checking module, the hoisting weight checking module, the construction period checking module, the economy checking module and the economy optimization module and is used for adjusting the initial type, the number and the arrangement position of the tower crane.
As shown in tables 1-3, the single hoisting operation time of each tower crane in Table 3 is calculated and obtained by means of the calculation formula of the single hoisting operation time of each tower crane based on the tower crane parameter database shown in Table 1 and the material information base shown in Table 2,
TABLE 1 Tower crane parameter database
Figure BDA0002463906540000061
TABLE 2 materials information base
Material numbering Kind of material Initial coordinates Coordinates of seating Weight (D)
1 Form panel (-26,35,0) (0,0,3) 159.74
2 Reinforcing bar (-26,60,0) (0,0,3) 449.28
3 Support for supporting (-26,10,0) (0,0,3) 172.03
4 Steel column (136,22,0) (170,10,4.8) 1347.84
5 Steel beam (136,22,0) (175,0,4.8) 1872.00
6 Steel floor (136,22,0) (175,15,4.8) 2184.22
7 Prefabricated column (43,-9.3,0) (62,-20,3.3) 2062.51
8 Support for supporting (103,-9.3,0) (62,-20,3.3) 132.00
9 Precast beam (43,-9.3,0) (59,-20,3.3) 3300.24
10 Support for supporting (103,-9.3,0) (59,-20,3.3) 495.00
11 Prefabricated panel (43,-9.3,0) (65,-23,3.3) 2100.00
12 Support for supporting (103,-9.3,0) (65,-23,3.3) 945.00
…… …… …… …… ……
TABLE 3 Tower crane hoisting operation time
Figure BDA0002463906540000062
Figure BDA0002463906540000071
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.

Claims (7)

1. A tower crane model selection and arrangement optimization method aiming at group towers is characterized by comprising the following steps:
s1: giving an initial tower crane type selection and arrangement scheme, establishing a material information base of all the required tower cranes for hoisting and a database of each parameter of alternative tower cranes in the project, and giving the initial tower crane type selection and arrangement scheme on the basis;
s2: checking the coverage area, checking whether the proposed building and the material to be hoisted are both in the coverage area of the tower crane, if not, displaying the information of the proposed building or the material to be hoisted which does not fall into the coverage area in the system, adjusting the model, the number and the arrangement position of the tower crane, and checking the coverage area again;
s3: distributing materials, namely distributing all materials in a material information base according to the arrangement positions of the tower cranes, determining the materials to be hoisted by each tower crane respectively, and forming a material list of each tower crane;
s4: performing collision check, simulating the operation process of the tower crane, checking whether the tower crane collides with a building to be built and the tower crane, if so, displaying collision information in the system, adjusting the model and the arrangement position of the tower crane according to the information, and jumping to the step S2;
s5: checking the hoisting weight, checking whether each tower crane can meet the hoisting requirements of each material in the respective material list or not by contrasting the hoisting weight curve of each tower crane, if not, displaying the material information and the tower crane information which do not meet the requirements in the system, adjusting the type and the arrangement position of the tower crane according to the information, and jumping to the step S2;
s6: checking a construction period, respectively fitting a single hoisting operation time calculation formula for completing hoisting of different types of materials by using a statistical method according to operation time data of various types of tower cranes in the previous engineering, sequentially substituting specific material information in respective material lists of the tower cranes into the time calculation formula, summing to obtain the total operation time of the tower cranes, and if the total operation time is longer than the engineering construction period, adjusting the types, the number and the arrangement positions of the tower cranes and jumping to the step S2;
s7: the method comprises the following steps of (1) economy checking, calculating the total cost of each tower crane in the whole service process according to the economy parameter values of each tower crane, comparing the total cost with the budget cost of the tower crane of a proposed project, displaying the excess amount in a system and adjusting the type, quantity and arrangement position of the tower cranes if the budget cost is exceeded, and jumping to the step S2;
s8: and (4) optimizing economy, storing the tower crane arrangement scheme obtained in the step S6 as a candidate scheme by the system, sequentially replacing models of all tower cranes according to the cost reduction direction, replacing only one tower crane each time, skipping to the step S2, and outputting the candidate scheme as a final tower crane arrangement scheme if the requirements cannot be met after all the tower cranes are replaced once.
2. The tower crane model selection and arrangement optimization method for the tower group according to claim 1, characterized in that: the material information base is obtained on the basis of a Building Information Model (BIM) according to a construction method and construction deployment, and the material information recorded in the material information base comprises the types, the in-position heights, the plane coordinates and the weights of all materials to be hoisted in the project; the tower crane parameter database can be updated in real time, corresponding parameters of various types of tower cranes commonly used in the market are recorded, the parameters comprise technical parameters and economic parameters, the technical parameters comprise the arm length, the hoisting curve, the lifting speed, the rotating speed and the amplitude changing speed of various types of tower cranes, and the economic parameters comprise rent, tower crane foundation cost, operation and maintenance cost and attachment cost.
3. The tower crane model selection and arrangement optimization method for the tower group according to claim 2, characterized in that: the calculation formula of the single hoisting operation time of each tower crane in the step S6 is as follows,
Figure FDA0002463906530000021
in the formula: t isiThe single hoisting operation time of the tower crane;
t0-static time of tower crane operation process;
omega-tower crane rotation angular velocity;
v1-tower crane amplitude variation speed;
v2-the tower crane lifting speed;
theta is the rotation included angle of the tower crane in the single hoisting process;
r is the amplitude variation distance of the tower crane in the single hoisting process;
h, the lifting height of the tower crane in the single lifting process;
alpha-adjusting coefficients of the rotation time, the amplitude variation time and the lifting time of the tower crane, wherein the adjusting coefficients are obtained by statistical analysis and fitting of the previous engineering operation time data of various types of tower cranes.
4. The tower crane model selection and arrangement optimization method for the tower group according to claim 1, characterized in that: and in the step S3, the material distribution follows the principle of being close, namely all materials are distributed to the tower crane closest to the plane position where the materials are located.
5. The tower crane model selection and arrangement optimization method for the tower group according to claim 1, characterized in that: the material distribution in the step S3 may also follow an average distribution principle, and if the material is only within the coverage of a single tower crane, the material is distributed to the tower crane, and if the material is within the coverage of multiple tower cranes, the material is distributed to a tower crane with fewer hoisting tasks.
6. The tower crane model selection and arrangement optimization method for the tower group according to claim 1, characterized in that: the steps S4-S7 are adjustable in sequence.
7. A system for a tower crane model selection and arrangement optimization method aiming at tower groups based on any one of claims 1-6 is characterized in that: the system comprises an initial tower crane arrangement scheme generation module, a coverage range checking module, a material distribution module, a collision checking module, a hoisting weight checking module, a construction period checking module, an economy checking module and an economy optimization module which correspond to the steps S1-S8 respectively, and further comprises a modification module, wherein the modification module can be called by the coverage range checking module, the collision checking module, the hoisting weight checking module, the construction period checking module, the economy checking module and the economy optimization module and is used for adjusting the initial tower crane model, the number and the arrangement position.
CN202010327982.0A 2020-04-23 2020-04-23 Tower crane model selection and arrangement optimization method and system for group tower Active CN111539570B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010327982.0A CN111539570B (en) 2020-04-23 2020-04-23 Tower crane model selection and arrangement optimization method and system for group tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010327982.0A CN111539570B (en) 2020-04-23 2020-04-23 Tower crane model selection and arrangement optimization method and system for group tower

Publications (2)

Publication Number Publication Date
CN111539570A true CN111539570A (en) 2020-08-14
CN111539570B CN111539570B (en) 2023-09-26

Family

ID=71975368

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010327982.0A Active CN111539570B (en) 2020-04-23 2020-04-23 Tower crane model selection and arrangement optimization method and system for group tower

Country Status (1)

Country Link
CN (1) CN111539570B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112069671A (en) * 2020-08-28 2020-12-11 中冶(上海)钢结构科技有限公司 Steel structure hoisting equipment type selection and arrangement optimization method based on BIM model
CN113378271A (en) * 2021-06-10 2021-09-10 广联达科技股份有限公司 Method for calculating installation height of group tower and computer readable storage medium
CN113761677A (en) * 2021-08-12 2021-12-07 广州五羊建设机械有限公司 Tower crane structure design method for realizing profit maximization
CN113807609A (en) * 2021-10-09 2021-12-17 上海建工一建集团有限公司 Automatic generation and digital optimization method for climbing scheme of tower crane and steel platform
CN115419073A (en) * 2022-09-21 2022-12-02 中建八局科技建设有限公司 Tower group layout method of tower crane for group pit construction
CN117574595A (en) * 2023-08-24 2024-02-20 广州市第三市政工程有限公司 Intelligent construction method for selecting component hoisting equipment based on BIM technology

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106372302A (en) * 2016-08-31 2017-02-01 浙江精工钢结构集团有限公司 Tower crane automatic model selection and optimization system and method based on BIM (Building Information Modeling) technology
KR101935898B1 (en) * 2017-11-21 2019-01-07 현대건설 주식회사 Temporary-plan supporting system based on Building Information Motatdeling and method of the same
CN110399629A (en) * 2019-05-29 2019-11-01 北京工业大学 A kind of tower crane type selecting and layout optimization modeling method based on mixing shaping planning
US20200081351A1 (en) * 2018-09-11 2020-03-12 Xyzprinting, Inc. Method of dynamically adjusting lifting parameter

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106372302A (en) * 2016-08-31 2017-02-01 浙江精工钢结构集团有限公司 Tower crane automatic model selection and optimization system and method based on BIM (Building Information Modeling) technology
KR101935898B1 (en) * 2017-11-21 2019-01-07 현대건설 주식회사 Temporary-plan supporting system based on Building Information Motatdeling and method of the same
US20200081351A1 (en) * 2018-09-11 2020-03-12 Xyzprinting, Inc. Method of dynamically adjusting lifting parameter
CN110399629A (en) * 2019-05-29 2019-11-01 北京工业大学 A kind of tower crane type selecting and layout optimization modeling method based on mixing shaping planning

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘猛;黄春;王京京;王文琦;张睿;: "基于混合整数线性规划的塔吊选型与布置优化", vol. 37, no. 02, pages 142 - 150 *
杨静;张育飞;刘栋;徐苍博;: "Revit下计算机辅助塔机规划系统", no. 02, pages 107 - 111 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112069671A (en) * 2020-08-28 2020-12-11 中冶(上海)钢结构科技有限公司 Steel structure hoisting equipment type selection and arrangement optimization method based on BIM model
CN113378271A (en) * 2021-06-10 2021-09-10 广联达科技股份有限公司 Method for calculating installation height of group tower and computer readable storage medium
CN113378271B (en) * 2021-06-10 2024-04-12 广联达科技股份有限公司 Method for calculating installation height of group tower and computer readable storage medium
CN113761677A (en) * 2021-08-12 2021-12-07 广州五羊建设机械有限公司 Tower crane structure design method for realizing profit maximization
CN113807609A (en) * 2021-10-09 2021-12-17 上海建工一建集团有限公司 Automatic generation and digital optimization method for climbing scheme of tower crane and steel platform
CN113807609B (en) * 2021-10-09 2024-04-19 上海建工一建集团有限公司 Automatic generation and digital optimization method for climbing scheme of tower crane and steel platform
CN115419073A (en) * 2022-09-21 2022-12-02 中建八局科技建设有限公司 Tower group layout method of tower crane for group pit construction
CN117574595A (en) * 2023-08-24 2024-02-20 广州市第三市政工程有限公司 Intelligent construction method for selecting component hoisting equipment based on BIM technology

Also Published As

Publication number Publication date
CN111539570B (en) 2023-09-26

Similar Documents

Publication Publication Date Title
CN111539570A (en) Tower crane type selection and arrangement optimization method and system for group towers
Hou et al. Combined optimization for offshore wind turbine micro siting
CN102425326B (en) Installation construction process of bolt net rack cylindrical shell storage bin
CN111461927B (en) Tower crane type selection system and method based on BIM and time-varying reliability analysis
CN108280281A (en) A kind of construction cost control method and system based on BIM technology
CN103996074A (en) CFD and improved PSO based microscopic wind-farm site selection method of complex terrain
CN110322038B (en) Method and equipment for automatically arranging fans based on mesoscale data
CN103942422B (en) Granular-computation-based long-term prediction method for converter gas holder positions in metallurgy industry
CN101794996A (en) Real-time predicting method for output of wind electric field
JP6144921B2 (en) Architectural design method, manufacturing method using the same, and design apparatus used therefor
CN110817223A (en) Scheduling simulation method based on intelligent three-dimensional warehouse of stacker
CN112801687A (en) Overhead line engineering-based cost prediction model construction method
CN110288133A (en) Planning substation automatic addressing method based on distant view year saturation loading distribution map
CN109870119B (en) FAST active reflecting surface type precision real-time monitoring method based on digital twins technology
CN109558629B (en) Method and device for generating reinforcement arrangement scheme
CN103745274A (en) Short-term power prediction method applied to dispersed wind power
CN111382538A (en) Spherical net rack suspension assembly integral lifting construction method
CN113487090A (en) Method, device and equipment for arranging machine positions of offshore wind power plant
CN117113745B (en) Stress rechecking method and system for tower crane cross beam foundation
CN110361970B (en) Method for selecting and lifting control of hanging points of hanging stand
CN117195449A (en) Wind farm arrangement optimization method, device, equipment and medium
CN103995977A (en) Double-fed wind turbine generator set parameter identification method based on LVRT transient response characteristic analysis
CN114818054A (en) Variable stiffness optimization method for squeezed branch tray pile group based on genetic algorithm control
CN208889148U (en) A kind of generator centering practice teaching platform
JP2001134628A (en) Device for optimally designing framed structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant