CN111431276A - Anti-misoperation system for power grid dispatching terminal - Google Patents

Anti-misoperation system for power grid dispatching terminal Download PDF

Info

Publication number
CN111431276A
CN111431276A CN202010228418.3A CN202010228418A CN111431276A CN 111431276 A CN111431276 A CN 111431276A CN 202010228418 A CN202010228418 A CN 202010228418A CN 111431276 A CN111431276 A CN 111431276A
Authority
CN
China
Prior art keywords
misoperation
service
power grid
real
ticket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010228418.3A
Other languages
Chinese (zh)
Inventor
杨阳
曾远方
林泽宏
周娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Power Grid Co Ltd
Dongguan Power Supply Bureau of Guangdong Power Grid Co Ltd
Original Assignee
Guangdong Power Grid Co Ltd
Dongguan Power Supply Bureau of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Power Grid Co Ltd, Dongguan Power Supply Bureau of Guangdong Power Grid Co Ltd filed Critical Guangdong Power Grid Co Ltd
Priority to CN202010228418.3A priority Critical patent/CN111431276A/en
Publication of CN111431276A publication Critical patent/CN111431276A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S40/00Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
    • Y04S40/12Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment
    • Y04S40/124Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment using wired telecommunication networks or data transmission busses

Abstract

The embodiment of the invention discloses an anti-misoperation system of a power grid dispatching end, which comprises an OCS system, a database and an operation ticket management console, wherein the OCS system is in communication connection with the database through a real-time data bus and is connected with the operation ticket management console through the real-time data bus; and the operation ticket management console completes the graphical ticket drawing and ticket drawing verification process of the scheduling command ticket of the dispatcher by utilizing the original picture function of the OCS system. The system of the invention can integrate the scheduling command order compilation and the equipment control order compilation of the dispatcher, simultaneously supports two modes of programmed ordering and programmed operation of the dispatching terminal, and the operation item can directly control the equipment and can also be converted into a network order issuing order.

Description

Anti-misoperation system for power grid dispatching terminal
Technical Field
The embodiment of the invention relates to the technical field of power grid dispatching anti-misoperation, in particular to an anti-misoperation system for a power grid dispatching end.
Background
With the continuous development and growth of the scale of the power grid, the scheduling operation amount is increased day by day, taking 2018 as an example, the scheduling execution overhaul work of a certain main network in a certain market reaches 4492, 6684 operation instruction tickets are executed, and the complexity and requirements of the operation are also increased continuously. In order to improve the efficiency of command issuing and remote control operation in scheduling, the PCS9000 master station system and the network command issuing system are already established in scheduling. The PCS9000 master station system can be used for manually and remotely operating all switches and part of disconnecting links of a power grid, and has the functions of remote signaling and remote measuring of a full network topology and master network equipment; by deploying the dispatching network command workstation in the transformer substation, the single-track operation of dispatching the network command is realized. However, no matter the dispatcher remotely operates or the network sends out the single-track operation, all need different systems of manual operation to accomplish remote control and order, because of the system lacks the mistake prevention function, the condition of mistake remote control, mistake order down appears very easily, artifical management and control wastes time and energy, and the security is not high to operating efficiency is low, does not satisfy the requirement of regulation and control integration level promotion.
The current situation of the dispatching power-on/power-off operation command flow is analyzed, and two core problems influencing efficiency are obtained: firstly, a dispatcher does not directly control equipment and needs to send a command through a network or communicate with an operation field through a dispatching telephone, so that the time consumption is long, risks exist and the safety is poor; and secondly, the safety error-proof checking means is backward, the state checking is manual, the tide checks the multi-system operation, the waiting time is long, and a worthless link exists. And thirdly, the execution of the dispatching order is divided into a six-step method, wherein after the state of the equipment is manually confirmed by a dispatcher in each step of execution, the order issuing operation is confirmed, the time for the field personnel to wait for the order issuing is long, and the state checking workload before and after the operation of the dispatcher is large.
The programmed operation of the equipment, the sequence control operation of the existing plant station end and the sequence control operation mode have two problems: firstly, the main station programming operation is generally a specific programming control sequence for curing specific lines and equipment, and has strong limitation and a narrow application range; secondly, station-side programmed operation mainly aims at a single station and a single device, cannot be applied to wider devices and multi-terminal cooperation operation, does not have a cross-station comprehensive network topology anti-misoperation function, and is not strong in practicability.
Disclosure of Invention
Therefore, the embodiment of the invention provides an anti-misoperation system for a power grid dispatching end, which aims to solve the problems in the prior art.
In order to achieve the above object, an embodiment of the present invention provides the following:
in one aspect of the embodiment of the invention, an anti-misoperation system of a power grid dispatching end is provided, and comprises an OCS system, a database and an operation ticket management console, wherein the OCS system is in communication connection with the database through a real-time data bus, and is connected with the operation ticket management console through the real-time data bus; and the operation ticket management console completes the graphical ticket drawing and ticket drawing verification process of the scheduling command ticket of the dispatcher by utilizing the original picture function of the OCS system.
As a preferred embodiment of the present invention, the OCS system automatically lists the device operation task list through the database.
As a preferred aspect of the present invention, the database includes error-prevention rule data, grid real-time data, and grid model data.
As a preferred scheme of the present invention, the OCS system includes a graphics system, a control service, and a security check service, the graphics system is connected to the control service, the control service is connected to the security check service, the security check service is connected to the real-time data bus, the graphics system realizes graphics ticketing through an instruction of the control service, and the security check service completes an anti-error check function through an instruction of the control service.
As a preferred scheme of the present invention, the security check service includes a five-prevention check service, a load flow calculation service, a state check service, and a rule check service.
As a preferable scheme of the present invention, the five-prevention check service includes an anti-error check of operations of the switch, the disconnecting link and the grounding disconnecting link, and locks operations that do not satisfy the five-prevention rule.
As a preferable aspect of the present invention, the power flow calculation service includes: and performing load flow calculation in real time according to the current operation in the simulation rehearsal, billing and operation processes, performing topology coloring on the electric island according to the load flow calculation result, providing a visual presentation means, performing voltage out-of-limit and line or main transformer overload checking according to the load flow calculation result, prompting a user to perform out-of-limit branch and out-of-limit ratio if the checking is unsuccessful, and performing locking operation.
As a preferred aspect of the present invention, the status checking service includes: and checking the current equipment state and the operation order target state in the operation process, and checking whether the current equipment state is consistent with the operation order target state.
As a preferred aspect of the present invention, the rule checking service includes: before real-time remote control operation, an operator must perform operation rehearsal under the simulation link of the safety check system according to an operation ticket, and the real-time remote control operation can be performed on the premise of success of the rehearsal.
As a preferred scheme of the present invention, an anti-error rule maintenance interface and an operation ticket system customized maintenance interface are further connected to the real-time data bus, and both the anti-error rule maintenance interface and the operation ticket system customized maintenance interface are used for providing to the operation interface.
The embodiment of the invention has the following advantages:
the system of the invention can integrate the scheduling command order compilation and the equipment control order compilation of the dispatcher, simultaneously supports two modes of programmed ordering and programmed operation of the dispatching terminal, and the operation item can directly control the equipment and can also be converted into a network order issuing order.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below. It should be apparent that the drawings in the following description are merely exemplary, and that other embodiments can be derived from the drawings provided by those of ordinary skill in the art without inventive effort.
Fig. 1 is a block diagram of an anti-misoperation system according to an embodiment of the present invention.
Detailed Description
The present invention is described in terms of particular embodiments, other advantages and features of the invention will become apparent to those skilled in the art from the following disclosure, and it is to be understood that the described embodiments are merely exemplary of the invention and that it is not intended to limit the invention to the particular embodiments disclosed. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
As shown in fig. 1, the invention provides an anti-misoperation system for a power grid dispatching end, which comprises an OCS system, a database and an operation ticket management console, wherein the OCS system is in communication connection with the database through a real-time data bus, and is connected with the operation ticket management console through the real-time data bus; the operation ticket management console completes the graphic ticket drawing and ticket drawing verification process of the scheduling command ticket of the dispatcher by utilizing the original picture function of the OCS system, and the OCS system automatically lists the equipment operation task list through the database.
The database comprises error prevention rule data, power grid real-time data and power grid model data.
The OCS system comprises a graphic system, a control service and a safety check service, wherein the graphic system is connected with the control service, the control service is connected with the safety check service, the safety check service is connected on the real-time data bus, the graphic system realizes graphic ticketing through an instruction of the control service, and the safety check service completes an anti-error check function through the instruction of the control service.
The safety check service comprises a five-prevention check service, a load flow calculation service, a state check service and a rule check service.
The five-prevention check service comprises the error-proof check of the operation of the switch, the disconnecting link and the grounding disconnecting link, and the operation which does not meet the five-prevention rule is locked.
And (3) switch operation error checking: loop closing prompt, loop opening prompt, power loss load prompt, charging load prompt, grounding switch closing prompt, switch operation prompt of each side of the transformer and neutral point prompt of the transformer; and (3) error checking prevention of disconnecting link operation: locking a grounding switch-on and switch-off switch, a charged switch-on and switch-off switch, switching-on and switch-off prompt when a bus is reversed, switching-on and bypass switch prompt when a bypass is replaced, and grounding of operation prompts of a bus side switch and a load side switch; and (3) error checking prevention of disconnecting link operation: and prompting to switch on the grounding switch with electricity and prompting to switch on the grounding switch with the knife switch.
The load flow calculation service comprises the following steps: and performing load flow calculation in real time according to the current operation in the simulation rehearsal, billing and operation processes, performing topology coloring on the electric island according to the load flow calculation result, providing a visual presentation means, performing voltage out-of-limit and line or main transformer overload checking according to the load flow calculation result, prompting a user to perform out-of-limit branch and out-of-limit ratio if the checking is unsuccessful, and performing locking operation.
The state checking service includes: and checking the current equipment state and the operation order target state in the operation process, and checking whether the current equipment state is consistent with the operation order target state.
The rule checking service includes: before real-time remote control operation, an operator must perform operation rehearsal under the simulation link of the safety check system according to an operation ticket, and the real-time remote control operation can be performed on the premise of success of the rehearsal.
And the real-time data bus is also connected with an anti-error rule maintenance interface and an operation ticket system customized maintenance interface, and the anti-error rule maintenance interface and the operation ticket system customized maintenance interface are both used for providing the operation interface.
Intelligent operation: on the basis that all the conditions are met, after the intelligent operation button is scheduled and clicked, the whole process is dynamically displayed, the process is verified, abnormal interruption is realized, and the operation is automatically completed. The programmed intelligent anti-misoperation of the dispatching terminal is realized through the system functions.
The self-adaptive programming operation of the dispatching terminal: the method is divided into three modes:
the first mode is as follows: and the scheduling end performs programmed operation, and a scheduling end programmed operation system main body is deployed in the scheduling automation system and serves as a sub-module which is deployed in the safety I area and comprises modules of scheduling operation tickets, state checking, error-proof checking, instruction transmission and the like. When the order unit is selected as "Dongguan regulation", the equipment is in regulation operation. The control instructions which are dispatched by the four modules are cooperatively and orderly output to the equipment remote control module, so that the state change of the power grid equipment is safely finished;
and a second mode: the dispatching end is programmed to order, equipment without remote operation conditions automatically selects corresponding order units during ticket issuing, for example: and after the field operation is finished, repeating the operation to the dispatching, and after the system is checked, automatically judging whether the next instruction can be issued, finishing the change of the state of the power grid equipment in such a way, and automatically carrying out a mode in the whole process of the change of the state of the equipment, namely scheduling end programmed ordering.
And a third mode: based on the advantages and disadvantages of the two modes, the mode I and the mode II are organically fused, namely the self-adaptive programming operation of the dispatching terminal is realized.
The system of the invention can integrate the scheduling command order compilation and the equipment control order compilation of the dispatcher, simultaneously supports two modes of programmed ordering and programmed operation of the dispatching terminal, and the operation item can directly control the equipment and can also be converted into a network order issuing order.
Although the invention has been described in detail above with reference to a general description and specific examples, it will be apparent to one skilled in the art that modifications or improvements may be made thereto based on the invention. Accordingly, such modifications and improvements are intended to be within the scope of the invention as claimed.

Claims (10)

1. The anti-misoperation system of the power grid dispatching end is characterized by comprising an OCS system, a database and an operation ticket management console, wherein the OCS system is in communication connection with the database through a real-time data bus and is connected with the operation ticket management console through the real-time data bus; and the operation ticket management console completes the graphical ticket drawing and ticket drawing verification process of the scheduling command ticket of the dispatcher by utilizing the original picture function of the OCS system.
2. The power grid dispatching end anti-misoperation system according to claim 1, wherein the OCS system automatically lists an equipment operation task list through the database.
3. The system of claim 1, wherein the database comprises anti-misoperation rule data, grid real-time data and grid model data.
4. The power grid dispatching end anti-misoperation system according to claim 1, wherein the OCS system comprises a graphic system, a control service and a safety check service, the graphic system is connected with the control service, the control service is connected with the safety check service, the safety check service is connected with the real-time data bus, the graphic system realizes graphic ticketing through an instruction of the control service, and the safety check service completes an anti-misoperation function through the instruction of the control service.
5. The power grid dispatching end anti-misoperation system according to claim 4, wherein the safety check service comprises a five-prevention check service, a load flow calculation service, a state check service and a rule check service.
6. The power grid dispatching end anti-misoperation system according to claim 5, wherein the five-prevention check service comprises anti-misoperation check of the operations of the switch, the disconnecting link and the grounding disconnecting link, and the operations which do not meet the five-prevention rule are locked.
7. The power grid dispatching end anti-misoperation system according to claim 5, wherein the power flow calculation service comprises: and performing load flow calculation in real time according to the current operation in the simulation rehearsal, billing and operation processes, performing topology coloring on the electric island according to the load flow calculation result, providing a visual presentation means, performing voltage out-of-limit and line or main transformer overload checking according to the load flow calculation result, prompting a user to perform out-of-limit branch and out-of-limit ratio if the checking is unsuccessful, and performing locking operation.
8. The power grid dispatching end anti-misoperation system according to claim 5, wherein the state checking service comprises: and checking the current equipment state and the operation order target state in the operation process, and checking whether the current equipment state is consistent with the operation order target state.
9. The power grid dispatching end anti-misoperation system according to claim 5, wherein the rule checking service comprises: before real-time remote control operation, an operator must perform operation rehearsal under the simulation link of the safety check system according to an operation ticket, and the real-time remote control operation can be performed on the premise of success of the rehearsal.
10. The power grid dispatching end anti-misoperation system according to claim 5, wherein an anti-misoperation rule maintenance interface and an operation ticket system customized maintenance interface are further connected to the real-time data bus, and both the anti-misoperation rule maintenance interface and the operation ticket system customized maintenance interface are used for being provided for the operation interface.
CN202010228418.3A 2020-03-27 2020-03-27 Anti-misoperation system for power grid dispatching terminal Pending CN111431276A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010228418.3A CN111431276A (en) 2020-03-27 2020-03-27 Anti-misoperation system for power grid dispatching terminal

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010228418.3A CN111431276A (en) 2020-03-27 2020-03-27 Anti-misoperation system for power grid dispatching terminal

Publications (1)

Publication Number Publication Date
CN111431276A true CN111431276A (en) 2020-07-17

Family

ID=71549063

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010228418.3A Pending CN111431276A (en) 2020-03-27 2020-03-27 Anti-misoperation system for power grid dispatching terminal

Country Status (1)

Country Link
CN (1) CN111431276A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113675945A (en) * 2021-07-05 2021-11-19 中国长江电力股份有限公司 Misoperation-preventive locking method for operation execution and maintenance process of hydropower station centralized control center
CN115986936A (en) * 2022-12-30 2023-04-18 华能青铜峡新能源发电有限公司 Intelligent power dispatching control system and method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104467183A (en) * 2014-12-04 2015-03-25 国家电网公司 Dispatch anti-misoperation system for regional power grid in adjustment and control integrated mode
CN107834699A (en) * 2017-11-01 2018-03-23 贵州电网有限责任公司 Dispatching of power netwoks based on the regulation and control integration of ground county integrates anti-error system
CN109634243A (en) * 2018-12-27 2019-04-16 广东电网有限责任公司 A kind of scheduler program operating system based on intelligent robot

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104467183A (en) * 2014-12-04 2015-03-25 国家电网公司 Dispatch anti-misoperation system for regional power grid in adjustment and control integrated mode
CN107834699A (en) * 2017-11-01 2018-03-23 贵州电网有限责任公司 Dispatching of power netwoks based on the regulation and control integration of ground county integrates anti-error system
CN109634243A (en) * 2018-12-27 2019-04-16 广东电网有限责任公司 A kind of scheduler program operating system based on intelligent robot

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113675945A (en) * 2021-07-05 2021-11-19 中国长江电力股份有限公司 Misoperation-preventive locking method for operation execution and maintenance process of hydropower station centralized control center
CN113675945B (en) * 2021-07-05 2023-07-14 中国长江电力股份有限公司 Misoperation-preventive locking method for operation execution and overhaul flow of centralized control center of hydropower station
CN115986936A (en) * 2022-12-30 2023-04-18 华能青铜峡新能源发电有限公司 Intelligent power dispatching control system and method thereof
CN115986936B (en) * 2022-12-30 2023-09-12 华能青铜峡新能源发电有限公司 Intelligent power dispatching control system and method thereof

Similar Documents

Publication Publication Date Title
CN109617241B (en) Intelligent sequential control system and method based on panoramic data in transformer substation
CN109740837B (en) Power grid province and land network command and safety error prevention method based on regulation and control integration
CN110363447B (en) Urban rail transit line network level power dispatching system
CN103488159B (en) A kind of distribution box type smart home terminal and integrated protection controller
WO2017166735A1 (en) Power-grid self-healing system and self-healing logic thereof in 110kv chain power-supply mode
CN109634243A (en) A kind of scheduler program operating system based on intelligent robot
CN108233536A (en) A kind of intelligent program remote handling system
CN102664459B (en) Medium-voltage electrically-propelled ship power management system and management method
CN111431276A (en) Anti-misoperation system for power grid dispatching terminal
CN106685085A (en) Remote-programmed operation system in power grid dispatching
CN102324788A (en) Power dispatching integrated anti-misoperation simulation comprehensive management platform
CN102447305A (en) Topological anti-misoperation system for power grid
CN102064611A (en) Transformer substation sequentialization control system with visualization and interactivity
CN105281385A (en) Electric automobile AC-DC charging system and electric automobile AC-DC charging method
CN101661283B (en) System for completing sequential control by intelligent one-key operation
CN104331777A (en) Error-preventing management system for county level power grid dispatching operation
CN107896005A (en) A kind of comprehensive automation system of transformer substation
CN101609332A (en) Online three-layer synchronous anti-error locking system
CN107181321B (en) Method for realizing rapid load pulling based on power grid topological structure
CN115693951A (en) Second-level intelligent operation sequence control method based on power grid OCS (online charging system)
CN107359702A (en) Intelligent linkage Interlocking Methods based on IES700 systems
CN108879663B (en) One-key sequence control method and system for electric power system with exception handling
CN113361970B (en) Virtual dispatcher system and dispatching method based on power intelligent dispatching engine
CN103440396A (en) Intelligent analysis ticket making method and system of dispatch operation ticket
CN103117598A (en) Constant value remote setting maintenance-free system for transformer substation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200717

RJ01 Rejection of invention patent application after publication