CN111455800B - Construction method of double-layer double-width bridge with wide top and narrow bottom - Google Patents

Construction method of double-layer double-width bridge with wide top and narrow bottom Download PDF

Info

Publication number
CN111455800B
CN111455800B CN202010172330.4A CN202010172330A CN111455800B CN 111455800 B CN111455800 B CN 111455800B CN 202010172330 A CN202010172330 A CN 202010172330A CN 111455800 B CN111455800 B CN 111455800B
Authority
CN
China
Prior art keywords
double
layer
bridge
support
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010172330.4A
Other languages
Chinese (zh)
Other versions
CN111455800A (en
Inventor
方柯
王令侠
刘爱林
潘博
张臻元
谢玮
李旭
张爱花
刘幸福
周启辉
缪玉卢
董继红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
Original Assignee
China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Group Co Ltd MBEC filed Critical China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority to CN202010172330.4A priority Critical patent/CN111455800B/en
Publication of CN111455800A publication Critical patent/CN111455800A/en
Application granted granted Critical
Publication of CN111455800B publication Critical patent/CN111455800B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D1/00Bridges in general
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete

Abstract

The invention discloses a construction method of a double-layer double-width bridge with a wide top and a narrow bottom, which relates to the technical field of bridge construction and comprises the following steps: step S1, constructing a lower bridge pier of the bridge, wherein the lower bridge pier comprises a left amplitude region and a right amplitude region, a first support is erected in the left amplitude region, and a first lower beam is poured on the first support; step S2, constructing an upper bridge pier of the bridge, transversely moving the first lower beam on the first support to the right area, and pouring a second lower beam on the first support; step S3, erecting a second support on the first lower-layer beam, and pouring a first upper-layer beam on the second support; step S4, transversely moving the second support to the second lower-layer beam, and pouring a second upper-layer beam on the second support; and step S5, respectively traversing the first lower beam and the second lower beam to a preset position. The invention can reduce the support size, is simple to install and dismantle and reduces the construction cost.

Description

Construction method of double-layer double-width bridge with wide top and narrow bottom
Technical Field
The invention relates to the technical field of bridge construction, in particular to a construction method of a double-layer double-width bridge with a wide upper part and a narrow lower part.
Background
In the current domestic bridge engineering, referring to fig. 1, for a double-deck double-width bridge with a wide top and a narrow bottom, wherein the central lines of the beams of the upper and lower decks are not coincident, and L1 is greater than L2, the construction is generally carried out by using full framing. The construction method needs to set up two brackets below the lower bridge; after the construction of the lower bridge is finished, two supports are erected below the upper bridge, and the construction method has the following problems:
1. the whole support is large in size, difficult to install and dismantle and high in cost, and particularly in areas with poor geological conditions and difficult construction of the upright pile foundations of the support, the support erection cost is increased greatly;
2. in the support of the upper-layer bridge, part of support stand columns fall on the lower-layer bridge, the other part of the support stand columns fall on the ground, the length difference of the support stand columns is large, the support stand columns are not uniformly settled, and safety risks exist;
3. when the upper bridge is constructed, the construction load born by the lower bridge is asymmetric, so that the lower bridge is subjected to a larger torque, and the stress of the lower bridge structure also has a safety risk.
Disclosure of Invention
Aiming at the defects in the prior art, the invention aims to provide a construction method of a double-layer double-width bridge with a wide upper part and a narrow lower part, which is used for solving the problems of large whole support body, difficulty in installation and removal and high cost in the existing construction method.
In order to achieve the above purposes, the technical scheme adopted by the invention is as follows: a construction method of a double-layer double-width bridge with a wide top and a narrow bottom comprises the following steps:
s1, constructing a lower layer pier of the bridge, wherein the lower layer pier comprises a left amplitude region and a right amplitude region, a first support is erected in the left amplitude region, and a first lower layer beam is poured on the first support;
s2, constructing an upper layer pier of the bridge, transversely moving the first lower layer beam on the first support to the right width area, and pouring a second lower layer beam on the first support;
s3, erecting a second support on the first lower-layer beam, and pouring a first upper-layer beam on the second support;
s4, transversely moving the second support to the second lower-layer beam, and pouring a second upper-layer beam on the second support;
and S5, respectively moving the first lower layer beam and the second lower layer beam to a preset position in a transverse mode.
On the basis of the above technical solution, in step S2:
and after the first lower beam is transversely moved to the right amplitude area, the central line of the first lower beam is superposed with the central line of a preset theoretical first upper beam.
On the basis of the above technical solution, in step S2:
and after the second lower-layer beam is poured, the central line of the second lower-layer beam is superposed with the central line of a preset theoretical second upper-layer beam.
On the basis of the above technical solution, in step S3:
the center line of the second support is superposed with the center line of the first lower beam.
On the basis of the above technical solution, in step S4:
and the central line of the second support is superposed with the central line of the second lower-layer beam.
On the basis of the above technical solution, step S2 specifically includes the following steps:
and arranging a first slide way beam on the lower layer pier, and transversely moving the first lower layer beam to the right amplitude area through the first slide way beam.
On the basis of the above technical solution, step S4 specifically includes the following steps:
and second slideway beams are arranged on the first lower beam and the second lower beam, and the second support is transversely moved to the second lower beam through the second slideway beams.
On the basis of the above technical solution, step S4 specifically includes the following steps:
and arranging a sand cylinder on the second support, separating the second support from the first upper beam by using the sand cylinder, and transversely moving the second support to the second lower beam.
On the basis of the above technical solution, step S1 specifically includes the following steps:
and constructing the lower layer pier and erecting the first support of the bridge synchronously.
On the basis of the above technical solution, step S2 specifically includes the following steps:
and synchronously constructing the upper layer bridge pier and the first lower layer beam of the bridge in a transverse moving mode.
Compared with the prior art, the invention has the advantages that:
according to the construction method of the double-layer double-width bridge with the wide upper part and the narrow lower part, only one first support needs to be erected below the lower-layer bridge, and after the lower-layer bridge is constructed, one second support is erected below the upper-layer bridge, only two supports are needed, so that the support size is reduced, the installation and the removal are relatively simple, the construction cost is reduced, and the construction safety risk is low.
Drawings
FIG. 1 is a schematic structural view of a wide-top and narrow-bottom double-deck bridge with non-coincident centerlines of upper and lower deck beams;
FIG. 2 is a flow chart of a construction method of a double-deck double-width bridge with a wide top and a narrow bottom in the embodiment of the invention;
FIG. 3 is a diagram illustrating step S1 according to an embodiment of the present invention;
FIG. 4 is a diagram illustrating step S2 according to an embodiment of the present invention;
FIG. 5 is another diagram illustrating step S2 according to an embodiment of the present invention;
FIG. 6 is a diagram illustrating step S3 according to an embodiment of the present invention;
FIG. 7 is a diagram illustrating step S4 according to an embodiment of the present invention;
FIG. 8 is another diagram illustrating step S4 according to an embodiment of the present invention;
FIG. 9 is a right side view of FIG. 7;
FIG. 10 is a diagram illustrating step S5 according to an embodiment of the present invention;
in the figure: 1. a first bracket; 2. a first side mold; 3. a first lower beam; 4. a second lower beam; 5. a second bracket; 51. a column shoe; 52. a steel pipe frame; 53. a sand cylinder; 54. a cross beam; 55. a Bailey beam; 6. a second side mold; 7. a first upper beam; 8. a second upper beam; 100. a lower pier; 200. an upper layer pier; 300. a first slideway beam; 400. a second skid beam.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings and examples.
Referring to fig. 2, an embodiment of the present invention provides a construction method of a double-deck double-width bridge with a wide top and a narrow bottom, including the following steps:
and S1, constructing a lower-layer pier 100 of the bridge, wherein the lower-layer pier 100 comprises a left-width area and a right-width area, erecting a first support 1 in the left-width area, and pouring a first lower-layer beam 3 on the first support 1. Specifically, referring to fig. 3, two detachable first side molds 2 are provided at the first bracket 1, and the two first side molds 2 are assembled as a mold for casting the first lower girder 3. Preferably, the lower bridge pier 100 of the bridge is constructed and the first support 1 is erected synchronously, so that the construction time is saved.
Step S2, constructing the upper bridge pier 200 of the bridge, traversing the first lower beam 3 on the first bracket 1 to the right area, and casting the second lower beam 4 on the first bracket 1. Specifically, referring to fig. 4 and 5, the first side mold 2 is disassembled, the first runner girder 300 is provided on the lower pier 100, and the first lower girder 3 is laterally moved to the right panel area by the first runner girder 300. And then assembling the first side formwork 2, and pouring a second lower-layer beam 4 on the first side formwork 2. Preferably, the upper pier 200 and the first lower beam 3 are constructed in a horizontal moving manner, so that the construction time is saved.
Step S3 is to set up the second bracket 5 on the first lower beam 3 and to cast the first upper beam 7 on the second bracket 5. Specifically, referring to fig. 6, two detachable second side forms 6 are provided on the second bracket 5, and the two second side forms 6 are assembled as a mold for casting the first upper beam 7.
And step S4, transversely moving the second support 5 to the second lower-layer beam 4, and pouring the second upper-layer beam 8 on the second support 5. Specifically, referring to fig. 7 to 9, the second side mold 6 is disassembled, the second runner beam 400 is provided on the first lower beam 3 and the second lower beam 4, and the second bracket 5 is moved to the second lower beam 4 by the second runner beam 400. And assembling the second side formwork 6, and pouring a second upper-layer beam 8 on the second side formwork 6. Preferably, a sand cylinder 53 is provided on the second support 5, the second support 5 is detached from the first upper beam 7 using the sand cylinder 53, and the second support 5 is then laterally moved onto the second lower beam 4. Referring to fig. 9, the second support 5 generally includes a column base 51, a steel pipe frame 52, a sand tank 53, a cross beam 54, and a bery beam 55, the sand tank 53 is disposed between the steel pipe frame 52 and the cross beam 54, and when sand in the sand tank 53 is removed, the cross beam 54 moves downward to separate the second support 5 from the first upper beam 7.
And step S5, respectively traversing the first lower beam 3 and the second lower beam 4 to close to preset positions. Specifically, as shown in fig. 10, the first lower beam 3 and the second lower beam 4 are respectively laterally moved close to a predetermined position by the first chute beam 300.
Compared with the prior art, the construction method of the double-layer double-width bridge with the wide upper part and the narrow lower part only needs to set up one first support 1 below the lower-layer bridge, and after the lower-layer bridge is constructed, one second support 5 is set up below the upper-layer bridge, so that two supports are needed in total, the support size is reduced, the installation and the removal are relatively simple, and the construction cost is reduced.
In a preferred embodiment, as shown in fig. 4, after traversing the first lower beam 3 to the right panel area, the centre line of the first lower beam 3 coincides with the centre line of a predetermined theoretical first upper beam 7. After the second lower beam 4 is poured, the center line of the second lower beam 4 coincides with the center line of a preset theoretical second upper beam 8. When the first upper beam 7 and the second upper beam 8 are constructed, the second support 5 just falls on the first lower beam 3 or the second lower beam 4, the length of the upright columns of the supports is not different, the upright columns of the supports are uniformly settled, and no safety risk exists. At the same time. The construction load born by the first lower beam 3 or the second lower beam 4 is symmetrical, the first lower beam 3 or the second lower beam 4 is not affected by large torque, and the stress does not have safety risk.
As a preferred embodiment, referring to fig. 6 and 8, when the first and second upper girders 7 and 8 are constructed, the center line of the second bracket 5 coincides with the center line of the first lower girder 3 or the second lower girder 4. When the first upper-layer beam 7 and the second upper-layer beam 8 are constructed, the construction load born by the first lower-layer beam 3 or the second lower-layer beam 4 is symmetrical, the first lower-layer beam 3 or the second lower-layer beam 4 is not affected by large torque, and the stress does not have safety risk.
The present invention is not limited to the above-described embodiments, and it will be apparent to those skilled in the art that various modifications and improvements can be made without departing from the principle of the present invention, and such modifications and improvements are also considered to be within the scope of the present invention. Those not described in detail in this specification are within the skill of the art.

Claims (10)

1. A construction method of a double-layer double-width bridge with a wide top and a narrow bottom is characterized by comprising the following steps:
s1, constructing a lower layer pier (100) of the bridge, wherein the lower layer pier (100) comprises a left amplitude region and a right amplitude region, a first support (1) is erected in the left amplitude region, and a first lower layer beam (3) is poured on the first support (1);
s2, constructing an upper layer pier (200) of the bridge, transversely moving the first lower layer beam (3) on the first support (1) to the right width area, and pouring a second lower layer beam (4) on the first support (1);
s3, erecting a second bracket (5) on the first lower-layer beam (3), and pouring a first upper-layer beam (7) on the second bracket (5);
s4, transversely moving the second bracket (5) to the second lower-layer beam (4), and pouring a second upper-layer beam (8) on the second bracket (5);
and S5, respectively moving the first lower layer beam (3) and the second lower layer beam (4) transversely to close to preset positions.
2. The construction method of the double-deck double-width bridge with the wide top and the narrow bottom according to claim 1, wherein in step S2:
after the first lower beam (3) is transversely moved to the right amplitude area, the center line of the first lower beam (3) is superposed with the center line of a preset theoretical first upper beam (7).
3. The construction method of the double-deck double-width bridge with the wide top and the narrow bottom according to claim 2, wherein in step S2:
and after the second lower-layer beam (4) is poured, the center line of the second lower-layer beam (4) is superposed with the center line of a preset theoretical second upper-layer beam (8).
4. The construction method of the double-deck double-width bridge with the wide top and the narrow bottom according to claim 3, wherein in step S3:
the central line of the second bracket (5) is superposed with the central line of the first lower beam (3).
5. The construction method of the double-deck double-width bridge with the wide top and the narrow bottom according to claim 3, wherein in step S4:
the central line of the second bracket (5) is superposed with the central line of the second lower beam (4).
6. The construction method of the double-deck double-width bridge with the wide top and the narrow bottom as claimed in claim 1, wherein the step S2 specifically comprises the following steps:
and arranging a first slideway beam (300) on the lower layer pier (100), and transversely moving the first lower layer beam (3) to the right amplitude area through the first slideway beam (300).
7. The construction method of the double-deck double-width bridge with the wide top and the narrow bottom as claimed in claim 1, wherein the step S4 specifically comprises the following steps:
and second slideway beams (400) are arranged on the first lower-layer beam (3) and the second lower-layer beam (4), and the second bracket (5) is transversely moved onto the second lower-layer beam (4) through the second slideway beams (400).
8. The construction method of the double-deck double-width bridge with the wide top and the narrow bottom as claimed in claim 1, wherein the step S4 specifically comprises the following steps:
and arranging a sand cylinder (53) on the second bracket (5), separating the second bracket (5) from the first upper beam (7) by using the sand cylinder (53), and transversely moving the second bracket (5) to the second lower beam (4).
9. The construction method of the double-deck double-width bridge with the wide top and the narrow bottom as claimed in claim 1, wherein the step S1 specifically comprises the following steps:
the lower layer pier (100) of the bridge is constructed synchronously, and the first support (1) is erected.
10. The construction method of the double-deck double-width bridge with the wide top and the narrow bottom as claimed in claim 1, wherein the step S2 specifically comprises the following steps:
and synchronously constructing the upper layer pier (200) and the first lower layer beam (3) in a transverse mode.
CN202010172330.4A 2020-03-12 2020-03-12 Construction method of double-layer double-width bridge with wide top and narrow bottom Active CN111455800B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010172330.4A CN111455800B (en) 2020-03-12 2020-03-12 Construction method of double-layer double-width bridge with wide top and narrow bottom

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010172330.4A CN111455800B (en) 2020-03-12 2020-03-12 Construction method of double-layer double-width bridge with wide top and narrow bottom

Publications (2)

Publication Number Publication Date
CN111455800A CN111455800A (en) 2020-07-28
CN111455800B true CN111455800B (en) 2021-04-27

Family

ID=71682830

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010172330.4A Active CN111455800B (en) 2020-03-12 2020-03-12 Construction method of double-layer double-width bridge with wide top and narrow bottom

Country Status (1)

Country Link
CN (1) CN111455800B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112832136B (en) * 2021-01-06 2022-08-30 中铁大桥局集团第四工程有限公司 Cast-in-place support on beam and fractional local preloading method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000282414A (en) * 1999-03-31 2000-10-10 Yoshinori Tamura Girder moving device and beam erection method using the girder moving device
CN101713170A (en) * 2009-10-27 2010-05-26 中国第一冶金建设有限责任公司 Integral slide device and method of floor steel pipe column bracket of bridge end bay closure section construction
CN102140779A (en) * 2011-01-14 2011-08-03 中铁大桥局集团第六工程有限公司 Movable cast-in-situ support and movable construction method of box girder cast-in-situ support
CN206143644U (en) * 2016-10-28 2017-05-03 中铁二十四局集团安徽工程有限公司 Cast -in -place continuous case beam side die board displacement device
CN107044090A (en) * 2017-05-09 2017-08-15 中铁大桥局集团有限公司 A kind of construction method of dual deck bridge
CN107245953A (en) * 2017-07-14 2017-10-13 北京市市政建设工程有限责任公司 The bent device and crossed construction method of a kind of multilayer bridge structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000282414A (en) * 1999-03-31 2000-10-10 Yoshinori Tamura Girder moving device and beam erection method using the girder moving device
CN101713170A (en) * 2009-10-27 2010-05-26 中国第一冶金建设有限责任公司 Integral slide device and method of floor steel pipe column bracket of bridge end bay closure section construction
CN102140779A (en) * 2011-01-14 2011-08-03 中铁大桥局集团第六工程有限公司 Movable cast-in-situ support and movable construction method of box girder cast-in-situ support
CN206143644U (en) * 2016-10-28 2017-05-03 中铁二十四局集团安徽工程有限公司 Cast -in -place continuous case beam side die board displacement device
CN107044090A (en) * 2017-05-09 2017-08-15 中铁大桥局集团有限公司 A kind of construction method of dual deck bridge
CN107245953A (en) * 2017-07-14 2017-10-13 北京市市政建设工程有限责任公司 The bent device and crossed construction method of a kind of multilayer bridge structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
芜湖长江公铁大桥南引桥40.7m简支梁施工关键技术;王强等;《桥梁建设》;20190228;第49卷(第1期);全文 *

Also Published As

Publication number Publication date
CN111455800A (en) 2020-07-28

Similar Documents

Publication Publication Date Title
CN110004832B (en) Large-span cantilever truss type bent cap bracket system and construction method
CN105568854B (en) Shaped form fish-bellied type cast-in-situ steel reinforced concrete box girder construction method waterborne
CN106592406A (en) Through tied arch bridge and construction method thereof
CN104594204B (en) Urban light rail viaduct mountain type U beam Construction Supporting System and construction method
CN110593114A (en) Box girder construction method based on large-span box girder multi-hoop truss support bailey bracket
CN108411790A (en) A kind of adjustable installing bracket of prefabricated assembled segmentation bent cap
CN111455800B (en) Construction method of double-layer double-width bridge with wide top and narrow bottom
CN109267493B (en) Construction method for installing steel cover beam crossing river channel
CN204475184U (en) Urban light rail viaduct mountain type U beam Construction Supporting System
CN209584813U (en) Frame bridge system
CN210066504U (en) Large-span cantilever truss type bent cap support system
CN214656383U (en) Line is alternately low headroom and is pieced together wide cast-in-place case roof beam support
CN112342932B (en) Route crossing low-clearance spliced wide cast-in-situ box girder bracket and construction method
JP2003313824A (en) Construction method of overhead crossing, overhead crossing and moving frame
CN211689932U (en) Cast-in-place beam suspends support in midair
CN106760486A (en) Exterior wall mould and its erection method in foundation ditch
CN205741886U (en) A kind of extension die shoe frame for the construction of bridge rectangle pier
CN111945573A (en) Double-limb thin-wall high-pier tie beam support-free construction method
CN206801002U (en) Exterior wall mould in foundation ditch
CN215164713U (en) Supporting and leveling structure of steel pipe concrete arch construction platform
CN110656581A (en) Temporary bridge construction process
CN106192715B (en) The SRC portal-rigid frames bridge structure and its construction method of erection without scaffolding
CN211228120U (en) Bent cap formwork support
CN217781737U (en) Single-column high-pier capping beam construction support
CN107806103A (en) A kind of pattern foundation pit supporting structure steel truss shares system with assembled steel trestle column

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant