CN111411780A - Large volume concrete circulation cooling water pipe quick positioning construction method and positioning device - Google Patents

Large volume concrete circulation cooling water pipe quick positioning construction method and positioning device Download PDF

Info

Publication number
CN111411780A
CN111411780A CN201910012039.8A CN201910012039A CN111411780A CN 111411780 A CN111411780 A CN 111411780A CN 201910012039 A CN201910012039 A CN 201910012039A CN 111411780 A CN111411780 A CN 111411780A
Authority
CN
China
Prior art keywords
water pipe
cooling water
positioning
volume concrete
positioning device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910012039.8A
Other languages
Chinese (zh)
Inventor
李大卫
张生祥
刘振东
韩春涛
宋术然
龙桂元
任杰
刘静
邓秀华
李丙涛
何建科
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhonghangtian Construction Engineering Co Ltd
Original Assignee
Zhonghangtian Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhonghangtian Construction Engineering Co Ltd filed Critical Zhonghangtian Construction Engineering Co Ltd
Priority to CN201910012039.8A priority Critical patent/CN111411780A/en
Publication of CN111411780A publication Critical patent/CN111411780A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a large-volume concrete circulating cooling water pipe rapid positioning construction method and a positioning device, which comprise a water pipe positioning plate and a steel bar positioning plate, wherein one end of the water pipe positioning plate is provided with a water pipe lifting hook, the other end of the water pipe positioning plate is provided with a positioning block, a convex groove is arranged on the positioning block in a penetrating way, one end of a self-locking clamping piece is hinged inside the convex groove, and one end of a U-shaped elastic sheet is symmetrically and fixedly connected inside the convex groove; in addition, the novel energy-saving environment-friendly. The test and use prove that the invention has good popularization significance.

Description

Large volume concrete circulation cooling water pipe quick positioning construction method and positioning device
Technical Field
The invention relates to the technical field of circulating cooling water pipe positioning construction, in particular to a large-volume concrete circulating cooling water pipe rapid positioning construction method and a positioning device.
Background
The existing large-volume circulating cooling water pipe is positioned by adopting a form of cutting and welding steel bars to be fixed on a steel bar framework, so that the fixing period is long, a large amount of labor is wasted, the welding heat treatment on the stressed steel bars in the positioning welding process has adverse effects on stress, particularly irreversible heat effects are generated in stress areas of some key steel bars, the stress performance and the impression quality of the stressed steel bars are also affected due to improper welding operation, and the engineering quality is affected. And the welding positioning can not be adjusted, and the fixing and positioning device needs to be further improved.
Disclosure of Invention
The invention aims to provide a large-volume concrete circulating cooling water pipe rapid positioning construction method and a positioning device, so as to solve the problems in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme: the large volume concrete circulating cooling water pipe fast positioning construction method includes the following steps:
step 1, after the binding of upper and lower layers of reinforcing mesh sheets of the large-volume concrete is finished, arranging a circulating cooling water pipe and a positioning device between the upper and lower layers of reinforcing mesh sheets;
step 2, positioning and fixing a first circulating cooling water pipe according to the arrangement direction and the position of the cooling water pipe in the large-volume concrete cooling implementation scheme, and fixing an initial section by adopting a double-branch combined positioning device;
step 3, fixing the middle section of the circulating cooling water pipe by adopting a triple-branch combined positioning device;
step 4, continuously arranging the circulating cooling water pipes by utilizing the quick-connection joints or the butt-joint screw thread sleeves according to the arrangement direction and the positions of the cooling water pipes of the large-volume concrete cooling implementation scheme;
step 5, respectively positioning and fixing the two sides of the joint position of the circulating cooling water pipe in a triple-branch combined positioning device by using a double-branch combined positioning device, and positioning the joint position by using an unlocking device when positioning errors occur until the joint position reaches the original design position;
and 6, repeating the step 4 and the step 5 in sequence to complete the positioning arrangement of the circulating cooling water pipe in the whole large-volume concrete.
Quick positioner of large volume concrete circulative cooling water pipe, including water pipe locating plate and reinforcing bar locating plate, the one end of water pipe locating plate is equipped with the water pipe lifting hook, the other end of water pipe locating plate is equipped with the locating piece, run through on the locating piece and seted up the convex groove, the inside in convex groove articulates the one end that has the auto-lock card, the inside symmetry fixedly connected with U-shaped shell fragment's in convex groove one end, the other end of U-shaped shell fragment all with auto-lock card fixed connection, the one end of fixedly connected with pull rod on the auto-lock card, the convex groove is stretched out to the other end of pull rod, the one end of reinforcing bar locating plate is equipped with the reinforcing bar lifting hook, the card groove has evenly been seted up on the reinforcing bar locating plate, the convex groove is run.
Preferably, the water pipe lifting hook and the water pipe locating plate are integrally formed, the locating block and the water pipe locating plate are integrally formed, and the steel bar lifting hook and the steel bar locating plate are integrally formed.
Preferably, the other end of the pull rod is provided with a pull button.
Preferably, the water pipe lifting hook is hooked with the circulating cold water pipe, and the steel bar lifting hook is hooked with steel bars on the large-volume concrete steel bar net piece.
Compared with the prior art, the invention has the beneficial effects that: the invention not only is convenient and rapid to fix, but also can enable the positioning point to be adjusted at will, and meanwhile, the invention can not influence the stress performance and the impression quality of the stressed steel bar in use, thereby overcoming the defects of the prior art and having the advantages of convenient manufacture and installation, capability of adjusting the positioning point at will and convenient and rapid use; in addition, the novel energy-saving environment-friendly environment. The test and use prove that the invention has good popularization significance.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of a positioning device according to the present invention;
FIG. 3 is a schematic cross-sectional view taken along the line A-A in FIG. 2;
FIG. 4 is an enlarged view of portion B of FIG. 3;
FIG. 5 is a schematic structural diagram of a positioning block of the present invention.
In the figure: 1-water pipe positioning plate, 2-steel bar positioning plate, 3-water pipe lifting hook, 4-positioning block, 5-convex groove, 6-self-locking clamping piece, 7-U-shaped elastic piece, 8-pull rod, 9-steel bar lifting hook, 10-clamping strip groove, 11-pull button, 12-large volume concrete steel bar net piece, 13-steel bar and 14-circulating cold water pipe.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-5, the present invention provides a technical solution: the large volume concrete circulating cooling water pipe fast positioning construction method includes the following steps:
step 1, after the binding of upper and lower layers of reinforcing mesh sheets of the large-volume concrete is finished, arranging a circulating cooling water pipe and a positioning device between the upper and lower layers of reinforcing mesh sheets;
step 2, positioning and fixing a first circulating cooling water pipe according to the arrangement direction and the position of the cooling water pipe in the large-volume concrete cooling implementation scheme, and fixing an initial section by adopting a double-branch combined positioning device;
step 3, fixing the middle section of the circulating cooling water pipe by adopting a triple-branch combined positioning device;
step 4, continuously arranging the circulating cooling water pipes by utilizing the quick-connection joints or the butt-joint screw thread sleeves according to the arrangement direction and the positions of the cooling water pipes of the large-volume concrete cooling implementation scheme;
step 5, respectively positioning and fixing the two sides of the joint position of the circulating cooling water pipe in a triple-branch combined positioning device by using a double-branch combined positioning device, and positioning the joint position by using an unlocking device when positioning errors occur until the joint position reaches the original design position;
and 6, repeating the step 4 and the step 5 in sequence to complete the positioning arrangement of the circulating cooling water pipe in the whole large-volume concrete.
Quick positioner of large volume concrete circulative cooling water pipe, including water pipe locating plate 1 and reinforcing bar locating plate 2, the one end of water pipe locating plate is equipped with water pipe lifting hook 3, the other end of water pipe locating plate is equipped with locating piece 4, it has set up convex groove 5 to run through on the locating piece, the inside articulated one end that has auto-lock card 6 in convex groove, the inside symmetry fixedly connected with U-shaped shell fragment 7's of convex groove one end, the other end of U-shaped shell fragment all with auto-lock card fixed connection, the one end of fixedly connected with pull rod 8 on the auto-lock card, the convex groove is stretched out to the other end of pull rod, the one end of reinforcing bar locating plate is equipped with reinforcing bar lifting hook 9, the card strip groove 10 has evenly been seted up on the reinforcing bar.
Particularly, water pipe lifting hook and water pipe locating plate integrated into one piece, locating piece and water pipe locating plate integrated into one piece, reinforcing bar lifting hook and reinforcing bar locating plate integrated into one piece.
Specifically, the other end of the pull rod is provided with a pull knob 11.
Specifically, the water pipe hook is hooked with the circulating cold water pipe 14, and the steel bar hook is hooked with the steel bars 13 on the large-volume concrete steel bar mesh sheet 12.
The working principle is as follows: the invention hangs a steel bar hook on an upper layer of steel bar mesh sheet, hooks a water pipe hook at the bottom of a sliding plate on a circulating cooling water pipe, and simultaneously leads a steel bar positioning plate to pass through a convex groove (note that the groove surface of a clamping strip faces to the side of a self-locking clamping strip), when the circulating cooling water pipe reaches a designed corresponding position, the circulating cooling water pipe automatically pops into the clamping strip groove through a self-locking clamping strip to be fixed in a self-locking way, so as to finish a single positioning device, wherein a U-shaped elastic gasket can lead the self-locking clamping strip to be in a closed state for a long time, and the self-locking clamping strip is in an open state when being inserted into a notch clamping strip, the U-shaped elastic gasket is positioned between a fixing clamping strip bottom plate and the self-locking clamping strip, the upper part of the U-shaped elastic gasket is welded on the self-locking clamping strip, the pull rod is welded at the corresponding position of the self-locking clamping piece, and acts through the pull rod when the position of the circulating cooling water pipe is in error, so that the unlocking purpose is achieved, and the steel bar carving positioning plate is enabled to act and adjust the position. The installation is completed in place in sequence according to the method, so that a single positioning device forms a complete space stable framework, thereby achieving the positioning and fixing effect on the circulating cooling water pipe, and simultaneously, a triple support combination or a double support combination or a matching interval can be adopted for use.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The large volume concrete circulating cooling water pipe fast positioning construction method is characterized in that: the method comprises the following steps:
step 1, after the binding of the upper and lower layers of reinforcing mesh sheets of the large-volume concrete is finished, arranging a circulating cooling water pipe and a positioning device between the upper and lower layers of reinforcing mesh sheets;
step 2, positioning and fixing a first circulating cooling water pipe according to the arrangement direction and the position of the cooling water pipe in the large-volume concrete cooling implementation scheme, and fixing an initial section by adopting a double-branch combined positioning device;
step 3, fixing the middle section of the circulating cooling water pipe by adopting a triple-branch combined positioning device;
step 4, continuously arranging the circulating cooling water pipes by utilizing the quick-connection joints or the butt-joint screw thread sleeves according to the arrangement direction and the positions of the cooling water pipes of the large-volume concrete cooling implementation scheme;
step 5, positioning and fixing two sides of the joint position of the circulating cooling water pipe by using a double-branch combined positioning device and a triple-branch combined positioning device respectively, and positioning by using an unlocking device when positioning errors occur until the original design position is reached;
and 6, repeating the step 4 and the step 5 in sequence to complete the positioning arrangement of the circulating cooling water pipe in the whole large-volume concrete.
2. The large volume concrete circulating cooling water pipe quick positioning device is characterized in that: including water pipe locating plate and reinforcing bar locating plate, the one end of water pipe locating plate is equipped with the water pipe lifting hook, the other end of water pipe locating plate is equipped with the locating piece, run through on the locating piece and seted up the convex groove, the inside of convex groove articulates there is the one end of auto-lock card, the inside symmetry fixedly connected with U-shaped shell fragment's of convex groove one end, the other end of U-shaped shell fragment all with auto-lock card fixed connection, the one end of fixedly connected with pull rod on the auto-lock card, the convex groove is stretched out to the other end of pull rod, the one end of reinforcing bar locating plate is equipped with the reinforcing bar lifting hook, the card strip groove has evenly been seted up on the reinforcing bar locating plate, the convex groove is.
3. A quick positioning device for a large volume concrete circulation cooling water pipe according to claim 2, wherein: the water pipe lifting hook and the water pipe positioning plate are integrally formed, the positioning block and the water pipe positioning plate are integrally formed, and the steel bar lifting hook and the steel bar positioning plate are integrally formed.
4. A quick positioning device for a large volume concrete circulation cooling water pipe according to claim 2, wherein: the other end of the pull rod is provided with a pull button.
5. A quick positioning device for a large volume concrete circulation cooling water pipe according to claim 2, wherein: the water pipe lifting hook is hooked with the circulating cold water pipe, and the steel bar lifting hook is hooked with steel bars on the large-volume concrete steel bar net piece.
CN201910012039.8A 2019-01-07 2019-01-07 Large volume concrete circulation cooling water pipe quick positioning construction method and positioning device Pending CN111411780A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910012039.8A CN111411780A (en) 2019-01-07 2019-01-07 Large volume concrete circulation cooling water pipe quick positioning construction method and positioning device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910012039.8A CN111411780A (en) 2019-01-07 2019-01-07 Large volume concrete circulation cooling water pipe quick positioning construction method and positioning device

Publications (1)

Publication Number Publication Date
CN111411780A true CN111411780A (en) 2020-07-14

Family

ID=71490683

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910012039.8A Pending CN111411780A (en) 2019-01-07 2019-01-07 Large volume concrete circulation cooling water pipe quick positioning construction method and positioning device

Country Status (1)

Country Link
CN (1) CN111411780A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114856200A (en) * 2022-05-31 2022-08-05 中国十七冶集团有限公司 Self-circulation cooling construction method for U-shaped cooling water pipe in mass concrete

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114856200A (en) * 2022-05-31 2022-08-05 中国十七冶集团有限公司 Self-circulation cooling construction method for U-shaped cooling water pipe in mass concrete

Similar Documents

Publication Publication Date Title
CN111411780A (en) Large volume concrete circulation cooling water pipe quick positioning construction method and positioning device
CN113356379A (en) Limiting support piece and using method thereof
CN110469014B (en) Formwork support keel connection reinforcing device for concrete pouring and disassembly-free heat preservation formwork
CN111705960A (en) Cast-in-place concrete built-in heat-insulation wall structure and construction method
CN204960304U (en) Post -cast strip built -up plate
CN215166895U (en) Cast-in-place concrete structure external thermal insulation integration exempts from to tear open template
CN103286519B (en) A kind of nuclear power station Leak-tight liner manufacture method
CN206360340U (en) A kind of floor beam plate post-cast strip template support system
CN212561479U (en) Lap joint type pipe pile head
CN211523625U (en) Wall heat-insulating fireproof waterproof composite system for building
CN208040851U (en) A kind of steel reinforced type steel corner brace
CN211058177U (en) Reusable tool for reserving separation seam of waterproof protective layer
CN210199001U (en) Cement boiling box
CN210342680U (en) Building construction template connector link
CN208633266U (en) A kind of ultra-high performance concrete frame structure assembled architecture
CN220204920U (en) Supporting structure suitable for construction of large-volume concrete cooling water pipe
CN209637229U (en) Prevention of mass concrete circulating cooling water pipe positioning device
CN219346415U (en) Fused salt heat-storage steam-supply heat preservation water tank
CN206091295U (en) Design formula door and window entrance to a cave formwork support
CN217811685U (en) Spacing support piece
CN217571585U (en) Air source heat pump water pipeline welding positioning tool
CN205875707U (en) Wall form reentrant corner tool to lock
CN215472617U (en) Constant temperature polyurethane foaming mould
CN221255760U (en) Assembled water stop steel plate
CN110952680A (en) Wall heat-insulating fireproof waterproof composite system for building

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination