CN111395186A - Method for erecting temporary pier of large-span steel-concrete composite beam cable-stayed bridge - Google Patents
Method for erecting temporary pier of large-span steel-concrete composite beam cable-stayed bridge Download PDFInfo
- Publication number
- CN111395186A CN111395186A CN202010251099.8A CN202010251099A CN111395186A CN 111395186 A CN111395186 A CN 111395186A CN 202010251099 A CN202010251099 A CN 202010251099A CN 111395186 A CN111395186 A CN 111395186A
- Authority
- CN
- China
- Prior art keywords
- temporary pier
- steel
- cable
- span
- stayed bridge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D11/00—Suspension or cable-stayed bridges
- E01D11/04—Cable-stayed bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/30—Metal
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域technical field
本发明属于临时墩支设技术领域,具体涉及一种大跨径钢混组合梁斜拉桥临时墩支设方法。The invention belongs to the technical field of temporary pier support, in particular to a temporary pier support method for a long-span steel-concrete composite beam cable-stayed bridge.
背景技术Background technique
临时墩是桥梁施工时为了结构受力和安全所架设的临时桥墩,随着桥梁设计和建造技术的不断发展,大跨径钢混组合梁斜拉桥越来越多地被修建。在大跨径钢箱梁斜拉桥的施工过程中,为保证斜拉桥梁体在未合龙之前的安全稳定,必须设置临时墩。然而,新增临时墩会引起塔偏发生明显变化,波动较大,增加了大跨径钢混组合梁斜拉桥线形控制的难度,临时墩在后续施工过程中将承受较大的反复拉压荷载,且受斜拉索水平分力作用及温度影响,主梁与临时墩连接设计不当会产生较大水平力,因此现缺少一种临时连接施工精度高、安全风险小、可操作性强的大跨径钢混组合梁斜拉桥临时墩。Temporary piers are temporary piers erected for structural stress and safety during bridge construction. With the continuous development of bridge design and construction technology, long-span steel-concrete composite girder cable-stayed bridges are being built more and more. During the construction of the long-span steel box girder cable-stayed bridge, temporary piers must be set up to ensure the safety and stability of the cable-stayed bridge body before closing. However, the addition of temporary piers will cause significant changes in tower deflection and large fluctuations, which increases the difficulty of linear control of long-span steel-concrete composite girder cable-stayed bridges. In addition, due to the horizontal component action of the stay cable and the influence of temperature, the improper design of the connection between the main beam and the temporary pier will generate a large horizontal force. Temporary piers of long-span steel-concrete composite beam cable-stayed bridges.
发明内容SUMMARY OF THE INVENTION
本发明所要解决的技术问题在于针对上述现有技术中的不足,提供一种大跨径钢混组合梁斜拉桥临时墩支设方法,通过抗风性能检测和现场地形、地质条件、施工难度和施工安全确定临时墩在边跨的最佳支设位置,设置边界约束条件,确定临时墩安装时机和临时墩拆除时机,为后续临时墩支设做充分准备,通过在钢主梁底部安装上支撑耳板,上支撑耳板与两个安装在横向限位架上的下支撑耳板配合,下支撑耳板和上支撑耳板上均开设有与支撑连接件配合的腰形孔,允许斜拉桥在纵向上有一定的位移变化,限制钢主梁竖向位移变化,受力明确,便于推广使用。The technical problem to be solved by the present invention is to provide a temporary pier support method for a long-span steel-concrete composite beam cable-stayed bridge in view of the above-mentioned deficiencies in the prior art. Determine the best supporting position of temporary piers on the side spans and the construction safety, set boundary constraints, determine the timing of temporary pier installation and temporary pier removal, and make full preparations for subsequent temporary pier support. Supporting lugs, the upper supporting lugs are matched with two lower supporting lugs installed on the lateral limit frame, and the lower supporting lugs and the upper supporting lugs are both provided with waist-shaped holes that cooperate with the supporting connectors, allowing oblique The tension bridge has a certain displacement change in the longitudinal direction, which limits the vertical displacement change of the steel main beam, and the force is clear, which is convenient for popularization and use.
为解决上述技术问题,本发明采用的技术方案是:一种大跨径钢混组合梁斜拉桥临时墩支设方法,所述大跨径钢混组合梁斜拉桥为三跨双塔双索面钢混组合梁斜拉桥,其特征在于,该方法包括以下步骤:In order to solve the above technical problems, the technical scheme adopted in the present invention is: a temporary pier support method for a long-span steel-concrete composite beam cable-stayed bridge, wherein the long-span steel-concrete composite beam cable-stayed bridge is a three-span double-tower double-tower cable-stayed bridge. The cable-stayed steel-concrete composite beam cable-stayed bridge is characterized in that the method comprises the following steps:
步骤一、确定临时墩支设位置:构建大跨径钢混组合梁斜拉桥模拟模型并经过等比例模型的风洞试验对大跨径钢混组合梁斜拉桥模拟模型进行抗风性能检测,获取大跨径钢混组合梁斜拉桥模拟模型抗风性能提高下,临时墩在边跨的支设位置区间;Step 1: Determine the location of temporary pier support: Build a simulation model of a long-span steel-concrete composite beam cable-stayed bridge and test the wind resistance performance of the simulation model of a long-span steel-concrete composite beam cable-stayed bridge through the wind tunnel test of the isometric model. , to obtain the location interval of temporary piers in the side spans under the improved wind resistance performance of the simulation model of the long-span steel-concrete composite beam cable-stayed bridge;
结合现场地形、地质条件、施工难度和施工安全确定临时墩在边跨的最佳支设位置;According to the site topography, geological conditions, construction difficulty and construction safety, determine the best supporting position of the temporary pier on the side span;
步骤二、设置边界约束条件:限制三跨双塔双索面钢混组合梁斜拉桥竖向位移和横向位移,允许三跨双塔双索面钢混组合梁斜拉桥沿桥延伸方向的纵向位移;Step 2. Set boundary constraints: limit the vertical displacement and lateral displacement of the three-span, double-tower, double-cable plane, steel-concrete composite beam cable-stayed bridge, and allow the three-span, double-tower, double-cable plane, steel-concrete composite beam cable-stayed bridge along the extension direction of the bridge. longitudinal displacement;
步骤三、确定临时墩安装时机:模拟临时墩在边跨的最佳支设位置所对应的梁段施工全过程中受力,临时墩在边跨的最佳支设位置所对应的梁段施工全过程包含多道施工工序,在边跨的最佳支设位置所对应的梁段施工全过程中受力最小的一道施工工序所对应的时机即为临时墩安装时机;Step 3: Determine the installation timing of the temporary pier: simulate the stress during the construction of the beam section corresponding to the best support position of the side span, and the temporary pier is constructed at the beam section corresponding to the best support position of the side span. The whole process includes multiple construction processes. The time corresponding to the construction process of the beam section corresponding to the best support position of the side span during the whole process of construction with the smallest force is the installation time of the temporary pier;
所述施工工序包括纵横梁安装、斜拉索一张、桥面板架设、斜拉索二张、施工临时荷载、吊机前移和浇筑湿接缝;The construction process includes installation of vertical and horizontal beams, one stay cable, bridge deck erection, two stay cables, construction temporary load, crane forward movement and pouring of wet joints;
步骤四、确定临时墩拆除时机:在边跨合龙后,模拟后续各个梁段施工全过程中临时墩反力变化,在后续各个梁段施工全过程中临时墩反力最小的一道施工工序所对应的时机即为临时墩拆除时机;
步骤五、临时墩支设,过程如下:Step 5. Temporary pier support, the process is as follows:
步骤501、构建临时墩:根据临时墩在边跨的最佳支设位置,在钢主梁底部安装上支撑耳板,并在钢主梁下部构建与上支撑耳板配合的临时墩,所述临时墩包括由下至上依次连接的桩基、钢管底架、承重梁、限位机构和连接机构,所述桩基伸入至地层内,所述承重梁包括沿斜拉桥宽度方向设置在所述钢管底架上的横向承重梁和沿斜拉桥长度方向设置在所述横向承重梁上的纵向承重梁,所述限位机构包括横向安装在纵向承重梁上的限位梁和两个对称安装在限位梁上用于限位所述连接机构的横向限位架,所述连接机构包括两个安装在限位梁上且位于两个横向限位架之间梁段上的下支撑耳板,上支撑耳板伸入至两个下支撑耳板之间区域,下支撑耳板和上支撑耳板上均开设有腰形孔,纵向承重梁位于限位梁的两端分别安装有千斤顶;Step 501, constructing a temporary pier: According to the optimal supporting position of the temporary pier on the side span, a support ear plate is installed at the bottom of the steel main beam, and a temporary pier matched with the upper support ear plate is constructed at the lower part of the steel main beam. The temporary pier includes a pile foundation, a steel tube underframe, a load-bearing beam, a limit mechanism and a connection mechanism sequentially connected from bottom to top. The lateral load-bearing beam on the steel tube underframe and the longitudinal load-bearing beam arranged on the lateral load-bearing beam along the length direction of the cable-stayed bridge, the limit mechanism includes a limit beam installed laterally on the longitudinal load-bearing beam and two symmetrically installed on the lateral load-bearing beam. A lateral limit frame on the limit beam for limiting the connecting mechanism, the connecting mechanism includes two lower support lugs mounted on the limit beam and located on the beam section between the two lateral limit frames, The upper support lug plate extends into the area between the two lower support lugs, the lower support lug plate and the upper support lug plate are both provided with waist-shaped holes, and the longitudinal load-bearing beams are located at the two ends of the limit beams with jacks installed respectively;
步骤502、在边跨的最佳支设位置所对应的梁段施工全过程中受力最小的一道施工工序过程中,利用千斤顶对支撑钢主梁进行支撑并将钢主梁支撑调节至指定高度,待边跨的最佳支设位置所对应的梁段施工全过程中受力最小的一道施工工序结束后,将支撑连接件插入下支撑耳板和上支撑耳板中,完成临时墩的安装连接,并停止千斤顶对支撑钢主梁的支撑;Step 502 , in the construction process of the beam section corresponding to the optimal support position of the side span with the least force in the whole process of construction, use the jack to support the supporting steel main beam and adjust the steel main beam support to the specified height After the construction process of the beam section corresponding to the optimal support position of the side span with the smallest force in the whole process is completed, insert the support connector into the lower support ear plate and the upper support ear plate to complete the installation of the temporary pier Connect, and stop the support of the jack to the supporting steel main beam;
步骤503、边跨合龙后,在后续各个梁段实际施工全过程中临时墩反力最小的一道施工工序过程中,利用千斤顶对支撑钢主梁进行支撑,将支撑连接件从下支撑耳板和上支撑耳板中抽出,同时利用千斤顶将临时墩所受内力进行逐步释放,完成临时墩的拆除。Step 503: After the side spans are closed, in the construction process with the smallest reaction force of the temporary pier in the actual construction of each subsequent beam section, the supporting steel main beam is supported by the jack, and the supporting connector is supported from the lower support ear plate and The upper support lugs are pulled out, and at the same time, the internal force of the temporary pier is gradually released by the jack to complete the demolition of the temporary pier.
上述的一种大跨径钢混组合梁斜拉桥临时墩支设方法,其特征在于:所述桩基包括多个呈阵列式排布的混凝土基础柱,所述钢管底架包括固定在所述混凝土基础柱上的钢管柱,相邻两个钢管柱之间通过斜拉式的加固杆连接,横向承重梁安装在钢管柱底端。The above-mentioned method for erecting temporary piers of a long-span steel-concrete composite beam cable-stayed bridge is characterized in that: the pile foundation comprises a plurality of concrete foundation columns arranged in an array; The steel pipe column on the concrete foundation column is connected by a cable-stayed reinforcing rod between two adjacent steel pipe columns, and the transverse load-bearing beam is installed at the bottom end of the steel pipe column.
上述的一种大跨径钢混组合梁斜拉桥临时墩支设方法,其特征在于:步骤502中在支撑连接件位于下支撑耳板和上支撑耳板之间的外侧套设缓冲垫块。The above-mentioned method for erecting temporary piers of a long-span steel-concrete composite girder cable-stayed bridge is characterized in that: in step 502, a buffer pad is sleeved on the outer side of the support connector located between the lower support ear plate and the upper support ear plate .
上述的一种大跨径钢混组合梁斜拉桥临时墩支设方法,其特征在于:所述缓冲垫块为橡胶缓冲垫块。The above-mentioned method for erecting temporary piers of a long-span steel-concrete composite beam cable-stayed bridge is characterized in that: the buffer pad is a rubber buffer pad.
上述的一种大跨径钢混组合梁斜拉桥临时墩支设方法,其特征在于:所述横向限位架包括横向限位立杆和安装在横向限位立杆远离所述连接机构一端的横向斜撑。The above-mentioned method for erecting temporary piers of a long-span steel-concrete composite beam cable-stayed bridge is characterized in that: the lateral limit frame comprises a lateral limit pole and an end installed at the end of the lateral limit pole away from the connecting mechanism of horizontal diagonal braces.
上述的一种大跨径钢混组合梁斜拉桥临时墩支设方法,其特征在于:所述横向承重梁和钢管柱的连接位置处、横向承重梁和纵向承重梁的连接位置处、限位梁和纵向承重梁的连接位置处、下支撑耳板和位梁的连接位置处、以及上支撑耳板和钢主梁的连接位置处均设置有多个加劲板。The above-mentioned temporary pier support method for a long-span steel-concrete composite beam cable-stayed bridge is characterized in that: the connection position of the transverse load-bearing beam and the steel pipe column, the connection position of the transverse load-bearing beam and the longitudinal load-bearing beam, the limit A plurality of stiffening plates are arranged at the connection positions of the position beam and the longitudinal load-bearing beam, the connection positions of the lower support lugs and the position beams, and the connection positions of the upper support lugs and the steel main beam.
上述的一种大跨径钢混组合梁斜拉桥临时墩支设方法,其特征在于:所述支撑连接件为圆钢,所述圆钢的外径与腰形孔的内宽相等。The above-mentioned method for erecting temporary piers of a long-span steel-concrete composite beam cable-stayed bridge is characterized in that: the support connecting piece is a round steel, and the outer diameter of the round steel is equal to the inner width of the girdle hole.
本发明与现有技术相比具有以下优点:Compared with the prior art, the present invention has the following advantages:
1、本发明通过抗风性能检测和现场地形、地质条件、施工难度和施工安全确定临时墩在边跨的最佳支设位置,设置边界约束条件,确定临时墩安装时机和临时墩拆除时机,为后续临时墩支设做充分准备,便于推广使用。1. The present invention determines the optimal support position of the temporary pier on the side span through the detection of wind resistance performance and the on-site topography, geological conditions, construction difficulty and construction safety, sets boundary constraints, and determines the installation timing of the temporary pier and the removal timing of the temporary pier, Make full preparations for the subsequent temporary pier support, which is convenient for popularization and use.
2、本发明通过设置桩基和钢管底架作为临时墩基础,桩基和钢管底架均为阵列式排布,满足强度设计需求,在临时墩基础上设置承重梁作为临时墩基础和与钢主梁连接的连接机构的过渡连接,稳定可靠,满足受力要求,通过在承重梁上安装限位机构限定临时墩和斜拉桥的连接位置,利用横向安装在纵向承重梁上的限位梁限定钢主梁的纵向连接区间,利用两个横向限位架限定钢主梁的横向连接区间,连接定位精度高,连接机构中通过两个安装在限位梁上且位于两个横向限位架之间梁段上的下支撑耳板和一个安装在钢主梁底部且伸入至两个下支撑耳板之间区域的上支撑耳板之间的配合,下支撑耳板和上支撑耳板上均开设有与支撑连接件配合的腰形孔,允许斜拉桥在纵向上有一定的位移变化,限制钢主梁竖向位移变化,受力明确,同时配备千斤顶为临时墩安装进行竖向微调,以安装到设计高度,可靠稳定,使用效果好。2. In the present invention, the pile foundation and the steel pipe underframe are arranged as the temporary pier foundation, and the pile foundation and the steel pipe underframe are arranged in an array to meet the strength design requirements, and the load-bearing beam is set on the temporary pier foundation as the temporary pier foundation and the steel The transition connection of the connecting mechanism of the main beam connection is stable and reliable, and meets the force requirements. The connection position of the temporary pier and the cable-stayed bridge is limited by installing the limit mechanism on the load-bearing beam, and the limit beam installed on the longitudinal load-bearing beam is used. The longitudinal connection section of the steel main beam is defined, and the transverse connection section of the steel main beam is defined by two lateral limit frames, and the connection positioning accuracy is high. The fit between the lower support lug on the middle beam section and an upper support lug installed at the bottom of the steel main beam and extending into the area between the two lower support lugs, the lower support lug and the upper support lug There are waist-shaped holes on the upper part that cooperate with the supporting connectors, allowing the cable-stayed bridge to have a certain displacement change in the longitudinal direction, limiting the vertical displacement change of the steel main girder, and the force is clear. Fine-tuning to install to the design height, reliable and stable, and good use effect.
3、本发明方法步骤简单,受力明确且安装方便,施工速度快,保证施工阶段结构安全的同时,通过支撑连接件使临时墩增加桥梁受力和变形影响达到最小的效果,现场实施可操作性强,以便于临时墩快速精准的安装和拆除,且安装、拆除过程对桥梁结构不发生扰动,此外由于其为临时性工程,设计时兼顾经济性,边跨合龙后及时拆除,便于推广使用。3. The method of the present invention has simple steps, clear force, convenient installation, fast construction speed, and ensures the safety of the structure during the construction stage. At the same time, the temporary pier can increase the force and deformation of the bridge by supporting the connecting piece to achieve the minimum effect, and the on-site implementation can be operated. It is easy to install and dismantle the temporary piers quickly and accurately, and the bridge structure will not be disturbed during the installation and dismantling process. In addition, because it is a temporary project, economical design is taken into account. .
综上所述,本发明通过抗风性能检测和现场地形、地质条件、施工难度和施工安全确定临时墩在边跨的最佳支设位置,设置边界约束条件,确定临时墩安装时机和临时墩拆除时机,为后续临时墩支设做充分准备,通过在钢主梁底部安装上支撑耳板,上支撑耳板与两个安装在横向限位架上的下支撑耳板配合,下支撑耳板和上支撑耳板上均开设有与支撑连接件配合的腰形孔,允许斜拉桥在纵向上有一定的位移变化,限制钢主梁竖向位移变化,受力明确,便于推广使用。To sum up, the present invention determines the optimal support position of the temporary pier on the side span through the detection of the wind resistance performance and the on-site topography, geological conditions, construction difficulty and construction safety, sets the boundary constraints, and determines the installation timing of the temporary pier and the temporary pier. The timing of dismantling is to make full preparation for the subsequent temporary pier support. By installing the upper support ear plate at the bottom of the steel main beam, the upper support ear plate cooperates with the two lower support ear plates installed on the lateral limit frame, and the lower support ear plate is installed on the horizontal limit frame. There are waist-shaped holes matched with the support connectors on both the upper and upper support lugs, allowing the cable-stayed bridge to have a certain displacement change in the longitudinal direction, limiting the vertical displacement change of the steel main beam, and the force is clear, which is convenient for popularization and use.
下面通过附图和实施例,对本发明的技术方案做进一步的详细描述。The technical solutions of the present invention will be further described in detail below through the accompanying drawings and embodiments.
附图说明Description of drawings
图1为本发明临时墩(未安装千斤顶)的结构示意图。FIG. 1 is a schematic structural diagram of a temporary pier (without a jack) of the present invention.
图2为图1的左视图。FIG. 2 is a left side view of FIG. 1 .
图3为本发明临时墩的使用状态图。Fig. 3 is a use state diagram of the temporary pier of the present invention.
图4为图3(未安装千斤顶)的左视图。Fig. 4 is a left side view of Fig. 3 (without the jack installed).
图5为本发明的方法流程框图。FIG. 5 is a flow chart of the method of the present invention.
附图标记说明:Explanation of reference numbers:
1—桩基; 2—钢管柱; 3—加固杆;1—pile foundation; 2—steel column; 3—reinforcing rod;
4—横向承重梁; 5—纵向承重梁; 6—限位梁;4—transverse load-bearing beam; 5—longitudinal load-bearing beam; 6—limit beam;
7—横向限位架; 7-1—横向限位立杆; 7-2—横向斜撑;7—transverse limit frame; 7-1—transverse limit pole; 7-2—transverse diagonal brace;
8—下支撑耳板; 9—上支撑耳板; 10—支撑连接件;8—lower support lugs; 9—upper support lugs; 10—support connectors;
11—缓冲垫块; 12—千斤顶; 13—钢主梁;11—buffer block; 12—jack; 13—steel main beam;
14—腰形孔。14 - Waist hole.
具体实施方式Detailed ways
如图1至图5所示,本发明的一种大跨径钢混组合梁斜拉桥临时墩支设方法,所述大跨径钢混组合梁斜拉桥为三跨双塔双索面钢混组合梁斜拉桥,该方法包括以下步骤:As shown in Figures 1 to 5, a temporary pier support method for a long-span steel-concrete composite beam cable-stayed bridge of the present invention, the long-span steel-concrete composite beam cable-stayed bridge is a three-span double-tower double-cable plane Steel-concrete composite beam cable-stayed bridge, the method includes the following steps:
步骤一、确定临时墩支设位置:构建大跨径钢混组合梁斜拉桥模拟模型并经过等比例模型的风洞试验对大跨径钢混组合梁斜拉桥模拟模型进行抗风性能检测,获取大跨径钢混组合梁斜拉桥模拟模型抗风性能提高下,临时墩在边跨的支设位置区间;Step 1: Determine the location of temporary pier support: Build a simulation model of a long-span steel-concrete composite beam cable-stayed bridge and test the wind resistance performance of the simulation model of a long-span steel-concrete composite beam cable-stayed bridge through the wind tunnel test of the isometric model. , to obtain the location interval of temporary piers in the side spans under the improved wind resistance performance of the simulation model of the long-span steel-concrete composite beam cable-stayed bridge;
结合现场地形、地质条件、施工难度和施工安全确定临时墩在边跨的最佳支设位置;According to the site topography, geological conditions, construction difficulty and construction safety, determine the best supporting position of the temporary pier on the side span;
步骤二、设置边界约束条件:限制三跨双塔双索面钢混组合梁斜拉桥竖向位移和横向位移,允许三跨双塔双索面钢混组合梁斜拉桥沿桥延伸方向的纵向位移;Step 2. Set boundary constraints: limit the vertical displacement and lateral displacement of the three-span, double-tower, double-cable plane, steel-concrete composite beam cable-stayed bridge, and allow the three-span, double-tower, double-cable plane, steel-concrete composite beam cable-stayed bridge along the extension direction of the bridge. longitudinal displacement;
步骤三、确定临时墩安装时机:模拟临时墩在边跨的最佳支设位置所对应的梁段施工全过程中受力,临时墩在边跨的最佳支设位置所对应的梁段施工全过程包含多道施工工序,在边跨的最佳支设位置所对应的梁段施工全过程中受力最小的一道施工工序所对应的时机即为临时墩安装时机;Step 3: Determine the installation timing of the temporary pier: simulate the stress during the construction of the beam section corresponding to the best support position of the side span, and the temporary pier is constructed at the beam section corresponding to the best support position of the side span. The whole process includes multiple construction processes. The time corresponding to the construction process of the beam section corresponding to the best support position of the side span during the whole process of construction with the smallest force is the installation time of the temporary pier;
所述施工工序包括纵横梁安装、斜拉索一张、桥面板架设、斜拉索二张、施工临时荷载、吊机前移和浇筑湿接缝;The construction process includes installation of vertical and horizontal beams, one stay cable, bridge deck erection, two stay cables, construction temporary load, crane forward movement and pouring of wet joints;
步骤四、确定临时墩拆除时机:在边跨合龙后,模拟后续各个梁段施工全过程中临时墩反力变化,在后续各个梁段施工全过程中临时墩反力最小的一道施工工序所对应的时机即为临时墩拆除时机;
需要说明的是,步骤一至步骤四中模拟过程均在Midas Civil 2019软件中完成。It should be noted that the simulation process in steps 1 to 4 is completed in Midas Civil 2019 software.
步骤五、临时墩支设,过程如下:Step 5. Temporary pier support, the process is as follows:
步骤501、构建临时墩:根据临时墩在边跨的最佳支设位置,在钢主梁13底部安装上支撑耳板9,并在钢主梁13下部构建与上支撑耳板9配合的临时墩,所述临时墩包括由下至上依次连接的桩基1、钢管底架、承重梁、限位机构和连接机构,所述桩基1伸入至地层内,所述承重梁包括沿斜拉桥宽度方向设置在所述钢管底架上的横向承重梁4和沿斜拉桥长度方向设置在所述横向承重梁4上的纵向承重梁5,所述限位机构包括横向安装在纵向承重梁5上的限位梁6和两个对称安装在限位梁6上用于限位所述连接机构的横向限位架7,所述连接机构包括两个安装在限位梁6上且位于两个横向限位架7之间梁段上的下支撑耳板8,上支撑耳板9伸入至两个下支撑耳板8之间区域,下支撑耳板8和上支撑耳板9上均开设有腰形孔14,纵向承重梁5位于限位梁6的两端分别安装有千斤顶12;Step 501 , constructing a temporary pier: According to the optimal supporting position of the temporary pier on the side span, install the supporting
步骤502、在边跨的最佳支设位置所对应的梁段施工全过程中受力最小的一道施工工序过程中,利用千斤顶12对支撑钢主梁13进行支撑并将钢主梁13支撑调节至指定高度,待边跨的最佳支设位置所对应的梁段施工全过程中受力最小的一道施工工序结束后,将支撑连接件10插入下支撑耳板8和上支撑耳板9中,完成临时墩的安装连接,并停止千斤顶12对支撑钢主梁13的支撑;Step 502: During the construction process of the beam section corresponding to the optimal support position of the side span, in the construction process with the least force in the whole process, use the
步骤503、边跨合龙后,在后续各个梁段实际施工全过程中临时墩反力最小的一道施工工序过程中,利用千斤顶12对支撑钢主梁13进行支撑,将支撑连接件10从下支撑耳板8和上支撑耳板9中抽出,同时利用千斤顶12将临时墩所受内力进行逐步释放,完成临时墩的拆除。Step 503: After the side spans are closed, during the construction process with the smallest reaction force of the temporary pier in the actual construction of each subsequent beam section, the supporting steel
需要说明的是,通过设置桩基1和钢管底架作为临时墩基础,桩基1和钢管底架均为阵列式排布,满足强度设计需求,在临时墩基础上设置承重梁作为临时墩基础和与钢主梁13连接的连接机构的过渡连接,稳定可靠,满足受力要求,通过在承重梁上安装限位机构限定临时墩和斜拉桥的连接位置,利用横向安装在纵向承重梁5上的限位梁6限定钢主梁13的纵向连接区间,利用两个横向限位架7限定钢主梁13的横向连接区间,连接定位精度高,可靠稳定;连接机构中通过两个安装在限位梁6上且位于两个横向限位架7之间梁段上的下支撑耳板8和一个安装在钢主梁13底部且伸入至两个下支撑耳板8之间区域的上支撑耳板9之间的配合,下支撑耳板和上支撑耳板上均开设有与支撑连接件配合的腰形孔,允许斜拉桥在纵向上有一定的位移变化,限制钢主梁竖向位移变化,受力明确,同时配备千斤顶为临时墩安装进行竖向微调,以安装到设计高度。It should be noted that by setting the pile foundation 1 and the steel pipe underframe as the temporary pier foundation, the pile foundation 1 and the steel pipe underframe are arranged in an array to meet the strength design requirements, and a load-bearing beam is set on the temporary pier foundation as the temporary pier foundation. The transitional connection with the connecting mechanism connected with the steel
实际操作中,支撑连接件10从下支撑耳板8和上支撑耳板9中抽出,即实现了临时墩与钢主梁13的分离,相当于临时墩的拆除效果,桩基1、钢管底架、承重梁、限位机构和连接机构的拆除根据实际施工间隙或人力安排,后续拆除即可。In actual operation, the
本实施例中,所述桩基1包括多个呈阵列式排布的混凝土基础柱,所述钢管底架包括固定在所述混凝土基础柱上的钢管柱2,相邻两个钢管柱2之间通过斜拉式的加固杆3连接,横向承重梁4安装在钢管柱2底端。In this embodiment, the pile foundation 1 includes a plurality of concrete foundation columns arranged in an array, and the steel tube underframe includes a steel tube column 2 fixed on the concrete foundation column, and the one between the two adjacent steel tube columns 2 They are connected by a cable-stayed reinforcing rod 3 , and a transverse load-
本实施例中,步骤502中在支撑连接件10位于下支撑耳板8和上支撑耳板9之间的外侧套设缓冲垫块11。In this embodiment, in step 502 , a buffer block 11 is sleeved on the outer side of the
本实施例中,所述缓冲垫块11为橡胶缓冲垫块。In this embodiment, the buffer pad 11 is a rubber buffer pad.
本实施例中,所述横向限位架7包括横向限位立杆7-1和安装在横向限位立杆7-1远离所述连接机构一端的横向斜撑7-2。In this embodiment, the lateral limiting frame 7 includes a lateral limiting vertical rod 7-1 and a lateral diagonal brace 7-2 installed at one end of the lateral limiting vertical rod 7-1 away from the connecting mechanism.
本实施例中,所述横向承重梁4和钢管柱2的连接位置处、横向承重梁4和纵向承重梁5的连接位置处、限位梁6和纵向承重梁5的连接位置处、下支撑耳板8和位梁6的连接位置处、以及上支撑耳板9和钢主梁13的连接位置处均设置有多个加劲板。In this embodiment, the connection position of the transverse load-
本实施例中,所述支撑连接件10为圆钢,所述圆钢的外径与腰形孔14的内宽相等。In this embodiment, the
本发明使用时,通过抗风性能检测和现场地形、地质条件、施工难度和施工安全确定临时墩在边跨的最佳支设位置,设置边界约束条件,确定临时墩安装时机和临时墩拆除时机,为后续临时墩支设做充分准备,根据临时墩设计要求在钢主梁13下侧安装一个上支撑耳板9,在地层内构筑桩基1,搭建钢管柱2,并利用加固杆3加固钢管柱2,在钢管柱2顶端固定横向承重梁4和纵向承重梁5组成的承重梁,在承重梁上安装限位机构和千斤顶12,利用千斤顶12支撑钢主梁13并将钢主梁13支撑调节至指定高度,在限位梁6上且位于两个横向限位架7之间梁段上安装两个与上支撑耳板9配合的下支撑耳板8,利用支撑连接件10穿过上支撑耳板9和下支撑耳板8上的腰形孔14将钢主梁13和临时墩连接,下支撑耳板和上支撑耳板上均开设有腰形孔的目的是允许斜拉桥在纵向上有一定的位移变化,限制钢主梁竖向位移变化,受力明确,同时配备千斤顶为临时墩安装进行竖向微调,以安装到设计高度,方法步骤简单,受力明确且安装方便,施工速度快,保证施工阶段结构安全的同时,通过支撑连接件使临时墩增加桥梁受力和变形影响达到最小的效果,现场实施可操作性强,以便于临时墩快速精准的安装和拆除,且安装、拆除过程对桥梁结构不发生扰动,此外由于其为临时性工程,设计时兼顾经济性,边跨合龙后及时拆除。When the present invention is used, the best supporting position of the temporary pier on the side span is determined through the detection of the wind resistance performance and the on-site topography, geological conditions, construction difficulty and construction safety, the boundary constraint conditions are set, and the installation timing of the temporary pier and the removal timing of the temporary pier are determined. In order to make full preparations for the subsequent temporary pier support, install an upper support ear plate 9 on the lower side of the steel main beam 13 according to the design requirements of the temporary pier, build the pile foundation 1 in the stratum, build the steel pipe column 2, and use the reinforcement rod 3 to reinforce Steel pipe column 2, a load-bearing beam composed of a transverse load-bearing beam 4 and a longitudinal load-bearing beam 5 is fixed at the top of the steel pipe column 2, a limit mechanism and a jack 12 are installed on the load-bearing beam, and the jack 12 is used to support the steel main beam 13 and the steel main beam 13 The support is adjusted to a specified height, and two lower support lugs 8 matched with the upper support lugs 9 are installed on the limit beam 6 and located on the beam section between the two lateral limit frames 7, and the support connectors 10 are used to pass through The waist-shaped holes 14 on the upper support ear plate 9 and the lower support ear plate 8 connect the steel main beam 13 and the temporary pier, and the waist-shaped holes are opened on the lower support ear plate and the upper support ear plate for the purpose of allowing the cable-stayed bridge. There is a certain displacement change in the longitudinal direction, which limits the vertical displacement change of the steel main beam, and the force is clear. At the same time, it is equipped with a jack for vertical fine-tuning of the temporary pier installation to install it to the design height. The method and steps are simple, the force is clear and the installation is convenient. , the construction speed is fast, while ensuring the structural safety of the construction stage, the temporary pier can be increased to the minimum effect of the stress and deformation of the bridge by supporting the connecting piece. Moreover, the bridge structure will not be disturbed during the installation and dismantling process. In addition, because it is a temporary project, the design takes into account the economy, and the side spans are dismantled in time after they are closed.
以上所述,仅是本发明的较佳实施例,并非对本发明作任何限制,凡是根据本发明技术实质对以上实施例所作的任何简单修改、变更以及等效结构变化,均仍属于本发明技术方案的保护范围内。The above are only preferred embodiments of the present invention and do not limit the present invention. Any simple modifications, changes and equivalent structural changes made to the above embodiments according to the technical essence of the present invention still belong to the technology of the present invention. within the scope of the program.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010251099.8A CN111395186B (en) | 2020-04-01 | 2020-04-01 | A kind of temporary pier support method for long-span steel-concrete composite beam cable-stayed bridge |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010251099.8A CN111395186B (en) | 2020-04-01 | 2020-04-01 | A kind of temporary pier support method for long-span steel-concrete composite beam cable-stayed bridge |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN111395186A true CN111395186A (en) | 2020-07-10 |
| CN111395186B CN111395186B (en) | 2021-10-19 |
Family
ID=71429425
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202010251099.8A Active CN111395186B (en) | 2020-04-01 | 2020-04-01 | A kind of temporary pier support method for long-span steel-concrete composite beam cable-stayed bridge |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN111395186B (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN112411386A (en) * | 2020-11-26 | 2021-02-26 | 中铁三局集团有限公司 | Method for erecting and dismantling continuous beam No. 0 block reinforced concrete-filled steel tube support |
| CN113174850A (en) * | 2021-04-25 | 2021-07-27 | 中建七局第四建筑有限公司 | Cable-stayed bridge supporting body |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2309217C2 (en) * | 2005-11-23 | 2007-10-27 | Открытое акционерное общество ОАО "Институт по изысканиям и проектированию мостовых переходов"-"Гипротрансмост" | Method and device for bridge pier reconstruction during pier girder repair or support parts replacement |
| CN201250386Y (en) * | 2008-09-10 | 2009-06-03 | 中铁八局集团第一工程有限公司 | Rocker-bar bearing for resisting wind and provisionally buttressing in cable-stayed bridge cantilever construction |
| CN202865734U (en) * | 2012-09-07 | 2013-04-10 | 江苏中兴水务有限公司 | Novel ship shore approach bridge supporting seat for water intaking pump vessel |
| CN204455790U (en) * | 2014-12-09 | 2015-07-08 | 中交公路规划设计院有限公司 | Improve the cable stayed bridge of outer end bay without suspension cable of lateral dynamics stress performance |
| CN207109546U (en) * | 2017-07-14 | 2018-03-16 | 广西路桥工程集团有限公司 | A kind of interim hinge device of arch rib |
| CN208899315U (en) * | 2018-08-24 | 2019-05-24 | 南京万通城市建设设计咨询有限公司 | The Multifunctional bridge beam support of hyperspace displacement can be achieved |
| CN110042769A (en) * | 2019-06-03 | 2019-07-23 | 四川公路桥梁建设集团有限公司 | Auxiliary span full-cantilever assembling construction method for composite beam cable-stayed bridge |
-
2020
- 2020-04-01 CN CN202010251099.8A patent/CN111395186B/en active Active
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2309217C2 (en) * | 2005-11-23 | 2007-10-27 | Открытое акционерное общество ОАО "Институт по изысканиям и проектированию мостовых переходов"-"Гипротрансмост" | Method and device for bridge pier reconstruction during pier girder repair or support parts replacement |
| CN201250386Y (en) * | 2008-09-10 | 2009-06-03 | 中铁八局集团第一工程有限公司 | Rocker-bar bearing for resisting wind and provisionally buttressing in cable-stayed bridge cantilever construction |
| CN202865734U (en) * | 2012-09-07 | 2013-04-10 | 江苏中兴水务有限公司 | Novel ship shore approach bridge supporting seat for water intaking pump vessel |
| CN204455790U (en) * | 2014-12-09 | 2015-07-08 | 中交公路规划设计院有限公司 | Improve the cable stayed bridge of outer end bay without suspension cable of lateral dynamics stress performance |
| CN207109546U (en) * | 2017-07-14 | 2018-03-16 | 广西路桥工程集团有限公司 | A kind of interim hinge device of arch rib |
| CN208899315U (en) * | 2018-08-24 | 2019-05-24 | 南京万通城市建设设计咨询有限公司 | The Multifunctional bridge beam support of hyperspace displacement can be achieved |
| CN110042769A (en) * | 2019-06-03 | 2019-07-23 | 四川公路桥梁建设集团有限公司 | Auxiliary span full-cantilever assembling construction method for composite beam cable-stayed bridge |
Non-Patent Citations (2)
| Title |
|---|
| 刘士林: "《斜拉桥》", 31 August 2002 * |
| 张喜刚: "苏通大桥总体设计", 《苏通大桥总体设计》 * |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN112411386A (en) * | 2020-11-26 | 2021-02-26 | 中铁三局集团有限公司 | Method for erecting and dismantling continuous beam No. 0 block reinforced concrete-filled steel tube support |
| CN113174850A (en) * | 2021-04-25 | 2021-07-27 | 中建七局第四建筑有限公司 | Cable-stayed bridge supporting body |
Also Published As
| Publication number | Publication date |
|---|---|
| CN111395186B (en) | 2021-10-19 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110331668B (en) | Construction method of bidirectional inclined V-shaped bridge tower of cable-stayed bridge without back cables | |
| CN106702910B (en) | A kind of main girder construction technique of the double rope face low-pylon cable-stayed bridges of double tower | |
| CN110004832B (en) | Large-span cantilever truss type bent cap bracket system and construction method | |
| CN113550230B (en) | Special-shaped arch tower double-cable-plane steel cable-stayed bridge assembly type construction and control method | |
| CN111663449A (en) | Combined cast-in-place box girder support system and construction method | |
| CN105568854B (en) | Shaped form fish-bellied type cast-in-situ steel reinforced concrete box girder construction method waterborne | |
| CN113882238A (en) | Long-span top-supporting cable-aided beam-arch composite rigid-frame bridge and its construction method | |
| CN105970800B (en) | The abutment connecting structure and its construction method of monoblock type combination beam is seamless bridge | |
| CN102691266B (en) | Construction Method of Superelevation Composite Support in Cast-in-place Section of Side Span of Bridge | |
| CN115344936A (en) | A construction method of continuous rigid frame bridge with high piers | |
| CN114592436A (en) | A kind of lower support system of bridge pier cover beam and construction method thereof | |
| CN110184903B (en) | A truss-type prefabricated pipe column assembled bridge pier | |
| CN108374326A (en) | A kind of combined rigid structure steel plate girder bridge pier consolidation construction | |
| CN116065487A (en) | Accurate installation construction method for upper-span high-speed steel box girder | |
| CN206090275U (en) | Assembled rectangular concrete -filled steel tube makes up truss bridge | |
| CN111979891A (en) | A kind of semi-penetrating rectangular steel tube concrete composite truss bridge and construction method | |
| CN111910522A (en) | A beam-arch composite rigid frame lower arch support active jacking auxiliary support construction system | |
| CN117604883B (en) | Steel-concrete composite Y-shaped inclined leg structure and construction method | |
| CN111395186B (en) | A kind of temporary pier support method for long-span steel-concrete composite beam cable-stayed bridge | |
| CN114561865A (en) | Prestressed concrete cover beam based on prefabricated prestressed UHPC shell and its construction technology | |
| CN116084293A (en) | Cast-in-place concrete main arch ring three-angle steel arch frame formwork system and construction method | |
| CN212834992U (en) | A kind of suspension bridge based on long and narrow mountain topography | |
| CN218989851U (en) | Fully assembled steel-concrete plate truss combined bridge | |
| CN217839750U (en) | Steel guide beam for incremental launching construction of large-scale curve steel box girder bridge | |
| CN219586557U (en) | Construction structure of folding section of stiff framework of cast-in-situ box Liang Waizhi |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CP03 | Change of name, title or address |
Address after: 710065 Office Building 27, Chang'an International Enterprise Headquarters, Xifeng Road, High tech Zone, Xi'an City, Shaanxi Province Patentee after: Shaanxi Traffic Control Tongyu Traffic Research Co.,Ltd. Address before: 710100 office building 27, international enterprise headquarters, Chang'an District, Xi'an City, Shaanxi Province Patentee before: Shaanxi Tongyu Highway Research Institute Co.,Ltd. |
|
| CP03 | Change of name, title or address |