CN111389139A - High-efficient intelligent building sprays dust fall system - Google Patents

High-efficient intelligent building sprays dust fall system Download PDF

Info

Publication number
CN111389139A
CN111389139A CN202010205421.3A CN202010205421A CN111389139A CN 111389139 A CN111389139 A CN 111389139A CN 202010205421 A CN202010205421 A CN 202010205421A CN 111389139 A CN111389139 A CN 111389139A
Authority
CN
China
Prior art keywords
spraying
equipment
main control
dust
intelligent building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010205421.3A
Other languages
Chinese (zh)
Inventor
陆欣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN202010205421.3A priority Critical patent/CN111389139A/en
Publication of CN111389139A publication Critical patent/CN111389139A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D47/00Separating dispersed particles from gases, air or vapours by liquid as separating agent
    • B01D47/06Spray cleaning
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01VGEOPHYSICS; GRAVITATIONAL MEASUREMENTS; DETECTING MASSES OR OBJECTS; TAGS
    • G01V8/00Prospecting or detecting by optical means
    • G01V8/10Detecting, e.g. by using light barriers

Landscapes

  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Physics & Mathematics (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Geophysics (AREA)
  • Road Paving Machines (AREA)

Abstract

The invention discloses a high-efficiency intelligent building spraying dust-settling system, and relates to the technical field of building spraying dust-settling. This high-efficient intelligent building sprays dust fall system, including spraying main control equipment, spraying equipment, equipment control unit and the pressure boost unit of intaking, spray main control equipment near closing on the place intake for carry out whole management and control and pipeline pressure boost water source to the system and carry, a plurality of spraying equipment are installed respectively at construction site temporary road roadside. This high-efficient intelligent building sprays dust fall system, through the setting to the system, can spray the dust fall through the automatic moving object that goes on fixed road surface and the road surface that goes on right of infrared detection device, reduced the drawback that ordinary spraying needs manual operation, practiced thrift operating time, increased work efficiency, reduced the waste to the water resource.

Description

High-efficient intelligent building sprays dust fall system
Technical Field
The invention relates to the technical field of building spraying dust suppression, in particular to a high-efficiency intelligent building spraying dust suppression system.
Background
In recent years, indexes of PM10 and PM2.5 in cities are high, haze weather frequently occurs, and dust pollution becomes a main factor of urban air pollution, so that the dust pollution is solved by researching and controlling the dust pollution, implementing a blue-sky defense action plan, continuously enhancing the safety and acquisition of people in ecological environment improvement, and being an urgent need for promoting ecological civilization construction and building beautiful cities.
With the rapid development of urbanization, the construction of urban infrastructure is in a period of high-speed development, the urban area is continuously enlarged, and the pollution condition of waste materials and garbage on the construction site is more and more serious. Wherein the dust on the construction site becomes the main cause of urban air pollution. The main reasons causing dust pollution in construction sites include: building construction raise dust, house removal raise dust and municipal construction raise dust.
Disclosure of Invention
Technical problem to be solved
Aiming at the defects of the prior art, the invention provides a high-efficiency intelligent building spraying dust-settling system, which solves the problem of serious dust emission on a building construction site.
(II) technical scheme
In order to achieve the purpose, the invention is realized by the following technical scheme: a high-efficiency intelligent building spraying dust-settling system comprises a spraying main control device, a spraying device, a device control unit and a water inlet pressurizing unit, wherein the spraying main control device is arranged near a water inlet of a near field, used for carrying out integral management and control on the system and pipeline pressurized water source conveying, a plurality of spraying devices are respectively arranged at the roadside of the temporary road of the construction site, the spraying control unit is electrically connected with a spraying device, an infrared detection device and a secondary control device control unit, a central processing unit is arranged in the device control unit, the main control device control unit is connected with the central processing unit by signals and receives by using a data receiving module in the auxiliary control device control unit, therefore, data collected by the auxiliary control equipment control unit are transmitted to the main control equipment control unit in real time, and effective work is carried out. The central processing unit is electrically connected with the display screen, the data processing module and the data integration module, the data receiving module is electrically connected with the data processing module, the data processing module is electrically connected with the data integration module, the data integration module displays the processed and integrated data on the display screen and transmits the information to the central processing unit, and the central processing unit transmits instructions to the spraying equipment. The central processing unit is also electrically connected with a fault self-checking unit for effectively controlling the spraying of the faults of the secondary control equipment and recording information.
Preferably, the main control equipment is electrically connected with the spraying machine through a water pipeline, and pressure spraying water is provided for the spraying equipment through a water source pressurizing unit in the main control equipment.
Preferably, the main control equipment is electrically connected with the auxiliary control equipment and connected with the spraying machine, and the auxiliary control equipment is controlled to spray and reduce dust on the road surface through a processor in the main control equipment.
Preferably, the central processing unit in the main control device is electrically connected with the auxiliary control device, and the processor in the main control device controls the infrared detection device of the auxiliary control device to perform effective detection, transmission and reception instructions in the set detection distance.
Preferably, the main control equipment is reserved with a water source access port, an output port and a power supply access port for accessing and outputting a power supply and a water source.
Preferably, the spraying equipment comprises a spraying port, an infrared detection device, a growth regulation spraying pipe and an equipment control unit, wherein the infrared detection device is uniformly distributed on the spraying equipment from top to bottom, when a moving object exists on the road surface, the object blocks an infrared signal so as to judge the length and the height of the object, the equipment control unit feeds the signal back to a central processing unit of the main control equipment, and after the judgment of the central processing unit, an instruction is transmitted to carry out high-pressure spraying work on the object.
Preferably, the spraying opening is formed by vertically and uniformly dividing six spraying holes, and effective spraying operation can be carried out on objects or pavements.
Preferably, the central processing unit receives the instruction of a manager, adjusts the spraying control, and can automatically send signals to the moving objects and specified time to perform spraying dust suppression work on the road surface and the moving objects on the road.
(III) advantageous effects
The invention provides a high-efficiency intelligent building spraying dust-settling system. The method has the following beneficial effects: this high-efficient intelligent building sprays dust fall system, through the setting to the system, can spray the dust fall through the automatic moving object that goes on fixed road surface and the road surface that goes on right of infrared detection device, reduced the drawback that ordinary spraying needs manual operation, practiced thrift operating time, increased work efficiency, reduced the waste to the water resource.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic diagram of the control unit of the apparatus of the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-2, the present invention provides a technical solution: a high-efficiency intelligent building spraying dust-settling system comprises a spraying main control device, a spraying device, a device control unit and a water inlet pressurizing unit, wherein the spraying device comprises a spraying port, an infrared detection device, a growth regulation spraying pipe and a device control unit, the spraying port is formed by uniformly dividing six spraying holes up and down, and can effectively spray objects or pavements, the infrared detection device is uniformly divided on the spraying device up and down, when moving objects exist on the pavements, the objects block infrared signals, so that the height of the objects is judged, the device control unit feeds the signals back to a central processing unit of the main control device, after the signals are judged by the processor, a transmission instruction is transmitted to perform high-pressure spraying work on the objects, the main control device is reserved with a water source access port, an output port and a power source access port, a power source is accessed and output, and the central processing unit in the main control device is electrically connected with, the infrared detection device of the auxiliary control device is controlled to effectively detect, transmit and receive instructions in a set detection distance through a processor in the main control device, the main control device is electrically connected with the auxiliary control device and connected with a spraying machine, the auxiliary control device is controlled to spray and dust fall on a road surface through the processor in the main control device, the main control device is electrically connected with the spraying machine through a water pipeline, pressure spraying water is provided for the spraying device through a water source pressurizing unit in the main control device, the spraying main control device is arranged near a water intake of a near site and used for integrally controlling the system and conveying a pipeline pressurizing water source, a plurality of spraying devices are respectively arranged on the temporary road side of a construction site, movable objects and a spraying coverage area on the road surface are effectively monitored and sprayed, and the device control units are all electrically connected with the spraying device, the infrared detection device and the auxiliary control device control unit, the device control unit is internally provided with a central processing unit which receives instructions of managers and adjusts the spraying control, can automatically send signals to moving objects and specified time to spray dust fall work on the road surface and moving objects on the road, and the main control device control unit is in signal connection with the central processing unit and receives the signals by utilizing a data receiving module in the auxiliary control device control unit, so that the data collected by the auxiliary control device control unit is transmitted to the main control device control unit in real time to effectively work. The central processing unit is electrically connected with the display screen, the data processing module and the data integration module, the data receiving module is electrically connected with the data processing module, the data processing module is electrically connected with the data integration module, the data integration module displays the processed and integrated data on the display screen and transmits the information to the central processing unit, and the central processing unit transmits instructions to the spraying equipment. The central processing unit is also electrically connected with a fault self-checking unit for effectively controlling the spraying of the faults of the auxiliary control equipment and recording information.
To sum up, this high-efficient intelligent building sprays dust fall system, through the setting to the system, can spray the dust fall through infrared detection device automatic going on fixed road surface right and the moving object on the road surface, reduced ordinary drawback that needs manual operation that sprays, practiced thrift operating time, increased work efficiency, reduced the waste to the water resource.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (8)

1. A high-efficiency intelligent building spraying dust-settling system is characterized by comprising a spraying main control device, a spraying device, a device control unit and a water inlet pressurizing unit, wherein the spraying main control device is arranged near a water inlet of a near site and used for integrally controlling the system and conveying a pipeline pressurizing water source, a plurality of spraying devices are respectively arranged on the roadside of a temporary road of a construction site and used for effectively monitoring and spraying movable objects and a spraying coverage area on the road surface, the device control unit is electrically connected with the spraying device, an infrared detection device and a secondary control device control unit, a central processing unit is arranged in the device control unit, the main control device control unit is in signal connection with the central processing unit and receives data by using a data receiving module in the secondary control device control unit, so that the data collected by the secondary control device control unit is transmitted to the main control device control unit in real time, and performing effective work. The central processing unit is electrically connected with the display screen, the data processing module and the data integration module, the data receiving module is electrically connected with the data processing module, the data processing module is electrically connected with the data integration module, the data integration module displays the processed and integrated data on the display screen and transmits the information to the central processing unit, and the central processing unit transmits instructions to the spraying equipment. The central processing unit is also electrically connected with a fault self-checking unit for effectively controlling the spraying of the faults of the secondary control equipment and recording information.
2. The high-efficiency intelligent building spraying dust-settling system of claim 1, which is characterized in that: the main control equipment is electrically connected with the spraying machine through a water pipeline, and pressure spraying water is provided for the spraying equipment through a water source pressurizing unit in the main control equipment.
3. The high-efficiency intelligent building spraying dust-settling system of claim 1, which is characterized in that: the main control equipment is electrically connected with the auxiliary control equipment and connected with the spraying machine, and the auxiliary control equipment is controlled to spray and reduce dust on the road surface through a processor in the main control equipment.
4. The high-efficiency intelligent building spraying dust-settling system of claim 1, which is characterized in that: the central processing unit in the main control equipment is electrically connected with the auxiliary control equipment, and the processor in the main control equipment controls the infrared detection device of the auxiliary control equipment to effectively detect, transmit and receive instructions in the set detection distance.
5. The high-efficiency intelligent building spraying dust-settling system of claim 1, which is characterized in that: the main control equipment is reserved with a water source access port, an output port and a power supply access port for accessing and outputting a power supply and a water source.
6. The high-efficiency intelligent building spraying dust-settling system of claim 1, which is characterized in that: the spraying equipment comprises a spraying port, an infrared detection device, a growth regulation spraying pipe and an equipment control unit, wherein the infrared detection device is uniformly distributed on the spraying equipment from top to bottom, when a moving object exists on a road surface, the object blocks an infrared signal, so that the length and the height of the object are judged, the equipment control unit feeds the signal back to a central processing unit of the main control equipment, and after the judgment of the processor, a transmission instruction is transmitted to carry out high-pressure spraying work on the object.
7. The high-efficiency intelligent building spraying dust-settling system of claim 1, which is characterized in that: the spraying port is formed by uniformly dividing six spraying holes up and down, and can effectively spray objects or pavements.
8. The high-efficiency intelligent building spraying dust-settling system of claim 1, which is characterized in that: the central processing unit receives the instruction of a manager, adjusts the spraying control, and can automatically send signals to the moving objects and specified time to spray and reduce dust for the moving objects on the road surface and the road.
CN202010205421.3A 2020-03-23 2020-03-23 High-efficient intelligent building sprays dust fall system Pending CN111389139A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010205421.3A CN111389139A (en) 2020-03-23 2020-03-23 High-efficient intelligent building sprays dust fall system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010205421.3A CN111389139A (en) 2020-03-23 2020-03-23 High-efficient intelligent building sprays dust fall system

Publications (1)

Publication Number Publication Date
CN111389139A true CN111389139A (en) 2020-07-10

Family

ID=71416355

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010205421.3A Pending CN111389139A (en) 2020-03-23 2020-03-23 High-efficient intelligent building sprays dust fall system

Country Status (1)

Country Link
CN (1) CN111389139A (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AT409724B (en) * 2001-04-19 2002-10-25 Scheuch Gmbh Exhaust gas cleaning assembly has at least two successive filter stages, using spray scrubber or wet electro-filter and biological filter with temperature control
CN201959687U (en) * 2011-03-18 2011-09-07 鞍山市普天冶金成套设备有限公司 Automatic spraying dust remover
CN103977659A (en) * 2014-05-30 2014-08-13 济南东之林智能软件有限公司 Water-spray type dust suppression system and control device thereof
WO2016085032A1 (en) * 2014-11-24 2016-06-02 오홍근 Dust collection system
CN108096978A (en) * 2017-12-29 2018-06-01 郑州智谷工业技术有限公司 A kind of construction site Environmental-protecting dust-removing system
CN108646601A (en) * 2018-05-15 2018-10-12 安徽天卓信息技术有限公司 A kind of wisdom building site atomizing spray control system based on Internet of Things
CN109566184A (en) * 2019-01-21 2019-04-05 高晟邺 A kind of outdoor double remote air cleaning flower casees of pressure
CN208943727U (en) * 2018-05-09 2019-06-07 陕西科美机电设备有限公司 Mine infrared Water-gas linkage atomizing dust removing device
CN110013718A (en) * 2019-04-09 2019-07-16 河南小威环境科技有限公司 A kind of dust control and governing system and method
CN210145725U (en) * 2019-04-11 2020-03-17 中建三局第三建设工程有限责任公司 Automatic spraying and dust falling system for construction site

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AT409724B (en) * 2001-04-19 2002-10-25 Scheuch Gmbh Exhaust gas cleaning assembly has at least two successive filter stages, using spray scrubber or wet electro-filter and biological filter with temperature control
CN201959687U (en) * 2011-03-18 2011-09-07 鞍山市普天冶金成套设备有限公司 Automatic spraying dust remover
CN103977659A (en) * 2014-05-30 2014-08-13 济南东之林智能软件有限公司 Water-spray type dust suppression system and control device thereof
WO2016085032A1 (en) * 2014-11-24 2016-06-02 오홍근 Dust collection system
CN108096978A (en) * 2017-12-29 2018-06-01 郑州智谷工业技术有限公司 A kind of construction site Environmental-protecting dust-removing system
CN208943727U (en) * 2018-05-09 2019-06-07 陕西科美机电设备有限公司 Mine infrared Water-gas linkage atomizing dust removing device
CN108646601A (en) * 2018-05-15 2018-10-12 安徽天卓信息技术有限公司 A kind of wisdom building site atomizing spray control system based on Internet of Things
CN109566184A (en) * 2019-01-21 2019-04-05 高晟邺 A kind of outdoor double remote air cleaning flower casees of pressure
CN110013718A (en) * 2019-04-09 2019-07-16 河南小威环境科技有限公司 A kind of dust control and governing system and method
CN210145725U (en) * 2019-04-11 2020-03-17 中建三局第三建设工程有限责任公司 Automatic spraying and dust falling system for construction site

Similar Documents

Publication Publication Date Title
CN110189058B (en) Municipal environment management control system based on block chain
CN105607561A (en) Constructional engineering environment monitoring device
CN102641636A (en) High-rise water spray dust-setting device for controlling PM2.5 air quality from exceeding standard
CN102409720A (en) Water-saving cleaning system for large-scale photovoltaic array and control method thereof
CN116234131A (en) Street lamp monitoring system based on Internet of things and control method thereof
CN114493546A (en) Building waterproof network operation system for smart city planning and design and operation method thereof
CN202230376U (en) Transportation energy management and control system
CN111389139A (en) High-efficient intelligent building sprays dust fall system
CN203034480U (en) Urban underground public pipeline
CN202370032U (en) Large-scale photovoltaic array water-saving cleaning system
CN104597851A (en) Intelligent orchard environment adjustment and control system
CN2534767Y (en) City public lighting monitoring system
CN212305731U (en) Wisdom street lamp network management system
CN211189559U (en) Full-automatic full-coverage spraying device
CN206235615U (en) Cabin formula automatic monitor station
CN107013876A (en) A kind of wisdom street lamp with radio frequency recognition function
CN211386279U (en) Sled dress formula kitchen garbage is processing workstation on spot
CN112053258A (en) Based on municipal works construction project wisdom building site environmental monitoring management system
CN110801695A (en) Full-automatic full-coverage spraying device
CN213777324U (en) Wireless automatic monitoring device for leakage of conveying pipeline
CN212081072U (en) Green intelligent chemical ground dust fall lighting system
CN101500357A (en) Center control system
CN216411937U (en) Wisdom building site atomizing sprays control system based on thing networking
CN205276430U (en) High -rise building rainwater recoverer
CN114123272B (en) Intelligent energy management system and method suitable for urban and rural power grid

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200710