CN111457349B - A reinforced structure for snakelike tube panel - Google Patents
A reinforced structure for snakelike tube panel Download PDFInfo
- Publication number
- CN111457349B CN111457349B CN202010341902.7A CN202010341902A CN111457349B CN 111457349 B CN111457349 B CN 111457349B CN 202010341902 A CN202010341902 A CN 202010341902A CN 111457349 B CN111457349 B CN 111457349B
- Authority
- CN
- China
- Prior art keywords
- steel plate
- tube panel
- snakelike
- steel sheet
- serpentine
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F22—STEAM GENERATION
- F22B—METHODS OF STEAM GENERATION; STEAM BOILERS
- F22B37/00—Component parts or details of steam boilers
- F22B37/02—Component parts or details of steam boilers applicable to more than one kind or type of steam boiler
- F22B37/24—Supporting, suspending, or setting arrangements, e.g. heat shielding
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Thermal Sciences (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Rigid Pipes And Flexible Pipes (AREA)
Abstract
The invention provides a reinforcing structure for a snakelike tube panel, and belongs to the technical field of reinforcement of snakelike tube panels. According to the invention, the hanging pipe is connected with the bearing steel plate, the bearing steel plate is connected with the integral steel plate, the serpentine pipe screen can pass through the integral steel plate through the open holes, the integral steel plate can suspend and fix the serpentine pipe screen, the serpentine pipe screen is horizontally arranged in the furnace, the integral steel plate is provided with a plurality of first open holes and a plurality of second open holes, the first open holes are positioned at the upper end of the integral steel plate, the first open holes can be used for four serpentine pipes in the serpentine pipe screen to pass through, the second open holes are positioned at the lower end of the integral steel plate, and the second open holes can be used for two serpentine pipes in the serpentine pipe screen to pass through. The invention has the advantages of strengthening the suspension support of the heating surface serpentine tube panel, preventing the potential safety hazard in the operation process of the boiler, improving the bearing capacity of the steel plate and prolonging the service life.
Description
Technical Field
The invention relates to a reinforcing structure for a snakelike tube panel, and belongs to the technical field of reinforcement of snakelike tube panels.
Background
The heating surface in the tower boiler is composed of coiled pipes, and the special arrangement mode determines that the support of the coiled pipe panel in the boiler can only select small supporting plates welded on the hanging pipes. When the steam parameters of the boiler are higher, the material of the hanging pipe is correspondingly improved. For example, the hanging pipe quality of 600MW and 1000MW grade ultra-supercritical boiler which is operated domestically at present is upgraded to SA 213-T91. The welding performance of the material SA213-T91 is poor, and the hanging pipe small supporting plate after being welded into a screen is separated.
Disclosure of Invention
The present invention is directed to solving the above problems of the prior art, and further to providing a reinforcing structure for a serpentine tube panel.
The purpose of the invention is realized by the following technical scheme:
a reinforcing structure for a serpentine tube panel, comprising: the device comprises a hanging pipe, a bearing steel plate, an integral steel plate, a snakelike pipe panel, a first opening and a second opening;
wherein, hang the pipe and be connected with bearing the steel sheet, bear the steel sheet and be connected with integral steel sheet, snakelike tube panel accessible trompil passes integral steel sheet, and integral steel sheet suspends in midair fixedly to snakelike tube panel, snakelike tube panel is arranged at the stove level, is provided with the first trompil of a plurality of and a plurality of second trompil on the integral steel sheet, and first trompil is located the upper end of integral steel sheet, and four snakelike pipes in the size of first trompil can supply snakelike tube panel pass, and the second trompil is located the lower extreme of integral steel sheet, and two snakelike pipes in the size of second trompil can supply snakelike tube panel to pass.
The hanging pipe is connected with the bearing steel plate in a welding mode.
The bearing steel plate is connected with the integral steel plate in a welding mode.
Seven first open holes are formed in the integral steel plate.
And two second open holes are formed in the integral steel plate.
The invention has the beneficial effects that:
in the invention, the smoke temperature at the lower part of the tube panel is higher, and the bearing capacity of the steel plate is reduced, so that different types of first openings and second openings are arranged in the vertical direction of the integral steel plate, the first openings are positioned at the upper ends of the second openings, the first openings can be penetrated by four coiled tubes in the coiled tube panel, and the second openings can be penetrated by two coiled tubes in the coiled tube panel, so that the bearing capacity of the steel plate is improved, and the service life is prolonged.
The invention is suitable for tower boilers, prevents potential safety hazards in the operation process of the boilers, provides a reinforcing structure for the serpentine tube panel of the tower boiler, has a reinforcing effect on the suspension support of the serpentine tube panel of the heating surface, and does not influence the overall safety of the boiler even if a small supporting plate of a part of the suspension tubes of the tower boiler falls off in the operation process.
Drawings
Fig. 1 is a schematic structural view of a reinforcing structure for a serpentine tube panel according to the present invention.
FIG. 2 is a cross-sectional view A-A of FIG. 1 illustrating a reinforcement for a serpentine tube panel according to the present invention.
The reference numeral in the figure, 1 is hanging the pipe, 2 is bearing steel sheet, 3 are integral steel sheet, 4 are snakelike tube panel, 5 are first trompil, and 6 are the second trompil.
Detailed Description
The invention will be described in further detail below with reference to the accompanying drawings: the present embodiment is implemented on the premise of the technical solution of the present invention, and a detailed implementation is given, but the scope of the present invention is not limited to the following embodiments.
As shown in fig. 1 and 2, the present embodiment relates to a reinforcing structure for a serpentine tube panel, including: the device comprises a hanging pipe 1, a bearing steel plate 2, an integral steel plate 3, a snakelike pipe screen 4, a first opening 5 and a second opening 6;
wherein, hang pipe 1 and bear steel sheet 2 and be connected, bear steel sheet 2 and be connected with integral steel sheet 3, integral steel sheet 3 is passed through the trompil to 4 accessible trompil of coiled pipe screen, and integral steel sheet 3 suspends in midair fixedly to coiled pipe screen 4, coiled pipe screen 4 is arranged at the stove level, is provided with the first trompil 5 of a plurality of and a plurality of second trompil 6 on the integral steel sheet 3, and first trompil 5 is located integral steel sheet 3's upper end, and four coiled pipes in the size of first trompil 5 can supply coiled pipe screen 4 to pass, and second trompil 6 is located integral steel sheet 3's lower extreme, and two coiled pipes in the size of second trompil 6 can supply coiled pipe screen 4 to pass.
The hanging pipe 1 is connected with the bearing steel plate 2 in a welding mode.
The bearing steel plate 2 and the integral steel plate 3 are connected in a welding mode.
Seven first open holes 5 are arranged on the integral steel plate 3.
Two second open holes 6 are arranged on the integral steel plate 3.
Example 1
In this embodiment, the serpentine tube panel 4 is suspended and fixed by the suspension tube 1, the bearing steel plate 2 and the integral steel plate 3. As shown in fig. 2, the bearing steel plate 2 is welded with the hanging pipe 1, the integral steel plate 3 is welded with the bearing steel plate 2, and the integral steel plate 3 is used for hanging and fixing the serpentine pipe panel 4. And snakelike tube panel 4 is arranged at the stove level, hangs pipe 1 and bears steel sheet 2 and adopt the welding form to be connected, bears steel sheet 2 and integral steel sheet 3 and adopts the welding form to be connected, and snakelike tube panel 4 passes integral steel sheet 3, and integral steel sheet 3 suspends snakelike tube panel 4 in midair and supports.
As shown in fig. 1, the integral steel plate 3 is provided with a plurality of first openings 5 and a plurality of second openings 6, the first openings 5 are located at the upper end of the integral steel plate 3, the first openings 5 are sized to allow four serpentine tubes in the serpentine tube panel 4 to pass through, the second openings 6 are located at the lower end of the integral steel plate 3, and the second openings 6 are sized to allow two serpentine tubes in the serpentine tube panel 4 to pass through. Due to the fact that the smoke temperature of the lower portion of the tube panel is high, the bearing capacity of the steel plate is reduced, and therefore by means of the structure, the bearing capacity of the steel plate can be improved, and the service life of the steel plate is prolonged.
This embodiment is applicable to tower boiler, and the potential safety hazard that appears among the prevention boiler operation process provides a reinforced structure for snakelike tube panel of tower boiler, has played the effect of strengthening to the support that suspends in midair of snakelike tube panel of heating surface, even tower boiler has the little layer board of partial hanging pipe to drop at the operation in-process, does not influence the holistic safety of boiler yet.
The above description is only a preferred embodiment of the present invention, and these embodiments are based on different implementations of the present invention, and the scope of the present invention is not limited thereto, and any changes or substitutions that can be easily conceived by those skilled in the art within the technical scope of the present invention are included in the scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.
Claims (5)
1. A reinforcing structure for a serpentine tube panel, comprising: hang pipe (1) and snakelike tube panel (4), its characterized in that still includes: the steel plate comprises a bearing steel plate (2), an integral steel plate (3), a first open hole (5) and a second open hole (6);
wherein, hang pipe (1) and be connected with bearing steel sheet (2), bear steel sheet (2) and be connected with integral steel sheet (3), integral steel sheet (3) are passed to snakelike tube panel (4) accessible trompil, and integral steel sheet (3) suspend in midair fixedly snakelike tube panel (4), snakelike tube panel (4) are arranged at stove level, are provided with a plurality of first trompil (5) and a plurality of second trompil (6) on integral steel sheet (3), and first trompil (5) are located the upper end of integral steel sheet (3), and four snakelike pipes in the size of first trompil (5) can supply snakelike tube panel (4) to pass, and second trompil (6) are located the lower extreme of integral steel sheet (3), and two snakelike pipes in the size of second trompil (6) can supply snakelike tube panel (4) to pass.
2. A reinforcement structure for serpentine tube panels according to claim 1, characterized in that the hanging tube (1) is connected with the bearing steel plate (2) by welding.
3. A reinforcement structure for serpentine tube panels according to claim 1, characterized in that said load-bearing steel plates (2) are connected to the monolithic steel plates (3) by welding.
4. A reinforcing structure for serpentine tube panels according to claim 1, characterized in that said monolithic steel plate (3) is provided with seven first openings (5).
5. A reinforcement structure for serpentine tube panels according to claim 1, characterized in that said monolithic steel plate (3) is provided with two second openings (6).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010341902.7A CN111457349B (en) | 2020-04-27 | 2020-04-27 | A reinforced structure for snakelike tube panel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010341902.7A CN111457349B (en) | 2020-04-27 | 2020-04-27 | A reinforced structure for snakelike tube panel |
Publications (2)
Publication Number | Publication Date |
---|---|
CN111457349A CN111457349A (en) | 2020-07-28 |
CN111457349B true CN111457349B (en) | 2021-10-26 |
Family
ID=71676912
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010341902.7A Active CN111457349B (en) | 2020-04-27 | 2020-04-27 | A reinforced structure for snakelike tube panel |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111457349B (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3906876B2 (en) * | 1997-09-16 | 2007-04-18 | 石川島播磨重工業株式会社 | Seismic structure of inner pipe in hexagonal pressurized fluidized bed boiler. |
CN201547750U (en) * | 2009-11-30 | 2010-08-11 | 上海锅炉厂有限公司 | Hanger plate suspension structure used for coiled pipe screen |
CN201871592U (en) * | 2010-11-25 | 2011-06-22 | 郑州锅炉股份有限公司 | Pipe clamp for processing of boiler coils |
CN202188486U (en) * | 2011-08-15 | 2012-04-11 | 哈尔滨哈锅锅炉工程技术有限公司 | Hanging device of undamaged heating surface of boiler of serpentine tube |
CN204345607U (en) * | 2014-12-23 | 2015-05-20 | 哈尔滨锅炉厂有限责任公司 | For the bracing or strutting arrangement of the horizontal heating surface of boiler |
CN205606524U (en) * | 2016-05-18 | 2016-09-28 | 苏州海陆重工股份有限公司 | Suspension type economizer top cable suspension device |
-
2020
- 2020-04-27 CN CN202010341902.7A patent/CN111457349B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3906876B2 (en) * | 1997-09-16 | 2007-04-18 | 石川島播磨重工業株式会社 | Seismic structure of inner pipe in hexagonal pressurized fluidized bed boiler. |
CN201547750U (en) * | 2009-11-30 | 2010-08-11 | 上海锅炉厂有限公司 | Hanger plate suspension structure used for coiled pipe screen |
CN201871592U (en) * | 2010-11-25 | 2011-06-22 | 郑州锅炉股份有限公司 | Pipe clamp for processing of boiler coils |
CN202188486U (en) * | 2011-08-15 | 2012-04-11 | 哈尔滨哈锅锅炉工程技术有限公司 | Hanging device of undamaged heating surface of boiler of serpentine tube |
CN204345607U (en) * | 2014-12-23 | 2015-05-20 | 哈尔滨锅炉厂有限责任公司 | For the bracing or strutting arrangement of the horizontal heating surface of boiler |
CN205606524U (en) * | 2016-05-18 | 2016-09-28 | 苏州海陆重工股份有限公司 | Suspension type economizer top cable suspension device |
Also Published As
Publication number | Publication date |
---|---|
CN111457349A (en) | 2020-07-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111457349B (en) | A reinforced structure for snakelike tube panel | |
JP5362901B2 (en) | Thermal power plant | |
CN106642063A (en) | Novel superheater hoisting installation | |
CN201547750U (en) | Hanger plate suspension structure used for coiled pipe screen | |
CN207434249U (en) | Duplex support | |
CN206377645U (en) | A kind of new superheater hanging apparatus | |
JP3934139B2 (en) | Furnace wall structure | |
CN205606524U (en) | Suspension type economizer top cable suspension device | |
CN210717475U (en) | Large-scale water tube boiler with enhanced structural stability | |
CN102384461B (en) | Large steam generator | |
CN201262393Y (en) | Dry-type bottom ignition device of circulating fluidized bed boiler | |
CN101324328B (en) | A recovery boiler plant and a method in a recovery boiler | |
CN203785452U (en) | Furnace top structure of large-sized arc-shaped porous high-temperature electric furnace | |
CN203703954U (en) | Central cylinder structure of boiler cyclone separator | |
CN208346630U (en) | A kind of gap bridge pipeline K font door frame | |
CN209801439U (en) | Vertical shell-and-tube structure steam electric boiler | |
CN212841504U (en) | Furnace tube supporting structure of organic heat carrier heating furnace | |
CN218846866U (en) | Sectional type heat accumulation case | |
CN215597313U (en) | Hot water heater structure for boiler equipment | |
CN103411233B (en) | A kind ofly only shake device for what prevent flame boiler furnace wall from rocking | |
CN206055596U (en) | Coil group support fixed structure | |
CN212565755U (en) | Burner mounting structure of horizontal gas boiler | |
CN212987646U (en) | Cast iron module boiler | |
CN211372391U (en) | Anti-falling structure of central cylinder of separator | |
CN220793106U (en) | Steam-water separation system of flue gas waste heat boiler of industrial silicon ore furnace |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |