CN111519550A - A hanging basket suspension pouring system for a central cable-plane concrete cable-stayed bridge - Google Patents

A hanging basket suspension pouring system for a central cable-plane concrete cable-stayed bridge Download PDF

Info

Publication number
CN111519550A
CN111519550A CN202010398623.4A CN202010398623A CN111519550A CN 111519550 A CN111519550 A CN 111519550A CN 202010398623 A CN202010398623 A CN 202010398623A CN 111519550 A CN111519550 A CN 111519550A
Authority
CN
China
Prior art keywords
cable
truss
longitudinal beam
basket
anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010398623.4A
Other languages
Chinese (zh)
Inventor
李习春
杨天伟
肖广生
何润
刘洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Xiamen Engineering Co Ltd
Original Assignee
CCCC First Highway Xiamen Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Xiamen Engineering Co Ltd filed Critical CCCC First Highway Xiamen Engineering Co Ltd
Priority to CN202010398623.4A priority Critical patent/CN111519550A/en
Publication of CN111519550A publication Critical patent/CN111519550A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明提供了一种中央索面混凝土斜拉桥挂篮悬浇系统,所述挂篮为三角挂篮,承载平台、下桁架、上桁架分别通过锚固单元锚固于已浇筑梁段上,通过悬挂单元将底篮吊挂在上桁架上,通过行走单元牵引上桁架及底篮在梁段上位移,通过牵索单元将斜拉索与挂篮连接起来形成前支点;所述承载平台包括两侧的辅纵梁以及中间的主纵梁,主纵梁和辅纵梁通过若干联系梁连接,所述主纵梁的非锚端设有牵索单元,所述牵索单元上设有相对滑移装置用于调节斜拉索张拉角度,本发明解决了单索面斜拉桥采用常规牵索挂篮施工横向稳定性差的问题,也发挥了斜拉桥采用牵索挂篮的优势。

Figure 202010398623

The invention provides a hanging and pouring system for a hanging basket of a central cable-plane concrete cable-stayed bridge. The hanging basket is a triangular hanging basket. The unit hangs the bottom basket on the upper truss, pulls the upper truss and the bottom basket to displace on the beam section through the walking unit, and connects the stay cable and the hanging basket through the pulling cable unit to form a front fulcrum; the bearing platform includes two sides. The auxiliary longitudinal beam and the main longitudinal beam in the middle, the main longitudinal beam and the auxiliary longitudinal beam are connected by several connecting beams, the non-anchor end of the main longitudinal beam is provided with a pulling cable unit, and the pulling cable unit is provided with a relative sliding device for In order to adjust the tension angle of the cable-stayed cable, the invention solves the problem of poor lateral stability in the construction of the single-cable plane cable-stayed bridge using the conventional drag-cable hanging basket, and also brings into play the advantage of using the drag-cable hanging basket for the cable-stayed bridge.

Figure 202010398623

Description

一种中央索面混凝土斜拉桥挂篮悬浇系统A hanging basket suspension pouring system for a central cable-plane concrete cable-stayed bridge

技术领域technical field

本发明涉及混凝土斜拉桥主梁施工技术领域,特别涉及一种中央索面混凝土斜拉桥挂篮悬浇系统。The invention relates to the technical field of main girder construction of concrete cable-stayed bridges, in particular to a hanging basket suspension pouring system of a central cable-plane concrete cable-stayed bridge.

背景技术Background technique

斜拉桥主梁施工方法与梁式桥基本相同,大跨度斜拉桥一般采用悬臂浇筑法或悬臂拼装法,对于跨径不大的斜拉桥,根据现场工程地形等施工条件也可以采用全支架现浇法、活动支架现浇法、顶推法和转体法施工。上述几种施工方法中,由于悬臂法适用范围较广而成为斜拉桥主梁最常用的施工方法,其余几种施工方法使用范围较为有限。斜拉桥主梁施工采用的挂篮形式很多,各有特色,但常用挂篮形式归纳起来可以分为三类,即后锚点挂篮、劲性骨架挂篮和前支点挂篮。对于单箱多室箱形截面的中央索面预应力混凝土斜拉桥来说,常规的前支点挂篮已经不能满足施工的需要。The construction method of the main beam of the cable-stayed bridge is basically the same as that of the girder bridge. The long-span cable-stayed bridge generally adopts the cantilever casting method or the cantilever assembly method. Pouring method, movable bracket cast-in-place method, jacking method and rotation method construction. Among the above construction methods, the cantilever method has become the most commonly used construction method for the main beam of the cable-stayed bridge due to its wide application range, while the other construction methods are limited in scope. There are many forms of hanging baskets used in the construction of the main beam of cable-stayed bridges, each with its own characteristics, but the commonly used hanging baskets can be summarized into three categories, namely rear anchor hanging baskets, rigid skeleton hanging baskets and front fulcrum hanging baskets. For a single-box multi-chamber box-section central cable-plane prestressed concrete cable-stayed bridge, the conventional front fulcrum hanging basket can no longer meet the needs of construction.

发明内容SUMMARY OF THE INVENTION

为解决上述技术问题,本发明提供了一种中央索面混凝土斜拉桥挂篮悬浇系统,所述挂篮为三角挂篮,包括上桁架、由承载平台和下桁架构成的底篮、锚固单元、悬挂单元、行走单元、牵索单元、模板单元,所述承载平台、下桁架、上桁架分别通过锚固单元锚固于已浇筑梁段上,通过悬挂单元将底篮吊挂在上桁架上,通过行走单元牵引上桁架及底篮在梁段上位移,通过牵索单元将斜拉索与挂篮连接起来形成前支点;所述承载平台包括两侧的辅纵梁以及中间的主纵梁,主纵梁和辅纵梁通过若干联系梁连接,所述主纵梁的非锚端设有牵索单元,所述牵索单元上设有相对滑移装置用于调节斜拉索张拉角度。In order to solve the above technical problems, the present invention provides a hanging and pouring system for a central cable-plane concrete cable-stayed bridge. unit, suspension unit, walking unit, pulling cable unit, template unit, the bearing platform, lower truss, and upper truss are respectively anchored on the poured beam section through the anchoring unit, and the bottom basket is hung on the upper truss through the suspension unit, The upper truss and the bottom basket are pulled by the walking unit to displace on the beam section, and the stay cable and the hanging basket are connected to form the front fulcrum through the pulling cable unit; the bearing platform includes the auxiliary longitudinal beams on both sides and the main longitudinal beam in the middle. The main longitudinal beam and the auxiliary longitudinal beam are connected by several connecting beams, the non-anchor end of the main longitudinal beam is provided with a stay cable unit, and the stay cable unit is provided with a relative sliding device for adjusting the tension angle of the stay cable.

进一步,所述承载平台由内侧的2道主纵梁、外侧2道辅助纵梁和若干道联系梁组成,采用钢板焊接成钢箱整体,2道主纵梁的向后延伸形成主纵梁锚段,所述主纵梁锚段的两侧分别设有轨道梁用于底篮牵引行走。Further, the bearing platform is composed of 2 main longitudinal beams on the inner side, 2 auxiliary longitudinal beams on the outer side and several connecting beams, which are welded by steel plates to form a whole steel box, and the rearward extension of the 2 main longitudinal beams forms the main longitudinal beam anchors. The two sides of the main longitudinal beam anchor section are respectively provided with track beams for the traction of the bottom basket.

进一步,所述上桁架由4榀三角桁架组成,包括2榀内三角桁架和2榀外三角桁架,所述内三角桁架位于主梁边腹板顶部,所述外三角桁架位于主梁斜腹板顶部,所述对应侧的内三角桁架、外三角间通过平联连接成整体。Further, the upper truss is composed of 4 triangular trusses, including 2 inner triangular trusses and 2 outer triangular trusses, the inner triangular truss is located on the top of the side web of the main girder, and the outer triangular truss is located on the inclined web of the main girder. At the top, the inner triangular trusses and the outer triangles on the corresponding side are connected into a whole by parallel connection.

进一步,所述下桁架由若干桁架片通过平联连接构成,桁架片内部设有斜撑支撑,所述桁架片与承载平台的辅纵梁采用上、下销接方式连接,下桁架的锚端设有锚固桁片。Further, the lower truss is composed of a plurality of truss pieces connected by parallel connection, the truss pieces are provided with diagonal bracing supports, the truss pieces and the auxiliary longitudinal beams of the bearing platform are connected by upper and lower pin connections, and the anchor ends of the lower trusses are connected. Equipped with anchor girders.

进一步,所述行走单元包括上桁架行走单元和底篮行走单元,所述上桁架行走单元包括预设在梁段上的行走反力架、上桁架底部的反压滚轮、设置在上桁架中部下端支撑垫块,通过牵引千斤顶及牵引索牵引行走;所述底篮行走单元包括套设在上桁架的纵梁非锚段的行走滑靴、设置在主纵梁两侧的轨道梁上的反挂滑车、连接行走滑靴与反挂滑车的联系钢带、预设在上桁架的纵梁前端的牵引反力架,通过千斤顶及牵引索牵引行走。Further, the walking unit includes an upper truss walking unit and a bottom basket walking unit, and the upper truss walking unit includes a walking reaction frame preset on the beam section, a back pressure roller at the bottom of the upper truss, and a lower end of the middle of the upper truss. The support pad is pulled and traveled by traction jacks and traction cables; the bottom basket walking unit includes a walking shoe sleeved on the non-anchor section of the longitudinal beam of the upper truss, and anti-hanging shoes arranged on the track beams on both sides of the main longitudinal beam The pulley, the connecting steel belt connecting the walking shoes and the anti-trailer pulley, and the traction reaction frame preset at the front end of the longitudinal beam of the upper truss, are pulled by the jack and the traction cable.

进一步,所述锚固单元设置在已浇筑梁段混凝土上,包括主纵梁锚固、辅助纵梁锚固、下桁架锚固、上桁架锚固、反挂滑车锚固。Further, the anchoring unit is arranged on the concrete of the poured beam section, including main longitudinal beam anchoring, auxiliary longitudinal beam anchoring, lower truss anchoring, upper truss anchoring, and reverse pulley anchoring.

进一步,所述悬挂单元设置在挂篮上桁架与底篮之间,包括辅助纵梁前悬吊、下桁架前悬吊。Further, the suspension unit is arranged between the upper truss and the bottom basket of the hanging basket, including auxiliary longitudinal beam front suspension and lower truss front suspension.

进一步,所述相对滑移装置设置在主纵梁前端,所述主纵梁前端伸长上翘形成滑移斜面,滑移斜面的长度与对应斜拉索的辐射范围成正比,所述相对滑移装置由调节块限位器、调节块、分配梁、销轴、轨道、轨道限位器构成,所述轨道限位器焊接安装在滑移斜面上下两侧,所述调节块限位器焊接安装在滑移斜面的左右两侧,4根轨道采用精轧螺纹钢,穿过上下轨道限位器的预留孔洞并利用螺母进行固定,所述调节块穿设在轨道上,并限制在调节块限位器中,利用螺母将调节块上下限制住保证调节块能够固定在轨道任意位置,利用销轴将调节块与分配梁进行销接,使得分配梁能够绕着销轴轴线旋转,从而达到分配梁角度调节更加方便快速,保证斜拉索张拉角度,使得斜拉索受力装置能够在滑移平面上滑动。Further, the relative sliding device is arranged at the front end of the main longitudinal beam, the front end of the main longitudinal beam is elongated and upturned to form a sliding slope, and the length of the sliding slope is proportional to the radiation range of the corresponding stay cable, and the relative sliding The moving device is composed of an adjustment block limiter, an adjustment block, a distribution beam, a pin shaft, a track, and a track limiter. The track limiter is welded and installed on the upper and lower sides of the sliding slope, and the adjustment block limiter is welded. Installed on the left and right sides of the sliding slope, the 4 rails are made of fine-rolled threaded steel, pass through the reserved holes of the upper and lower rail limiters and are fixed with nuts. In the block stopper, the adjusting block is limited up and down by a nut to ensure that the adjusting block can be fixed at any position on the track, and the adjusting block is pinned to the distribution beam by a pin, so that the distribution beam can rotate around the axis of the pin, so as to achieve The adjustment of the angle of the distribution beam is more convenient and fast, and the tension angle of the stay cable is ensured, so that the force bearing device of the stay cable can slide on the sliding plane.

进一步,所述底篮设有定位装置,包括顶升机构,主纵梁前、后锚杆组,止推机构。Further, the bottom basket is provided with a positioning device, including a jacking mechanism, front and rear anchor rod groups of the main longitudinal beam, and a thrust mechanism.

进一步,所述模板单元的底模和侧模均采用大块钢模板,与底篮连接成整体,随底篮共同前移和提升,所述内膜采用小块钢模组拼而成,面板后设置槽钢背楞,侧板采用对拉螺杆固定,顶板采用小钢管进行支撑,不设置内模底板。Further, the bottom mold and the side mold of the template unit are made of large steel templates, which are connected to the bottom basket as a whole, and move forward and lift together with the bottom basket. The inner film is made of small steel molds. The back corrugation of channel steel is set at the back, the side plate is fixed by the pull screw, the top plate is supported by small steel pipe, and the bottom plate of the inner mold is not set.

有益效果beneficial effect

应用本发明的技术方案,在混凝土斜拉桥主梁浇筑状态下,保留前支点挂篮前端设置斜拉索牵索机构,采用斜拉索承担挂篮平台自身重力,在上桁架锚固于已浇筑梁段上后,在挂篮平台上设置连于上桁架的吊杆,将挂篮平台与上桁架连接,并限定前吊杆在施工中始终保持一定拉力,形成后支点的形式,使挂篮平台的后锚固点直接作用于已浇梁段上的反力减少到不足平台反力的一半,并利用上桁架较大的刚度,确保混凝土主梁的线形匀顺并符合设计要求。在挂篮行走状态下,采用内侧上桁架滑靴挂吊平台,平台采用行走滑轮挂吊在已浇筑的梁段相结合的行走方式,使得行走除了梁段受力还有上桁架受力。Applying the technical scheme of the present invention, in the pouring state of the main girder of the concrete cable-stayed bridge, the front end of the hanging basket of the front fulcrum is reserved and the cable-stayed cable mechanism is installed, and the cable-stayed cable is used to bear the weight of the hanging basket platform, and the upper truss is anchored to the already poured truss. After the beam section is installed, a boom connected to the upper truss is set on the hanging basket platform to connect the hanging basket platform with the upper truss, and the front boom is limited to maintain a certain tension during construction to form a rear fulcrum, so that the hanging basket The reaction force directly acting on the poured beam section by the rear anchor point of the platform is reduced to less than half of the platform reaction force, and the higher stiffness of the upper truss is used to ensure that the line of the concrete main beam is uniform and meets the design requirements. In the walking state of the hanging basket, the upper truss shoe on the inner side is used to hang the platform, and the platform adopts the walking mode of the walking pulley hanging on the poured beam section, so that in addition to the beam section, the upper truss is also stressed.

附图说明Description of drawings

图1为本发明实施例的结构示意图;1 is a schematic structural diagram of an embodiment of the present invention;

图2为图1中上桁架的结构示意图;Fig. 2 is the structural schematic diagram of the upper truss in Fig. 1;

图3为图1中承重底篮的结构示意图;Fig. 3 is the structural representation of the load-bearing bottom basket in Fig. 1;

图4为图1中行走小车的结构示意图;Fig. 4 is the structural representation of the walking trolley in Fig. 1;

图5为图1中锚固系统的结构示意图;FIG. 5 is a schematic structural diagram of the anchoring system in FIG. 1;

图6为图1中牵索系统的结构示意图。FIG. 6 is a schematic structural diagram of the guying system in FIG. 1 .

具体实施方式Detailed ways

以下结合具体实施例,对本发明进一步说明。以下实施例仅用于说明本发明而非用于限制本发明的范围。The present invention will be further described below with reference to specific embodiments. The following examples are only used to illustrate the present invention and not to limit the scope of the present invention.

如图1-6所示,本发明提供了一种中央索面混凝土斜拉桥挂篮悬浇系统,包括承载平台、下桁架、上桁架、牵索单元、行走单元、锚固单元、悬挂单元、模板单元。其中,承载平台包括主纵梁1和辅助纵梁2,主纵梁1由四节段组成,主纵梁1之间、主纵梁1与辅助纵梁2之间由联系梁7采用高强螺栓进行连接;下桁架由桁架片3和锚固桁片9组成,桁架片3共计5片,由纵梁以及桁架间的平联和斜撑组成,与挂篮承载平台辅助纵梁2采用上、下销接方式连接;上桁架包括内侧主桁架11、外侧主桁架12、桁架锚杆组13以及支撑垫块19,内侧主桁架11及外侧主桁架12由纵梁、立柱、前后拉杆等组成。纵梁及立柱均采用Q345钢板焊接而成的钢箱,前、后拉杆均采用钢板带,立柱接头和节点板均采用高强螺栓连接;牵索系统包括分配梁26、调节块25、销轴26、Φ40精轧螺纹钢形成的轨道及螺母27。调节块25可在主纵梁1沿着斜面轨道槽内滑动,分配梁26与调节块25采用销接方式,能够绕着调节块转动,因而能调整前支点斜拉索纵桥向的位置和角度,以适应斜拉索空间位置和角度的变化;行走单元包括滑靴18及联系钢带、牵引反力架16、反挂滑车21、反挂滑车底座20、轨道梁10、牵引千斤顶及牵引索,已浇混凝土强度达标,挂篮承载平台前移前,上桁架先前移一个节段,然后主桁尾部与已浇混凝土节段锚固,承载平台下降实现脱模。承载平台下放到位后,插入承载平台和主桁之间联系钢带的插销,调整后部反挂滑车21,让其受力,然后撤除所有的前后锚杆组8,承载平台即可在两台千斤顶作用下通过反力架16及φ32精轧螺纹钢筋牵引主桁上的滑靴,从而带动挂篮底篮实现前移;As shown in Figures 1-6, the present invention provides a hanging basket suspension pouring system for a central cable-plane concrete cable-stayed bridge, including a bearing platform, a lower truss, an upper truss, a cable unit, a walking unit, an anchoring unit, a suspension unit, Template unit. Among them, the bearing platform includes a main longitudinal beam 1 and an auxiliary longitudinal beam 2. The main longitudinal beam 1 is composed of four segments. Between the main longitudinal beam 1 and between the main longitudinal beam 1 and the auxiliary longitudinal beam 2, the connecting beam 7 adopts high-strength bolts. Connect; the lower truss is composed of truss piece 3 and anchor truss piece 9. The truss piece 3 has a total of 5 pieces. The upper truss includes an inner main truss 11, an outer main truss 12, a truss anchor rod group 13 and a support block 19. The inner main truss 11 and the outer main truss 12 are composed of longitudinal beams, columns, front and rear tie rods, etc. Longitudinal beams and columns are made of steel boxes welded with Q345 steel plates, front and rear tie rods are made of steel strips, column joints and gusset plates are connected by high-strength bolts; the stay cable system includes distribution beam 26, adjustment block 25, pin 26 , The track and nut 27 formed by Φ40 finishing rebar. The adjustment block 25 can slide in the main longitudinal beam 1 along the inclined track groove, and the distribution beam 26 and the adjustment block 25 are pinned and can be rotated around the adjustment block, so that the position and the longitudinal bridge direction of the front fulcrum stay cable can be adjusted. Angle, to adapt to the change of the space position and angle of the stay cable; the walking unit includes the sliding shoe 18 and the connecting steel belt, the traction reaction frame 16, the reverse pulley 21, the reverse pulley base 20, the track beam 10, the traction jack and the traction The strength of the poured concrete reaches the standard. Before the hanging basket bearing platform is moved forward, the upper truss is moved forward by one segment, and then the tail of the main truss is anchored with the poured concrete segment, and the bearing platform is lowered to realize demoulding. After the bearing platform is lowered into place, insert the bolt connecting the steel belt between the bearing platform and the main girder, adjust the rear reverse pulley 21 to make it bear the force, and then remove all the front and rear anchor rod groups 8, and the bearing platform can be installed on the two sets. Under the action of the jack, the sliding shoe on the main truss is pulled through the reaction frame 16 and the φ32 fine-rolled threaded steel bar, so as to drive the bottom basket of the hanging basket to move forward;

锚固单元包括对应设置的主纵梁锚固、辅助纵梁锚固、下桁架锚固、上桁架锚固、反挂滑车锚固。其中,主纵梁锚固包括前锚杆组8和后锚杆组,其中锚杆组8由分配梁22、Φ40精轧螺纹钢23以及螺母垫片24组成。主纵梁前锚杆组8设在主纵梁1中部,主纵梁后锚杆组设在主纵梁1尾部,其作用是平衡挂篮斜拉索初张拉时产生的倾覆力,同时亦作为抗风安全锚固点,下桁架锚固设在尾部连接的锚固桁片9的上方,上桁架锚固包括其纵梁后端设有的桁架锚杆组13,悬挂系统包括辅助纵梁前悬吊14、下桁架前悬吊15,使得底篮和上桁架连接成整体,模板系统由底模、侧模、内模等组成,模板单元的底模和侧模均采用大块钢模板,与底篮连接成整体,随底篮共同前移和提升,所述内膜采用小块钢模组拼而成,面板后设置槽钢背楞,侧板采用对拉螺杆固定,顶板采用小钢管进行支撑,不设置内模底板。The anchoring unit includes corresponding main longitudinal beam anchorage, auxiliary longitudinal beam anchorage, lower truss anchorage, upper truss anchorage, and anti-trailer pulley anchorage. Among them, the main longitudinal beam anchorage includes a front bolt group 8 and a rear bolt group, wherein the bolt group 8 is composed of a distribution beam 22 , a Φ40 finish-rolled threaded steel 23 and a nut washer 24 . The front anchor rod group 8 of the main longitudinal beam is located in the middle of the main longitudinal beam 1, and the rear anchor rod group of the main longitudinal beam is located at the tail of the main longitudinal beam 1. Also as a wind-resistant safety anchor point, the lower truss is anchored above the anchor truss 9 connected at the tail, the upper truss anchor includes the truss bolt group 13 provided at the rear end of its longitudinal beam, and the suspension system includes auxiliary longitudinal beam front suspension 14, The lower truss is suspended by 15 in front, so that the bottom basket and the upper truss are connected as a whole. The formwork system is composed of bottom mold, side mold, inner mold, etc. As a whole, it moves forward and lifts together with the bottom basket. The inner membrane is made of small steel modules. The back of the channel steel is set behind the panel. Set the inner mold base plate.

使用时,在浇筑混凝土斜拉桥主梁混凝土前,进行预埋上主桁左右限位,连接内外侧主桁形成整体,单侧内外侧主桁同步行进,主桁行走前,安装内外侧主桁反压滚轮,拆除主桁后锚锚杆组,在主桁下方设计位置安装支撑垫块并固定牢靠,固定滑靴,避免主桁行走带动滑靴。采用千斤顶和预埋反力点作为前进装置,每一行程15cm,主桁走到设计位置后,利用主桁锚杆组进行锚固打紧。主桁行走到位后,将辅助纵梁前吊杆通过分配梁锚固在内侧主桁上,应锚辅助纵梁最前面锚固孔,避免锚固分配梁与C 型滑靴位置冲突,用于挂篮下放。斜拉索索力转换至箱梁并进行第二次张拉后(即斜拉索体系转换后),再利用主纵梁前锚杆组和辅助纵梁前吊杆组将挂篮下放500mm,操作液压千斤顶应同步平衡下放。待挂篮承重底架下放到达指定位置,采用钢吊带连接C型滑靴与辅助纵梁和行走小车,并保证钢带的上下销接点的连接牢固。然后在轨道未受力之前,将行走小车挂座锚固到位并紧贴底板,挂篮承重底架自身重力受力转换至钢吊带和行走小车上,最终受力在主桁及上一节混凝土上,最后拆除所有的锚杆组,安装C型滑靴和行走轨道反力装置,满足挂篮底篮行走条件。在内侧主桁前端安装70t穿心千斤顶作为前移动力,千斤顶与C型滑靴通过Φ32mm精轧螺纹钢筋连接;在行走轨道末端安装25t穿心千斤顶,千斤顶与行走小车通过直径Φ15.24mm钢绞线连接,挂篮在牵引机构作用下前移至下一节段。挂篮承重底架到位后,迅速对所有锚杆组进行锚固,包括内侧主桁前吊杆,增加锚固点,减少风险,在保证锚杆组完全受力之后,方可拆除钢吊带和行走小车。通过前吊杆和锚杆组提升挂篮,安装止推机构,张拉机构等,立模、调整标高,底模标高调整时,应设专人统一指挥,各控制点派人负责监控。When in use, before pouring the concrete of the main girder of the concrete cable-stayed bridge, the left and right limits of the upper main truss are pre-buried, and the inner and outer main trusses are connected to form a whole. The inner and outer main trusses of one side move synchronously. The back pressure roller of the truss is removed, the rear anchor bolt group of the main truss is removed, the support block is installed at the designed position under the main truss and fixed firmly, and the sliding shoe is fixed to prevent the sliding shoe from being driven by the walking of the main truss. The jack and the pre-embedded reaction force point are used as advance devices, and each stroke is 15cm. After the main truss reaches the design position, the anchor rod group of the main truss is used for anchoring and tightening. After the main girder is in place, anchor the front boom of the auxiliary longitudinal beam on the inner main girder through the distribution beam, and anchor the front anchoring hole of the auxiliary longitudinal beam to avoid the position conflict between the anchor distribution beam and the C-type sliding shoe, which is used for hanging baskets . After the cable force of the stay cable is converted to the box girder and tensioned for the second time (that is, after the conversion of the stay cable system), use the front anchor rod group of the main longitudinal beam and the front suspension rod group of the auxiliary longitudinal beam to lower the hanging basket by 500mm. Hydraulic jacks should be lowered synchronously and balanced. When the load-bearing chassis of the hanging basket is lowered to the designated position, the steel sling is used to connect the C-type sliding shoe, the auxiliary longitudinal beam and the walking trolley, and the connection between the upper and lower pin joints of the steel belt is ensured. Then, before the track is not stressed, anchor the hanging seat of the walking trolley in place and close to the bottom plate. The gravity force of the hanging basket load-bearing chassis itself is transferred to the steel sling and the walking trolley, and finally the force is applied to the main truss and the concrete of the previous section. , and finally remove all anchor rod groups, install C-type sliding shoes and walking track reaction force device to meet the walking conditions of hanging basket bottom basket. A 70t through-center jack is installed at the front end of the inner main girder as the forward movement force. The jack and the C-type slipper are connected by Φ32mm fine-rolled threaded steel bars; a 25t through-center jack is installed at the end of the walking track, and the jack and the traveling trolley pass through the diameter of Φ15.24mm steel strand. Line connection, the hanging basket moves forward to the next segment under the action of the traction mechanism. After the load-bearing chassis of the hanging basket is in place, quickly anchor all the anchor rod groups, including the front boom of the inner main girder, increase the anchorage points and reduce the risk. After ensuring that the anchor rod group is fully stressed, the steel sling and the walking trolley can be removed. . Lift the hanging basket through the front boom and the anchor rod group, install the thrust mechanism, the tension mechanism, etc., when the mold is erected, the elevation is adjusted, and the bottom mold elevation is adjusted, a special person should be assigned for unified command, and each control point is assigned to be responsible for monitoring.

以上所述仅为本发明的优选实施例而已,并不用于限制本发明,对于本领域的技术人员来说,本发明可以有各种更改和变化。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.

Claims (10)

1. A hanging basket suspension casting system of a central cable-faced concrete cable-stayed bridge is characterized in that the bearing platform, the lower truss and the upper truss are respectively anchored on a poured beam section through anchoring units, the bottom basket is hung on the upper truss through suspension units, the upper truss and the bottom basket are drawn to displace on the beam section through the walking units, and a stay cable and the hanging basket are connected through the stay cable units to form a front pivot; the bearing platform comprises auxiliary longitudinal beams on two sides and a middle main longitudinal beam, the main longitudinal beam and the auxiliary longitudinal beams are connected through a plurality of connecting beams, a guy cable unit is arranged at the non-anchor end of the main longitudinal beam, and a relative sliding device is arranged on the guy cable unit and used for adjusting the stretching angle of the stay cable.
2. The suspended basket casting system of a central cable-faced concrete cable-stayed bridge according to claim 1, wherein the bearing platform is composed of 2 inner main longitudinal beams, 2 outer auxiliary longitudinal beams and a plurality of connecting beams, steel plates are welded into a whole steel box, the 2 main longitudinal beams extend backwards to form a main longitudinal beam anchor section, and two sides of the main longitudinal beam anchor section are respectively provided with a track beam for bottom basket traction walking.
3. The system of claim 1, wherein the upper truss is composed of 4 trusses of inner and outer trusses, the inner trusses are located at the top of the side web of the main beam, the outer trusses are located at the top of the inclined web of the main beam, and the inner and outer trusses on the corresponding sides are connected into a whole through a flat connection.
4. The system of claim 1, wherein the lower truss is formed by connecting a plurality of truss pieces in parallel, the truss pieces are internally provided with diagonal bracing supports, the truss pieces are connected with the auxiliary longitudinal beams of the bearing platform in an upper and lower pin joint manner, and the anchor end of the lower truss is provided with an anchoring truss piece.
5. The hanging basket suspension casting system of the central cable-faced concrete cable-stayed bridge according to claim 1, wherein the traveling unit comprises an upper truss traveling unit and a bottom basket traveling unit, the upper truss traveling unit comprises a traveling reaction frame preset on a beam section, a back pressure roller at the bottom of an upper truss, and a support cushion block arranged at the lower end of the middle part of the upper truss, and the traveling unit is pulled by a traction jack and a traction cable; the bottom basket walking unit comprises a walking sliding shoe sleeved on a longitudinal beam non-anchor section of the upper truss, an inverse hanging pulley arranged on the rail beams on two sides of the main longitudinal beam, a contact steel belt for connecting the walking sliding shoe and the inverse hanging pulley, and a traction reaction frame preset at the front end of the longitudinal beam of the upper truss, and the bottom basket walking unit is dragged to walk through a jack and a traction cable.
6. The system of claim 1, wherein the anchoring unit is disposed on the poured beam section concrete, and comprises a main longitudinal beam anchor, an auxiliary longitudinal beam anchor, a lower longitudinal beam anchor, an upper truss anchor and a reverse hanging pulley anchor, the main longitudinal beam anchor comprises a front anchor rod set disposed in the middle of the main longitudinal beam and a rear anchor rod set disposed at the tail of the main longitudinal beam, and the lower truss anchor is disposed above the anchoring truss.
7. The suspended basket casting system of the central cable-faced concrete cable-stayed bridge according to claim 1, wherein the suspension unit is arranged between an upper truss and a bottom basket of the suspended basket and comprises an auxiliary longitudinal beam front suspension and a lower truss front suspension.
8. The hanging basket suspension casting system of the central cable-faced concrete cable-stayed bridge according to claim 1, wherein the relative sliding device is arranged at the front end of the main longitudinal beam, the front end of the main longitudinal beam is extended and upwarps to form a sliding slope, the length of the sliding slope is in direct proportion to the radiation range of the corresponding stay cable, the relative sliding device is composed of an adjusting block limiter, an adjusting block, a distribution beam, a pin shaft, a track and a track limiter, the track limiter is welded and installed at the upper side and the lower side of the sliding slope, the adjusting block limiter is welded and installed at the left side and the right side of the sliding slope, 4 tracks are made of finish-rolled thread steel, pass through reserved holes of the upper and lower track limiters and are fixed by nuts, the adjusting block is penetrated through the track and limited in the adjusting block limiter, the upper and the lower limits of the adjusting block are limited by the nuts to ensure that the adjusting block can be, the adjusting block is connected with the distribution beam in a pin joint mode through the pin shaft, so that the distribution beam can rotate around the axis of the pin shaft, the angle adjustment of the distribution beam is more convenient and quick, the stretching angle of the stay cable is guaranteed, and the stay cable stress device can slide on a sliding plane.
9. The suspended basket casting system of the central cable-faced concrete cable-stayed bridge according to claim 1, wherein the bottom basket is provided with a positioning device which comprises a jacking mechanism, a front anchor rod group, a rear anchor rod group and a thrust mechanism.
10. The central cable-side concrete cable-stayed bridge hanging basket suspension casting system according to claim 1, wherein the bottom die and the side dies of the die plate unit are made of large steel die plates, are connected with the bottom basket into a whole, move forward and lift along with the bottom basket together, the inner film is formed by assembling small steel die plates, a channel steel back edge is arranged behind the face plate, the side plates are fixed by using counter-pulling screw rods, the top plate is supported by using small steel tubes, and an inner die bottom plate is not arranged.
CN202010398623.4A 2020-05-12 2020-05-12 A hanging basket suspension pouring system for a central cable-plane concrete cable-stayed bridge Pending CN111519550A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010398623.4A CN111519550A (en) 2020-05-12 2020-05-12 A hanging basket suspension pouring system for a central cable-plane concrete cable-stayed bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010398623.4A CN111519550A (en) 2020-05-12 2020-05-12 A hanging basket suspension pouring system for a central cable-plane concrete cable-stayed bridge

Publications (1)

Publication Number Publication Date
CN111519550A true CN111519550A (en) 2020-08-11

Family

ID=71908176

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010398623.4A Pending CN111519550A (en) 2020-05-12 2020-05-12 A hanging basket suspension pouring system for a central cable-plane concrete cable-stayed bridge

Country Status (1)

Country Link
CN (1) CN111519550A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112942132A (en) * 2021-04-01 2021-06-11 中交二航局第二工程有限公司 Front supporting point composite hanging basket and shifting method thereof
CN118958174A (en) * 2024-10-15 2024-11-15 中铁五局集团第一工程有限责任公司 A super-large segment front support hanging basket device for bridge construction

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05106210A (en) * 1991-10-16 1993-04-27 P S Co Ltd How to construct a concrete cable-stayed bridge
CN202031033U (en) * 2011-04-18 2011-11-09 湖南中铁五新钢模有限责任公司 Hang fill construction hanging basket for four-lane broad width continuous beam of high-speed railway
CN202064295U (en) * 2011-05-23 2011-12-07 湖南中铁五新钢模有限责任公司 Rear running mechanism of cradle
CN203782590U (en) * 2014-02-18 2014-08-20 中交第二公路工程局有限公司 Tension and cable force adjusting device for stayed cable of cable stayed bridge
CN204370312U (en) * 2014-12-10 2015-06-03 上海市基础工程集团有限公司 The Hanging basket on front support tensioning system of adjustable angle
CN105484163A (en) * 2015-12-23 2016-04-13 中铁大桥局集团第五工程有限公司 Girder-pier sequential construction method of pier top segment of auxiliary pier of cable stayed bridge
CN107034791A (en) * 2017-06-27 2017-08-11 中交第三航务工程局有限公司 A kind of assembling method of Cantilever Casting Construction Hanging Basket
CN207714163U (en) * 2017-12-19 2018-08-10 中交二公局第二工程有限公司 A kind of combined type Hanging Basket
CN210104574U (en) * 2019-03-21 2020-02-21 联建建设工程有限公司 Large-span front fulcrum pull cable hanging basket prestressing system conversion system
CN212358036U (en) * 2020-05-12 2021-01-15 中交一公局厦门工程有限公司 A hanging basket suspension pouring system for a central cable-plane concrete cable-stayed bridge

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05106210A (en) * 1991-10-16 1993-04-27 P S Co Ltd How to construct a concrete cable-stayed bridge
CN202031033U (en) * 2011-04-18 2011-11-09 湖南中铁五新钢模有限责任公司 Hang fill construction hanging basket for four-lane broad width continuous beam of high-speed railway
CN202064295U (en) * 2011-05-23 2011-12-07 湖南中铁五新钢模有限责任公司 Rear running mechanism of cradle
CN203782590U (en) * 2014-02-18 2014-08-20 中交第二公路工程局有限公司 Tension and cable force adjusting device for stayed cable of cable stayed bridge
CN204370312U (en) * 2014-12-10 2015-06-03 上海市基础工程集团有限公司 The Hanging basket on front support tensioning system of adjustable angle
CN105484163A (en) * 2015-12-23 2016-04-13 中铁大桥局集团第五工程有限公司 Girder-pier sequential construction method of pier top segment of auxiliary pier of cable stayed bridge
CN107034791A (en) * 2017-06-27 2017-08-11 中交第三航务工程局有限公司 A kind of assembling method of Cantilever Casting Construction Hanging Basket
CN207714163U (en) * 2017-12-19 2018-08-10 中交二公局第二工程有限公司 A kind of combined type Hanging Basket
CN210104574U (en) * 2019-03-21 2020-02-21 联建建设工程有限公司 Large-span front fulcrum pull cable hanging basket prestressing system conversion system
CN212358036U (en) * 2020-05-12 2021-01-15 中交一公局厦门工程有限公司 A hanging basket suspension pouring system for a central cable-plane concrete cable-stayed bridge

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
梁磊磊;徐财进;刘晨;孔聪: "复合式前支点挂篮设计施工", 《公路交通科技(应用技术版)》, no. 02, 15 February 2020 (2020-02-15), pages 1 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112942132A (en) * 2021-04-01 2021-06-11 中交二航局第二工程有限公司 Front supporting point composite hanging basket and shifting method thereof
CN118958174A (en) * 2024-10-15 2024-11-15 中铁五局集团第一工程有限责任公司 A super-large segment front support hanging basket device for bridge construction

Similar Documents

Publication Publication Date Title
CN104631343B (en) From traveling rhombus keying cradle in truss type structure and suspended basket and construction method
CN102261039B (en) Integral thrusting construction method of network tied arch bridge
CN100543235C (en) Method and system for erecting steel truss girder with cable-assisted full cantilever
CN101173503A (en) Three-point walking single cable face cable-dragging suspension basket
CN103243658B (en) The spelling method of cable stayed bridge dragging suspension basket
CN207714163U (en) A kind of combined type Hanging Basket
CN109868755A (en) A kind of cradle construction method of Rhombic Truss Hanging Basket and cantilever beam
CN110700119B (en) Design construction method of walking system on assembled bailey beam hanging basket
CN110528402A (en) A kind of construction method of the more purlin piece combination Hanging Baskets of ultra-wide box beam
CN2597531Y (en) Single rope face tracting rope hanging cage
CN202055176U (en) Composite hanging basket with center cable plane and big cantilever girder structure
CN111519550A (en) A hanging basket suspension pouring system for a central cable-plane concrete cable-stayed bridge
CN110453614A (en) Self-lifting corrugated steel web cast-in-place box girder hanging basket
CN107905111A (en) A kind of rigid frame-continuous girder end bay construction technology
CN1123861A (en) Construction of prestressed concrete stayed cable bridge
CN106988230B (en) Hanging basket structure used in reinforced concrete arch bridge construction process
CN112267390A (en) Single-column pier reinforcing structure for improving bridge anti-overturning capacity
CN207987749U (en) Ride cable-styled erection crane
CN212358036U (en) A hanging basket suspension pouring system for a central cable-plane concrete cable-stayed bridge
CN210104589U (en) Basket is hung to rhombus truss
CN107761575A (en) Ultra-wide box beam Hanging Basket and its bottom basket system
CN110528401A (en) Suspended pouring construction hanging basket system
CN115341482B (en) A unilaterally widened unbalanced cantilever box beam hanging basket and construction method thereof
CN109505268A (en) A kind of walking rail-free triangle hanging basket and construction method
CN212559207U (en) Bridge floor crane

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 361021 Silver River Road, Jimei District, Xiamen, Fujian Province, No. 139

Applicant after: CCCC FIRST HIGHWAY XIAMEN ENGINEERING Co.,Ltd.

Address before: No. 141, Yinjiang Road, Jimei District, Xiamen City, Fujian Province 361021

Applicant before: CCCC FIRST HIGHWAY XIAMEN ENGINEERING Co.,Ltd.

CB02 Change of applicant information