CN111438260A - Efficient collaborative circular assembly line - Google Patents

Efficient collaborative circular assembly line Download PDF

Info

Publication number
CN111438260A
CN111438260A CN202010276977.1A CN202010276977A CN111438260A CN 111438260 A CN111438260 A CN 111438260A CN 202010276977 A CN202010276977 A CN 202010276977A CN 111438260 A CN111438260 A CN 111438260A
Authority
CN
China
Prior art keywords
placing
blanking
rope
frame
assembly line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010276977.1A
Other languages
Chinese (zh)
Inventor
叶玉宏
叶林海
叶月胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dongguan Lexing Electronics Co ltd
Original Assignee
Dongguan Lexing Electronics Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dongguan Lexing Electronics Co ltd filed Critical Dongguan Lexing Electronics Co ltd
Priority to CN202010276977.1A priority Critical patent/CN111438260A/en
Publication of CN111438260A publication Critical patent/CN111438260A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21DWORKING OR PROCESSING OF SHEET METAL OR METAL TUBES, RODS OR PROFILES WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21D28/00Shaping by press-cutting; Perforating
    • B21D28/02Punching blanks or articles with or without obtaining scrap; Notching
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21DWORKING OR PROCESSING OF SHEET METAL OR METAL TUBES, RODS OR PROFILES WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21D43/00Feeding, positioning or storing devices combined with, or arranged in, or specially adapted for use in connection with, apparatus for working or processing sheet metal, metal tubes or metal profiles; Associations therewith of cutting devices
    • B21D43/02Advancing work in relation to the stroke of the die or tool
    • B21D43/04Advancing work in relation to the stroke of the die or tool by means in mechanical engagement with the work
    • B21D43/12Advancing work in relation to the stroke of the die or tool by means in mechanical engagement with the work by chains or belts
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21DWORKING OR PROCESSING OF SHEET METAL OR METAL TUBES, RODS OR PROFILES WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21D53/00Making other particular articles
    • B21D53/46Making other particular articles haberdashery, e.g. buckles, combs; pronged fasteners, e.g. staples
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B26HAND CUTTING TOOLS; CUTTING; SEVERING
    • B26DCUTTING; DETAILS COMMON TO MACHINES FOR PERFORATING, PUNCHING, CUTTING-OUT, STAMPING-OUT OR SEVERING
    • B26D7/00Details of apparatus for cutting, cutting-out, stamping-out, punching, perforating, or severing by means other than cutting
    • B26D7/06Arrangements for feeding or delivering work of other than sheet, web, or filamentary form
    • B26D7/0625Arrangements for feeding or delivering work of other than sheet, web, or filamentary form by endless conveyors, e.g. belts
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B26HAND CUTTING TOOLS; CUTTING; SEVERING
    • B26FPERFORATING; PUNCHING; CUTTING-OUT; STAMPING-OUT; SEVERING BY MEANS OTHER THAN CUTTING
    • B26F1/00Perforating; Punching; Cutting-out; Stamping-out; Apparatus therefor
    • B26F1/38Cutting-out; Stamping-out
    • B26F1/40Cutting-out; Stamping-out using a press, e.g. of the ram type

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Forests & Forestry (AREA)
  • Automatic Assembly (AREA)

Abstract

The invention relates to the technical field of rope buckle manufacturing, in particular to a high-efficiency collaborative circular assembly line which comprises a working frame, wherein the working frame is provided with a circular conveying belt, a chain is arranged in the circular conveying belt, the working frame is provided with a power mechanism which is connected with the chain and drives the circular conveying belt to circularly rotate and feed materials, the outer side of the working frame is provided with an assembly line platform, the assembly line platform is provided with a plurality of threading jigs, the inner side of the working frame is provided with blanking equipment, and the blanking equipment is internally provided with blanking jigs. The invention realizes the continuous work assembly line work, improves the work efficiency and ensures the processing quality and the production yield.

Description

Efficient collaborative circular assembly line
Technical Field
The invention relates to the technical field of rope buckle manufacturing, in particular to a high-efficiency collaborative circular assembly line.
Background
The rope fastener is widely applied in the clothing industry, is a common clothing fastener, is usually matched with a rope component for use, is suitable for packaging, clothing, outdoor articles, pocket accessories and the like, and also comprises various types such as a Chinese character 'ri' fastener, a Chinese character 'kou' fastener, a Chinese character 'mu' fastener, a hook fastener, a spring press fastener and the like. Traditional spring is pressed and is detained assembly between the rope component is generally to aim the perforation that passes spring pressure through the workman with the rope component singly according to the naked eye and detain and carry out the stringing equipment, it is difficult to once only accomplish the stringing equipment smoothly, need alternate many times repeatedly, it is long to consume time, after that seal the latch closure and carry out artifical blanking work again at the both ends fag end dress of rope component, can only punch single work piece at every turn, latent potential safety hazard is big, and whole production process all adopts artifical unloading of going up, the operation is complicated and trivial details, it produces the processing flow to be difficult to form ripe assembly line, work efficiency is low, can't guarantee processingquality and production yields.
Disclosure of Invention
The invention aims to provide a high-efficiency collaborative circular assembly line aiming at the defects of the prior art, so that the uninterrupted continuous working assembly line works, the working efficiency is improved, and the processing quality and the production yield are ensured.
In order to achieve the purpose, the efficient collaborative circular assembly line comprises a working frame, wherein the working frame is provided with a circular conveying belt, a chain is arranged in the circular conveying belt, the working frame is provided with a power mechanism which is connected with the chain and drives the circular conveying belt to circularly rotate for feeding, an assembly line platform is arranged on the outer side of the working frame, the assembly line platform is provided with a plurality of threading jigs, blanking equipment is arranged on the inner side of the working frame, and blanking jigs are arranged in the blanking equipment.
Preferably, the threading jig comprises a frame body, a spring pressing buckle and a rope member, the frame body is provided with an assembly body used for inserting and assembling the rope member on the spring pressing buckle, and the assembly body comprises an inserting piece used for inserting and placing the spring pressing buckle and a hooking piece used for hooking and hanging the rope member.
Preferably, the inserting piece comprises a first inserting column and a second inserting column arranged opposite to the first inserting column, the hooking piece comprises a first rope crochet hook and a second rope crochet hook, the first rope crochet hook is connected with the first inserting column, and the second rope crochet hook is connected with the second inserting column.
Preferably, both ends of the frame body are respectively provided with a bearing part used for being connected with the assembly body and a fixing part used for being connected with the assembly line platform, a connecting part is arranged between the bearing part and the fixing part, the bearing part, the connecting part and the fixing part are integrally formed, the fixing part is provided with a plurality of mounting holes, and the mounting holes are arranged in a triangular shape.
Preferably, the blanking equipment includes the frame, the top of frame is provided with the punching press head, the bottom of frame is provided with the workstation that is used for placing the blanking tool, the bottom interval of punching press head is provided with a plurality of blanking piece, the workstation be provided with blanking piece assorted blanking groove.
Preferably, the blanking jig comprises a material rack, the material rack comprises a first placing portion and a second placing portion arranged opposite to the first placing portion, a plurality of placing grooves are formed in the first placing portion and the second placing portion respectively, the placing grooves comprise a first bayonet and a second bayonet which are arranged side by side, and isolating strips are arranged between the first bayonet and the second bayonet.
Preferably, the rack is hollow and is integrally formed with the first placing part and the second placing part, and a plurality of reinforcing ribs 814 are arranged between the first placing part and the second placing part.
Preferably, the workstation is protruding type structure, the both sides of frame all are provided with the clamping bolt, the clamping bolt spiro union has fastening nut, be provided with location splint between clamping bolt and the fastening nut, the waist type groove that supplies the clamping bolt to pass is seted up to location splint, the one end of location splint is provided with the sawtooth groove, the fixed locating piece that is provided with of frame, the locating piece be provided with sawtooth groove assorted sawtooth rack.
Preferably, the workbench is provided with a guide post, and the stamping head is provided with a guide groove matched with the guide post.
Preferably, the power mechanism comprises a driving motor and a cam divider, the driving motor is connected with the cam divider through a synchronous belt transmission mechanism, the output end of the cam divider is connected with a chain wheel in a driving mode, the chain wheel is meshed with a chain, the working frame is provided with a plurality of guide wheels, and the guide wheels are in transmission connection with the annular conveying belt.
The invention has the beneficial effects that: the utility model provides a high-efficient cooperation ring-shaped assembly line, includes the work frame, the work frame is provided with endless conveyor, be provided with the chain in the endless conveyor, the work frame is provided with and is used for being connected and drive endless conveyor is the power unit of cyclic rotation pay-off with the chain, the outside of work frame is provided with the assembly line platform, the assembly line platform is provided with a plurality of threading tool, the inboard of work frame is provided with blanking equipment, be provided with blanking tool in the blanking equipment.
During operation, many workman evenly distributed realize every threading tool at the assembly line platform, blanking equipment corresponds a workman's work of distribution respectively, at first the workman accomplishes the wire rope handling equipment work that the spring pressed the knot through the threading tool, and press a plurality of spring that have assembled to detain neatly and place at blanking tool, place blanking tool at endless conveyor belt after that, power unit is through being connected with the chain and then drive endless conveyor belt and do the circulation and rotate the pay-off, the workman takes blanking tool from endless conveyor belt and places blanking equipment again and accomplish the blanking work that the spring pressed the knot. Production cost is effectively practiced thrift to whole working process, fully carries out reasonable work distribution to manpower resources, reduces the area of assembly line, increases the cooperation between the workman, has effectively avoided effectively leading to the stagnation of whole assembly line because of certain workman's processing is detained, reduces the waste of man-hour. The invention realizes the continuous work assembly line work, improves the work efficiency and ensures the processing quality and the production yield.
Drawings
FIG. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a schematic structural view after the blanking apparatus is hidden in the present invention.
Fig. 3 is a schematic structural view of the threading jig of the present invention.
Fig. 4 is a schematic structural view of another angle of the threading jig of the present invention.
Fig. 5 is a schematic structural view of the blanking apparatus of the present invention.
Fig. 6 is a partially enlarged structural diagram of a in fig. 5.
Fig. 7 is a schematic view of another angle structure of fig. 5.
Fig. 8 is a schematic structural view of the blanking jig of the present invention.
The reference numerals include:
1-working frame 2-endless conveyer belt 3-chain
4-power mechanism 41-driving motor 42-cam divider
43-synchronous belt drive 44-sprocket
5-pipeline platform
6-threading jig
61-frame body 611-bearing part 612-fixing part
613 connecting part 614 mounting hole
62-Assembly
621-insert 6211-first penetrating column 6212-second penetrating column
622-hook hanger 6221-first rope crochet-hook 6222-second rope crochet-hook
7-punching equipment 71-frame
72-punch 721-cutting block 722-guide groove
73-workbench 731-blanking groove 732-guide post
74-clamping bolt 75-fastening nut
76-positioning clamp plate 761-waist-shaped groove 762-sawtooth groove
77-positioning block 771-sawtooth rack
8-blanking jig
81-material rack 811-first placing part 812-second placing part
813-placing groove 8131-first bayonet 8132-second bayonet
8133-parting bead
82-reinforcing rib
9-spring press buckle 10-rope component 11-guide wheel.
Detailed Description
The present invention is described in detail below with reference to the attached drawings.
As shown in fig. 1 to 8, the efficient collaborative circular production line comprises a work frame 1, wherein the work frame 1 is provided with a circular conveyor belt 2, a chain 3 is arranged in the circular conveyor belt 2, the work frame 1 is provided with a power mechanism 4 which is connected with the chain 3 and drives the circular conveyor belt 2 to circularly rotate for feeding, a production line platform 5 is arranged on the outer side of the work frame 1, the production line platform 5 is provided with a plurality of threading jigs 6, blanking equipment 7 is arranged on the inner side of the work frame 1, and blanking jigs 8 are arranged in the blanking equipment 7.
During operation, many workman evenly distributed are at assembly line platform 5, realize every threading tool 6, blanking equipment 7 corresponds a workman's work of distribution respectively, at first the workman passes through threading tool 6 and accomplishes the reeving equipment work that the spring pressed to detain 9, and press a plurality of assembled spring and detain 9 neatly and place blanking tool 8, place blanking tool 8 at endless conveyor belt 2 after that, power unit 4 is through being connected with chain 3 and then drive endless conveyor belt 2 and do the circulation and rotate the pay-off, the workman takes blanking tool 8 from endless conveyor belt 2 and places blanking equipment 7 again and accomplishes the blanking work that the spring pressed to detain 9. Production cost is effectively practiced thrift to whole working process, fully carries out reasonable work distribution to manpower resources, reduces the area of assembly line, increases the cooperation between the workman, has effectively avoided effectively leading to the stagnation of whole assembly line because of certain workman's processing is detained, reduces the waste of man-hour. The invention realizes the continuous work assembly line work, improves the work efficiency and ensures the processing quality and the production yield.
As shown in fig. 1, 2 and 3, the threading jig 6 of the present embodiment includes a frame body 61, a snap 9 and a rope member 10, the frame body 61 is provided with an assembly body 62 for inserting and assembling the rope member 10 in the snap 9, and the assembly body 62 includes an insertion part 621 for inserting and placing the snap 9 and a hooking part 622 for hooking and hanging the rope member 10. Specifically, during operation, firstly, a worker presses the spring pressing buckle 9 to open a built-in through hole, the spring pressing buckle 9 penetrates through the through hole from bottom to top and is inserted into the insertion piece 621, then the spring pressing buckle 9 is loosened to close the built-in through hole, the spring pressing buckle 9 is placed in the insertion piece 621 in a standing mode, then rope heads at two ends of the rope member 10 are hung on the hook-and-hook piece 622, finally, the worker presses the spring pressing buckle 9 to slide along the insertion piece 621 from top to bottom and penetrate into the rope member 10, then the rope heads at two ends of the rope member 10 are separated and picked off from the hook-and-hook piece 622, and then rope threading assembly work is completed. The rope member 10 includes a round rope, a flat rope or a rope belt, and is not limited to the rope member 10 used for clothes, but may also be used for leather bags, backpack, grocery bags, shoes, toys, etc. the rope member 10 of the present invention may be assembled and processed in various types, and has good compatibility and strong practicability.
As shown in fig. 3, the insertion piece 621 of the present embodiment includes a first penetrating column 6211 and a second penetrating column 6212 opposite to the first penetrating column 6211, the hooking member 622 includes a first rope hooking needle 6221 and a second rope hooking needle 6222, the first rope hooking needle 6221 is connected to the first penetrating column 6211, and the second rope hooking needle 6222 is connected to the second penetrating column 6212. Specifically, a worker presses the spring pressing buckle 9 to open two built-in through holes, the spring pressing buckle 9 respectively penetrates through the first penetrating column 6211 and the second penetrating column 6212 from bottom to top through the two through holes, then the spring pressing buckle 9 is loosened to close the two built-in through holes, the spring pressing buckle 9 is placed between the first penetrating column 6211 and the second penetrating column 6212 in a standing mode, then rope heads at two ends of the rope member 10 are respectively hooked on the first rope hooking needle 6221 and the second rope hooking needle 6222, finally the worker presses the spring pressing buckle 9 from top to bottom to respectively slide along the first penetrating column 6211 and the second penetrating column 6212, then the rope members are inserted into the rope member 10 after passing through the first rope hooking needle 6221 and the second rope hooking needle 6222, and then the rope heads at two ends of the rope member 10 are separated and detached from the hooking member 622, so that rope penetrating and assembling work is completed.
As shown in fig. 3 and 4, two ends of the frame body 61 of the present embodiment are respectively provided with a bearing part 611 for connecting with the assembly 62 and a fixing part 612 for connecting with the assembly line platform 5, a connecting part 613 is disposed between the bearing part 611 and the fixing part 612, the bearing part 611, the connecting part 613 and the fixing part 612 are integrally formed, the fixing part 612 is provided with a plurality of mounting holes 614, and the mounting holes 614 are arranged in a triangular shape. Specifically, the integrally formed bearing part 611, the connecting part 613 and the fixing part 612 have good structural stability, and are convenient to process and manufacture, the frame body 61 is fixedly mounted on the workbench 73 through the fixing part 612, and the bearing part 611 is used for bearing and supporting the assembly 62, so that the working stability of the assembly 62 is improved. Preferably, the three mounting holes 614 are arranged in a triangular manner, so that the structure is firmer and more reliable, and the mounting and the connection are stable.
As shown in fig. 1, 5 and 7, the blanking apparatus 7 of this embodiment includes a frame 71, a stamping head 72 is disposed at the top of the frame 71, a working table 73 for placing a blanking jig 8 is disposed at the bottom of the frame 71, a plurality of blanking blocks 721 are disposed at intervals at the bottom of the stamping head 72, and the working table 73 is provided with a blanking slot 731 matched with the blanking blocks 721. Specifically, during operation, the work or material rest 81 is positioned and inserted on the workbench 73, so that the blanking groove 731 is located in the work or material rest 81, a worker presses down a switch, the stamping head 72 correspondingly punches a plurality of sealing ring buckles placed between the first placing portion 811 and the second placing portion 812 through the plurality of punching blocks 721, when the punching blocks 721 and the blanking groove 731 are pressed together, the blanking operation is completed, the blanking operation of a plurality of workpieces is synchronously completed at one time, time consumption is short, and the blanking efficiency is high.
As shown in fig. 5 and 8, the blanking jig 8 of the present embodiment includes a rack 81, where the rack 81 includes a first placing portion 811 and a second placing portion 812 disposed opposite to the first placing portion 811, each of the first placing portion 811 and the second placing portion 812 is provided with a plurality of placing grooves 813, each of the placing grooves 813 includes a first bayonet 8131 and a second bayonet 8132 disposed side by side, and a spacer 8133 is disposed between the first bayonet 8131 and the second bayonet 8132. Specifically, a worker installs sealing buckles on two end rope heads of a rope member 10 which has finished a stringing and assembling work, then the rope member 10 is placed in a placing groove 813 which is arranged in parallel of a first placing part 811 and a second placing part 812, the two end rope heads of the rope member 10 are respectively placed at a first bayonet 8131 and a second bayonet 8132 which are arranged side by side, then the two end rope heads are separated by a separation strip 8133, the two end rope heads are prevented from being twisted together, the positioning effect is good, the sealing buckles are positioned between the first placing part 811 and the second placing part 812, so as to facilitate the next blanking operation, a plurality of placing grooves 813 are uniformly and symmetrically arranged at the first placing part 811 and the second placing part 812, the worker only needs to correspondingly place a plurality of rope members 10 which are installed with the sealing buckles in the plurality of placing grooves 813, thereby being beneficial to realize the blanking work of finishing the plurality of rope members 10 at one time, the mode of loading and positioning a plurality of workpieces by a blanking jig 8 to effectively replace the mode of taking workpieces, greatly reduces the working danger, and has good positioning function and working safety.
As shown in fig. 8, the rack 81 of the present embodiment is hollow and integrally formed with a first placing portion 811 and a second placing portion 812, and a plurality of reinforcing ribs 814 are disposed between the first placing portion 811 and the second placing portion 812. Specifically, the inside cavity of work or material rest 81 is convenient for plant at workstation 73, and the location is connected reliable and stable, and first portion 811 of placing, second portion 812 and work or material rest 81 integrated into one piece not only stable in structure, small and compact structure, convenient production and processing moreover, low in manufacturing cost. The plurality of reinforcing ribs 814 arranged between the first placing portion 811 and the second placing portion 812 can improve the structural stability of the rack 81, and the compression-resistant and bearing capacity of the rack 81 is enhanced.
As shown in fig. 5 and 6, the workbench 73 of the present embodiment has a convex structure, the two sides of the frame 71 are provided with clamping bolts 74, the clamping bolts 74 are screwed with fastening nuts 75, positioning splints 76 are provided between the clamping bolts 74 and the fastening nuts 75, waist-shaped grooves 761 for the clamping bolts 74 to pass through are provided on the positioning splints 76, one end of the positioning splints 76 is provided with a sawtooth groove 762, the frame 71 is fixedly provided with a positioning block 77, and the positioning block 77 is provided with a sawtooth strip 771 matched with the sawtooth groove 762. Specifically, through adjusting the swing positioning splint 76, one end of the positioning splint 76 compresses the outer side of the workbench 73, the other end of the positioning splint 76 is locked and clamped with the sawtooth strip 771 of the positioning block 77 through the sawtooth groove 762, and then the fastening nut 75 is screwed on the clamping bolt 74, so that the working position of the positioning splint 76 is further fixed, the positioning effect on the workbench 73 is improved, and the workbench 73 works more stably and reliably.
As shown in fig. 5 and 7, the table 73 of the present embodiment is provided with a guide post 732, and the press head 72 is provided with a guide groove 722 that matches the guide post 732. Specifically, when the punching head 72 performs a punching operation, the guide posts 732 and the guide slots 722 are inserted into each other, so that an effect of automatically calibrating the position is achieved, and the punching accuracy is improved.
As shown in fig. 1 and fig. 2, the power mechanism 4 of the present embodiment includes a driving motor 41 and a cam divider 42, the driving motor 41 is connected to the cam divider 42 through a synchronous belt transmission mechanism 43, an output end of the cam divider 42 is connected to a chain wheel 44 in a driving manner, the chain wheel 44 is meshed with the chain 3, the work frame 1 is provided with a plurality of guide wheels 11, and the guide wheels 11 are connected to the endless conveyor belt 2 in a driving manner. Specifically, driving motor 41 passes through synchronous belt drive 43 drive cam splitter 42 and operates, and cam splitter 42 passes through sprocket 44 and the meshing transmission of chain 3, and then drives endless conveyor 2 and do the circulation and rotate the pay-off, evenly sets up in a plurality of guide pulleys 11 of work frame 1 and the laminating of endless conveyor 2 rolls, effectively reduces the frictional resistance that moves, and the guidance quality is good, makes endless conveyor 2 operate more steadily smoothly.
The above description is only a preferred embodiment of the present invention, and for those skilled in the art, the present invention should not be limited by the description of the present invention, which should be interpreted as a limitation.

Claims (10)

1. The utility model provides a high-efficient cooperation ring shape assembly line, includes the work frame, the work frame is provided with endless conveyor, its characterized in that: the circular conveyer belt is internally provided with a chain, the working frame is provided with a power mechanism which is used for being connected with the chain and driving the circular conveyer belt to circularly rotate for feeding, the outer side of the working frame is provided with a production line platform, the production line platform is provided with a plurality of threading jigs, the inner side of the working frame is provided with blanking equipment, and the blanking equipment is internally provided with blanking jigs.
2. An efficient collaborative torus shaped pipeline as claimed in claim 1, wherein: the threading jig comprises a frame body, a spring pressing buckle and a rope component, wherein the frame body is provided with an assembly body used for inserting and assembling the rope component in the spring pressing buckle, and the assembly body comprises an inserting piece used for inserting and placing the spring pressing buckle and a hooking piece used for hooking a suspension rope component.
3. An efficient collaborative torus shaped pipeline as claimed in claim 2, wherein: the inserting piece comprises a first inserting column and a second inserting column arranged opposite to the first inserting column, the hooking piece comprises a first rope crochet hook and a second rope crochet hook, the first rope crochet hook is connected with the first inserting column, and the second rope crochet hook is connected with the second inserting column.
4. An efficient collaborative torus shaped pipeline as claimed in claim 2, wherein: the support body is provided with the bearing part that is used for being connected with the assembly body and the fixed part that is used for being connected with the assembly line platform respectively at the both ends of support body, be provided with connecting portion between bearing part and the fixed part, bearing part, connecting portion, fixed part integrated into one piece, the fixed part is provided with a plurality of mounting hole, the mounting hole is triangle-shaped and arranges.
5. An efficient collaborative torus shaped pipeline as claimed in claim 1, wherein: the blanking equipment comprises a rack, wherein a punching head is arranged at the top of the rack, a workbench used for placing blanking jigs is arranged at the bottom of the rack, a plurality of blanking blocks are arranged at the bottom of the punching head at intervals, and blanking grooves matched with the blanking blocks are formed in the workbench.
6. An efficient collaborative torus shaped pipeline as claimed in claim 5, wherein: the blanking jig comprises a material rack, the material rack comprises a first placing portion and a second placing portion arranged opposite to the first placing portion, a plurality of placing grooves are formed in the first placing portion and the second placing portion respectively, the placing grooves comprise a first bayonet and a second bayonet which are arranged side by side, and isolating strips are arranged between the first bayonet and the second bayonet.
7. An efficient collaborative torus shaped pipeline as claimed in claim 6, wherein: the work or material rest is inside cavity and with first portion of placing, the integrated into one piece of second portion of placing, be provided with a plurality of strengthening rib 814 between first portion of placing and the second portion of placing.
8. An efficient collaborative torus shaped pipeline as claimed in claim 5, wherein: the workstation is protruding type structure, the both sides of frame all are provided with the clamping bolt, clamping bolt spiro union has fastening nut, be provided with the locating splint between clamping bolt and the fastening nut, the waist type groove that supplies the clamping bolt to pass is seted up to the locating splint, the one end of locating splint is provided with the sawtooth groove, the fixed locating piece that is provided with of frame, the locating piece be provided with sawtooth groove assorted sawtooth rack.
9. An efficient collaborative torus shaped pipeline as claimed in claim 5, wherein: the workstation is provided with the guide post, the punching press head is provided with the guide way with the guide post assorted.
10. An efficient collaborative torus shaped pipeline as claimed in claim 1, wherein: the power mechanism comprises a driving motor and a cam divider, the driving motor is connected with the cam divider through a synchronous belt transmission mechanism, the output end of the cam divider is connected with a chain wheel in a driving mode, the chain wheel is meshed with a chain, the working frame is provided with a plurality of guide wheels, and the guide wheels are in transmission connection with the annular conveying belt.
CN202010276977.1A 2020-04-10 2020-04-10 Efficient collaborative circular assembly line Pending CN111438260A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010276977.1A CN111438260A (en) 2020-04-10 2020-04-10 Efficient collaborative circular assembly line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010276977.1A CN111438260A (en) 2020-04-10 2020-04-10 Efficient collaborative circular assembly line

Publications (1)

Publication Number Publication Date
CN111438260A true CN111438260A (en) 2020-07-24

Family

ID=71651438

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010276977.1A Pending CN111438260A (en) 2020-04-10 2020-04-10 Efficient collaborative circular assembly line

Country Status (1)

Country Link
CN (1) CN111438260A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114506072A (en) * 2022-01-20 2022-05-17 合肥学院 Intelligent 3D printing device for industrial manufacturing
CN116214613A (en) * 2023-05-09 2023-06-06 山东理工大学 Flexible graphite composite grounding body circulating conveying and cutting device and use method

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103241512A (en) * 2013-04-17 2013-08-14 上海贝思特电线电缆有限公司 Annular assembly line
CN103569589A (en) * 2013-11-21 2014-02-12 常州市兴维邦精密机械制造有限公司 Stream line for assembling
CN104354027A (en) * 2014-10-28 2015-02-18 安费诺(常州)电子有限公司 Quick pressing plate fixture for machine tool
CN205820447U (en) * 2016-07-19 2016-12-21 马春阳 A kind of device that material strips is processed
CN207238887U (en) * 2017-10-13 2018-04-17 深圳市欣全鑫五金制品有限公司 A kind of automatic blanking die of sheet metal component for realizing precise positioning
CN208543552U (en) * 2018-05-31 2019-02-26 广东煜城科技有限公司 A kind of toy cloth cutting machine
CN209185821U (en) * 2018-12-05 2019-08-02 浙江大东鞋业有限公司 A kind of annular flow-line equipment
CN110496891A (en) * 2019-07-16 2019-11-26 浙江巨星工具有限公司 Three knife automatic cutting shaping mechanisms of double-colored oxidation
CN209807209U (en) * 2019-01-28 2019-12-20 安徽星星服装股份有限公司 Automatic elastic rope threading device
CN209867093U (en) * 2019-04-19 2019-12-31 浙江亿佳拉链科技有限公司 Zipper processing tooth punching equipment
CN110853914A (en) * 2019-11-28 2020-02-28 耒阳市亚湘电子科技有限公司 Network transformer hanging wire mechanism
CN212264274U (en) * 2020-04-10 2021-01-01 东莞市乐星电子有限公司 Efficient collaborative circular assembly line
CN212260697U (en) * 2020-04-10 2021-01-01 东莞市乐星电子有限公司 Threading tool is detained to spring pressure
CN212357788U (en) * 2020-04-10 2021-01-15 东莞市乐星电子有限公司 Wire rope blanking jig and equipment

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103241512A (en) * 2013-04-17 2013-08-14 上海贝思特电线电缆有限公司 Annular assembly line
CN103569589A (en) * 2013-11-21 2014-02-12 常州市兴维邦精密机械制造有限公司 Stream line for assembling
CN104354027A (en) * 2014-10-28 2015-02-18 安费诺(常州)电子有限公司 Quick pressing plate fixture for machine tool
CN205820447U (en) * 2016-07-19 2016-12-21 马春阳 A kind of device that material strips is processed
CN207238887U (en) * 2017-10-13 2018-04-17 深圳市欣全鑫五金制品有限公司 A kind of automatic blanking die of sheet metal component for realizing precise positioning
CN208543552U (en) * 2018-05-31 2019-02-26 广东煜城科技有限公司 A kind of toy cloth cutting machine
CN209185821U (en) * 2018-12-05 2019-08-02 浙江大东鞋业有限公司 A kind of annular flow-line equipment
CN209807209U (en) * 2019-01-28 2019-12-20 安徽星星服装股份有限公司 Automatic elastic rope threading device
CN209867093U (en) * 2019-04-19 2019-12-31 浙江亿佳拉链科技有限公司 Zipper processing tooth punching equipment
CN110496891A (en) * 2019-07-16 2019-11-26 浙江巨星工具有限公司 Three knife automatic cutting shaping mechanisms of double-colored oxidation
CN110853914A (en) * 2019-11-28 2020-02-28 耒阳市亚湘电子科技有限公司 Network transformer hanging wire mechanism
CN212264274U (en) * 2020-04-10 2021-01-01 东莞市乐星电子有限公司 Efficient collaborative circular assembly line
CN212260697U (en) * 2020-04-10 2021-01-01 东莞市乐星电子有限公司 Threading tool is detained to spring pressure
CN212357788U (en) * 2020-04-10 2021-01-15 东莞市乐星电子有限公司 Wire rope blanking jig and equipment

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114506072A (en) * 2022-01-20 2022-05-17 合肥学院 Intelligent 3D printing device for industrial manufacturing
CN116214613A (en) * 2023-05-09 2023-06-06 山东理工大学 Flexible graphite composite grounding body circulating conveying and cutting device and use method

Similar Documents

Publication Publication Date Title
CN111438260A (en) Efficient collaborative circular assembly line
CN107900653B (en) Automatic assembling machine for rubber rings
CN212264274U (en) Efficient collaborative circular assembly line
CN207366453U (en) Die cutting product CCD automatic checkout equipments
CN213735764U (en) Belt buckle sticking film machine
CN109171123A (en) Zipper head penetrating machine and its application method
CN111731757B (en) Streamline equipment
CN209986498U (en) Front cover automatic feeding and riveting device for automatic assembly of drill chuck
CN217487830U (en) Zipper assembly equipment
CN106181358A (en) Mix medicine glass erecting device and the medicine mixer kludge comprising it
CN1306786A (en) Making process of open end zipper
CN215941341U (en) Discharging pin arranging device
CN209507034U (en) A kind of product robot dress reincarnation producing line
CN201079973Y (en) Conveying device for board jointing machine
CN212260697U (en) Threading tool is detained to spring pressure
CN212357788U (en) Wire rope blanking jig and equipment
CN209773943U (en) Automatic assembling device for molten steel sampler
CN211747395U (en) Universal zipper head penetrating equipment
CN209986499U (en) Front sleeve automatic feeding and riveting device for automatic assembly of drill chuck
CN210401803U (en) Automatic chip mounter for optical filter
CN209849732U (en) Female steel band structure of pay-off line
CN214230048U (en) Automatic wear hanging clock machine of detaining
CN203127891U (en) Peeling mechanism
CN107720404B (en) A kind of wire feeder
CN221089284U (en) Automatic punching machine for luggage strap

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination