CN111456088A - Subway station with overlapped assembly type structure and assembly construction method - Google Patents

Subway station with overlapped assembly type structure and assembly construction method Download PDF

Info

Publication number
CN111456088A
CN111456088A CN202010398564.0A CN202010398564A CN111456088A CN 111456088 A CN111456088 A CN 111456088A CN 202010398564 A CN202010398564 A CN 202010398564A CN 111456088 A CN111456088 A CN 111456088A
Authority
CN
China
Prior art keywords
side wall
negative
layer
pouring
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010398564.0A
Other languages
Chinese (zh)
Inventor
权县民
刘运生
梁宇
石立民
聂善军
吴天林
黄海龙
王小军
张强
黄磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cccc First Harbor Engineering Transportation Engineering Co ltd
Cccc Harbin Metro Investment And Construction Of Metro Ltd
CCCC First Harbor Engineering Co Ltd
Original Assignee
Cccc First Harbor Engineering Transportation Engineering Co ltd
Cccc Harbin Metro Investment And Construction Of Metro Ltd
CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cccc First Harbor Engineering Transportation Engineering Co ltd, Cccc Harbin Metro Investment And Construction Of Metro Ltd, CCCC First Harbor Engineering Co Ltd filed Critical Cccc First Harbor Engineering Transportation Engineering Co ltd
Priority to CN202010398564.0A priority Critical patent/CN111456088A/en
Publication of CN111456088A publication Critical patent/CN111456088A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/04Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Abstract

The invention relates to a subway station with an overlapped assembly type structure and an assembly construction method. At present, when a station is constructed, a large number of templates are needed, the field workload is large, and the construction period is long. The cast-in-place wet operation also causes environmental water pollution, noise pollution and air pollution. The utility model provides an coincide assembled structure subway station right, its constitution includes roof (1), medium plate (2), bottom plate (3), heat exhausting flue (5) and side wall (4), characterized by: the bottom plate to two negative layers of bottom construction joints be cast-in-place reinforced concrete structure, the grout sleeve that leaks is pre-buried in construction joint department connects upper portion side wall atress reinforcing bar, and the side wall endothelium is the prefabricated section of taking the truss muscle, as inboard template simultaneously, in inserting the grout sleeve bottom, through pouring high-efficient grout material and connecting the atress reinforcing bar, establish cast-in-place area on the construction joint, pour side wall cavity concrete, form the side wall congruent structure. The method is applied to the field of subway construction.

Description

Subway station with overlapped assembly type structure and assembly construction method
The technical field is as follows:
the invention relates to a subway station with an overlapped assembly type structure and an assembly construction method.
Background art:
the excavation method of the underground station of the subway mainly comprises an open excavation method, a cover excavation method and a shallow-buried underground excavation method. When various excavation methods relate to construction of underground station structures of subways, structures such as side walls, stand columns, bottom plates, middle plates and top plates of the station structures are usually constructed by adopting on-site formwork erecting, on-site concrete pouring and on-site maintenance methods. The cast-in-place construction method has the advantages of good integrity, high rigidity, good shock resistance and the like. But has obvious disadvantages for adapting to the schedule arrangement of the construction site and the requirement of green construction. Not only needs a large number of templates, but also has large field workload and longer construction period. The cast-in-place wet operation also causes environmental water pollution, noise pollution and air pollution.
The invention content is as follows:
the invention aims to provide a subway station with a superposed assembly type structure and an assembly construction method.
The above purpose is realized by the following technical scheme:
a folding assembly type structure subway station comprises: roof, medium plate, bottom plate, heat extraction wind channel and side wall, bottom plate to two layers of bottom construction joints of burden be cast-in-place reinforced concrete structure, the pre-buried grout sleeve that leaks outward of construction joint department connects upper portion side wall atress reinforcing bar, the side wall endothelium is the prefabricated section of taking the truss muscle, simultaneously as inboard template, in the grout sleeve is inserted to the bottom, connect the atress reinforcing bar through pouring high-efficient grout material, vertical piecemeal width is about 2m, interblock distribution muscle structure is strengthened, construction joint upper portion sets up cast-in-place area, pour into side wall cavity concrete, form the side wall congruent structure.
Coincide assembled structure subway station, two layer side wall concreting of burden to two layer top construction joints department of burden, construction joints department side wall atress reinforcing bar reserves reinforcing bar connector, connects upper portion side wall atress reinforcing bar, the medium plate bottom skin be the prefabricated section of taking the truss muscle, as the bottom skin template simultaneously, vertical piecemeal width is about 2m, the interblock distribution muscle structure is strengthened, the equal on-the-spot ligature of epithelium reinforcing bar, the heat removal wind channel reinforcing bar connecting hole is reserved to the medium plate prefabricated section for the heat removal wind channel is installed to the later stage, medium plate concreting to one layer side wall bottom construction joints department, forms the medium plate beta structure, the pre-buried grout sleeve of leaking outside of joint, connects upper portion side wall atress reinforcing bar.
Coincide assembled structure subway station, installation of negative one deck side wall prefabricated section, connection and cast-in-place area set up with two layers on the negative, negative one deck side wall concrete placement to negative one deck top construction joint department, construction joint department side wall atress reinforcing bar is reserved the reinforcing bar and is plugged into the ware, connects the upper portion reinforcing bar, the roof base coat be the prefabricated section of taking the truss muscle, as the base coat template simultaneously, vertical piecemeal width is about 2m, the structure of interblock distribution muscle is strengthened, the equal on-the-spot ligature of epithelium reinforcing bar, roof concrete placement forms roof congruent structure.
Coincide assembled structure subway station, station structure back of capping, installation medium plate lower part heat extraction air flue, heat extraction air flue for whole U type is prefabricated, the muscle is hung to the upper portion hourglass, penetrates heat extraction air flue in the medium plate preformed hole through jacking equipment, upper portion is fixed with the gasket with the nut, adopts high-efficient grout material to fill closely knit in the cavity.
The assembly construction method of the subway station with the superposed assembly type structure comprises the following steps:
(1) constructing a waterproof layer of the cushion layer;
after the foundation pit is excavated to the substrate, a cushion layer and a waterproof layer wrapped outside the bottom plate are applied in time;
(2) installing a negative two-layer side wall reinforcing steel bar limiter, embedding a bottom plate and pouring concrete;
reserving a side wall waterproof layer, installing a negative two-layer side wall reinforcing steel bar limiter 11 (fixing a negative two-layer side wall grouting sleeve and a stress reinforcing steel bar), binding bottom plate reinforcing steel bars, embedding lateral support positioning reinforcing steel bars 10 (with a longitudinal distance of 1 m), and pouring bottom plate concrete to a horizontal construction joint at the bottom of the negative two-layer side wall;
(3) the negative two-layer precast block and the column shaping template 15 are installed and fixed by a lateral bracket 16;
dismantling a third steel support, paving a waterproof layer of the negative second-layer side wall, hoisting a prefabricated block (prefabricated with inner truss ribs) of the negative second-layer side wall and a structural column shaping template 15, fixing a lateral support system, and installing an operation platform;
(4) pouring concrete of the side walls and the columns of the negative second layer and placing middle plate precast blocks;
pouring high-strength grouting material into the grouting sleeve of the negative second-layer side wall to ensure the effective connection of stress ribs of the side walls, pouring the negative second-layer side wall (forming a superposed structure) and structural column concrete after the connection precision of the distribution ribs is adjusted, removing the lateral support after pouring to the horizontal construction joint at the top of the negative second layer to reach the strength, erecting a local buckling support 19, and placing a middle plate precast block (bottom belt truss rib prefabrication);
(5) installing a negative layer side wall reinforcing steel bar limiter, embedding a middle plate and pouring concrete;
the method comprises the following steps of (1) paving and reserving a waterproof layer of a side wall, installing a negative layer side wall reinforcing steel bar limiter (fixing a negative layer side wall grouting sleeve and stressed reinforcing steel bars), binding reinforcing steel bars of a middle plate cast-in-place layer (reserving a heat exhausting duct hole), embedding lateral support positioning reinforcing steel bars (with a longitudinal distance of 1 m), and pouring middle plate concrete to a horizontal construction joint at the bottom of the negative layer;
(6) installing a layer of prefabricated blocks and a column shaping template, and fixing a lateral bracket;
dismantling a second steel support, laying a side wall waterproof layer on the second steel support, hoisting a prefabricated block (prefabricated with inner truss ribs) and a column shaping template on the second steel support, fixing a lateral support system, and installing an operation platform;
(7) carrying out concrete pouring on a layer of side walls and columns and placing prefabricated blocks of a top plate;
pouring high-strength grouting material into the negative layer of side wall grouting sleeve to ensure effective connection of the stress ribs of the side walls, pouring a negative layer of side walls (forming a superposed structure) and structural column concrete after the connection precision of the distributed ribs is adjusted, removing the lateral supports after pouring to the horizontal construction joint at the top of the negative layer to reach the strength, erecting local coil buckling supports, and placing a top plate precast block (bottom belt truss rib prefabrication);
(8) and (3) binding steel bars on the top plate and pouring concrete:
dismantling the first steel support, paving and reserving the waterproof layer of the side wall, binding the steel bars of the cast-in-place layer of the top plate, and pouring concrete;
(9) earthing 24, restoring the road surface, installing a heat exhaust channel, constructing a platform plate 25 and other internal structures;
laying a roof plate fully covered with a waterproof layer, backfilling and earthing, laying pipelines, recovering the pavement, installing a heat exhaust duct in a station, and constructing internal structures such as a station bedplate and the like;
the whole U-shaped prefabrication of the upper row of hot air ducts, the steel bars leak outwards, the holes of the steel bars of the upper row of hot air ducts are upwards installed through the holes reserved in the middle plate, the holes penetrate through the top surface of the middle plate and are connected in a bolt and gasket mode, the steel bar holes are grouted compactly, and other station table plates and other structures are cast in situ.
The invention has the beneficial effects that:
1. the subway underground station adopts a construction mode of combining an overlapping structure with local integral cast-in-place; the inner skin of the side wall, the middle plate and the lower skin of the top plate are prefabricated reinforced concrete structures with local thickness and truss ribs, and a prefabricated component with the truss ribs is used as an inner mold to form an overlapped structure with the rear cast-in-place structure; the bottom plate and the beam column joint are all cast-in-place.
The side wall atress reinforcing bar adopts grout sleeve (filling high-efficient grout material) and steel bar connector type to connect, and medium plate and roof atress reinforcing bar adopt the steel bar connector to connect, and cast-in-place partial distribution muscle is whole ligature, and prefabricated section parting punishment cloth muscle structure enhancement processing.
The invention can effectively shorten the construction period under severe cold and long climate conditions, reduce the occupied area under narrow and narrow field conditions and relieve the pressure of traffic relief, can effectively promote the early working depth of design, production, construction, equipment and the like by taking prefabrication and assembly as a main line, deeply integrates the traditional organization management mode which is characterized by 'sectioning, cutting and interrupting' and realizes integrated management; the concrete pouring quality is improved, the concrete self-waterproof quality is improved, the structure water leakage is avoided, and the method is suitable for the construction of subway station structures in various stratums.
The station is built in a combination mode of an overlapping structure and local integral cast-in-place; meanwhile, the prefabricated slab with the superposed structure replaces a traditional temporary template; the local coil buckle bracket replaces a full bracket; the side wall stressed steel bars adopt a grouting sleeve connection type; the upper row of hot air ducts is prefabricated in an integral U-shaped mode, and is installed after the structure is capped through the middle plate in a pre-embedded mode, and the construction period is shortened.
In order to ensure seamless connection between the reinforcing steel bars of the line pair and the prefabricated blocks of the opposite surfaces, automatic processing and shaping limiting measures are promoted to be adopted, and the construction quality can be improved from centimeter level to millimeter level; the adoption of the vibration-free superfluid shrinkage-free concrete avoids the concrete pouring quality defect caused by artificial inertia and insufficient experience.
The assembly type construction organization reduces the amount of field labor, realizes standardization and flow process, and reduces human errors and personal casualties; factory prefabricated construction, reinforcing bar are bound in advance, the template faces forever and combines and the support system is optimized, can effectively reduce the field demand to the job site.
The assembly type structure saves most of on-site steel bar binding and support arrangement, shortens the procedure connection, saves about 2 months for the construction period of the main structure (about 30%), can complete road restoration in the current year (one winter-break period of 4 months), and creates conditions for subsequent site cleaning so as to carry out through measurement and internal structure construction as early as possible.
Description of the drawings:
FIG. 1 is a schematic view of the cross-sectional form of a foundation pit of the present invention.
FIG. 2 is a schematic diagram of installation of a negative two-layer side wall reinforcing steel bar limiter, pre-embedding of a bottom plate and concrete pouring.
FIG. 3 is a schematic view of the installation of the negative two-layer precast block and the column shaping template and the fixation of the lateral bracket.
FIG. 4 is a schematic diagram of concrete pouring of the negative two-layer side wall and the column and placement of the middle plate precast block.
FIG. 5 is a schematic view of installation of the negative-layer side wall reinforcing steel bar limiter, middle plate pre-embedding and concrete pouring.
FIG. 6 is a schematic view of the installation of a negative layer precast block and a column sizing template.
FIG. 7 is a schematic view of the placement of negative side walls, column concrete placement, and top plate precast blocks.
FIG. 8 is a schematic view of top plate binding steel bars and concrete pouring.
FIG. 9 is a schematic view of the inner structures of soil covering, road surface restoration, hot air exhaust duct installation, and station boards.
Fig. 10 is a schematic view of a bottom plate steel reinforcement cage and a stopper module.
Figure 11 is a schematic view of the positioning of the diaphragm wall stop.
Fig. 12 is a schematic cross-sectional view of a standard single column double span of a station.
FIG. 13 is a schematic view of the assembly of the side wall precast blocks and the connection of the reinforcing steel bars.
FIG. 14 is a schematic view of a side wall preform.
Fig. 15 is a schematic diagram of the assembly of the top and middle plate precast blocks.
FIG. 16 is a schematic view of the transverse assembly of prefabricated wall and slab blocks.
FIG. 17 is a schematic diagram of the assembly of the side wall precast blocks and the pre-embedding and pre-embedding.
FIG. 18 is a schematic diagram of the prefabrication of a rail head duct.
FIG. 19 is a structural connection diagram of the present invention.
In the figure: 1. top plate, 2, middle plate, 3, bottom plate, 4, side wall, 5, hot air exhaust channel, 6, first concrete support, 7, second steel support, 8, third steel support, 9, ground elevation, 10, support positioning steel bar, 11, steel bar stopper, 12, longitudinal horizontal construction joint, 13, grouting sleeve, 14, middle longitudinal beam, 15, negative two-layer shaped template/structural column, 16, lateral support, 17, negative two-layer side wall prefabricated plate, 18, prefabricated middle plate, 19, disk buckle support, 20, bolt tensioning, 21, negative one-layer side wall, 22, negative one-layer shaped template/structural column, 23, prefabricated top plate, 24, earth covering, 25, platform plate, 26, underground continuous wall, 27, steel plate, 28, steel pipe support, 29, buckle fixing, 30, water stop steel plate, 31, positioning steel plate clamp, 32, angle template, 33, steel bar connector, 34. truss muscle, 35, bottom plate atress owner muscle, 36, bottom plate bed course, 37, protective layer cushion block, 38, additional atress muscle, 39, buckle bolt, 40, location steel sheet, 41, locator seam, 42, side wall atress muscle, 43, truss muscle, 44, bottom plate distribution muscle, 45, stagnant water adhesive tape, 46, coarse surface, 47, channel-section steel is taut, 48, construction joint end cap design steel masterplate, 49, embedded nut, 50, distribution strengthening rib, 51, nut and gasket, 52, medium plate reservation reinforcing bar hole, 53, hang the muscle, 54, go up the exhaust hole of airing exhaust, 55, go up exhaust flue, 56, reinforcing bar anchor plate, 57, prefabricated block, 58, handle hole.
The specific implementation mode is as follows:
example 1:
structural node connection introduction
A folding assembly type structure subway station comprises: roof 1, medium plate 2, bottom plate 3, side wall 4 and heat extraction flue 5, the structure nodal connection:
the bottom plate is connected with the side wall
(1) A construction joint 12 from the bottom plate to the bottom of the negative second floor is of a cast-in-place reinforced concrete structure, and an externally-leaked grouting sleeve 13 is embedded in the construction joint and connected with upper side wall stressed steel bars;
(2) the inner skin of the side wall is a prefabricated block with truss ribs (both stress ribs and distribution ribs are carried), and simultaneously serves as an inner side template, the bottom of the prefabricated block is inserted into a grouting sleeve, the stress ribs are connected by pouring high-efficiency grouting material, the width of the longitudinal blocks is about 2m, and the structure of the distribution ribs among the blocks is reinforced;
(3) and (4) setting a cast-in-place strip on the construction joint, and pouring concrete in the cavity of the side wall to form a side wall laminated structure.
Example 2:
the middle plate is connected with the side wall
(1) Pouring the concrete of the side wall of the negative second floor to the construction joint at the top of the negative second floor, reserving a steel bar connector for the stressed steel bars of the side wall at the construction joint, and connecting the upper steel bars;
(2) the middle plate bottom skin is a precast block with truss ribs and is also used as a bottom skin template, the longitudinal block width is about 2m, the inter-block distribution rib structure is reinforced, and the upper skin steel bars are all bound on site; a middle plate precast block is reserved with a heat exhaust air duct steel bar connecting hole for later installation of a heat exhaust air duct;
(3) pouring the middle plate concrete to the bottom construction joint of the negative layer to form a middle plate superposed structure, embedding an externally-leaked grouting sleeve at the joint, and connecting the upper side wall stress steel bars;
example 3:
the top plate is connected with the side wall
(1) Pouring the side wall concrete of the negative layer to a construction joint at the top of the negative layer, reserving a steel bar connector for the stressed steel bars of the side wall at the construction joint, and connecting the upper steel bars;
(2) the bottom skin of the top plate is a prefabricated block with truss ribs and is used as a bottom skin template, the width of each block is about 2m, the structure of distributed ribs among the blocks is reinforced, and the upper steel bars are bound on site;
(3) and pouring the top plate concrete to form a top plate laminated structure.
Example 4:
the heat exhausting air duct is connected with the middle plate
(1) After the station structure is capped, a heat exhaust air duct at the lower part of the middle plate is installed;
(2) the heat exhaust air duct is prefabricated in an integral U shape, hanging ribs are leaked outside the upper part of the heat exhaust air duct, the heat exhaust air duct penetrates into a reserved hole of the middle plate through jacking equipment, and the upper part of the heat exhaust air duct is fixed by a gasket and a nut;
(3) the cavity is filled with high-efficiency grouting material compactly.
Example 5:
step 1: constructing a waterproof layer of the cushion layer;
after the foundation pit is excavated to the substrate, a cushion layer and a waterproof layer wrapped outside the bottom plate are applied in time;
and a step 2: installing a negative two-layer side wall reinforcing steel bar limiter, embedding a bottom plate and pouring concrete;
reserving a side wall waterproof layer, installing a negative two-layer side wall reinforcing steel bar limiter 11 (fixing a negative two-layer side wall grouting sleeve and a stress reinforcing steel bar), binding bottom plate reinforcing steel bars, embedding lateral support positioning reinforcing steel bars 10 (with a longitudinal distance of 1 m), and pouring bottom plate concrete to a horizontal construction joint at the bottom of the negative two-layer side wall;
step 3: the negative two-layer precast block and the column shaping template 15 are installed and fixed by a lateral bracket 16;
dismantling a third steel support, paving a waterproof layer of the negative second-layer side wall, hoisting a prefabricated block (prefabricated with inner truss ribs) of the negative second-layer side wall and a structural column shaping template 15, fixing a lateral support system, and installing an operation platform;
and step 4: pouring concrete of the side walls and the columns of the negative second layer and placing middle plate precast blocks;
pouring high-strength grouting material into the grouting sleeve of the negative second-layer side wall to ensure the effective connection of stress ribs of the side walls, pouring the negative second-layer side wall (forming a superposed structure) and structural column concrete after the connection precision of the distribution ribs is adjusted, removing the lateral support after pouring to the horizontal construction joint at the top of the negative second layer to reach the strength, erecting a local buckling support 19, and placing a middle plate precast block (bottom belt truss rib prefabrication);
step 5: installing a negative layer side wall reinforcing steel bar limiter, embedding a middle plate and pouring concrete;
the method comprises the following steps of (1) paving and reserving a waterproof layer of a side wall, installing a negative layer side wall reinforcing steel bar limiter (fixing a negative layer side wall grouting sleeve and stressed reinforcing steel bars), binding reinforcing steel bars of a middle plate cast-in-place layer (reserving a heat exhausting duct hole), embedding lateral support positioning reinforcing steel bars (with a longitudinal distance of 1 m), and pouring middle plate concrete to a horizontal construction joint at the bottom of the negative layer;
step 6: installing a layer of prefabricated blocks and a column shaping template, and fixing a lateral bracket;
dismantling a second steel support, laying a side wall waterproof layer on the second steel support, hoisting a prefabricated block (prefabricated with inner truss ribs) and a column shaping template on the second steel support, fixing a lateral support system, and installing an operation platform;
step 7: carrying out concrete pouring on a layer of side walls and columns and placing prefabricated blocks of a top plate;
pouring high-strength grouting material into the negative layer of side wall grouting sleeve to ensure effective connection of the stress ribs of the side walls, pouring a negative layer of side walls (forming a superposed structure) and structural column concrete after the connection precision of the distributed ribs is adjusted, removing the lateral supports after pouring to the horizontal construction joint at the top of the negative layer to reach the strength, erecting local coil buckling supports, and placing a top plate precast block (bottom belt truss rib prefabrication);
step 8: and (3) binding steel bars on the top plate and pouring concrete:
dismantling the first steel support, paving and reserving the waterproof layer of the side wall, binding the steel bars of the cast-in-place layer of the top plate, and pouring concrete;
step 9: earthing 24, restoring the road surface, installing a heat exhaust channel, constructing a platform plate 25 and other internal structures;
laying a roof plate fully covered with a waterproof layer, backfilling and earthing, laying pipelines, recovering the pavement, installing a heat exhaust duct in a station, and constructing internal structures such as a station bedplate and the like;
the whole U-shaped prefabrication of the upper row of hot air ducts, the steel bars leak outwards, the holes of the steel bars of the upper row of hot air ducts are upwards installed through the holes reserved in the middle plate, the holes penetrate through the top surface of the middle plate and are connected in a bolt and gasket mode, the steel bar holes are grouted compactly, and other station table plates and other structures are cast in situ.

Claims (5)

1. A folding assembly type structure subway station comprises: roof, medium plate, bottom plate, heat extraction wind channel and side wall, characterized by: the bottom plate to two negative layers of bottom construction joint be cast-in-place reinforced concrete structure, the grout sleeve that leaks is pre-buried outward in construction joint department connects upper portion side wall atress reinforcing bar, and the side wall endothelium is the prefabricated section of taking the truss muscle, as inboard template simultaneously, in the grout sleeve is inserted to the bottom, connects the atress reinforcing bar through pouring high-efficient grout material, vertical piecemeal width is about 2m, the interblock distribution muscle structure is strengthened, construction joint upper portion sets up cast-in-place area, pours side wall cavity concrete, forms the side wall coincide structure.
2. A folding assembly construction type subway station as claimed in claim 1, wherein: negative two-layer side wall concrete placement to negative two-layer top construction joint department, construction joint department side wall atress reinforcing bar reserves reinforcing bar connector, connects upper portion side wall atress reinforcing bar, the medium plate end skin be the prefabricated section of taking the truss muscle, as end skin template simultaneously, vertical piecemeal width is about 2m, the interblock distribution muscle structure is strengthened, the equal on-the-spot ligature of epithelium reinforcing bar, the exhaust airway reinforcing bar connecting hole is reserved to the medium plate prefabricated section for later stage installation exhaust airway, medium plate concrete placement to negative one-layer side wall bottom construction joint department, forms the medium plate coincide structure, the pre-buried grout sleeve of leaking outside of seam crossing connects upper portion side wall atress reinforcing bar.
3. A folding assembly construction type subway station as claimed in claim 2, wherein: negative one deck side wall prefabricated section installation, connection and cast-in-place area set up with two layers on the negative side, negative one deck side wall concrete placement to negative one deck top construction joint department, and construction joint department side wall atress reinforcing bar reserves the reinforcing bar connector of plugging into, connects the upper portion reinforcing bar, the roof bottom skin be the prefabricated section of taking the truss muscle, as the bottom skin template simultaneously, vertical piecemeal width is about 2m, the interblock distribution muscle structure is strengthened, the equal on-the-spot ligature of epitheca reinforcing bar, roof concrete placement forms roof superimposed structure.
4. A folding assembly construction type subway station as claimed in claim 3, wherein: after the station structure is closed, install the medium plate lower part the heat extraction wind channel, the heat extraction wind channel be whole U type prefabrication, the muscle is hung to the upper portion hourglass outward, penetrate the heat extraction wind channel through jacking equipment in the medium plate preformed hole, upper portion is fixed with the gasket with the nut, adopts high-efficient grout material packing closely knit in the cavity.
5. An assembly construction method for a subway station of a superimposed assembly type structure as claimed in any one of claims 1 to 4, characterized in that: the method comprises the following steps:
(1) constructing a waterproof layer of the cushion layer;
after the foundation pit is excavated to the substrate, a cushion layer and a waterproof layer wrapped outside the bottom plate are applied in time;
(2) installing a negative two-layer side wall reinforcing steel bar limiter, embedding a bottom plate and pouring concrete;
reserving a side wall waterproof layer, installing a negative two-layer side wall reinforcing steel bar limiter 11 (fixing a negative two-layer side wall grouting sleeve and a stress reinforcing steel bar), binding bottom plate reinforcing steel bars, embedding lateral support positioning reinforcing steel bars 10 (with a longitudinal distance of 1 m), and pouring bottom plate concrete to a horizontal construction joint at the bottom of the negative two-layer side wall;
(3) the negative two-layer precast block and the column shaping template 15 are installed and fixed by a lateral bracket 16;
dismantling a third steel support, paving a waterproof layer of the negative second-layer side wall, hoisting a prefabricated block (prefabricated with inner truss ribs) of the negative second-layer side wall and a structural column shaping template 15, fixing a lateral support system, and installing an operation platform;
(4) pouring concrete of the side walls and the columns of the negative second layer and placing middle plate precast blocks;
pouring high-strength grouting material into the grouting sleeve of the negative second-layer side wall to ensure the effective connection of stress ribs of the side walls, pouring the negative second-layer side wall (forming a superposed structure) and structural column concrete after the connection precision of the distribution ribs is adjusted, removing the lateral support after pouring to the horizontal construction joint at the top of the negative second layer to reach the strength, erecting a local buckling support 19, and placing a middle plate precast block (bottom belt truss rib prefabrication);
(5) installing a negative layer side wall reinforcing steel bar limiter, embedding a middle plate and pouring concrete;
the method comprises the following steps of (1) paving and reserving a waterproof layer of a side wall, installing a negative layer side wall reinforcing steel bar limiter (fixing a negative layer side wall grouting sleeve and stressed reinforcing steel bars), binding reinforcing steel bars of a middle plate cast-in-place layer (reserving a heat exhausting duct hole), embedding lateral support positioning reinforcing steel bars (with a longitudinal distance of 1 m), and pouring middle plate concrete to a horizontal construction joint at the bottom of the negative layer;
(6) installing a layer of prefabricated blocks and a column shaping template, and fixing a lateral bracket;
dismantling a second steel support, laying a side wall waterproof layer on the second steel support, hoisting a prefabricated block (prefabricated with inner truss ribs) and a column shaping template on the second steel support, fixing a lateral support system, and installing an operation platform;
(7) carrying out concrete pouring on a layer of side walls and columns and placing prefabricated blocks of a top plate;
pouring high-strength grouting material into the negative layer of side wall grouting sleeve to ensure effective connection of the stress ribs of the side walls, pouring a negative layer of side walls (forming a superposed structure) and structural column concrete after the connection precision of the distributed ribs is adjusted, removing the lateral supports after pouring to the horizontal construction joint at the top of the negative layer to reach the strength, erecting local coil buckling supports, and placing a top plate precast block (bottom belt truss rib prefabrication);
(8) and (3) binding steel bars on the top plate and pouring concrete:
dismantling the first steel support, paving and reserving the waterproof layer of the side wall, binding the steel bars of the cast-in-place layer of the top plate, and pouring concrete;
(9) earthing 24, restoring the road surface, installing a heat exhaust channel, constructing a platform plate 25 and other internal structures;
laying a roof plate fully covered with a waterproof layer, backfilling and earthing, laying pipelines, recovering the pavement, installing a heat exhaust duct in a station, and constructing internal structures such as a station bedplate and the like;
the whole U-shaped prefabrication of the upper row of hot air ducts, the steel bars leak outwards, the holes of the steel bars of the upper row of hot air ducts are upwards installed through the holes reserved in the middle plate, the holes penetrate through the top surface of the middle plate and are connected in a bolt and gasket mode, the steel bar holes are grouted compactly, and other station table plates and other structures are cast in situ.
CN202010398564.0A 2020-05-12 2020-05-12 Subway station with overlapped assembly type structure and assembly construction method Pending CN111456088A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010398564.0A CN111456088A (en) 2020-05-12 2020-05-12 Subway station with overlapped assembly type structure and assembly construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010398564.0A CN111456088A (en) 2020-05-12 2020-05-12 Subway station with overlapped assembly type structure and assembly construction method

Publications (1)

Publication Number Publication Date
CN111456088A true CN111456088A (en) 2020-07-28

Family

ID=71684701

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010398564.0A Pending CN111456088A (en) 2020-05-12 2020-05-12 Subway station with overlapped assembly type structure and assembly construction method

Country Status (1)

Country Link
CN (1) CN111456088A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112227416A (en) * 2020-10-28 2021-01-15 中建八局第二建设有限公司 Construction method of assembled steel pipe support and distribution beam combined support
CN113006133A (en) * 2021-01-29 2021-06-22 广州地铁设计研究院股份有限公司 Construction method of middle plate hole suitable for assembly type station
CN113089719A (en) * 2021-02-23 2021-07-09 中铁十九局集团第三工程有限公司 Laminated wall structure and construction method thereof
CN113863372A (en) * 2021-10-28 2021-12-31 中交一航局城市交通工程有限公司 Installation method of prefabricated structure of air duct at top of underground station rail
CN114319161A (en) * 2022-01-17 2022-04-12 青岛中科坤泰装配建筑科技有限公司 Subway station prefabricated platform plate structure and installation method thereof
CN114855868A (en) * 2022-06-10 2022-08-05 中铁第六勘察设计院集团有限公司 Structure and construction method of side wall of vehicle station formed by combination of similar-omega-shaped inserting plates and convex wall columns
CN115288148A (en) * 2022-06-28 2022-11-04 北京城建设计发展集团股份有限公司 Middle floor based on internal support system and construction method thereof

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112227416A (en) * 2020-10-28 2021-01-15 中建八局第二建设有限公司 Construction method of assembled steel pipe support and distribution beam combined support
CN113006133A (en) * 2021-01-29 2021-06-22 广州地铁设计研究院股份有限公司 Construction method of middle plate hole suitable for assembly type station
CN113006133B (en) * 2021-01-29 2022-10-14 广州地铁设计研究院股份有限公司 Construction method of middle plate hole suitable for assembly type station
CN113089719A (en) * 2021-02-23 2021-07-09 中铁十九局集团第三工程有限公司 Laminated wall structure and construction method thereof
CN113863372A (en) * 2021-10-28 2021-12-31 中交一航局城市交通工程有限公司 Installation method of prefabricated structure of air duct at top of underground station rail
CN114319161A (en) * 2022-01-17 2022-04-12 青岛中科坤泰装配建筑科技有限公司 Subway station prefabricated platform plate structure and installation method thereof
CN114855868A (en) * 2022-06-10 2022-08-05 中铁第六勘察设计院集团有限公司 Structure and construction method of side wall of vehicle station formed by combination of similar-omega-shaped inserting plates and convex wall columns
CN115288148A (en) * 2022-06-28 2022-11-04 北京城建设计发展集团股份有限公司 Middle floor based on internal support system and construction method thereof

Similar Documents

Publication Publication Date Title
CN111456088A (en) Subway station with overlapped assembly type structure and assembly construction method
CN203475598U (en) Shock-proof prefabricated building of steel bar truss shearing wall composite structure
CN105350581A (en) Advanced sealing structure for basement top slab settlement post-cast strips
CN110158645A (en) Prefabricated components Hybrid connections assembly concrete pipe gallery
CN107355008B (en) Prefabricated connection structure and method for newly added concrete filled steel tubular column and existing structure
CN111119928B (en) Novel tunnel primary support structure and construction method
CN110042862B (en) Subway station prefabricated rail top air duct, connection node with prefabricated middle plate and construction method
CN212271005U (en) Superposed assembly type structure subway station
CN111173042B (en) Advanced water stop post-cast strip of foundation slab and construction method
CN112030630A (en) Grouting bag for ballastless track adjusting layer and using method thereof
CN210562325U (en) Structure seam structure of comprehensive pipe rack
CN210263131U (en) Assembled is from stagnant water underground pipe gallery structure
CN110004980B (en) Composite assembled underground structure and first-reverse-then-forward construction method
CN210369292U (en) Cast-in-place coincide mould shell integral structure of assembled building
CN106437763A (en) Inverted arch steel end die and construction method thereof
CN106193120A (en) Basement is encorbelmented, and base plate is inverse makees structure and construction method
CN212223971U (en) Post-cast strip side-fixing inner-supporting steel plate combined template
CN210369293U (en) Integrated structure of assembled building heat preservation formwork
CN111535339B (en) Construction process of concrete dam body of refuse landfill
CN112610022B (en) Old building translation construction method near deep foundation pit
CN212656260U (en) Assembled rail top air duct structure of underground station
CN210887323U (en) Connect and build engineering underground structure construction joint watertight fittings
CN111535361A (en) Assembled rail top air duct structure of underground station and construction method thereof
JP4010388B2 (en) High-strength reinforced concrete precast plate
CN108331385B (en) Inspection pit precast column structure and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
CB02 Change of applicant information

Address after: 300450 Building 8, Yuejin Road shipping center, Tianjin Port Free Trade Zone, Binhai New Area, Tianjin

Applicant after: CCCC First Harbor Engineering Co.,Ltd.

Applicant after: CCCC FIRST HARBOR ENGINEERING TRANSPORTATION ENGINEERING Co.,Ltd.

Applicant after: CCCC HARBIN METRO INVESTMENT AND CONSTRUCTION OF METRO Ltd.

Address before: 150086 room 402, 4th floor, unit 1, building 1, Jinjue Vientiane, 640 Harbin street, Nangang District, Harbin City, Heilongjiang Province

Applicant before: CCCC HARBIN METRO INVESTMENT AND CONSTRUCTION OF METRO Ltd.

Applicant before: CCCC First Harbor Engineering Co.,Ltd.

Applicant before: CCCC FIRST HARBOR ENGINEERING TRANSPORTATION ENGINEERING Co.,Ltd.

CB02 Change of applicant information
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination