CN111535242A - Steel pipe pile cap water bottom-hanging device and construction method thereof - Google Patents

Steel pipe pile cap water bottom-hanging device and construction method thereof Download PDF

Info

Publication number
CN111535242A
CN111535242A CN202010334569.7A CN202010334569A CN111535242A CN 111535242 A CN111535242 A CN 111535242A CN 202010334569 A CN202010334569 A CN 202010334569A CN 111535242 A CN111535242 A CN 111535242A
Authority
CN
China
Prior art keywords
hanging
column
pair
cubic
pipe pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010334569.7A
Other languages
Chinese (zh)
Other versions
CN111535242B (en
Inventor
安秀山
张喜林
李亮
李建明
娄雅冬
许琳丽
朱龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Harbor Engineering Co Ltd
Original Assignee
CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbor Engineering Co Ltd filed Critical CCCC First Harbor Engineering Co Ltd
Priority to CN202010334569.7A priority Critical patent/CN111535242B/en
Publication of CN111535242A publication Critical patent/CN111535242A/en
Application granted granted Critical
Publication of CN111535242B publication Critical patent/CN111535242B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • E02B3/068Landing stages for vessels
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals
    • E02D5/285Prefabricated piles made of steel or other metals tubular, e.g. prefabricated from sheet pile elements

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a steel pipe pile cap water bottom-hanging device, which comprises: the balance frame comprises four balance beams, four clamping columns, a reinforcing chassis and a plurality of hanging ribs; the lifting mechanism comprises four lifting bottom pieces, one lifting bottom piece corresponds to one clamping column, and the lifting bottom pieces comprise fixing columns, ring blocking pieces, sliding sleeves, a pair of supporting blocks and a pair of magnetic suckers; and the positioning frame surrounds the steel pipe pile and is not in contact with the steel pipe pile, and the positioning frame is provided with four positioning holes. The invention also discloses a construction method of the steel pipe pile cap water bottom hoisting device. The horizontal cross frame and the bottom hanging mechanism can be assembled into a whole in advance on land, the construction speed is high, the working efficiency is high, the quality of the pile cap is improved, and the service life is prolonged.

Description

Steel pipe pile cap water bottom-hanging device and construction method thereof
Technical Field
The invention relates to the field of pile cap implementation of an overwater wharf, in particular to an overwater bottom-hanging device for a steel pipe pile cap and a construction method of the overwater bottom-hanging device.
Background
During construction on water, many docks adopt the high-rise beam slab form, and preceding pile platform stake adopts the steel-pipe pile more, and cast in situ reinforced concrete is adopted to the pile cap of steel-pipe pile, and its effect is in order to avoid destroying and adjust the straightness that hangs down of steel-pipe pile itself, makes it can be fixed in the holding power layer better. In the prior art, a loop bottom hanging process, a bottom die hanging process and a steel hoop bottom hanging process are generally adopted. However, when concrete is poured, the bending part of the pocket loop is easy to deform, so that the pile cap is inclined, and the pocket loop is difficult to completely remove, so that the quality of the pile cap is affected; the bottom die suspension process ensures that pile cap steel bars are required to be disconnected at the frame beam, so that the strength is influenced; the steel hoop bottom-hanging process can damage the surface anticorrosion and crack-resistant layer of the steel pipe pile, so that the anticorrosion and crack-resistant effects are deteriorated, and the steel pipe pile is corroded.
Disclosure of Invention
An object of the present invention is to solve at least the above problems and to provide at least the advantages described later.
The invention also aims to provide a water bottom-hanging device of the pile cap of the steel pipe pile and a construction method thereof.
To achieve these objects and other advantages and in accordance with the purpose of the invention, there is provided a steel pipe pile cap water floating bottom device, comprising:
the balance frame comprises four balance beams, four clamping columns, a reinforcing chassis and a plurality of hanging ribs, wherein the four balance beams are of an integrally formed cross-shaped structure and are horizontally arranged, one clamping column is vertically and downwards arranged on one balance beam, a pair of accommodating grooves are formed in the circumferential direction of the clamping column and are symmetrically arranged relative to the axis of the clamping column, notches of the pair of accommodating grooves are opposite, a pair of elastic locks are respectively arranged in the pair of accommodating grooves, each elastic lock comprises a spring with one end arranged in the accommodating groove and arranged along the axial direction of the accommodating groove and a right trapezoid elastic block fixedly connected with the other end of the spring, the reinforcing chassis is horizontally and fixedly arranged under the cross of the four balance beams, one ends of the hanging ribs are welded at one point and positioned right above the cross of the four balance beams, and the other ends of the hanging ribs are respectively welded on the four balance beams or the reinforcing chassis;
the bottom hanging mechanism comprises four bottom hanging pieces, one bottom hanging piece corresponds to one clamping column, the bottom hanging piece comprises a fixing column, a ring blocking piece, a sliding sleeve, a pair of supporting blocks and a pair of magnetic suckers, the fixing column is vertically arranged and comprises a hollow cubic column positioned above and a solid cylinder positioned below, a pair of through holes coaxially arranged are formed in the cubic column, the through holes are arranged close to the top end of the cubic column, threads are arranged on the outer wall of the cylinder, the length of a diagonal line of a horizontal section of the cubic column is smaller than the diameter of the cylinder, the ring blocking piece is positioned at the lower end of the cubic column, the ring blocking piece is formed by a plurality of iron sheets horizontally arranged at intervals around the cubic column, the sliding sleeve is sleeved on the cubic column in a sliding mode and positioned above the ring blocking plate, the pair of supporting blocks are symmetrically arranged relative to the sliding sleeve, and the pair of magnetic suckers are respectively arranged on the pair of supporting blocks and, wherein the distance between the ring baffle and the top end of the cubic column is less than twice the height of the sliding sleeve, the height of the cubic column is less than the height of the clamping column, and the distance between the top end of the cubic column and the top end of the clamping column is less than the height of the sliding sleeve;
the positioning frame is arranged around the steel pipe pile and does not contact the steel pipe pile, and four positioning holes are formed in the positioning frame;
the four clamping columns of the balancing stand are respectively inserted into the cubic columns of the four hanging bottom pieces of the hanging bottom mechanism, the right-angle trapezoidal elastic blocks horizontally extend into the through holes, the cylinders of the four hanging bottom pieces are fixedly arranged after being inserted into the four positioning holes through nuts, battens, boards and multilayer boards are sequentially laid above the positioning frame from bottom to top, and the upper surfaces of the multilayer boards are in contact with the lower surfaces of the ring baffles.
Preferably, each balance beam is a triangular prism structure with one side surface horizontally arranged.
Preferably, each iron sheet is of a rectangular structure, the long edge of each iron sheet is welded with the outer wall of the cubic column, and the wide edge of each iron sheet is 5-10 mm.
Preferably, the locating frame includes inner tube and urceolus and the reinforcing bar net of connecting inner tube and urceolus that vertical coaxial cover was established, the top edge and the lower limb of inner tube all turn over towards its axis level and turn over, the top edge and the lower limb of urceolus are all kept away from its axis level and are turned over, set up on the reinforcing bar net the locating hole, the inboard of inner tube with the outside of urceolus all encircles and establishes the billet, and billet horizontal thickness all is greater than the inner tube with the width of turning over of urceolus.
Preferably, the ratio of the length of the cube to the length of the cylinder is 1: 3.
The invention also provides a construction method of the steel pipe pile cap water bottom hoisting device, which comprises the following steps:
the method comprises the following steps that firstly, a sliding sleeve is sleeved on a cubic column from top to bottom and is in contact with a ring blocking piece, four clamping columns of a balancing stand are respectively inserted into the cubic columns of four hanging bottom pieces of a hanging bottom mechanism, and a pair of right-angled trapezoid elastic blocks of an elastic lock arranged on the clamping columns horizontally extend into through holes to enable the clamping columns to be connected with the cubic column, so that the assembly of the hanging bottom mechanism and the balancing stand is completed;
step two, arranging a positioning frame at the periphery of the steel pipe pile, and moving the bottom hanging mechanism and the balance frame assembled in the step one by a hoisting device through a hoisting rib, so that cylinders of four bottom hanging pieces are respectively inserted into four positioning holes of the positioning frame and are fixed from the lower end of the cylinder through nuts, and the assembly of the bottom hanging mechanism, the balance frame and the positioning frame is completed to form a supporting system;
thirdly, laying battens, boards and multilayer boards above a positioning frame of the supporting system from bottom to top in sequence, and adjusting the positions of nuts on the cylinders to enable the upper surfaces of the multilayer boards to be in contact with the lower surfaces of the ring stoppers to form a pile cap suspended bottom template;
separating the sliding sleeves of the four bottom hanging pieces from the located cubic columns, controlling the sliding sleeves to slide upwards, enabling the right-angled trapezoidal elastic blocks of the pair of elastic locks arranged on the clamping columns to retract from the through holes when the sliding sleeves slide upwards, and continuing to slide upwards until the pair of magnetic suction cups are adsorbed on the lower surfaces of the four balance beams;
and fifthly, pouring reinforced concrete on the pile cap suspended bottom template to finish the overwater pile cap suspended bottom.
The invention at least comprises the following beneficial effects:
the balance frame and the hoisting bottom mechanism can be assembled into a whole in advance on land, and then the whole is hoisted to the steel pipe pile, so that the construction speed is high, and the working efficiency is high. The balance frame is of a cross structure, the clamping columns are arranged below the end parts of the four balance beams, the reinforcing chassis is arranged right below the balance frame, the hanging ribs are arranged right above the balance frame, a three-dimensional framework is formed, the three-dimensional framework is subsequently reserved in the pile cap body and is integrated with poured concrete, the anti-strain capacity of the pile cap is enhanced, the quality of the pile cap is improved, and the service life is prolonged. According to the invention, through the arrangement of the sliding sleeve and the magnetic sucker, the connection between the bottom hanging piece and the balance frame can be rapidly released, and the fixing column is removed, so that the repeated utilization is facilitated, and the construction progress is accelerated.
Additional advantages, objects, and features of the invention will be set forth in part in the description which follows and in part will become apparent to those having ordinary skill in the art upon examination of the following or may be learned from practice of the invention.
Drawings
FIG. 1 is a schematic diagram of the overall structure of one embodiment of the present invention;
FIG. 2 is a schematic structural view of the balance frame according to one embodiment of the present invention;
fig. 3 is a partial structural schematic diagram of the hanging bottom mechanism according to one technical scheme of the invention;
FIG. 4 is a schematic structural diagram of the locking column according to one embodiment of the present invention;
fig. 5 is a top view of the positioning frame according to one embodiment of the present invention.
Detailed Description
The present invention is further described in detail below with reference to the drawings and examples so that those skilled in the art can practice the invention with reference to the description.
It will be understood that terms such as "having," "including," and "comprising," as used herein, do not preclude the presence or addition of one or more other elements or groups thereof. In the description of the present invention, the terms "transverse," "longitudinal," "axial," "radial," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," and the like refer to orientations or positional relationships that are illustrated in the accompanying drawings, which are used for convenience in describing the present invention and to simplify the description, and do not indicate or imply that the referenced device or element must have a particular orientation, be constructed and operated in a particular orientation, and thus, are not to be considered limiting of the present invention.
As shown in fig. 1 to 5, the present invention provides a water-borne suspended bottom device for a pile cap of a steel pipe pile 10, comprising:
the balancing stand comprises four balancing beams 11, four clamping columns 12, a reinforcing chassis 13 and a plurality of hanging ribs 14, wherein the four balancing beams 11 are in an integrally formed cross structure and are horizontally arranged, one clamping column 12 is vertically and downwards arranged on one balancing beam 11, a pair of accommodating grooves 15 are formed in the circumferential direction of the clamping column 12, the pair of accommodating grooves 15 are symmetrically arranged around the axis of the clamping column 12, the notches are opposite, a pair of spring locks are respectively arranged in the pair of accommodating grooves 15, the spring lock comprises a spring 16 with one end arranged in the accommodating groove 15 and arranged along the axial direction of the accommodating groove 15, a right-angle trapezoid spring block 17 fixedly connected with the other end of the spring 16, the reinforcing chassis 13 is horizontally and fixedly arranged right below the cross of the four balance beams 11, one end of each of the plurality of hanging ribs 14 is welded to one point and is positioned right above the cross of the four balance beams 11, and the other end of each of the plurality of hanging ribs is welded to the four balance beams 11 or the reinforcing chassis 13;
the hanging bottom mechanism comprises four hanging bottom pieces, one hanging bottom piece corresponds to one clamping column 12, the hanging bottom piece comprises a fixed column, a ring stopper 22, a sliding sleeve 23, a pair of supporting blocks 24 and a pair of magnetic suction cups 25, the fixed column is vertically arranged and comprises a hollow cubic column 211 positioned above and a solid cylinder 212 positioned below, a pair of through holes 200 coaxially arranged are formed in the cubic column 211, the through holes 200 are arranged close to the top end of the cubic column 211, the outer wall of the cylinder 212 is provided with threads, the diagonal length of the horizontal section of the cubic column 211 is smaller than the diameter of the cylinder 212, the ring stopper 22 is positioned at the lower end of the cubic column 211, the ring stopper 22 is formed by a plurality of iron sheets horizontally arranged at intervals around the cubic column 211, the sliding sleeve 23 is slidably sleeved on the cubic column 211 and positioned above the ring stopper, and the pair of supporting blocks 24 are symmetrically arranged relative to the sliding sleeve 23, a pair of magnetic suction cups 25 are respectively arranged on a pair of supporting blocks 24 and extend out of the sliding sleeve 23 along the vertical direction, wherein the distance between the ring baffle and the top end of the cubic column 211 is less than twice of the height of the sliding sleeve 23, the height of the cubic column 211 is less than the height of the clamping column 12, and the distance between the top end of the cubic column 211 and the top end of the clamping column 12 is less than the height of the sliding sleeve 23;
a positioning frame 3 disposed around the steel pipe pile 10 without contacting the steel pipe pile 10, the positioning frame 3 having four positioning holes 34;
the four clamping columns 12 of the balance frame are respectively inserted into the cubic columns 211 of the four bottom hanging pieces of the bottom hanging mechanism, the right-angle trapezoidal elastic blocks 17 horizontally extend into the through holes 200, the cylinders 212 of the four bottom hanging pieces are fixedly arranged through the nuts 7 after being inserted into the four positioning holes 34, the battens 4, the planks 5 and the multilayer boards 6 are sequentially laid above the positioning frame 3 from bottom to top, and the upper surfaces of the multilayer boards 6 are in contact with the lower surfaces of the ring baffles.
During construction, the sliding sleeve 23 is sleeved on the cubic column 211, then the four clamping columns 12 of the balance frame are respectively and correspondingly inserted into the cubic columns 211 of the four bottom hanging pieces, the right-angle trapezoidal elastic block 17 of the elastic lock is pushed by the elastic force of the spring 16 to extend out of the through hole 200, the inclined plane of the right-angle trapezoidal elastic block 17 inclines downwards, and the part extending out of the through hole 200 cannot exceed the inclined plane all the time, so that the connection between the clamping columns 12 and the cubic column 211 is realized, and the assembly of the bottom hanging mechanism and the balance frame is completed; arranging a positioning frame 3 at the periphery of the steel pipe pile 10, moving the bottom lifting mechanism and the balance frame assembled in the step one by a lifting device through lifting ribs 14, respectively inserting the cylinders 212 of four bottom lifting pieces into four positioning holes 34 of the positioning frame 3, and fixing the cylinders from the lower ends of the cylinders 212 through nuts 7, so as to complete the assembly of the bottom lifting mechanism, the balance frame and the positioning frame 3 and form a supporting system; sequentially laying a batten 4, a wood board 5 and a multilayer board 6 from bottom to top on a positioning frame 3 of the supporting system, and adjusting the position of a nut 7 on a cylinder 212 to enable the upper surface of the multilayer board 6 to be in contact with the lower surface of a ring stopper 22 to form a pile cap suspended bottom template; the sliding sleeves 23 of the four hanging bottom pieces are separated from the located cubic columns 211, the sliding sleeves 23 are controlled to slide upwards, when the sliding sleeves 23 slide upwards to enable the pair of snap-lock right-angle trapezoidal elastic blocks 17 arranged on the clamping columns 12 to retract from the through holes 200, the sliding sleeves 23 continuously slide upwards until the pair of magnetic suction cups 25 are adsorbed on the lower surfaces of the four balance beams 11, at this time, the sliding sleeves 23 are not connected with the cubic columns 211, but the sliding sleeves 23 still cover the upper end parts of the cubic columns 211 and the through holes 200, when the reinforced concrete pouring is carried out on the pile cap hanging bottom template to complete the water pile cap hanging bottom, the sliding sleeves 23 can protect the poured reinforced concrete from being plugged into the cubic columns 211 from the through holes 200, and the reuse of the cubic columns 211 is facilitated. When the pile cap bottom hanging template is dismounted, the fixing column is screwed out forcibly by unscrewing the nut 7 of the cylinder 212, and meanwhile, the iron sheet of the ring stopper 22 is bent under the action of the screwed-out external force, so that the fixing column can be conveniently pulled out from the lower part.
The horizontal cross frame and the bottom hanging mechanism can be assembled into a whole in advance on land, and then the whole is hoisted to the steel pipe pile 10, so that the construction speed is high, and the working efficiency is high. The fixing column for the hanging bottom can be quickly detached and is convenient to recycle. The balance frame is of a cross structure and is provided with the reinforcing chassis 13 and the hanging ribs 14, and the reinforcing chassis and the hanging ribs are all kept in the pile cap body subsequently and are integrated with poured concrete, so that the stress between the pile cap and the steel pipe pile 10 is improved, the strain resistance of the pile cap is enhanced, the quality of the pile cap is improved, and the service life is prolonged. According to the invention, through the arrangement of the sliding sleeve 23 and the magnetic sucker 25, the connection between the hanging bottom piece and the balancing stand can be rapidly released, and the construction progress is accelerated.
In another technical scheme, each balance beam 11 is a triangular prism structure with one side surface horizontally arranged, and the balance frame is favorably arranged horizontally.
In another technical scheme, each iron sheet is of a rectangular structure, the long edge of each iron sheet is welded with the outer wall of the cubic column 211, and the wide edge is 5-10mm, so that deformation is conveniently realized to facilitate the removal of the fixed column.
In another technical scheme, the positioning frame 3 includes an inner cylinder 31 and an outer cylinder 32 which are vertically coaxially sleeved and a reinforcing mesh 33 which connects the inner cylinder 31 and the outer cylinder 32, the upper edge and the lower edge of the inner cylinder 31 are horizontally turned towards the axis thereof, the upper edge and the lower edge of the outer cylinder 32 are horizontally turned away from the axis thereof, the reinforcing mesh 33 is provided with the positioning holes 34, wood blocks 35 are annularly arranged on the inner side of the inner cylinder 31 and the outer side of the outer cylinder 32, and the horizontal thickness of the wood blocks 35 is greater than the turning width of the inner cylinder 31 and the outer cylinder 32, so that the positioning frame 3 is ensured not to scratch the anticorrosive coating on the outer wall of the steel pipe pile 10 during construction, and meanwhile, a suspended bottom formwork for pouring a pile cap provides stable support.
In another technical scheme, the length ratio of the cubic column 211 to the column 212 is 1:3, and the overall fixing column is preferably firm and stable.
The invention also provides a construction method of the steel pipe pile 10 pile cap water bottom hoisting device, which comprises the following steps:
step one, sleeving a sliding sleeve 23 on a cubic column 211 from top to bottom and contacting with a ring stopper 22, respectively inserting four clamping columns 12 of a balance frame into the cubic columns 211 of four bottom hanging pieces of a bottom hanging mechanism, and horizontally extending a pair of right-angled trapezoidal elastic blocks 17 of elastic locks arranged on the clamping columns 12 into through holes 200 to connect the clamping columns 12 with the cubic column 211 so as to complete the assembly of the bottom hanging mechanism and the balance frame;
step two, arranging the positioning frame 3 at the periphery of the steel pipe pile 10, and moving the bottom-hanging mechanism and the balance frame assembled in the step one by the hoisting device through the hoisting ribs 14, so that the cylinders 212 of the four bottom-hanging pieces are respectively inserted into the four positioning holes 34 of the positioning frame 3 and are fixed from the lower ends of the cylinders 212 through the nuts 7, and the assembly of the bottom-hanging mechanism, the balance frame and the positioning frame 3 is completed to form a supporting system;
thirdly, laying a batten 4, a plank 5 and a multilayer board 6 above a positioning frame 3 of the supporting system from bottom to top in sequence, and adjusting the position of a nut 7 on a cylinder 212 to enable the upper surface of the multilayer board 6 to be in contact with the lower surface of a ring stopper 22 to form a pile cap suspended bottom template;
step four, separating the sliding sleeves 23 of the four bottom hanging pieces from the located cubic columns 211, controlling the sliding sleeves 23 to slide upwards, enabling the right-angled trapezoidal elastic blocks 17 of the pair of elastic locks arranged on the clamping columns 12 to retract from the through holes 200 when the sliding sleeves 23 slide upwards, and continuing to slide the sliding sleeves 23 to enable the pair of magnetic suction cups 25 to be adsorbed on the lower surfaces of the four balance beams 11;
and fifthly, pouring reinforced concrete on the pile cap suspended bottom template to finish the overwater pile cap suspended bottom.
The horizontal cross frame and the bottom hanging mechanism can be assembled into a whole in advance on land, and then the whole is hoisted to the steel pipe pile 10, so that the construction speed is high, and the working efficiency is high. . The balance frame is of a cross structure and is provided with the reinforcing chassis 13 and the hanging ribs 14, and the reinforcing chassis and the hanging ribs are all kept in the pile cap body subsequently and are integrated with poured concrete, so that the stress between the pile cap and the steel pipe pile 10 is improved, the strain resistance of the pile cap is enhanced, the quality of the pile cap is improved, and the service life is prolonged. According to the invention, through the arrangement of the sliding sleeve 23 and the magnetic sucker 25, the connection between the hanging bottom piece and the balance frame can be quickly released, the construction progress is accelerated, and the fixing column for hanging bottom can be quickly detached, so that the repeated utilization is convenient. During actual construction, the existing double-spliced channel steel can be arranged below the positioning frame 3, so that the stability of the positioning frame 3 is enhanced.
While embodiments of the invention have been described above, it is not limited to the applications set forth in the description and the embodiments, which are fully applicable in various fields of endeavor to which the invention pertains, and further modifications may readily be made by those skilled in the art, it being understood that the invention is not limited to the details shown and described herein without departing from the general concept defined by the appended claims and their equivalents.

Claims (6)

1. Steel-pipe pile cap overwater suspended bottom device, its characterized in that includes:
the balance frame comprises four balance beams, four clamping columns, a reinforcing chassis and a plurality of hanging ribs, wherein the four balance beams are of an integrally formed cross-shaped structure and are horizontally arranged, one clamping column is vertically and downwards arranged on one balance beam, a pair of accommodating grooves are formed in the circumferential direction of the clamping column and are symmetrically arranged relative to the axis of the clamping column, notches of the pair of accommodating grooves are opposite, a pair of elastic locks are respectively arranged in the pair of accommodating grooves, each elastic lock comprises a spring with one end arranged in the accommodating groove and arranged along the axial direction of the accommodating groove and a right trapezoid elastic block fixedly connected with the other end of the spring, the reinforcing chassis is horizontally and fixedly arranged under the cross of the four balance beams, one ends of the hanging ribs are welded at one point and positioned right above the cross of the four balance beams, and the other ends of the hanging ribs are respectively welded on the four balance beams or the reinforcing chassis;
the bottom hanging mechanism comprises four bottom hanging pieces, one bottom hanging piece corresponds to one clamping column, the bottom hanging piece comprises a fixing column, a ring blocking piece, a sliding sleeve, a pair of supporting blocks and a pair of magnetic suckers, the fixing column is vertically arranged and comprises a hollow cubic column positioned above and a solid cylinder positioned below, a pair of through holes coaxially arranged are formed in the cubic column, the through holes are arranged close to the top end of the cubic column, threads are arranged on the outer wall of the cylinder, the length of a diagonal line of a horizontal section of the cubic column is smaller than the diameter of the cylinder, the ring blocking piece is positioned at the lower end of the cubic column, the ring blocking piece is formed by a plurality of iron sheets horizontally arranged at intervals around the cubic column, the sliding sleeve is sleeved on the cubic column in a sliding mode and positioned above the ring blocking plate, the pair of supporting blocks are symmetrically arranged relative to the sliding sleeve, and the pair of magnetic suckers are respectively arranged on the pair of supporting blocks and, wherein the distance between the ring baffle and the top end of the cubic column is less than twice the height of the sliding sleeve, the height of the cubic column is less than the height of the clamping column, and the distance between the top end of the cubic column and the top end of the clamping column is less than the height of the sliding sleeve;
the positioning frame is arranged around the steel pipe pile and does not contact the steel pipe pile, and four positioning holes are formed in the positioning frame;
the four clamping columns of the balancing stand are respectively inserted into the cubic columns of the four hanging bottom pieces of the hanging bottom mechanism, the right-angle trapezoidal elastic blocks horizontally extend into the through holes, the cylinders of the four hanging bottom pieces are fixedly arranged after being inserted into the four positioning holes through nuts, battens, boards and multilayer boards are sequentially laid above the positioning frame from bottom to top, and the upper surfaces of the multilayer boards are in contact with the lower surfaces of the ring baffles.
2. The steel-pipe pile cap water bottom-hanging device of claim 1, wherein each balance beam is a triangular prism structure with one side surface horizontally arranged.
3. The steel-pipe pile cap water bottom-hanging device of claim 1, wherein each iron sheet is of a rectangular structure, the long side of the iron sheet is welded with the outer wall of the cubic column, and the wide side of the iron sheet is 5-10 mm.
4. The steel-pipe pile cap overwater bottom-hanging device as claimed in claim 1, wherein the positioning frame comprises an inner cylinder and an outer cylinder which are vertically and coaxially sleeved, and a reinforcing mesh which connects the inner cylinder and the outer cylinder, the upper edge and the lower edge of the inner cylinder are both horizontally turned towards the axis of the inner cylinder, the upper edge and the lower edge of the outer cylinder are both horizontally turned away from the axis of the outer cylinder, the reinforcing mesh is provided with the positioning holes, wood blocks are annularly arranged on the inner side of the inner cylinder and the outer side of the outer cylinder, and the horizontal thickness of each wood block is larger than the turning width of the inner cylinder and the outer cylinder.
5. The steel-pipe pile cap water bottom-hanging device of claim 1, wherein the length ratio of the cubic column to the cylinder is 1: 3.
6. The construction method of the steel pipe pile cap water bottom-hanging device according to claim 1, characterized by comprising the steps of:
the method comprises the following steps that firstly, a sliding sleeve is sleeved on a cubic column from top to bottom and is in contact with a ring blocking piece, four clamping columns of a balancing stand are respectively inserted into the cubic columns of four hanging bottom pieces of a hanging bottom mechanism, and a pair of right-angled trapezoid elastic blocks of an elastic lock arranged on the clamping columns horizontally extend into through holes to enable the clamping columns to be connected with the cubic column, so that the assembly of the hanging bottom mechanism and the balancing stand is completed;
step two, arranging a positioning frame at the periphery of the steel pipe pile, and moving the bottom hanging mechanism and the balance frame assembled in the step one by a hoisting device through a hoisting rib, so that cylinders of four bottom hanging pieces are respectively inserted into four positioning holes of the positioning frame and are fixed from the lower end of the cylinder through nuts, and the assembly of the bottom hanging mechanism, the balance frame and the positioning frame is completed to form a supporting system;
thirdly, laying battens, boards and multilayer boards above a positioning frame of the supporting system from bottom to top in sequence, and adjusting the positions of nuts on the cylinders to enable the upper surfaces of the multilayer boards to be in contact with the lower surfaces of the ring stoppers to form a pile cap suspended bottom template;
separating the sliding sleeves of the four bottom hanging pieces from the located cubic columns, controlling the sliding sleeves to slide upwards, enabling the right-angled trapezoidal elastic blocks of the pair of elastic locks arranged on the clamping columns to retract from the through holes when the sliding sleeves slide upwards, and continuing to slide upwards until the pair of magnetic suction cups are adsorbed on the lower surfaces of the four balance beams;
and fifthly, pouring reinforced concrete on the pile cap suspended bottom template to finish the overwater pile cap suspended bottom.
CN202010334569.7A 2020-04-24 2020-04-24 Steel pipe pile cap water bottom-hanging device and construction method thereof Active CN111535242B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010334569.7A CN111535242B (en) 2020-04-24 2020-04-24 Steel pipe pile cap water bottom-hanging device and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010334569.7A CN111535242B (en) 2020-04-24 2020-04-24 Steel pipe pile cap water bottom-hanging device and construction method thereof

Publications (2)

Publication Number Publication Date
CN111535242A true CN111535242A (en) 2020-08-14
CN111535242B CN111535242B (en) 2021-06-29

Family

ID=71971268

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010334569.7A Active CN111535242B (en) 2020-04-24 2020-04-24 Steel pipe pile cap water bottom-hanging device and construction method thereof

Country Status (1)

Country Link
CN (1) CN111535242B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA1100737A (en) * 1977-11-14 1981-05-12 Horst Schramm Method and arrangement for the manufacture of pre- cast plate-like concrete elements on the building site
CN2887958Y (en) * 2006-05-18 2007-04-11 上海十三冶建设有限公司建筑分公司 Formwork hanger for abovewater foundation construction
CN107700477A (en) * 2017-10-16 2018-02-16 中交航局第工程有限公司 Pile cover waterborne hangs bottom technique
CN209555867U (en) * 2019-01-24 2019-10-29 中建筑港集团有限公司 A kind of pile cover bed die support construction of monoblock type installation

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA1100737A (en) * 1977-11-14 1981-05-12 Horst Schramm Method and arrangement for the manufacture of pre- cast plate-like concrete elements on the building site
CN2887958Y (en) * 2006-05-18 2007-04-11 上海十三冶建设有限公司建筑分公司 Formwork hanger for abovewater foundation construction
CN107700477A (en) * 2017-10-16 2018-02-16 中交航局第工程有限公司 Pile cover waterborne hangs bottom technique
CN209555867U (en) * 2019-01-24 2019-10-29 中建筑港集团有限公司 A kind of pile cover bed die support construction of monoblock type installation

Also Published As

Publication number Publication date
CN111535242B (en) 2021-06-29

Similar Documents

Publication Publication Date Title
CN211395327U (en) Variable cross-section hollow pier construction device
CN207277817U (en) Falsework rack connecting structure
CN111535242B (en) Steel pipe pile cap water bottom-hanging device and construction method thereof
US6368023B1 (en) Jack-in piling systems' apparatus and their method of use
CN110722344B (en) Oil cylinder replacing device and oil cylinder replacing method
CN112726824A (en) Mounting and hoisting method for assembled steel structure building steel column node
CN204212413U (en) The special connecting piece of a kind of mould middle cross beam and bottom support
CN109763644B (en) Large-diameter cylinder sliding form system and construction method thereof
CN216515141U (en) Novel cantilever construction creeping formwork device
CN108105477B (en) Automatic positioning device for building concrete pouring
CN102433994A (en) Construction method of equipment base pre-reservation anchor bolt square hole
CN102704691A (en) Whole-bundle disanchoring device and disanchoring method adopting same
CN210210806U (en) T beam mold board strutting arrangement
WO2010074680A1 (en) Concrete forming system
CN206680990U (en) A kind of steel reinforcement cage fixing mould
CN111017590A (en) Shipping method and support frame of conduit frame assembly
CN215669642U (en) Temporary bracket arranged by steel casing
CN220747635U (en) Construction template for overflow trough of secondary sedimentation tank
CN218842903U (en) Creeping formwork construction platform
CN212837846U (en) Special-shaped template trolley for cast-in-place construction under large-diameter tunnel rail
CN214530164U (en) Anti-tilt bridge structure
CN218596932U (en) From climbing formula turnover formwork reinforced structure
CN219154538U (en) Gas cylinder vehicle
CN221030142U (en) Bored concrete pile head processing apparatus
CN220763017U (en) Road bridge square pile pouring device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant