CN111424817A - Quick installation limiting connection node structure of column top steel structure - Google Patents

Quick installation limiting connection node structure of column top steel structure Download PDF

Info

Publication number
CN111424817A
CN111424817A CN202010246355.4A CN202010246355A CN111424817A CN 111424817 A CN111424817 A CN 111424817A CN 202010246355 A CN202010246355 A CN 202010246355A CN 111424817 A CN111424817 A CN 111424817A
Authority
CN
China
Prior art keywords
force transmission
plate
column
steel structure
column top
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010246355.4A
Other languages
Chinese (zh)
Inventor
王军
刘明路
邱顶宏
唐春林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Shanghai Steel Structure Technology Co Ltd
Original Assignee
MCC Shanghai Steel Structure Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Shanghai Steel Structure Technology Co Ltd filed Critical MCC Shanghai Steel Structure Technology Co Ltd
Priority to CN202010246355.4A priority Critical patent/CN111424817A/en
Publication of CN111424817A publication Critical patent/CN111424817A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • E04B2001/2415Brackets, gussets, joining plates
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B2001/249Structures with a sloping roof

Abstract

The invention relates to the field of steel structure construction, in particular to a structure for quickly installing a limiting connection node on a column top steel structure; comprises a concrete column (3) and a column top steel structure (4); the method is characterized in that: the device also comprises a limit conversion piece (1) and a force transmission backing plate (2); the limiting conversion piece (1) is arranged at the top of the concrete column (3), the force transmission base plate (2) is arranged on the limiting conversion piece (1) and is fastened by sleeving a nut on the stud, and a column top steel structure (4) is arranged on a cross-shaped support steel plate of the force transmission base plate (2). The force transmission path of the connecting node is clear and can be in place once during installation, construction is convenient and rapid, and deviation can be adjusted during installation.

Description

Quick installation limiting connection node structure of column top steel structure
Technical Field
The invention relates to the field of steel structure construction, in particular to a structure for quickly installing a limiting connection node of a column top steel structure.
Background
In recent years, with the rapid development of steel structure building structural systems in China, on the premise of meeting basic building functions, building roof structural systems have more choices, and space roof steel structures and support systems thereof are more and more widely applied. In the work progress, the condition that adopts the pre-buried steel construction of traditional capital to bury the piece is comparatively common, nevertheless because the difference of concrete construction precision and the standard requirement of steel construction precision leads to pre-buried precision often can not satisfy the construction requirement, has increased the installation degree of difficulty of capital steel construction, has reduced the efficiency of construction, because of pre-buried piece construction and capital steel construction contact surface machining precision reason simultaneously, the capital buries the unable inseparable laminating of piece and steel construction, has the unbalanced problem of structure atress.
Disclosure of Invention
The invention aims to overcome the defects and provides a limit connection node structure for quickly mounting a column top steel structure.
In order to achieve the above object, the present invention is realized by:
a column top steel structure rapid installation limiting connection node structure comprises a steel column or a concrete column with a pre-embedded steel plate and a column top steel structure; the device also comprises a limit conversion piece and a force transmission backing plate; the force transmission base plate comprises a flat plate and a rectangular convex block arranged in the center of the bottom of the flat plate, through holes are formed in the periphery of the flat plate, the position of the rectangular convex block is matched with the position of the rectangular same groove of the limiting conversion piece, and the position of the through hole is matched with the position of the stud on the limiting conversion piece; a cross supporting steel plate is arranged on the top of the force transmission base plate; the limiting conversion piece is arranged at the top of the concrete column, the force transmission base plate is arranged on the limiting conversion piece and is fastened with the stud through sleeving a nut on the stud, and a column top steel structure is arranged on the cross-shaped support steel plate of the force transmission base plate.
The construction method for quickly installing the limiting connection node structure on the column top steel structure comprises the following steps:
1) the force transmission base plate and the column top steel structure factory are manufactured into a whole; the limiting conversion parts are manufactured in groups and are matched with nuts;
2) the nut is connected with the limiting conversion piece and the column top steel structure, so that the bottom surface of the limiting conversion piece is slightly higher than the bottom surface of the force transmission cushion block;
3) the column top steel structure is positioned on the embedded base plate or the steel column end plate;
4) loosening the nut to enable the limiting conversion piece to be attached to the embedded steel plate or the steel column end plate and carry out corner-attaching girth welding;
5) and screwing the nut to finish the installation.
The node structure is installed by adopting the design and the method, and has the following advantages:
1. the force transmission path of the node is clear.
2. One-time positioning, quick construction and adjustable installation deviation.
Drawings
Fig. 1 is a schematic view of the connection between the force transmission backing plate and the steel structure of the column top in the connection node structure.
Fig. 2 is an assembly diagram of the present connection node structure.
Fig. 3 is a schematic view of the connection between the position-limiting conversion member and the concrete column in the connection node structure.
Detailed Description
The invention is further illustrated by the following specific examples.
As shown in fig. 1 to 3, a column top steel structure rapid mounting limiting connection node structure comprises a steel column or a concrete column with a pre-embedded steel plate 3 and a column top steel structure 4; the device also comprises a limit conversion part 1 and a force transmission backing plate 2; the force transmission base plate 2 comprises a flat plate and a rectangular convex block arranged in the center of the bottom of the flat plate, through holes are formed in the periphery of the flat plate, the position of the rectangular convex block is matched with the position of the rectangular same groove of the limit conversion piece 1, and the position of the through hole is matched with the position of the stud on the limit conversion piece 1; a cross supporting steel plate is arranged on the top of the force transmission base plate 2; the limiting conversion part 1 is arranged at the top of the concrete column 3, the force transmission backing plate 2 is arranged on the limiting conversion part 1 and is fastened with the stud through sleeving a nut on the stud, and a column top steel structure 4 is arranged on a cross-shaped support steel plate of the force transmission backing plate 2.
The construction method for quickly installing the limiting connection node structure on the column top steel structure comprises the following steps:
1) the force transmission base plate and the column top steel structure factory are manufactured into a whole; the limiting conversion parts are manufactured in groups and are matched with nuts;
2) the nut is connected with the limiting conversion piece and the column top steel structure, so that the bottom surface of the limiting conversion piece is slightly higher than the bottom surface of the force transmission cushion block;
3) the column top steel structure is positioned on the embedded base plate or the steel column end plate;
4) loosening the nut to enable the limiting conversion piece to be attached to the embedded steel plate or the steel column end plate and carry out corner-attaching girth welding;
5) and screwing the nut to finish the installation.
The node structure is installed by adopting the design and the method, and has the following advantages:
1. the force transmission path of the node is clear.
2. One-time positioning, quick construction and adjustable installation deviation.

Claims (2)

1. A column top steel structure rapid installation limiting connection node structure comprises a steel column or a concrete column (3) embedded with a steel plate and a column top steel structure (4); the method is characterized in that: the device also comprises a limit conversion piece (1) and a force transmission backing plate (2); the force transmission backing plate (2) comprises a flat plate, a rectangular convex block arranged in the center of the bottom of the flat plate, and through holes arranged on the periphery of the flat plate, wherein the position of the rectangular convex block is matched with the position of the rectangular same groove of the limit conversion piece (1), and the position of the through hole is matched with the position of the stud on the limit conversion piece (1); a cross supporting steel plate is arranged at the top of the force transmission base plate (2); the limiting conversion piece (1) is arranged at the top of the concrete column (3), the force transmission base plate (2) is arranged on the limiting conversion piece (1) and is fastened by sleeving a nut on the stud, and a column top steel structure (4) is arranged on a cross-shaped support steel plate of the force transmission base plate (2).
2. The construction method for quickly installing the limit connection node structure of the column top steel structure as claimed in claim 1, wherein: the method comprises the following steps:
1) the force transmission base plate and the column top steel structure factory are manufactured into a whole; the limiting conversion parts are manufactured in groups and are matched with nuts;
2) the nut is connected with the limiting conversion piece and the column top steel structure, so that the bottom surface of the limiting conversion piece is slightly higher than the bottom surface of the force transmission cushion block;
3) the column top steel structure is positioned on the embedded base plate or the steel column end plate;
4) loosening the nut to enable the limiting conversion piece to be attached to the embedded steel plate or the steel column end plate and carry out corner-attaching girth welding;
5) and screwing the nut to finish the installation.
CN202010246355.4A 2020-03-31 2020-03-31 Quick installation limiting connection node structure of column top steel structure Pending CN111424817A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010246355.4A CN111424817A (en) 2020-03-31 2020-03-31 Quick installation limiting connection node structure of column top steel structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010246355.4A CN111424817A (en) 2020-03-31 2020-03-31 Quick installation limiting connection node structure of column top steel structure

Publications (1)

Publication Number Publication Date
CN111424817A true CN111424817A (en) 2020-07-17

Family

ID=71556090

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010246355.4A Pending CN111424817A (en) 2020-03-31 2020-03-31 Quick installation limiting connection node structure of column top steel structure

Country Status (1)

Country Link
CN (1) CN111424817A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101265725A (en) * 2008-03-27 2008-09-17 上海交通大学 Building method based on power plant steel structure great plate beam and column connected node
CN205637135U (en) * 2016-05-31 2016-10-12 安徽富煌建筑设计研究有限公司 Steel construction pipe truss beam column conversion node
KR20170083694A (en) * 2016-01-08 2017-07-19 (주)엔아이스틸 Roll forming steel plates built-up beam and steel frame using the same
GB2554967A (en) * 2017-06-12 2018-04-18 Eqrbs Ltd A joint
CN108517962A (en) * 2018-06-04 2018-09-11 王士奇 A kind of Tenon and bolt hybrid precast formula steel-structure beam-column node
CN109778897A (en) * 2019-02-28 2019-05-21 杭州西奥电梯现代化更新有限公司 The connection type and assembly method of assembled elevator steel construction and pedestal
CN110820936A (en) * 2019-08-22 2020-02-21 中国建筑股份有限公司 Box type house permanent module beam column node with cross-shaped steel plate and mounting method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101265725A (en) * 2008-03-27 2008-09-17 上海交通大学 Building method based on power plant steel structure great plate beam and column connected node
KR20170083694A (en) * 2016-01-08 2017-07-19 (주)엔아이스틸 Roll forming steel plates built-up beam and steel frame using the same
CN205637135U (en) * 2016-05-31 2016-10-12 安徽富煌建筑设计研究有限公司 Steel construction pipe truss beam column conversion node
GB2554967A (en) * 2017-06-12 2018-04-18 Eqrbs Ltd A joint
CN108517962A (en) * 2018-06-04 2018-09-11 王士奇 A kind of Tenon and bolt hybrid precast formula steel-structure beam-column node
CN109778897A (en) * 2019-02-28 2019-05-21 杭州西奥电梯现代化更新有限公司 The connection type and assembly method of assembled elevator steel construction and pedestal
CN110820936A (en) * 2019-08-22 2020-02-21 中国建筑股份有限公司 Box type house permanent module beam column node with cross-shaped steel plate and mounting method thereof

Similar Documents

Publication Publication Date Title
CN210081215U (en) Be suitable for frock clamp of high accuracy small part batch production
CN104972333A (en) Fixture for machining annular parts and method for machining parts through fixture
CN111424817A (en) Quick installation limiting connection node structure of column top steel structure
JP2006104770A (en) Installation implement for solar cell panel
CN210246661U (en) Special angle of various steel tile roof photovoltaic support is relaxed anchor clamps
CN216542043U (en) Automobile transmission box part machining clamp
CN214162708U (en) Workpiece positioning and clamping tool
CN211006747U (en) Universal horizontal adjustment ground anchor locator subassembly
CN214446060U (en) Brake installation tool
CN213421059U (en) Steel structure fastening support suitable for boiler
CN111421355B (en) Annular thin plate machining tool and fixing method
CN110729949A (en) Device convenient for mounting solar panel roof and using method thereof
CN110397075B (en) Universal horizontal adjustment ground anchor positioner assembly and installation method thereof
CN217942646U (en) Six-station four-shaft hydraulic clamp for machining pump body of automobile electronic oil pump
CN219234593U (en) Main shaft mount pad processing frock
CN210724638U (en) Device convenient to solar panel roof installation
CN115070461A (en) Machining clamp with eccentric characteristic of valve part
FI20206032A1 (en) Arrangement for fastening solar panels
CN220260085U (en) Y-shaped ring assembling device for pilot valve
CN211760947U (en) Stepless variable-pitch clamp
CN110682130A (en) No lug diesel engine frame < shape frock clamp for lifting by crane instrument processing
CN219649059U (en) Welding positioning tool
CN212527431U (en) Flexible clamping device for large cross-shaped sheet part
CN216803278U (en) Novel press-fit pole tool
CN215469233U (en) Disc workpiece inner hole positioning fixture

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200717

RJ01 Rejection of invention patent application after publication