CN111460567B - BIM-based stair surface clear height inspection system, application system-based stair surface clear height inspection method and process - Google Patents

BIM-based stair surface clear height inspection system, application system-based stair surface clear height inspection method and process Download PDF

Info

Publication number
CN111460567B
CN111460567B CN202010306569.6A CN202010306569A CN111460567B CN 111460567 B CN111460567 B CN 111460567B CN 202010306569 A CN202010306569 A CN 202010306569A CN 111460567 B CN111460567 B CN 111460567B
Authority
CN
China
Prior art keywords
data
distance
surface layer
stair
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010306569.6A
Other languages
Chinese (zh)
Other versions
CN111460567A (en
Inventor
蔡鑫润
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tonghan Construction Technology Hangzhou Co ltd
Original Assignee
Tonghan Construction Technology Hangzhou Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tonghan Construction Technology Hangzhou Co ltd filed Critical Tonghan Construction Technology Hangzhou Co ltd
Priority to CN202010306569.6A priority Critical patent/CN111460567B/en
Publication of CN111460567A publication Critical patent/CN111460567A/en
Application granted granted Critical
Publication of CN111460567B publication Critical patent/CN111460567B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F11/00Stairways, ramps, or like structures; Balustrades; Handrails
    • E04F11/02Stairways; Layouts thereof
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01BMEASURING LENGTH, THICKNESS OR SIMILAR LINEAR DIMENSIONS; MEASURING ANGLES; MEASURING AREAS; MEASURING IRREGULARITIES OF SURFACES OR CONTOURS
    • G01B21/00Measuring arrangements or details thereof, where the measuring technique is not covered by the other groups of this subclass, unspecified or not relevant
    • G01B21/02Measuring arrangements or details thereof, where the measuring technique is not covered by the other groups of this subclass, unspecified or not relevant for measuring length, width, or thickness
    • G01B21/08Measuring arrangements or details thereof, where the measuring technique is not covered by the other groups of this subclass, unspecified or not relevant for measuring length, width, or thickness for measuring thickness
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01BMEASURING LENGTH, THICKNESS OR SIMILAR LINEAR DIMENSIONS; MEASURING ANGLES; MEASURING AREAS; MEASURING IRREGULARITIES OF SURFACES OR CONTOURS
    • G01B21/00Measuring arrangements or details thereof, where the measuring technique is not covered by the other groups of this subclass, unspecified or not relevant
    • G01B21/16Measuring arrangements or details thereof, where the measuring technique is not covered by the other groups of this subclass, unspecified or not relevant for measuring distance of clearance between spaced objects

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to a method and a process for checking a system and an application system based on BIM stair surface clearance, which comprises a construction module, a building information module and a data processing module, wherein the construction module is used for receiving a civil engineering model input from the outside, constructing a building information model, storing and outputting the building information model; the screening module is used for picking up floor information in the building information model to form a comparison information group, picking up stair surface layer information to form an analysis information group, and outputting the comparison information group and the analysis information group; the judging module is used for picking up floor slab information in the comparison information group, judging the stair information of the analysis information group, judging the standard that the stair information is parallel to the floor slabs and picking up stair surface layer data which are judged successfully, the calculating module is used for calculating the distance between the stair surface layer in the judgment information group and the corresponding floor slab, generating a distance data group, calculating the distance between the adjacent floor slab surface layers, averaging all results and outputting average data. The invention has the effect of detecting the height of each stair surface layer so as to judge whether the stair surface layer conflicts with the floor design.

Description

BIM-based stair surface clear height inspection system, application system-based stair surface clear height inspection method and process
Technical Field
The invention relates to the technical field of building design, in particular to a BIM stair surface clear height inspection system, a method and a process based on an application system.
Background
At present, in the process of building design and construction, pipeline arrangement is usually required to be designed, so that the requirement of reasonable pipeline layout is met, wherein the distance between a pipeline and the ground is required to be considered for the design requirement of the pipeline, and whether the pipeline design scheme collides with the ground or not is confirmed. In the process of arrangement design, revit software is common and efficient software, and Revit is the name of a set of series software of Autodesk company. The Revit series software is constructed for a Building Information Model (BIM), can allow designers to independently screen out different types of building structures, facilitates the operation of analyzing, adjusting, labeling and the like of the specific types of building structures and structural members by the designers, and can help the architects to design, build and maintain buildings with better quality and higher energy efficiency. Revit is one of the most widely used software in BIM system in the construction industry in China.
The prior technical scheme can refer to Chinese invention patent with application publication number CN106709660A, and discloses a BIM-based building design method, which comprises the following steps: the method comprises a concept and scheme stage I, an initial stage II of expansion, a construction diagram model stage III and a construction diagram plotting stage IV; the invention fuses the BIM technology and the building design process, and converts the design process into the building construction informatization simulation process; a large amount of data generated by informatization enables the design process to tend to be refined and deep; communication in the design process is more convenient and visual; and simulation brings about a plurality of analysis methods and improves the precision of checking and debugging.
The above prior art solutions have the following drawbacks: at present, the Revit software can be conveniently applied to assist an operator to plan and design the position of a stair, but more accurate data information is lacked, so that the height of the stair is not strictly set, only the position of the stair and a connecting floor slab can be seen, the stair order can not be accurately reflected whether to accord with the distance between the floor slabs or not, the problems of conflict between stair design and floor setting and the like can not occur, and a plug-in capable of accurately acquiring the height of a floor lift and accurately judging whether the situation occurs or not is lacked.
Disclosure of Invention
Aiming at the defects in the prior art, the invention aims to provide a BIM-based stair surface layer clear height inspection system which has the characteristic of detecting the height of each stair surface layer so as to judge whether the stair surface layer has the condition of too low, too high or crossing the stair due to the conflict with the floor slab design.
The above object of the present invention is achieved by the following technical solutions:
a BIM-based stair tread clearance inspection system, comprising:
the building module is used for receiving an externally input civil model, building a building information model according to the civil model, storing and outputting the building information model;
the screening module is used for responding to the building information model, picking up all information marked as the floor slab in the building information model to form a comparison information group, picking up information of the stair surface layer in the building information model to form an analysis information group, and outputting the comparison information group and the analysis information group;
the judgment module is used for responding to the comparison information group and the analysis information group, picking up floor slab information in the comparison information group, judging the stair information of the analysis information group, picking up stair surface layer data which are successfully judged, and generating and outputting a judgment information group, wherein the judgment standard is parallel to the floor slab;
the calculation module is used for responding to the judgment information group and the comparison information group, calculating stair surface layer data in the judgment information group and floor data in the comparison information group, calculating the distance between a stair surface layer in the judgment information group and a corresponding floor, generating and outputting a distance data group, calculating adjacent stair surface layers in the judgment information group, calculating the distance between the adjacent floor surface layers, averaging all results, and generating and outputting average data;
and the comparison module is used for responding to the average data, the comparison information group and the judgment information group, calculating distance data between adjacent floor boards in the comparison information group, generating a limit data group, judging the limit data group and the judgment information group, wherein the judgment standard is that the distance information in the judgment information group is smaller than the distance data in the limit data group, picking up the distance data which does not accord with the judgment standard to form an error data group, outputting the error data group, judging the average data and the data in the judgment information group, wherein the judgment standard is that the data in the judgment information group is smaller than the average data, picking up the data which accords with the judgment standard, and generating and outputting the data as variability data.
By adopting the technical scheme, when an operator uses the system, the constructed civil engineering model is input into Revit software, the BIM technology can be called to analyze various building elements, a building information model capable of allowing the operator to independently screen different building elements is formed, at the moment, information of a floor slab and a stair can be screened by the screening module and output to the judging module, the judging module can screen the surface layers parallel to the floor slab from all the surface layers of the stair and form an information set, and the information set is output.
The present invention in a preferred example may be further configured to further comprise:
the threshold setting module is used for responding to the distance data set, calling a preset range value, generating threshold data and outputting the threshold data set by taking the data in the distance data set as a basis and the range value as a boundary;
the comparison module receives actual value data input from the outside, responds to the threshold value data set, compares the actual value data with the threshold value data, judges whether the actual value data meets requirements or not, judges whether the actual value data falls in the threshold value data range according to a judgment standard, picks up the actual value data meeting the judgment standard to generate a qualified data set, picks up the actual value data not meeting the judgment standard to generate an abnormal data set, and outputs the qualified data set and the abnormal data set;
and the alarm module responds to the qualified data set and the abnormal data set, stores the qualified data set and outputs the abnormal data set.
By adopting the technical scheme, an operator can preset a range value, the range value and the distance data set can be integrated after the threshold value setting module receives the distance data set to form a threshold value data set which takes the distance data as a basis and takes the range value as an upper range and a lower range, the threshold value data set is output, after the threshold value data set is received by the comparison module, the operator can input an actual value of construction in each stair surface layer constructed in the actual construction process, the comparison module can compare the actual value with the corresponding threshold value data, if the actual value falls within the threshold value data, the actual value meets the judgment standard, the actual value is considered to be qualified data, if the actual value does not meet the judgment standard, the actual value is considered to be abnormal data, the abnormal data is output to the alarm module, the alarm module can store and record qualified data, and output abnormal data for the operator to adjust, the abnormal data can remind the operator of the height misalignment of the stair surface layer corresponding to the construction worker, and the stair surface layer can be repaired conveniently by comparison so as to meet the design.
The present invention in a preferred example may be further configured to further include:
and the recording module receives actual value data input from the outside, responds to the distance data group, stores the actual value data and the distance data which correspond to each other, and supports the output of the actual value data and the distance data.
By adopting the technical scheme, the recording module can store the original data with corresponding relation such as actual values, distance data and the like, and an operator can check the corresponding data, so that the calculation accuracy of the system is checked, and the system is detected and calibrated.
Aiming at the defects in the prior art, the invention also aims to provide a stair surface layer clear height inspection method based on the BIM stair surface layer clear height inspection system, which has the characteristics of accurately measuring and calculating the distance between each layer of stair surface layer and the corresponding floor and marking on a building information model.
The above object of the present invention is achieved by the following technical solutions:
a stair surface clear height inspection method based on a BIM stair surface clear height inspection system is characterized by comprising the following steps:
building a civil engineering model;
building a building information model according to the civil engineering model;
screening all floor data in the building information model;
screening all stair surface layer data in the building information model;
judging the data of each stair surface layer, judging whether the data are parallel to the floor slab data or not according to a judgment standard, and forming a judgment information group by all data meeting the judgment standard;
establishing a two-dimensional coordinate system by taking the height of the lowest floor slab in the building information model as a transverse axis;
detecting the distance between each floor and the lowest floor, setting a scale, converting to obtain the longitudinal axis coordinate of each floor in a two-dimensional coordinate system, and marking the longitudinal axis coordinate of each floor in the two-dimensional coordinate system;
drawing a reference line parallel to a transverse axis at the longitudinal axis coordinate of each floor in a two-dimensional coordinate system;
measuring the distance between the stair surface layer and the lowest floor slab in the judgment information group, substituting the distance into a scale for operation to obtain the vertical coordinate of each stair surface layer in the judgment information group on a two-dimensional coordinate system, and marking the judgment points corresponding to the stair surface layer in the judgment information group on the two-dimensional coordinate system;
using a ray method, making rays from the judgment points along the direction of a longitudinal axis to a transverse axis, marking the intersection point of each ray and a first reference line touched by the ray as a measurement point, measuring the distance between each measurement point and the corresponding judgment point, and marking as a detection distance value;
sleeving all the detected distance values into a scale to calculate an actual distance value;
and marking the actual distance value at the corresponding position of the stair surface layer in the building information model.
By adopting the technical scheme, the method can be used for calculating the distance, so that the accurate stair surface layer can be picked up, the influence of the vertical surface layer of the stair on measurement and calculation is avoided, the distance from the stair surface layer to the floor where the stair surface layer is located is accurately calculated, the distance between the stair surface layer and the nearest floor can be directly calculated by using an ray method, once the situation that the stair design is unreasonable to cause floor crossing or too short occurs, the distance can be visually displayed through the numerical value, and the adjustment can be conveniently carried out by an operator.
The present invention in a preferred example may be further configured to: and calculating the distance between every two layers of floor slabs, judging whether an actual distance value with a numerical value larger than the distance between the two layers of floor slabs exists or not, and marking all the stair surface layers meeting the judgment conditions.
By adopting the technical scheme, if the stair surface layer meeting the judgment condition appears, the design error exists or the stair surface layer is judged to be corresponding to the lower floor slab, and at the moment, the marked abnormal stair surface layer can remind an operator to review the building information model in time, confirm the problem and modify the corresponding stair surface layer.
Aiming at the defects in the prior art, the invention provides a stair surface layer clear height inspection process based on a BIM stair surface layer clear height inspection system, which has the characteristic of timely comparing the construction condition with the design condition in the construction process so as to assist operators in adjusting the construction.
A stair surface clear height inspection process based on a BIM stair surface clear height inspection system comprises the following steps:
setting a range value and inputting the range value into a system;
building construction is carried out on the floor slab and the stair surface layer according to the building information model;
and measuring the distance between the actual stair surface layer and the corresponding floor slab, comparing the distance serving as actual value data with the threshold value data set, and if the actual value of the single-layer stair surface layer falls outside the threshold value data range, performing secondary processing on the stair surface layer until the actual value of the stair surface layer falls within the threshold value data range.
By adopting the technical scheme, after the construction is started, an operator can measure the height of the constructed stair surface layer, the measurement result is compared with the threshold data calculated by the system, and if the actual value is out of the threshold data range, the stair surface layer corresponding to the actual value is not in line with the design requirement, and the height of the stair surface layer needs to be corrected in time.
The present invention in a preferred example may be further configured to:
measuring the actual distance between two floor slabs and recording the actual distance as the actual floor height;
comparing the actual floor height with the height between two corresponding floor slabs in the comparison data set, performing difference operation on the actual floor height and the height to obtain a difference value, and recording the difference value as a floor height error;
averaging the original range value and the layer height error value to obtain a new range value, and replacing the original range value with the new range value to input into the system;
and taking the new threshold data given by the system as a reference to carry out subsequent stair surface layer construction.
By adopting the technical scheme, because the high error of layer can lead to the unable accurate error allowance of assisting operating personnel judgement reality of predetermined range numerical value in the actual construction process, calculate the high error of layer of reality and calculate the influence of high error of layer through the mode of averaging with the range numerical value, obtain the new range numerical value input system who fuses the high error influence of layer, the error value that allows when can further calibrate stair surface layer construction to improve building efficiency.
The invention in a preferred example may be further configured to:
after construction is finished, the distance between each layer of stair surface layer and the corresponding floor slab is measured and recorded as a final distance, the final distance of each layer of stair surface layer is subtracted from the distance data on the building information model, the obtained data is recorded as an adjustment value, the adjustment value and the range value are subjected to averaging operation, and the operation result is input into the system as a new range value.
By adopting the technical scheme, after construction is completed, the distance between the stair surface layer and the corresponding floor slab is measured through the final finished product of the construction, the difference is made between the distance and the distance data on the building information model, the real data value obtained by the construction and the initial theoretical data value can be fused, the adjustment value which actually has reference significance to the design is obtained, the adjustment value is adjusted to be in average operation with the range value, the actual construction experience can be blended into the preset value, the preset is adaptively adjusted, and the calibration effect of the next construction work is finally realized.
In summary, the invention includes at least one of the following beneficial technical effects:
1. compared with the functions of the existing Revit software, the method can accurately measure and calculate the distance from each layer of stair surface layer to the corresponding floor slab, thereby facilitating the accurate adjustment of the position and the height of the stair by an operator and improving the accuracy and the stability of the design of the stair surface layer;
2. the method is used for distance calculation, so that an accurate stair surface layer can be picked up, the influence of a vertical surface layer of the stair on measurement and calculation is avoided, the distance from the stair surface layer to a floor where the stair surface layer is located is accurately calculated, the distance between the stair surface layer and the floor where the stair surface layer is closest to can be directly calculated by using an ray method, and once the situation that the stair passes through the floor or is too short due to unreasonable design is caused, the distance can be visually displayed through numerical values, so that an operator can conveniently adjust the distance;
3. because the high error of layer can lead to the unable accurate error allowance of assistance judgement reality of predetermined range numerical value in the actual construction process, calculate the high error of layer of reality and calculate the influence of layer height error through the mode of solving the average with the range numerical value, obtain the new range numerical value input system who fuses the high error influence of layer, the error value that allows when can further calibrate stair surface layer construction to improve building efficiency.
Drawings
FIG. 1 is a schematic system diagram of example 1.
In the figure, 1, a module is constructed; 2. a screening module; 3. a judgment module; 4. a comparison module; 5. a calculation module; 6. a threshold setting module; 7. a comparison module; 8. an alarm module; 9. and (7) a recording module.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Example 1:
referring to fig. 1, the invention discloses a Building Information Modeling (BIM) -based stair surface clearance inspection system, which comprises:
the building module 1 receives a civil model input from the outside by using Revit software, and the BIM technology can build a building information model according to the civil model, store and output the building information model.
And the screening module 2 is used for responding to the building information model, picking up all information marked as the floor in the building information model to form a comparison information group, picking up information of the stair surface layer in the building information model to form an analysis information group, and outputting the comparison information group and the analysis information group.
And the judging module 3 is used for responding to the comparison information group and the analysis information group, picking up floor information in the comparison information group, judging the stair information of the analysis information group, picking up the stair surface layer data which is successfully judged, and generating and outputting a judgment information group, wherein the judgment standard is parallel to the floor.
Because in the existing Revit software, the stair surface layer information automatically picked up comprises the horizontal surface layer and the vertical surface layer of the stair, the horizontal surface layer needs to be screened out from the stair surface layer information first, and the vertical surface layer is prevented from interfering the final result.
The calculation module 5 is used for responding to the judgment information group and the comparison information group, calculating stair surface layer data in the judgment information group and floor data in the comparison information group, calculating the distance between each stair surface layer in the judgment information group and the corresponding floor, generating and outputting a distance data group, calculating adjacent stair surface layers in the judgment information group, calculating the distance between the adjacent floor surface layers, averaging all results, and generating and outputting average data;
and the comparison module 4 is used for responding to the average data, the comparison information group and the judgment information group, calculating distance data between adjacent floors in the comparison information group, generating a limit data group, judging the limit data group and the judgment information group according to the judgment standard that the distance information in the judgment information group is smaller than the distance data in the limit data group, picking up the distance data which does not accord with the judgment standard to form an error data group, outputting the error data group, judging the average data and the data in the judgment information group according to the judgment standard that the data in the judgment information group is smaller than the average data, picking up the data which accords with the judgment standard, and generating and outputting the data which is variability data.
The system flow can realize two functions, one of the two functions is that the information in the limit value data combination judgment information group is judged, whether the distance between each layer of stair surface layer and the corresponding floor slab is larger than the distance between two layers of floor slabs or not can be judged, if the distance is larger than the distance between two layers of floor slabs, the situation that the lower layer of stair and the upper layer of floor slab are overlapped or exceed the height of the floor slab occurs in the stair design process is shown, and an operator can find and adjust the wrong stair surface layer according to the wrong data group derived from the judgment result; and secondly, if the data in the judgment information group is smaller than the average data, the two conditions exist, or the lowest stair height is set too low, or the lower stair surface layer penetrates through the upper floor and is identified as the stair of the floor, the operator can judge the variability data, and the adjustment of the stair surface layer is carried out according to the condition corresponding to the variability data.
And the threshold setting module 6 is used for responding to the distance data set, calling a preset range value, generating threshold data and outputting the threshold data set by taking the data in the distance data set as a basis and the range value as a boundary.
The essence of the threshold data is that the result of the allowable error set by the operator is added on the basis of the calculation result, namely the maximum error which can be allowed during construction, and the operator can compare the actual distance with the threshold data during construction to judge whether the construction is qualified.
The comparison module 7 receives actual value data input from the outside, responds to the threshold value data set, compares the actual value data with the threshold value data, judges whether the actual value data meets requirements or not, judges whether the actual value data falls in the threshold value data range according to a judgment standard, picks up the actual value data meeting the judgment standard to generate a qualified data set, picks up the actual value data not meeting the judgment standard to generate an abnormal data set, and outputs the qualified data set and the abnormal data set.
And the alarm module responds to the qualified data set and the abnormal data set, stores the qualified data set and outputs the abnormal data set.
Data in the qualified data set is that the distance between the stair surface layer and the floor slab is within the maximum error range during actual construction, and only the data need be stored and recorded, the data in the abnormal data set represents that the actual value of construction is greater than the maximum allowable error, and the alarm module can give an alarm to constructors for the data, and reminds the operators to carry out secondary processing on the stair surface layers.
And the recording module 9 receives actual value data input from the outside, responds to the distance data group, stores the actual value data and the distance data which correspond to each other, and supports the output of the actual value data and the distance data.
The recording module 9 allows an operator to call corresponding actual value data and distance data group data for comparison when sampling inspection or adjustment is performed on the system, so that data acquisition when the operator debugs the system is facilitated.
Example 2:
the invention discloses a stair surface clear height inspection method based on a BIM stair surface clear height inspection system, which comprises the following steps of:
and (5) building a civil engineering model.
And building an information model according to the civil engineering model.
The building information model is built by means of the BIM technology, and an operator can be allowed to independently select individual elements in the building model for processing and operation.
And screening all the floor data in the building information model.
And screening all stair surface layer data in the building information model.
And judging the data of each stair surface layer, judging whether the data are parallel to the floor slab data or not according to the judgment standard, and forming a judgment information group by all the data meeting the judgment standard.
And establishing a two-dimensional coordinate system by taking the height of the lowest floor slab in the building information model as a horizontal axis.
And detecting the distance between each floor and the lowest floor, setting a scale, converting to obtain the longitudinal axis coordinate of each floor in a two-dimensional coordinate system, and marking the longitudinal axis coordinate of each floor in the two-dimensional coordinate system.
In a two-dimensional coordinate system, a reference line parallel to the horizontal axis is drawn at the ordinate of the vertical axis of each floor.
And measuring the distance between the stair surface layer and the lowest floor slab in the judgment information group, substituting the distance into a scale for operation, obtaining the vertical coordinate of each stair surface layer in the judgment information group on the two-dimensional coordinate system, and marking the judgment points corresponding to the stair surface layer in the judgment information group on the two-dimensional coordinate system.
And (3) using a ray method, making rays from the judgment points along the direction of a vertical axis to a horizontal axis, marking the intersection point of each ray and the first reference line touched by the ray as a measurement point, measuring the distance between each measurement point and the corresponding judgment point, and marking as a detection distance value.
And sleeving all the detected distance values into a scale to calculate the actual distance value.
And marking the actual distance value at the corresponding position of the stair surface layer in the building information model.
The method is implemented so far, the distances between all the stair surface layers parallel to the floor slabs and the floor slabs corresponding to the lower portions of the stair surface layers can be calculated and displayed on the building information model, in the process, the operation efficiency can be improved by using the ray method, when the ray method is applied, the floor slabs and the corresponding stair surface layers do not need to be selected independently, all the floor slabs and the stair surface layers can be represented on the same two-dimensional coordinate system, in the operation process, the intersection point of each ray and a first reference line touched by the ray is marked as a measuring point, the distance between each measuring point and the corresponding judging point is measured, the distance between the stair surface layer and the floor slab closest to the lower portion of the stair surface layer can be measured, and the method is efficient and convenient.
And calculating the distance between every two layers of floor slabs, judging whether an actual distance value with a numerical value larger than the distance between the two layers of floor slabs exists or not, and marking all the stair surface layers meeting the judgment conditions.
According to the method, the distance between the lower part of each stair surface layer and the floor closest to the stair surface layer is taken according to the previous steps, and if the distance value between the floor is smaller than the actual distance, the operation error is shown, and an operator needs to check.
Example 3:
the invention discloses a stair surface clear height inspection process based on a BIM stair surface clear height inspection system, which comprises the following steps of:
setting a range value and inputting the range value into the system.
And constructing the floor slab and the stair surface layer according to the building information model.
The construction in this step is not completed all the construction work, but data collection is carried out by matching with the step of washing the face while the construction of the stair surface layer is carried out.
And measuring the distance between the actual stair surface layer and the corresponding floor slab, comparing the distance serving as actual value data with the threshold value data set, and if the actual value of the stair surface layer falls outside the threshold value data range, performing secondary processing on the stair surface layer until the actual value of the stair surface layer falls within the threshold value data range.
According to the step, the actual construction of the stair surface layers can be adjusted by an operator in an auxiliary mode through the threshold data obtained through calculation of the acquisition system, and each stair surface layer can fall into the threshold data during construction, so that the construction of each stair surface layer is guaranteed to be in a qualified state.
And measuring the actual distance between two floor slabs and recording the actual distance as the actual floor height.
The height between the two-layer floor that corresponds in the contrast actual layer height and the contrast data set, make the difference operation with the two and obtain the difference numerical value, note and do the layer height error.
And averaging the original range value and the layer height error value to obtain a new range value, and replacing the original range value with the new range value to input the system.
And taking the new threshold data given by the system as a reference to carry out subsequent stair surface layer construction.
In the above steps, actual construction data are brought into original preset data, the distance error of the two floors in construction is taken into consideration as a reference index of a set range value, the accuracy of selecting the final range value can be effectively improved, the finally selected range value is guaranteed to be suitable for the current construction floors, and the distance between the floors can be aligned in the final stair surface layer construction.
After construction is finished, the distance between each layer of stair surface layer and the corresponding floor slab is measured and recorded as a final distance, the final distance of each layer of stair surface layer is subtracted from the distance data on the building information model, the obtained data is recorded as an adjustment value, the adjustment value and the range value are subjected to averaging operation, and the operation result is input into the system as a new range value.
The final error value adjusting range value of the construction can be used, because the error value of the same construction unit in the construction process has certain stability, the error value of the construction is used as a reference index to calculate a new range value, the error range of the subsequent construction can be effectively adjusted, and the effect of improving the design accuracy is gradually realized.
The implementation principle is as follows: the method and the process are respectively matched with a system, so that the advantage resources and the efficient processing performance of BIM to a building information model can be called, operators are assisted to time and find design bugs and algorithm bugs in a design stage, the operators can conveniently carry out design adjustment, the operators can acquire actual data of construction along with the construction in a construction stage, adjust a preset value and input the preset value into the system, and adjust the calculation result of the system, so that the calculation result is more consistent with the integral deviation of the construction, the consistency and the matching degree of the final construction result are realized, and after the construction is finished, the operators can record the deviation data of the construction for setting the deviation data of the subsequent construction, so that the matching of the data of the design stage and the construction capacity is improved, and the construction stability is gradually improved.
The embodiments of the present invention are preferred embodiments of the present invention, and the scope of the present invention is not limited by these embodiments, so: all equivalent changes made according to the structure, shape and principle of the invention are covered by the protection scope of the invention.

Claims (8)

1. A stair surface clear height inspection system based on BIM is characterized by comprising:
the building module (1) is used for receiving a civil model input from the outside, building a building information model according to the civil model, storing and outputting the building information model;
the screening module (2) is used for responding to the building information model, picking up all information marked as floor slabs in the building information model to form a comparison information group, picking up information of the stair surface layer in the building information model to form an analysis information group, and outputting the comparison information group and the analysis information group;
the judging module (3) is used for responding to the comparison information group and the analysis information group, picking up floor slab information in the comparison information group, judging the stair information of the analysis information group, picking up stair surface layer data which are successfully judged, and generating and outputting a judgment information group, wherein the judgment standard is parallel to the floor slab;
the calculation module (5) is used for responding to the judgment information group and the comparison information group, calculating the stair surface layer data in the judgment information group and the floor plate data in the comparison information group, calculating the distance between the stair surface layer in the judgment information group and the corresponding floor plate, generating and outputting a distance data group, calculating the adjacent stair surface layers in the judgment information group, calculating the distance between the adjacent stair surface layers, averaging all results, and generating and outputting average data;
and the comparison module (4) responds to the average data, the comparison information group and the judgment information group, calculates distance data between adjacent floor boards in the comparison information group, generates a limit data group, judges the limit data group and the distance data group, judges that the distance information in the distance data group is smaller than the distance data in the limit data group according to the standard, picks up the distance data which does not accord with the judgment standard to form an error data group, outputs the error data group, judges the average data and the data in the distance data group according to the standard that the data in the distance data group is smaller than the average data, picks up the data which accord with the judgment standard, and generates and outputs the variability data.
2. The BIM-based stair tread clearance inspection system of claim 1, further comprising:
the threshold setting module (6) is used for responding to the distance data set, calling a preset range value, generating threshold data and outputting the threshold data set by taking the range value as a boundary on the basis of data in the distance data set;
the comparison module (7) receives actual value data input from the outside, responds to the threshold value data set, compares the actual value data with the threshold value data, judges whether the actual value data meet the requirements or not, and takes the actual value data meeting the judgment standard to generate a qualified data set, takes the actual value data not meeting the judgment standard to generate an abnormal data set, and outputs the qualified data set and the abnormal data set;
and the alarm module responds to the qualified data set and the abnormal data set, stores the qualified data set and outputs the abnormal data set.
3. The BIM-based stair tread clearance inspection system of claim 1, further comprising:
and the recording module (9) receives actual value data input from the outside, responds to the distance data group, stores the actual value data and the distance data which correspond to each other, and supports the output of the actual value data and the distance data.
4. A method for inspecting stair tread clearance height based on a BIM stair tread clearance height inspection system as claimed in any one of claims 1 to 3, comprising the steps of:
building a civil engineering model;
building a building information model according to the civil engineering model;
screening all floor data in the building information model;
screening all stair surface layer data from the building information model;
judging the data of each stair surface layer, judging whether the data are parallel to the data of the floor slab or not according to the judgment standard, and forming a judgment information group by all the data meeting the judgment standard;
establishing a two-dimensional coordinate system by taking the height of the lowest floor slab in the building information model as a transverse axis;
detecting the distance between each floor and the lowest floor, setting a scale, converting to obtain the longitudinal axis coordinate of each floor in a two-dimensional coordinate system, and marking the longitudinal axis coordinate of each floor in the two-dimensional coordinate system;
drawing a reference line parallel to a transverse axis at the longitudinal axis coordinate of each floor in a two-dimensional coordinate system;
measuring the distance between the stair surface layer and the lowest floor slab in the judgment information group, substituting the distance into a scale for operation to obtain the vertical coordinate of each stair surface layer in the judgment information group on a two-dimensional coordinate system, and marking the judgment points corresponding to the stair surface layer in the judgment information group on the two-dimensional coordinate system;
using a ray method, making rays from the judgment points along the direction of a longitudinal axis to a transverse axis, marking the intersection point of each ray and a first reference line touched by the ray as a measurement point, measuring the distance between each measurement point and the corresponding judgment point, and marking as a detection distance value;
sleeving all the detected distance values into a scale to calculate an actual distance value;
and marking the actual distance value at the corresponding position of the stair surface layer in the building information model.
5. The stair tread clearance inspection method according to claim 4, further comprising the steps of:
and calculating the distance between every two layers of floor slabs, judging whether an actual distance value with a numerical value larger than the distance between the two layers of floor slabs exists or not, and marking all the stair surface layers meeting the judgment conditions.
6. A stair tread clearance inspection process using the BIM stair tread clearance inspection system of claim 2, comprising the steps of:
setting a range value and inputting the range value into a system;
building construction is carried out on the floor slab and the stair surface layer according to the building information model;
and measuring the distance between the actual stair surface layer and the corresponding floor slab, comparing the distance serving as actual value data with the threshold value data set, and if the actual value of the single-layer stair surface layer falls outside the threshold value data range, performing secondary processing on the stair surface layer until the actual value of the stair surface layer falls within the threshold value data range.
7. The stair tread clearance inspection process of claim 6, further comprising the steps of:
measuring the actual distance between two floor slabs and recording the actual distance as the actual floor height;
comparing the actual floor height with the height between two corresponding floor slabs in the comparison information group, performing difference operation on the actual floor height and the height to obtain a difference value, and recording the difference value as a floor height error;
averaging the preset range value and the layer height error value to obtain a new range value, and replacing the preset range value with the new range value to input into the system;
and taking the new threshold data given by the system as reference to carry out subsequent stair surface layer construction.
8. The stair tread clearance inspection process of claim 6, further comprising the steps of:
after construction is finished, the distance between each layer of stair surface layer and the corresponding floor slab is measured and recorded as a final distance, the final distance of each layer of stair surface layer is subtracted from the distance data on the building information model, the obtained data is recorded as an adjustment value, the adjustment value and the range value are subjected to averaging operation, and the operation result is input into the system as a new range value.
CN202010306569.6A 2020-04-17 2020-04-17 BIM-based stair surface clear height inspection system, application system-based stair surface clear height inspection method and process Active CN111460567B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010306569.6A CN111460567B (en) 2020-04-17 2020-04-17 BIM-based stair surface clear height inspection system, application system-based stair surface clear height inspection method and process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010306569.6A CN111460567B (en) 2020-04-17 2020-04-17 BIM-based stair surface clear height inspection system, application system-based stair surface clear height inspection method and process

Publications (2)

Publication Number Publication Date
CN111460567A CN111460567A (en) 2020-07-28
CN111460567B true CN111460567B (en) 2022-11-15

Family

ID=71680284

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010306569.6A Active CN111460567B (en) 2020-04-17 2020-04-17 BIM-based stair surface clear height inspection system, application system-based stair surface clear height inspection method and process

Country Status (1)

Country Link
CN (1) CN111460567B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112257138B (en) * 2020-09-05 2023-03-21 赛飞特工程技术集团有限公司 Remote safety inquiry method, system, intelligent terminal and storage medium
CN112948928B (en) * 2021-02-25 2023-10-20 深圳市万翼数字技术有限公司 Headroom calculating method and related device based on building information model
CN113255031B (en) * 2021-04-29 2022-08-05 上海大学 Method and system for automatically generating building clear height cloud picture based on Revit platform
CN114564795B (en) * 2021-12-31 2024-05-31 博迈科海洋工程股份有限公司 Automatic parameter matching method for fixed inclined ladder of offshore platform
CN117010075B (en) * 2023-09-26 2023-12-08 中国建筑西南设计研究院有限公司 Automatic checking method, medium and device for floor outline in BIM software

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109033716A (en) * 2018-09-05 2018-12-18 深圳市赛为智能股份有限公司 Fire incident data processing method, terminal and storage medium based on BIM

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9898557B2 (en) * 2015-02-27 2018-02-20 Aditazz, Inc. Method and system for generating building plans using slices
CN107977487A (en) * 2017-11-07 2018-05-01 山东住工装配建筑有限公司 A kind of assembly concrete architectural design method based on BIM technology
CN109763611B (en) * 2018-12-18 2021-02-02 广州机施建设集团有限公司 Construction method of steel structure special-shaped stair
CN110941871B (en) * 2019-12-16 2023-04-28 山东建筑大学 Automatic labeling method and system based on room information in Revit three-dimensional model

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109033716A (en) * 2018-09-05 2018-12-18 深圳市赛为智能股份有限公司 Fire incident data processing method, terminal and storage medium based on BIM

Also Published As

Publication number Publication date
CN111460567A (en) 2020-07-28

Similar Documents

Publication Publication Date Title
CN111460567B (en) BIM-based stair surface clear height inspection system, application system-based stair surface clear height inspection method and process
CN208887632U (en) Construction detection system and monitoring computer equipment based on 3 D laser scanning
CN108824816B (en) High-altitude long-span net frame sliding, positioning, installing and monitoring method
CN106886659A (en) The virtual pre-splicing and detection method of steel structure bridge based on 3 D laser scanning and cloud platform
CN108592895A (en) Construction detecting system based on 3 D laser scanning, method and apparatus
CN113435757B (en) BIM-based building masonry design and construction method
CN112489028B (en) Engineering quality acceptance method integrating information model and laser three-dimensional scanning technology
CN109405817B (en) Method for detecting verticality of circular stand column
CN107992670A (en) The simulation matching process of auto parts and components
CN110940299B (en) Method for measuring three-dimensional roughness of concrete surface
CN105403183A (en) Work template metering detection method for examining coupler
CN114234819B (en) Automatic detection method for quality of steel bar part based on three-dimensional laser scanning
CN115841484B (en) Steel structure welding quality detection system based on three-dimensional laser scanning
CN114511199A (en) Engineering project delivery acceptance management method, equipment and computer storage medium
CN111523221B (en) Pipeline marking system based on BIM technology and method of application system
CN116678368B (en) BIM technology-based intelligent acquisition method for assembled steel structure data
CN113191747A (en) High-rise building engineering measurement supervision control method
CN111380475A (en) Truss hanging rail inspection method based on three-dimensional scanner technology
CN113048956B (en) Monitoring method and system for steel structure construction based on three-dimensional scanning technology
CN113743483A (en) Road point cloud error scene analysis method based on spatial plane offset analysis model
CN117911412B (en) Dimension detection method and system for caterpillar track section for engineering machinery
CN113779817B (en) Method for analyzing reference stability of measurement control network
CN117739897A (en) Detection method of blade profile reinforcing ribs
CN106844823B (en) Modeling method for staircase civil engineering
CN114160767A (en) Arrangement method for confirming installation datum line of continuous casting equipment by adopting traversal method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant