CN111519882A - Movable telescopic scaffold and installation method thereof - Google Patents

Movable telescopic scaffold and installation method thereof Download PDF

Info

Publication number
CN111519882A
CN111519882A CN202010404812.8A CN202010404812A CN111519882A CN 111519882 A CN111519882 A CN 111519882A CN 202010404812 A CN202010404812 A CN 202010404812A CN 111519882 A CN111519882 A CN 111519882A
Authority
CN
China
Prior art keywords
vertical rods
scaffold
rod
ground
mobile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010404812.8A
Other languages
Chinese (zh)
Inventor
潘峰
韩亚明
沈浅灏
曹刘坤
徐沈京
王太源
杨磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 5 Group Co Ltd
Original Assignee
Shanghai Construction No 5 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 5 Group Co Ltd filed Critical Shanghai Construction No 5 Group Co Ltd
Priority to CN202010404812.8A priority Critical patent/CN111519882A/en
Publication of CN111519882A publication Critical patent/CN111519882A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/15Scaffolds primarily resting on the ground essentially comprising special means for supporting or forming platforms; Platforms
    • E04G1/152Platforms made of metal or with metal-supporting frame
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/24Scaffolds primarily resting on the ground comprising essentially special base constructions; comprising essentially special ground-engaging parts, e.g. inclined struts, wheels
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/34Scaffold constructions able to be folded in prismatic or flat parts or able to be turned down
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/08Scaffold boards or planks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/24Scaffolds primarily resting on the ground comprising essentially special base constructions; comprising essentially special ground-engaging parts, e.g. inclined struts, wheels
    • E04G2001/242Scaffolds movable on wheels or tracks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/24Scaffolds primarily resting on the ground comprising essentially special base constructions; comprising essentially special ground-engaging parts, e.g. inclined struts, wheels
    • E04G2001/248Inclined struts

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Movable Scaffolding (AREA)

Abstract

The invention provides a movable telescopic scaffold and an installation method thereof, wherein the movable telescopic scaffold comprises the following components: the telescopic folding scaffold is movable through the pulleys, the operation position is flexibly adjusted, and when the telescopic folding scaffold is moved to the operation position and needs to be fixed, the ground supporting device can be supported on the ground to fix the telescopic folding scaffold; the utility model discloses a folding support body of device during operation, including the hinge that connects on the montant, the hinge that connects on the montant is opened to the hinge that also has one in the middle of whole support body and passes through railing articulated montant with both sides pole setting, also sets up two bearing diagonal simultaneously and ensures that the device during operation is stable, thereby can save space when not using.

Description

Movable telescopic scaffold and installation method thereof
Technical Field
The invention relates to a movable telescopic scaffold and an installation method thereof.
Background
The scaffold is a necessary device for climbing operation, is related to all fields, is most widely applied in the building industry, and is mostly composed of stand columns, cross rods, connecting rods and pedals in the existing market.
Sometimes need change the scaffold position many times because the operation span is different, this in-process wastes a large amount of time and energy, influences the whole progress of construction, and the back of finishing using, removes it to the corner and deposits, occupies great space and inconvenient removal. The site worker climbs out of the safety range of the scaffold for improving the efficiency and works, so that the construction danger is increased.
Disclosure of Invention
The invention aims to provide a movable telescopic scaffold and an installation method thereof.
In order to solve the above problems, the present invention provides a movable type retractable scaffold, comprising:
four longitudinal vertical rods;
the pulleys and the ground supporting device are respectively arranged at the bottom of each longitudinal upright rod;
the vertical rods are respectively arranged between the two vertical rods, and the bottom ends of the vertical rods are away from the ground by a preset distance;
the two ends of each cross rod are respectively connected with the two adjacent vertical rods or respectively connected with the adjacent vertical rods and the vertical rods through hinges;
the two ends of each fence rod are respectively connected with the vertical rods and the middle upper parts of the vertical rods;
and the detachable platform pedal is respectively connected with the vertical rod and the middle upper part of the vertical rod.
Furthermore, in the movable telescopic scaffold, a first inclined support is connected between two adjacent vertical rods.
Furthermore, in the movable telescopic scaffold, a second inclined support is connected between the adjacent vertical rods and the vertical rods.
Further, in the above movable type retractable scaffold, the detachable platform step is further connected to the railing.
Further, in the above movable type retractable scaffold, the ground supporting means includes:
the upper part of the support frame is connected with the upright stanchion;
the screw rod is arranged at the lower part of the support frame;
the rotating rod is connected to the upper part of the screw rod and is used for adjusting the extending length of the screw rod;
and the supporting plate is connected to the bottom of the screw rod and is used for being in contact with the ground to support.
According to another aspect of the present invention, there is also provided a method for installing a movable type retractable scaffold, comprising:
four longitudinal vertical rods are arranged;
pulleys and ground supporting devices are respectively arranged at the bottom of each longitudinal upright rod;
vertical rods are respectively arranged between the two vertical rods, wherein the bottom ends of the vertical rods are away from the ground by a preset distance;
arranging a plurality of cross rods, wherein two ends of each cross rod are respectively connected with two adjacent vertical rods or respectively connected with adjacent vertical rods and vertical rods through hinges;
a plurality of detachable folding type enclosure poles are arranged, wherein two ends of each enclosure pole are respectively connected with the middle upper parts of the vertical rods and the vertical rods;
and the detachable platform pedal is respectively connected with the middle upper parts of the vertical rods and the vertical rods.
Further, in the above method, the method further includes:
and a first inclined support is connected between two adjacent vertical rods.
Further, in the above method, the method further includes:
and a second inclined support is connected between the adjacent vertical rod and the vertical rod.
Further, in the above method, the method further includes:
connecting the detachable platform deck to the railing.
Further, in the above method, ground support means are provided at the bottom of each longitudinal upright, comprising:
connecting the upper part of the support frame with the upright stanchion;
the upper part of the screw rod is connected with a rotating rod, and the rotating rod is used for adjusting the extending length of the screw rod;
a screw rod is arranged at the lower part of the support frame;
and the bottom of the screw rod is connected with a support plate, and the support plate is used for being in contact with the ground for supporting.
Compared with the prior art, the invention comprises the following steps: the telescopic folding scaffold is movable through the pulleys, the operation position is flexibly adjusted, and when the telescopic folding scaffold is moved to the operation position and needs to be fixed, the ground supporting device can be supported on the ground to fix the telescopic folding scaffold; the utility model discloses a folding support body of device during operation, including the hinge that connects on the montant, the hinge that connects on the montant is opened to the hinge that also has one in the middle of whole support body and passes through railing articulated montant with both sides pole setting, also sets up two bearing diagonal simultaneously and ensures that the device during operation is stable, thereby can save space when not using.
Drawings
Fig. 1 is a front view of a mobile retractable scaffold according to an embodiment of the present invention;
fig. 2 is a side view of a mobile, retractable scaffold according to an embodiment of the present invention;
FIG. 3 is a front view of a ground support apparatus according to an embodiment of the present invention;
FIG. 4 is a side view of a support fixture in accordance with an embodiment of the present invention;
fig. 5 is a schematic view of the installation of a mobile telescopic scaffold according to an embodiment of the present invention.
Detailed Description
In order to make the aforementioned objects, features and advantages of the present invention comprehensible, embodiments accompanied with figures are described in further detail below.
As shown in fig. 1 to 5, the present invention provides a movable telescopic scaffold, comprising:
four longitudinal uprights 1;
the pulleys 2 and the ground supporting devices 3 are respectively arranged at the bottom of each longitudinal upright rod 1;
the vertical rods 4 are respectively arranged between the two vertical rods, and the bottom ends of the vertical rods 4 are away from the ground by a preset distance;
the two ends of each cross rod 5 are respectively connected with two adjacent vertical rods or respectively connected with the adjacent vertical rods 2 and 1 through hinges 6;
the two ends of each fence rod 7 are respectively connected with the middle upper parts of the vertical rods 2 and the vertical rods 1;
and the detachable platform pedal 10 is respectively connected with the vertical rod 2 and the middle upper part of the vertical rod 1.
The invention comprises the following steps: the telescopic folding scaffold is movable through the pulleys, the operation position is flexibly adjusted, and when the telescopic folding scaffold is moved to the operation position and needs to be fixed, the ground supporting device can be supported on the ground to fix the telescopic folding scaffold; the utility model discloses a folding support body of device during operation, including the hinge that connects on the montant, the hinge that connects on the montant is opened to the hinge that also has one in the middle of whole support body and passes through railing articulated montant with both sides pole setting, also sets up two bearing diagonal simultaneously and ensures that the device during operation is stable, thereby can save space when not using.
The movable telescopic scaffold is simple in structure, low in manufacturing cost and easy to disassemble and assemble, the platform pedals can be disassembled, storage space is greatly saved, the scaffold is convenient to carry, store and carry, the installed pulleys are convenient to move the scaffold, the ground supporting device at the bottom can ensure the stability of a frame body, the integral foldability also provides convenience for the use scene of the scaffold, and working efficiency and construction progress are improved.
When the scaffold is detached, the scaffold can be used as a scaffold for operation, and can be folded when not in use, so that the space is saved. Meanwhile, the invention can also be flexibly carried and used when the structure of the operation layer is complex and the movement is inconvenient.
The invention can solve the problem of disassembling the prefabricated buckles at the upper ends of the prefabricated parts with different spans, reduce the operation time, and simultaneously solve the problem that the disassembled frame body can be rapidly and flexibly transported under the terrain with a complex operation layer, thereby effectively improving the disassembling speed and improving the overall construction progress.
In an embodiment of the mobile telescopic scaffolding of the present invention, as shown in fig. 2, a first inclined strut 9 is connected between two adjacent vertical rods.
In this case, a diagonal brace is provided between the adjacent uprights on the left and right sides to ensure stability.
In an embodiment of the mobile telescopic scaffolding of the present invention, as shown in fig. 1, a second diagonal brace 8 is connected between adjacent vertical poles and vertical poles.
In an embodiment of the mobile telescopic scaffold of the present invention, the detachable platform footplate 10 is further connected to the railing 5 to ensure the stability of the platform footplate and the railing.
As shown in fig. 3 and 4, in an embodiment of the mobile retractable scaffold of the present invention, the ground support device 3 includes:
the upper part of the support frame 31 is connected with the upright rod;
a screw rod 32 disposed at a lower portion of the support frame 31;
a rotating rod 33 connected to the upper part of the screw rod 32, wherein the rotating rod 33 is used for adjusting the extending length of the screw rod 32;
a supporting plate 34 connected to the bottom of the screw rod 32, the supporting plate 34 being for contact support with the ground.
As shown in fig. 5, a prefabricated wall panel 11 is selected for which a rigging needs to be dismantled; the movable telescopic scaffold is pushed to the front of the prefabricated wall plate 11, the movable telescopic scaffold, the fixed platform pedal 10 and the railing 7 are unfolded; a fixed ground bottom support 3; the railing 7 is properly adjusted, and after safety is ensured, safe construction is started.
As shown in fig. 1 to 5, the present invention provides a method for installing a movable telescopic scaffold, comprising:
step S1, four longitudinal vertical rods are arranged;
step S2, respectively arranging pulleys and ground supporting devices at the bottom of each longitudinal upright;
step S3, respectively arranging a vertical rod between two vertical rods, wherein the bottom end of the vertical rod is a preset distance away from the ground;
step S4, arranging a plurality of cross bars, wherein two ends of each cross bar are respectively connected with two adjacent vertical bars or respectively connected with adjacent vertical bars and vertical bars through hinges;
step S5, a plurality of detachable and foldable enclosure bars are arranged, wherein, two ends of each enclosure bar are respectively connected with the vertical bars and the middle upper parts of the vertical bars;
and step S6, connecting the detachable platform pedal with the middle upper parts of the vertical rods and the vertical rods respectively.
The invention comprises the following steps: the telescopic folding scaffold is movable through the pulleys, the operation position is flexibly adjusted, and when the telescopic folding scaffold is moved to the operation position and needs to be fixed, the ground supporting device can be supported on the ground to fix the telescopic folding scaffold; the utility model discloses a folding support body of device during operation, including the hinge that connects on the montant, the hinge that connects on the montant is opened to the hinge that also has one in the middle of whole support body and passes through railing articulated montant with both sides pole setting, also sets up two bearing diagonal simultaneously and ensures that the device during operation is stable, thereby can save space when not using.
The movable telescopic scaffold is simple in structure, low in manufacturing cost and easy to disassemble and assemble, the platform pedals can be disassembled, storage space is greatly saved, the scaffold is convenient to carry, store and carry, the installed pulleys are convenient to move the scaffold, the ground supporting device at the bottom can ensure the stability of a frame body, the integral foldability also provides convenience for the use scene of the scaffold, and working efficiency and construction progress are improved.
When the scaffold is detached, the scaffold can be used as a scaffold for operation, and can be folded when not in use, so that the space is saved. Meanwhile, the invention can also be flexibly carried and used when the structure of the operation layer is complex and the movement is inconvenient.
The invention can solve the problem of disassembling the prefabricated buckles at the upper ends of the prefabricated parts with different spans, reduce the operation time, and simultaneously solve the problem that the disassembled frame body can be rapidly and flexibly transported under the terrain with a complex operation layer, thereby effectively improving the disassembling speed and improving the overall construction progress.
As shown in fig. 2, in an embodiment of the method for installing a mobile retractable scaffold of the present invention, the method further includes:
and a first inclined support is connected between two adjacent vertical rods.
In this case, a diagonal brace is provided between the adjacent uprights on the left and right sides to ensure stability.
In an embodiment of the method for installing a mobile retractable scaffold of the present invention, the method further includes:
and a second inclined support is connected between the adjacent vertical rod and the vertical rod.
In an embodiment of the method for installing a mobile retractable scaffold of the present invention, the method further includes:
will the detachable platform footboard with the railing is connected to guarantee the stability of platform footboard and railing.
As shown in fig. 3 and 4, in one embodiment of the method for installing a mobile retractable scaffold according to the present invention, a ground support means is provided at the bottom of each vertical pole, and comprises:
connecting the upper part of the support frame with the upright stanchion;
the upper part of the screw rod is connected with a rotating rod, and the rotating rod is used for adjusting the extending length of the screw rod;
a screw rod is arranged at the lower part of the support frame;
and the bottom of the screw rod is connected with a support plate, and the support plate is used for being in contact with the ground for supporting.
As shown in fig. 5, a prefabricated wall panel is selected that requires removal of a hoist rigging; the movable telescopic scaffold is pushed to the front of a wall, and the movable telescopic scaffold, the fixed platform pedal and the railing are unfolded; fixing a ground bottom support; and adjusting the railing rod properly, and starting safe construction after ensuring safety.
The embodiments in the present description are described in a progressive manner, each embodiment focuses on differences from other embodiments, and the same and similar parts among the embodiments are referred to each other.
It will be apparent to those skilled in the art that various changes and modifications may be made in the invention without departing from the spirit and scope of the invention. Thus, if such modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include such modifications and variations.

Claims (10)

1. A mobile, telescopic scaffold, comprising:
four longitudinal vertical rods;
the pulleys and the ground supporting device are respectively arranged at the bottom of each longitudinal upright rod;
the vertical rods are respectively arranged between the two vertical rods, and the bottom ends of the vertical rods are away from the ground by a preset distance;
the two ends of each cross rod are respectively connected with the two adjacent vertical rods or respectively connected with the adjacent vertical rods and the vertical rods through hinges;
the two ends of each fence rod are respectively connected with the vertical rods and the middle upper parts of the vertical rods;
and the detachable platform pedal is respectively connected with the vertical rod and the middle upper part of the vertical rod.
2. A mobile telescopic scaffold according to claim 1, wherein a first diagonal brace is connected between adjacent legs.
3. A mobile telescopic scaffold according to claim 1, wherein a second diagonal brace is connected between adjacent vertical posts and uprights.
4. The mobile, retractable scaffold of claim 1, wherein said removable platform deck is further connected to said railing.
5. The mobile, retractable scaffold of claim 1, wherein said ground support means comprises:
the upper part of the support frame is connected with the upright stanchion;
the screw rod is arranged at the lower part of the support frame;
the rotating rod is connected to the upper part of the screw rod and is used for adjusting the extending length of the screw rod;
and the supporting plate is connected to the bottom of the screw rod and is used for being in contact with the ground to support.
6. A method for installing a mobile telescopic scaffold, comprising:
four longitudinal vertical rods are arranged;
pulleys and ground supporting devices are respectively arranged at the bottom of each longitudinal upright rod;
vertical rods are respectively arranged between the two vertical rods, wherein the bottom ends of the vertical rods are away from the ground by a preset distance;
arranging a plurality of cross rods, wherein two ends of each cross rod are respectively connected with two adjacent vertical rods or respectively connected with adjacent vertical rods and vertical rods through hinges;
a plurality of detachable folding type enclosure poles are arranged, wherein two ends of each enclosure pole are respectively connected with the middle upper parts of the vertical rods and the vertical rods;
and the detachable platform pedal is respectively connected with the middle upper parts of the vertical rods and the vertical rods.
7. The mobile, retractable scaffold of claim 6, further comprising:
and a first inclined support is connected between two adjacent vertical rods.
8. The mobile, retractable scaffold of claim 6, further comprising:
and a second inclined support is connected between the adjacent vertical rod and the vertical rod.
9. The mobile, retractable scaffold of claim 6, further comprising:
connecting the detachable platform deck to the railing.
10. A mobile telescopic scaffold according to claim 6, wherein ground support means are provided at the bottom of each longitudinal upright, comprising:
connecting the upper part of the support frame with the upright stanchion;
the upper part of the screw rod is connected with a rotating rod, and the rotating rod is used for adjusting the extending length of the screw rod;
a screw rod is arranged at the lower part of the support frame;
and the bottom of the screw rod is connected with a support plate, and the support plate is used for being in contact with the ground for supporting.
CN202010404812.8A 2020-05-14 2020-05-14 Movable telescopic scaffold and installation method thereof Pending CN111519882A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010404812.8A CN111519882A (en) 2020-05-14 2020-05-14 Movable telescopic scaffold and installation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010404812.8A CN111519882A (en) 2020-05-14 2020-05-14 Movable telescopic scaffold and installation method thereof

Publications (1)

Publication Number Publication Date
CN111519882A true CN111519882A (en) 2020-08-11

Family

ID=71912624

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010404812.8A Pending CN111519882A (en) 2020-05-14 2020-05-14 Movable telescopic scaffold and installation method thereof

Country Status (1)

Country Link
CN (1) CN111519882A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101314988A (en) * 2008-06-28 2008-12-03 张建元 Assembly scaffold
CN201605792U (en) * 2009-12-24 2010-10-13 苏州宝富轻工制品有限公司 Foldable lifting scaffold
JP2011052474A (en) * 2009-09-03 2011-03-17 Nikko Co Ltd Foldable working scaffold
CN103321397A (en) * 2013-05-03 2013-09-25 武济群 Folding scaffold
CN204282793U (en) * 2014-11-27 2015-04-22 中国建筑一局(集团)有限公司 Packaged type groined type type steel scaffold
CN208039774U (en) * 2018-03-21 2018-11-02 湖北沛函建设有限公司 A kind of dual-purpose removable scaffold of low layer
CN212613607U (en) * 2020-05-14 2021-02-26 上海建工五建集团有限公司 Movable telescopic scaffold

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101314988A (en) * 2008-06-28 2008-12-03 张建元 Assembly scaffold
JP2011052474A (en) * 2009-09-03 2011-03-17 Nikko Co Ltd Foldable working scaffold
CN201605792U (en) * 2009-12-24 2010-10-13 苏州宝富轻工制品有限公司 Foldable lifting scaffold
CN103321397A (en) * 2013-05-03 2013-09-25 武济群 Folding scaffold
CN204282793U (en) * 2014-11-27 2015-04-22 中国建筑一局(集团)有限公司 Packaged type groined type type steel scaffold
CN208039774U (en) * 2018-03-21 2018-11-02 湖北沛函建设有限公司 A kind of dual-purpose removable scaffold of low layer
CN212613607U (en) * 2020-05-14 2021-02-26 上海建工五建集团有限公司 Movable telescopic scaffold

Similar Documents

Publication Publication Date Title
JPH11241499A (en) Timbering
CN111155751A (en) Foldable construction platform and construction method
CN209799303U (en) A scalable platform for construction
KR102059552B1 (en) Modular work platform of a long span bridge main tower rebar and construction method using the same
CN212613607U (en) Movable telescopic scaffold
CN117248714B (en) Construction platform and construction method for horizontal beam plates of mutually climbing steel upright posts
CN210369816U (en) External scaffold
CN111519882A (en) Movable telescopic scaffold and installation method thereof
CN112252460A (en) Prefabricated balcony convenient to disassemble and method
CN114232968B (en) Attached lifting scaffold device
CN213563427U (en) Precast beam removes stretch-draw rack
CN105019657A (en) Building construction system
CN210264006U (en) Building faces limit structure post construction protection frame
CN109537868B (en) Portable operation platform for hoisting assembled main beams
CN209261194U (en) A kind of fixed bracket of collapsible quick overturn-preventing for movable Scaffold
CN107190974B (en) Cable tower combined type inner sliding die construction method and inner platform frame used by same
CN216405138U (en) Integrated pier making machine device
CN218562942U (en) Telescopic scaffold
JP2009121100A (en) Foldable working scaffold
CN219261673U (en) Movable scaffold for building construction
CN209817424U (en) Movable adjustable cantilever operation platform applicable to overlong cantilever structure
GB2408285A (en) Self-contained extensible mobile access tower
CN219604806U (en) Portable scaffold for house building
CN219654212U (en) Reinforcing operation platform for constructional engineering
CN220451374U (en) Foldable building scaffold

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination