CN111355270B - Island micro-grid group capacity optimization configuration method - Google Patents
Island micro-grid group capacity optimization configuration method Download PDFInfo
- Publication number
- CN111355270B CN111355270B CN202010247083.XA CN202010247083A CN111355270B CN 111355270 B CN111355270 B CN 111355270B CN 202010247083 A CN202010247083 A CN 202010247083A CN 111355270 B CN111355270 B CN 111355270B
- Authority
- CN
- China
- Prior art keywords
- power
- load
- microgrid
- shortage
- grid
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/38—Arrangements for parallely feeding a single network by two or more generators, converters or transformers
- H02J3/46—Controlling of the sharing of output between the generators, converters, or transformers
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
The invention discloses a capacity optimization configuration method for an island micro-grid group. According to the method, firstly, renewable energy sources and energy storage devices are reasonably distributed according to regional conditions, resources and loads of different islands, and the pumped storage power station is combined with a storage battery to form an energy storage system of an island micro-grid group together by utilizing the characteristics of low unit capacity cost, long service life, high reliability and the like of the pumped storage power station so as to maintain the power balance of the micro-grid group and inhibit the uncertainty fluctuation of the renewable energy sources, then the operation rule of the island micro-grid group is formulated by taking 100% green energy power supply as a target, and a coordination control strategy of the island micro-grid group is provided; and finally, optimizing the capacity target value by using an NSGA-II algorithm to obtain an optimal configuration scheme of the island micro-grid group for realizing the 100% green energy power supply target. The invention solves the problem of environmental pollution caused by the conventional fossil fuel units supplying power to islands.
Description
Technical Field
The invention belongs to the technical field of micro-grids of power systems, and particularly relates to a sea island micro-grid group capacity optimal configuration method based on a 100% green energy power supply control strategy.
Background
The existing power supply mode for island mainly comprises the erection of submarine cables or the power supply by conventional fossil fuel units such as diesel generators and gas turbines. But the engineering and maintenance costs for laying the submarine cable are high; the conventional fuel unit is difficult to power and transport and can bring serious pollution problems to the fragile island ecological environment, if renewable energy sources on the island can be fully utilized to supply power to local loads, the use of the conventional fuel unit can be reduced, but the volatility, randomness and intermittence of the renewable energy sources such as wind, light and the like cause uncertainty of fan and photovoltaic power generation, an energy storage device needs to be configured to inhibit the random fluctuation of the output of the fan and the photovoltaic device, so that the reasonable configuration of the capacities of the renewable energy sources, the energy storage device and the conventional fuel unit in the island micro-grid (MG) is the most critical step for successfully constructing the island micro-grid.
At present, when the configuration problem of the island micro-grid is researched, a conventional fuel unit is mostly used as a system for standby. Some scholars establish an objective function for minimizing the emission of pollution gas, indirectly improve the power supply proportion of renewable energy sources in a micro-grid by reasonably configuring the capacity of a conventional fuel unit, but still include the conventional fuel unit, and cannot really realize the full load requirement completely supplied by the renewable energy sources. The research does not contain a conventional fuel unit to serve as a system standby, namely when 100% of green energy is used for supplying power to the island micro-grid group, the energy storage device is a key factor for ensuring the stable and reliable operation of the system. The storage battery is still used as a main energy storage device during planning of the current micro-grid, but the storage battery has the problems of high construction cost, short service life, difficult operation and maintenance and the like, if the storage battery is configured on a large scale to ensure the power supply reliability of the island micro-grid group, the total cost is increased inevitably, and the small pumped storage power station has low unit capacity cost, long service life cycle and high reliability. Furthermore, the scholars indicate that it is difficult for a single small autonomous power system to guarantee all load demands by generating power from renewable energy sources alone.
According to the invention, firstly, renewable energy sources and energy storage devices are reasonably distributed according to the conditions of regional conditions, resources, loads and the like of different islands, and an island micro-grid group optimization configuration model consisting of micro-grids with different functional types is constructed; and then, aiming at realizing 100% green energy power supply, making a corresponding operation rule and providing a coordination control strategy of the island micro-grid group. And finally, solving a capacity optimization configuration model of the island micro-grid group by adopting an improved Non-inferior ordering Genetic Algorithm (NSGA-II) to obtain a configuration scheme for supplying power to the island load by 100% of green energy.
Disclosure of Invention
Aiming at the problem of the existing island micro-grid in realizing 100% green energy power supply, the invention provides a island micro-grid group capacity optimal configuration method based on a 100% green energy power supply control strategy, so as to effectively solve the problem of environmental pollution caused by the conventional fossil fuel units to the island power supply.
Therefore, the invention adopts the following technical scheme: a capacity optimization configuration method for an island micro-grid group comprises the following steps:
step 1), providing a specific power supply and energy storage device configuration scheme of a resource-enriched micro-grid and a high-load proportional micro-grid according to regional conditions, resources and load conditions of different islands; the resource-enriched micro-grid and the high-load proportion micro-grid are interconnected through a submarine cable to form a sea-island micro-grid group;
step 2), establishing a micro-grid group operation rule;
step 3), providing specific models of the power supply and the energy storage device;
step 4), providing a target function and constraint conditions for capacity optimization configuration of the island microgrid group;
step 5), providing a coordination control strategy for 100% green energy power supply of the island microgrid group;
and 6) carrying out model solution on the island microgrid group by adopting an improved Non-inferior sequencing Genetic Algorithm (NSGA-II).
The operation rules and the control strategy of the micro-grid group provided by the invention can coordinate the optimized operation among multiple micro-grids, promote the power mutual aid among the micro-grids of different power types, can be applied to island micro-grid groups, can also be popularized to the planning design of the micro-grid group in regions with rich renewable energy on the continents, and provide engineering reference for improving the power supply occupation ratio of the renewable energy for the micro-grid group.
In addition to the above-mentioned optimal configuration method, in step 1),
according to regional conditions, resources and load conditions of different islands, a resource-enriched microgrid is constructed on an island (namely a resource-enriched island) rich in renewable energy, and a plurality of wind generating sets and photovoltaic devices are configured; selecting a storage battery as an energy storage device on a resource enrichment island without building a pumped storage power station, and setting the resource enrichment type microgrid as MG1Let t period MG1The power generation powers of the inner wind generating set and the photovoltaic device are respectivelyLoaded withMixing MG1Is set as the source-to-load net power differenceConstructing a pumped storage power station as an energy storage device on a resource enrichment island with the pumped storage power station, and setting the resource enrichment type micro-grid as MG2Let t period MG2The power generation powers of the inner wind generating set and the photovoltaic device are respectivelyLoaded withMG2Is set as the source-to-load net power difference
In addition to the above-mentioned optimal configuration method, in step 1),
a high-load-ratio microgrid is constructed on islands with concentrated loads and is set as MG3In view of the secondary problems of noise, heat island effect and the like caused by the development of renewable energy sources such as wind, light and the like and the limited available area of small and medium-sized islands, a wind turbine set is not installed, a photovoltaic device is installed on the roof of a part of buildings only, a certain amount of storage batteries are configured to improve the power supply reliability of important loads in a load accumulation area, and the load in a time period of t is set asThe generated power of the photovoltaic device isThen MG3A source-to-load net power difference ofSuppose MG3The photovoltaic device is not enough to meet the power demand of the load accumulation area, only plays a role in partially relieving the power consumption voltage of the load accumulation area, and has
As a supplement to the above optimal configuration method, the operation rule of the microgrid group in step 2) is as follows:
rule one is as follows: the power generated by the renewable energy sources of each microgrid is preferentially supplied to the loads in the respective system;
rule two: when the resource-enriched micro-grid still has excess power after meeting the self load demand, the excess power is preferentially supplied to the high-load proportion micro-grid to meet the power consumption demand of the load accumulation area so as to improve the direct consumption rate of renewable energy sources, rather than charging the self energy storage device firstly;
rule three: in a discharging state, setting the priority of the energy storage device in the resource-enriched microgrid to be higher than that of the energy storage device in the high-load proportion microgrid, and according to the rule, when the renewable energy cannot meet the load requirement of the microgrid group, firstly, discharging by the energy storage device of the resource-enriched microgrid to compensate the power shortage of the microgrid group, and only using the energy storage device of the high-load proportion microgrid as the final reserve of a load gathering area; in a charging state, setting the priority of an energy storage device in the resource-enriched microgrid to be lower than that of an energy storage device in the high-load proportion microgrid, and preferentially absorbing the excess power by the energy storage device in the high-load proportion microgrid when the generated energy of the renewable energy exceeds the load requirement according to the rule so as to ensure that the energy storage device has sufficient reserve for a load gathering area;
rule four: when the resource-enriched micro-grid and the high-load proportion micro-grid have power shortage at the same time, the energy storage device compensates the power shortage of the high-load proportion micro-grid preferentially, namely, the power demand of a load center is met firstly; meanwhile, in order to ensure the power supply reliability of a load center, an energy storage device of the high-load proportion type micro-grid is set to supply power only to a load gathering area;
rule five: even if the micro-grid group is connected with a continental main grid, in order to achieve the aim of 100% green energy power supply of the micro-grid group, unidirectional characteristics of power transmission of the micro-grid group and the main grid are set, namely only the micro-grid group is allowed to transmit surplus power to the main grid, and electricity purchasing to the main grid is not allowed.
In addition to the above-mentioned optimal configuration method, in step 3),
the photovoltaic power generation model is as follows: Atand TRespectively the generated power of the photovoltaic device, the actual irradiance and the actual temperature of the photovoltaic component in the period of tSatisfy the requirement of The maximum output power of the photovoltaic device is the t period; r isPVIs the energy conversion efficiency of the photovoltaic device; pratedIs the rated power of the photovoltaic device; a. theratedIs the nominal irradiance of the photovoltaic device; alpha is alphaPIs the power temperature coefficient; t isstIs the temperature of the photovoltaic device under standard test conditions;
for a wind turbine, the actual wind speed model is:v (t) andthe wheel hub height of the fan is t periods respectivelyWind speed at the wind speed and wind speed at the crosswind point; h and HrefThe height of a fan hub wheel and the height of a wind measuring point are respectively; alpha is a surface roughness description factor; the generated power of the wind turbine set in the time period t is as follows;whereinFor the generated power of the wind turbine for a period t,satisfy the requirement of The maximum output power of the wind turbine set; pr、vr、vinAnd voutThe rated power, rated wind speed, cut-in wind speed and cut-out wind speed of the wind turbine set are respectively.
In addition to the above-mentioned optimal configuration method, in step 3), the relationship between the state of charge and the charge/discharge power of the storage battery isWherein, delta t is a time interval, and the state of charge and the power of the storage battery in the period of t are respectively SoCt、The power is negative during charging and positive during discharging; etac、ηdRespectively charge and discharge efficiency; ebThe rated capacity of the storage battery; the state of charge of the storage battery is kept within a safe range to meet the SoCmin≤SoCt≤SoCmax,SoCmax、SoCminUpper and lower limits of the state of charge, respectively; the charging and discharging power of the storage battery is limited by the maximum charging and discharging power, so as to meet the requirementsRated maximum charging and discharging power of the storage battery respectively, haveEpsilon is the ratio of the maximum charging and discharging power of the storage battery to the rated capacity.
For a pumped storage power station, in order to save construction cost, seawater is used as a lower reservoir of the pumped storage power station, a dual-water-channel pumped storage system which is beneficial to adjusting system voltage and keeping stable frequency is used, the pumped storage power station comprises a water pump and a hydroelectric generating set, the water pump of the pumped storage power station pumps the seawater to an (upper) reservoir by using excess power to be in a charging state of the pumped storage power station, and the pumping power of the water pump isSet to a negative value, i.e.Satisfy-WhereinA binary integer variable for determining whether the pumped storage power station is in a charging state at a time interval of tOtherwise The upper limit value and the lower limit value are rated for the pumping power of the water pump respectively; when the micro-grid group has power shortage and needs the pumped storage power station to generate power, the reservoir discharges water to drive the water turbine set to generate power, and the generating power of the water turbine set isSet to a positive value, satisfy the constraintWhereinA binary integer variable for judging whether the pumped storage power station is in a power generation state or not at the time of t time periodOtherwise Andsatisfy the requirement of The upper limit value and the lower limit value are rated for the generating power of the hydraulic turbine set respectively; the water quantity change relationship of the reservoir is as follows:wherein, delta t is a time interval, and the water quantity of the reservoir in the t period is Wt,WtSatisfies Wmin≤Wt≤Wmax,Wmax、WminThe maximum and minimum water storage capacity of the reservoir respectively; k is a radical ofP、kTThe water quantity and power ratio in the charging state and the power generation state is respectively.
As a supplement to the above optimal configuration method, the specific content of step 4) is as follows:
defining a self-power rate R of a microgrid groupselThe percentage of the renewable energy output meeting the load requirement in the whole year is represented, and the calculation formula is as follows:whereinThe load power value is the load power value cut off by the microgrid group in the T period because the microgrid group cannot meet the load demand, delta T is a time interval, and T is the total time period number; when all renewable energy sources and energy storage output of the microgrid group cannot meet load requirements, the load of the part with power shortage is cut off, so that R is causedselLess than 100%, so RselCan represent the proportion of renewable energy power supply meeting the load demand if RselWhen the load reaches 100%, the aim that the load is completely supplied with power by green energy sources can be realized; furthermore, the system satisfies the power constraint:whereinFor the power selling power of the micro-grid group to the main grid in the time period t,subscript i in (A) represents MGiThe charge and discharge power of the internal storage battery,and the sum of the charging and discharging power of all storage batteries in the microgrid group in the t period is represented.
As a supplement to the above optimal configuration method, the specific content of step 5) is as follows:
the island micro-grid group formulates a 100% green energy power supply control strategy according to the actual power output and load consumption condition of each micro-grid and the provided operation rule so as to coordinate the optimal scheduling of the micro-grid group; based onAccording to the source load net power difference of the resource enrichment type microgrid, three scenes that the resource enrichment type microgrid can meet self load requirements and cannot meet the self load requirements and the resource enrichment type microgrid has power shortage appear are divided into four execution strategies aiming at 9 situations under three scenes, wherein the 9 situations are respectively as follows:
Case1:resource-enriched micro-grid MG at the moment1And MG2All can meet the self-load requirement, and MG1And MG2Can compensate for MG3Power deficit of;
Case2:resource-enriched micro-grid MG at the moment1And MG2All can meet the self-load requirement, but MG1And MG2Cannot fully compensate for the MG3Power deficit of;
Case3:at the moment, only MG exists in the resource-enriched microgrid2Power shortage occurs but MG1Can compensate for MG2And MG3Power deficit of;
Case4:but do notAt the moment, only MG exists in the resource-enriched microgrid2Power shortage, MG1Can compensate for MG3But compensated for MG3The excess power after the power shortage can not be completely compensatedCompensation MG2Power deficit of;
Case5:and isAt the moment, only MG exists in the resource-enriched microgrid2Power shortage, MG1Cannot fully compensate for the MG3Power shortage of so as not to continue compensating MG2Power deficit of;
Case6:at the moment, only MG exists in the resource-enriched microgrid1Power shortage occurs but MG2Can compensate for MG1And MG3Power deficit of;
Case7:but do notAt the moment, only MG exists in the resource-enriched microgrid1Power shortage, MG2Can compensate for MG3But compensated for MG3Excess power after power shortage cannot fully compensate MG1Power deficit of;
Case8:and isAt the moment, only MG exists in the resource-enriched microgrid1Power shortage, MG2Cannot fully compensate for the MG3Power shortage of so as not to continue compensating MG1Power deficit of;
Case9:resource-enriched micro-grid MG at the moment1And MG2All the power shortage occurs, and the total power shortage of the micro-grid group is
Executing a first strategy: for Case1, Case3 and Case6, the renewable energy source has an excess power ofCalculating the t-period MG1And MG3Inner accumulator (set as B respectivelyESS1And BESS3) Maximum allowable charging power, and MG2The maximum charging power allowed by a water pump of the internal pumping power station is respectivelyAndis provided withIn the formula (I), the compound is shown in the specification,are respectively a storage battery BESS1Storage battery BESS3A nominal maximum charging power;the rated upper limit value is the pumping power of the water pump; SoC (system on chip)1 t、SoC3 tStorage battery B for t periods respectivelyESS1Storage battery BESS3The state of charge of; eb1、Eb3Are respectively a storage battery BESS1Storage battery BESS3Rated capacity of (d); according to rule three, when the energy storage device is charged, the excess power of the microgrid group is firstly supplied to the BESS3Charging, so it should be determined that BESS3Whether the excess power can be completely absorbed or not, if so, the whole excess power is supplied to BESS3Charging, BESS1And the pumped storage power station is in a standby state; if not, BESS3Can only be achieved byAbsorbing the excess power, the rest of the excess power being BESS1Absorbing with pumped storage power station, and judging BESS1And whether the pumped storage power station can fully absorb the portion of power. If B isESS1And the pumped storage power station can completely absorb the rest of the excess power when BESS1And pumped storage power stations, i.e. having available surplus capacityAndall are not zero, BESS1And pumped storage power station according to The ratio of the first and second power absorption units is equal to or greater than the ratio of the first and second power absorption units to the ratio of the second and third power absorption units to the ratio of the first and third power absorption units to the ratio of the second and fourth power absorption units to the ratio of the first and fourth power absorption units to the ratio of the second and fourth power absorption units to the ratio of the first and fourth power absorption units to the remainder of the excess power absorption, otherwise, selecting the remaining capacity absorption units from the two absorption units to absorb the remainder of the excess power; if B isESS1And the residual part of the excess power which can not be completely absorbed by the pumped storage power station can only be used for charging at the maximum allowable charging powerAbsorbing the excessive power, and selling electricity to the main network by the power part which cannot be absorbed by the energy storage device;
and executing a strategy two: aiming at Case2, the power shortage only occurs in the high-load proportional type microgrid, and a t period B is calculatedESS1、BESS3The maximum allowable discharge power and the maximum allowable power generation power of the hydraulic turbine set of the pumped storage power station are respectivelyAnd in the formula (I), the compound is shown in the specification,are respectively a storage battery BESS1Storage battery BESS3Rated maximum discharge power;the upper limit value is the rated power of the water turbine set; according to the third rule, when the energy storage device discharges, the power shortage of the microgrid group is firstly measured by BESS1And discharge compensation of pumped storage power station, so that whether the pumped storage power station and the pumped storage power station can fully compensate MG or not is judged3Power shortage of, if any, when BESS1And pumped storage power stations, i.e. having available surplus capacityAndall are not zero, BESS1And pumped storage power station according to Proportional common discharge compensation MG3Otherwise, selecting the device with available residual capacity among the two to discharge and compensate MG3Power deficit of; if the deficit cannot be fully compensated for, BESS1And the pumped storage power station can only discharge at the maximum power allowed by the pumped storage power stationDischarged and the rest of the power is partially depleted by BESS3Discharge compensation, if the remaining power shortage exceeds BESS3Maximum permitted discharge power, BESS3Can only be achieved byDischarging and cutting off the load of the part with power shortage;
and executing a strategy III: aiming at Case4 and Case7, the power shortage of the microgrid group only exists in the resource-enriched microgrid with the power shortage, the power shortage of the resource-enriched microgrid is the power shortage of the microgrid group, and when B is the power shortage of the microgrid groupESS1When the pumped storage power station can completely compensate the shortage, firstly, the energy storage device in the resource-enriched microgrid with the power shortage discharges to compensate the shortage, and when the shortage cannot be completely compensated, the energy storage device in the other resource-enriched microgrid compensates the rest power shortage part; when B is presentESS1And when the pumped storage power station can not completely compensate the shortage, the pumped storage power station and the pumped storage power station can only compensate the shortageAnddischarge and BESS3Four are MG according to the rule3The load gathering area supplies power, so that the load of the part which cannot compensate the power shortage in the resource-enriched micro-grid is cut off;
and executing a strategy four: for Case5, Case8 and Case9, the power deficit of the microgrid group is given by the MG3And power shortage in resource-rich microgrid, MG in Case5 or Case83Internal power deficit ofOrThe resource-enriched micro-grid has the power shortage ofOrMG in Case93Has a power shortage ofThe resource-enriched micro-grid has the power shortage ofWhen B is presentESS1And the pumped storage power station can fully compensate MG3Judging whether the two can continue to output power to completely compensate the power shortage of the resource-enriched micro-grid or not, if so, completely compensating the power shortage, and BESS1And pumped storage power stations, i.e. having available surplus capacityAndon the premise that all are not zero, BESS1And pumped storage power station according to The proportion of the residual capacity is used for jointly discharging and compensating the whole power shortage, otherwise, a device with available residual capacity is selected from the proportion of the residual capacity and the total power shortage is compensated by discharging; if the two can not completely compensate the power shortage of the resource-enriched micro-grid, BESS1And the pumping power station can onlyAnddischarge, first compensating MG3Is then supplementedPartial power shortage of the resource-enriched micro-grid is compensated, and the load of the residual power shortage part can be cut off only, BESS3According to the fourth rule, the system is always in a standby state; when B is presentESS1And the pumped storage power station cannot fully compensate MG3When the power is in shortage, only the corresponding part of the load can be cut off for the power shortage of the resource-enriched micro-grid, and meanwhile, BESS1And pumped storage power plants toAnddischarge compensated MG3Power shortage of MG3The surplus power is deficient by BESS3Compensation of output if MG3The remaining power shortage still exceeds BESS3Maximum permitted discharge power, BESS3Can only be achieved byApplying force and cutting off MG3There is still a load of the power deficit portion.
As a supplement to the above optimal configuration method, the specific content of step 6) is as follows:
firstly, initializing, and reading data of wind speed, illumination intensity, load and simulation duration;
secondly, generating an initial population I with the scale of 100, setting the individual of the population I as x, wherein the x comprises the fan capacity CWTPhotovoltaic capacity CPVCapacity E of storage batterybAnd reservoir capacity W of pumped storage power stationmaxCapacity of water pumpCapacity of water turbine setI.e. x ═ CWT1,CPV1,Eb1,CWT2,CPV2,Wmax,CPV3,Eb3]Wherein, CWT1、CPV1Are respectively MG1Internal fan and photovoltaic capacity; cWT2、CPV2Are respectively MG2Internal fan and photovoltaic capacity; cPV3Is MG3An internal photovoltaic capacity;
thirdly, calculating a capacity optimization target R according to the 100% green energy power supply coordination control strategy provided in the step 5) by using the capacity information of xselAnd performing non-dominant sorting;
selecting a parent population P from the initial population I by adopting a championship selection method to perform genetic operation to obtain a child population C, wherein the crossing rate is 0.9, and the variation rate is 0.1;
fifthly, calculating a related optimization target value of the child population C, and combining the child population C and the parent population P to form an intermediate population M;
sixthly, performing non-dominated sorting on the intermediate population M to form a population I' with the scale of 100;
seventhly, replacing the parent population P in the fourth step with I', and repeating the fourth step to the sixth step until the iteration times reach 50 to obtain a final optimization result; optimizing the individual x in the generated population I by adopting the NSGA-II algorithm to finally obtain RselAnd (3) obtaining a capacity configuration scheme x when the capacity reaches 100%, namely obtaining a capacity optimization configuration scheme of the island micro-grid group, which realizes the power supply target of 100% green energy for all loads.
The invention has the following beneficial effects: the invention is applied to the planning of the island micro-grid, can reasonably arrange renewable energy sources and energy storage devices according to the conditions of regional conditions, resources, loads and the like of different islands, and combines the pumped storage power station with the storage battery to form an energy storage system of the island micro-grid group together by utilizing the characteristics of low unit capacity cost, long service life, high reliability and the like of the pumped storage power station so as to maintain the power balance of the micro-grid group and inhibit the uncertain fluctuation of the renewable energy sources. The capacity target value is obtained based on the proposed coordination control strategy for 100% green energy power supply of the island micro-grid group, the capacity target value is optimized by using the NSGA-II algorithm, and the island micro-grid group configuration scheme for achieving the 100% green energy power supply target is obtained.
Detailed Description
The invention provides a capacity optimization configuration method for an island micro-grid group, which comprises the following steps:
step 1), providing a power supply and energy storage device configuration scheme for a resource-enriched microgrid and a high-load proportion microgrid according to the conditions of regional conditions, resources, loads and the like of different islands; the resource-enriched micro-grid and the high-load proportion micro-grid are interconnected through a submarine cable to form a sea-island micro-grid group;
step 2), establishing a micro-grid group operation rule;
step 3), providing specific models of the power supply and the energy storage device;
step 4), providing a target function and constraint conditions for capacity optimization configuration of the island microgrid group;
step 5), providing a coordination control strategy for 100% green energy power supply of the island microgrid group;
and 6) carrying out model solution on the island microgrid group by adopting an improved Non-inferior sequencing Genetic Algorithm (NSGA-II).
The specific content of step 1) is as follows:
according to the conditions of regional conditions, resources, loads and the like of different islands, a resource-enriched microgrid is constructed on an island (namely a resource-enriched island) rich in renewable energy, and a plurality of wind turbine units and photovoltaic devices are configured. Selecting a storage battery as an energy storage device on a resource enrichment island without building a pumped storage power station, and setting the resource enrichment type microgrid as MG1Let t period MG1The power generation powers of the inner wind turbine set and the photovoltaic device are respectivelyLoaded withMG1Is set as the source-to-load net power difference Constructing a pumped storage power station as an energy storage device on a resource enrichment island with the pumped storage power station, and setting the resource enrichment type micro-grid as MG2Let t period MG2The power generation powers of the inner wind turbine set and the photovoltaic device are respectivelyLoaded withMG2Is set as the source-to-load net power differenceA high-load-ratio microgrid is constructed on islands with concentrated loads and is set as MG3In view of the secondary problems of noise, heat island effect and the like caused by the development of renewable energy sources such as wind, light and the like and the limited available area of small and medium-sized islands, a wind turbine set is not installed, a photovoltaic device is installed on the roof of a part of buildings only, a certain amount of storage batteries are configured to improve the power supply reliability of important loads in a load accumulation area, and the load in a time period of t is set asThe generated power of the photovoltaic device isThen MG3A source-to-load net power difference ofThe present invention assumes MG3The photovoltaic device is not enough to meet the power demand of the load accumulation area, only plays a role in partially relieving the power consumption voltage of the load accumulation area, and has
The operation rule of the microgrid group in the step 2) is as follows:
rule one is as follows: the power generated by the renewable energy sources of each microgrid is preferentially supplied to the loads in the respective system;
rule two: when the resource-enriched micro-grid still has excess power after meeting the self load demand, the excess power is preferentially supplied to the high-load proportion micro-grid to meet the power consumption demand of the load accumulation area so as to improve the direct consumption rate of renewable energy sources, rather than charging the self energy storage device firstly;
rule three: in a discharging state, setting the priority of the energy storage device in the resource-enriched microgrid to be higher than that of the energy storage device in the high-load proportion microgrid, and according to the rule, when the renewable energy cannot meet the load requirement of the microgrid group, firstly, discharging by the energy storage device of the resource-enriched microgrid to compensate the power shortage of the microgrid group, and only using the energy storage device of the high-load proportion microgrid as the final reserve of a load gathering area; in a charging state, setting the priority of an energy storage device in the resource-enriched microgrid to be lower than that of an energy storage device in the high-load proportion microgrid, and preferentially absorbing the excess power by the energy storage device in the high-load proportion microgrid when the generated energy of the renewable energy exceeds the load requirement according to the rule so as to ensure that the energy storage device has sufficient reserve for a load gathering area;
rule four; when the resource-enriched micro-grid and the high-load proportion micro-grid have power shortage at the same time, the energy storage device compensates the power shortage of the high-load proportion micro-grid preferentially, namely, the power demand of a load center is met first. Meanwhile, in order to ensure the power supply reliability of a load center, an energy storage device of the high-load proportion type micro-grid is set to supply power only to a load gathering area;
a fifth rule; even if the micro-grid group is connected with a continental main grid, in order to achieve the aim of 100% green energy power supply of the micro-grid group, unidirectional characteristics of power transmission of the micro-grid group and the main grid are set, namely only the micro-grid group is allowed to transmit surplus power to the main grid, and electricity purchasing to the main grid is not allowed.
The specific content of step 3) is as follows:
the photovoltaic power generation model adopted by the invention is as follows: Atandrespectively the generated power of the photovoltaic device, the actual irradiance and the actual temperature of the photovoltaic component in the period of t,satisfy the requirement of The maximum output power of the photovoltaic device is the t period; r isPVIs the energy conversion efficiency of the photovoltaic device; pratedIs the rated power of the photovoltaic device; a. theratedIs the nominal irradiance of the photovoltaic device; alpha is alphaPIs the power temperature coefficient; t isstIs the temperature of the photovoltaic device under standard test conditions.
For a wind turbine, the actual wind speed model is:v (t) andrespectively setting the wind speed at the hub wheel height of the fan and the wind speed at a crosswind point in a period t; h and HrefThe height of a fan hub wheel and the height of a wind measuring point are respectively; α is a surface roughness description factor. The generated power of the wind turbine set in the time period t is as follows:whereinFor the generated power of the wind turbine for a period t,satisfy the requirement of The maximum output power of the wind turbine set; pr、vr、vinAnd voutThe rated power, rated wind speed, cut-in wind speed and cut-out wind speed of the wind turbine set are respectively.
For the storage battery, the relation between the charge state and the charge and discharge power isWherein, Delta t is a time interval, and the state of charge and the power of the storage battery in the period of t are respectively The power is negative during charging and positive during discharging; etac、ηdRespectively charge and discharge efficiency; ebThe rated capacity of the storage battery. The state of charge of the storage battery is kept within a safe range to meet the SoCmin≤SoCt≤SoCmax,SoCmax、SoCminUpper and lower limits of the state of charge, respectively; the charging and discharging power of the storage battery is limited by the maximum charging and discharging power, so as to meet the requirements Rated maximum charging and discharging power of the storage battery respectively, haveEpsilon is the ratio of the maximum charging and discharging power of the storage battery to the rated capacity.
For a pumped storage power station, in order to save construction cost, seawater is used as a lower water reservoir of the pumped storage power station, and a dual-water-channel pumped storage system which is beneficial to adjusting system voltage and keeping frequency stable is used, and comprises a water pump and a water-turbine generator set. The water pump of the pumped storage power station pumps the seawater to the upper reservoir by using the excess power to be in the charging state of the pumped storage power station, and the pumping power of the water pump isSet to a negative value, i.e. Satisfy-WhereinA binary integer variable for determining whether the pumped storage power station is in a charging state at a time interval of tOtherwise The rated upper and lower limit values of the pumping power of the water pump; when the micro-grid group has power shortage and needs the pumped storage power station to generate power, the reservoir discharges water to drive the water turbine set to generate power, and the generating power of the water turbine set isSet to a positive value, satisfy the constraintWhereinA binary integer variable for judging whether the pumped storage power station is in a power generation state or not at the time of t time periodOtherwise Andsatisfy the requirement of The upper limit value and the lower limit value are rated for the generating power of the hydraulic turbine set respectively; the water quantity change relationship of the reservoir is as follows:wherein, delta t is a time interval, and the water quantity of the reservoir in the t period is Wt,WtSatisfies Wmin≤Wt≤Wmax,Wmax、WminThe maximum and minimum water storage capacity of the reservoir respectively; k is a radical ofP、kTThe water quantity and power ratio in the charging state and the power generation state is respectively.
The specific content of the step 4) is as follows:
defining a self-power rate R of a microgrid groupselThe percentage of the renewable energy output meeting the load requirement in the whole year is represented, and the calculation formula is as follows:whereinAnd the load power value is the load power value cut off by the micro-grid group in the period t because the micro-grid group cannot meet the load requirement. When all renewable energy sources and energy storage output of the microgrid group cannot meet load requirements, the load of the part with power shortage is cut off, so that R is causedselLess than 100%, so RselCan represent the proportion of renewable energy power supply meeting the load demand if RselAnd when the load reaches 100%, the aim that the load is completely supplied with power by the green energy can be achieved. Furthermore, the system satisfies the power constraint:whereinFor the power selling power of the micro-grid group to the main grid in the time period t,subscript i in (A) represents MGiThe charging and discharging power of the internal storage battery is 1 or 3, soAnd the sum of the charging and discharging power of all storage batteries in the microgrid group in the t period is represented.
The specific content of step 5) is as follows:
the island micro-grid group formulates a 100% green energy power supply control strategy according to the actual power output and load consumption condition of each micro-grid and the provided operation rule so as to coordinate the optimal scheduling of the micro-grid group. Based onAccording to the premise of the resource-enriched micro-grid, the resource-enriched micro-grid can meet the self load demand, one of the resource-enriched micro-grids can not meet the self load demand and the resource-enriched micro-grid appearsThe power grid has three scenes of power shortage, and the power grid is divided into four execution strategies aiming at 9 situations under the three scenes, wherein the 9 situations are respectively as follows:
Case1:resource-enriched micro-grid MG at the moment1And MG2All can meet the self-load requirement, and MG1And MG2Can compensate for MG3Power deficit of;
Case2:resource-enriched micro-grid MG at the moment1And MG2All can meet the self-load requirement, but MG1And MG2Cannot fully compensate for the MG3Power deficit of;
Case3:at the moment, only MG exists in the resource-enriched microgrid2Power shortage occurs but MG1Can compensate for MG2And MG3Power deficit of;
Case4:but do notAt the moment, only MG exists in the resource-enriched microgrid2Power shortage, MG1Can compensate for MG3But compensated for MG3Excess power after power shortage cannot fully compensate MG2Power deficit of;
Case5:and isAt the moment, only MG exists in the resource-enriched microgrid2Power shortage, MG1Cannot fully compensate for the MG3Power shortage of so as not to continue compensating MG2Power deficit of;
Case6:at the moment, only MG exists in the resource-enriched microgrid1Power shortage occurs but MG2Can compensate for MG1And MG3Power deficit of;
Case7:but do notAt the moment, only MG exists in the resource-enriched microgrid1Power shortage, MG2Can compensate for MG3But compensated for MG3Excess power after power shortage cannot fully compensate MG1Power deficit of;
Case8:and isAt the moment, only MG exists in the resource-enriched microgrid1Power shortage, MG2Cannot fully compensate for the MG3Power shortage of so as not to continue compensating MG1Power deficit of;
Case9:resource-enriched micro-grid MG at the moment1And MG2All the power shortage occurs, and the total power shortage of the micro-grid group is
Executing a first strategy: for Case1, Case3 and Case6, the renewable energy source has an excess power ofCalculating the t-period MG1And MG3Inner accumulator (set as B respectivelyESS1And BESS3) Maximum allowable charging power, and MG2The maximum charging power allowed by a water pump of the internal pumping power station is respectivelyAndis provided withIn the formula (I), the compound is shown in the specification,are respectively a storage battery BESS1Storage battery BESS3A nominal maximum charging power;the rated upper limit value is the pumping power of the water pump; SoC (system on chip)1 t、SoC3 tStorage battery B for t periods respectivelyESS1Storage battery BESS3The state of charge of; eb1、Eb3Are respectively a storage battery BESS1Storage battery BESS3Rated capacity of (d); according to rule three, when the energy storage device is charged, the excess power of the microgrid group is firstly supplied to the BESS3Charging, so it should be determined that BESS3Whether the excess power can be completely absorbed or not, if so, the whole excess power is supplied to BESS3Charging, BESS1And the pumped storage power station is in a standby state; if not, BESS3Can only be achieved byAbsorbing the excess power, the rest of the excess power being BESS1Absorbing with pumped storage power station, and judging BESS1And whether the pumped storage power station can fully absorb the portion of power. If B isESS1And the pumped storage power station can completely absorb the rest of the excess power when BESS1And pumped storage power stations, i.e. having available surplus capacityAndall are not zero, BESS1And pumped storage power station according to The ratio of the first and second power absorption units is equal to or greater than the ratio of the first and second power absorption units to the ratio of the second and third power absorption units to the ratio of the first and third power absorption units to the ratio of the second and fourth power absorption units to the ratio of the first and fourth power absorption units to the ratio of the second and fourth power absorption units to the ratio of the first and fourth power absorption units to the remainder of the excess power absorption, otherwise, selecting the remaining capacity absorption units from the two absorption units to absorb the remainder of the excess power; if B isESS1And the residual part of the excess power which can not be completely absorbed by the pumped storage power station can only be used for charging at the maximum allowable charging powerAnd absorbing the excessive power, and selling electricity to the main network by the power part which cannot be absorbed by the energy storage device.
And executing a strategy two: aiming at Case2, the power shortage only occurs in the high-load proportional type microgrid, and a t period B is calculatedESS1、BESS3The maximum allowable discharge power and the maximum allowable power generation power of the hydraulic turbine set of the pumped storage power station are respectivelyAnd in the formula (I), the compound is shown in the specification,are respectively a storage battery BESS1Storage battery BESS3Rated maximum discharge power;the upper limit value is the rated power of the water turbine set; according to the third rule, when the energy storage device discharges, the power shortage of the micro-grid group firstly flows from BESS1And discharge compensation of pumped storage power station, so that whether the pumped storage power station and the pumped storage power station can fully compensate MG or not is judged3Power shortage of, if any, when BESS1And pumped storage power stations, i.e. having available surplus capacityAndall are not zero, BESS1And pumped storage power station according to Proportional common discharge compensation MG3Otherwise, selecting the device with available residual capacity among the two to discharge and compensate MG3Power deficit of; if the deficit cannot be fully compensated for, BESS1And the pumped storage power station can only discharge at the maximum power allowed by the pumped storage power stationDischarged and the rest of the power is partially depleted by BESS3Discharge compensation, if the remaining power shortage exceeds BESS3Maximum permitted discharge power, BESS3Can only be achieved byDischarging and cutting off the load of the part with power shortage.
And executing a strategy III: aiming at Case4 and Case7, the power shortage of the microgrid group only exists in the resource-enriched microgrid with the power shortage, the power shortage of the resource-enriched microgrid is the power shortage of the microgrid group, and when B is the power shortage of the microgrid groupESS1When the pumped storage power station can completely compensate the shortage, firstly, the energy storage device in the resource-enriched microgrid with the power shortage discharges to compensate the shortage, and when the shortage cannot be completely compensated, the energy storage device in the other resource-enriched microgrid compensates the rest power shortage part; when B is presentESS1And when the pumped storage power station can not completely compensate the shortage, the pumped storage power station and the pumped storage power station can only compensate the shortageAnddischarge and BESS3Four are MG according to the rule3The load gathering area supplies power, so that the load of the part which cannot compensate the power shortage in the resource-enriched micro-grid is cut off.
And executing a strategy four: for Case5, Case8 and Case9, the power deficit of the microgrid group is given by the MG3And power shortage in the resource-enriched microgrid. MG in Case5 or Case83Internal power deficit ofOrThe resource-enriched micro-grid has the power shortage ofOrMG in Case93Has a power shortage ofThe resource-enriched micro-grid has the power shortage ofWhen B is presentESS1And the pumped storage power station can fully compensate MG3Judging whether the two can continue to output power to completely compensate the power shortage of the resource-enriched micro-grid or not, if so, completely compensating the power shortage, and BESS1And pumped storage power stations, i.e. having available surplus capacityAndon the premise that all are not zero, BESS1And pumped storage power station according toThe proportion of the residual capacity is used for jointly discharging and compensating the whole power shortage, otherwise, a device with available residual capacity is selected from the proportion of the residual capacity and the total power shortage is compensated by discharging; if the two can not completely compensate the power shortage of the resource-enriched micro-grid, BESS1And the pumping power station can onlyAnddischarge, first compensating MG3Then compensating partial power shortage of the resource-enriched micro-grid, wherein the load of the residual power shortage part can be only cut off, BESS3And according to the fourth rule, the system is always in a standby state. When B is presentESS1And the pumped storage power station cannot fully compensate for MG3When the power is in shortage, only the corresponding part of the load can be cut off for the power shortage of the resource-enriched micro-grid, and meanwhile, BESS1And a pumped storage power station toAnddischarge compensated MG3Power shortage of MG3The surplus power is deficient by BESS3Compensation of output if MG3The remaining power shortage still exceeds BESS3Maximum permitted discharge power, BESS3Can only be achieved byApplying force and cutting off MG3There is still a load of the power deficit portion.
The specific contents of step 6) are as follows;
firstly, initializing, and reading data such as wind speed, illumination intensity, load, simulation duration and the like;
secondly, generating an initial population I with the scale of 100, setting the individual of the population I as x, wherein the x comprises the fan capacity CWTPhotovoltaic capacity CPVCapacity E of storage batterybAnd reservoir capacity W of pumped storage power stationmaxCapacity of water pumpCapacity of water turbine setI.e. x ═ CWT1,CPV1,Eb1,CWT2,CPV2,Wmax,CPV3,Eb3]Wherein, CWT1、CPV1Are respectively MG1Internal fan and photovoltaic capacity; cWT2、CPV2Are respectively MG2Internal fan and photovoltaic capacity; cPV3Is MG3An internal photovoltaic capacity;
thirdly, calculating a capacity optimization target R according to the 100% green energy power supply coordination control strategy provided in the step 5) by using the capacity information of xselAnd performing non-dominant sorting;
selecting a parent population P from the initial population I by adopting a championship selection method to perform genetic operation to obtain a child population C, wherein the crossing rate is 0.9, and the variation rate is 0.1;
fifthly, calculating a related optimization target value of the child population C, and combining the child population C and the parent population P to form an intermediate population M;
sixthly, performing non-dominated sorting on the intermediate population M to form a population I' with the scale of 100;
and seventhly, replacing the parent population P in the fourth step with I', and repeating the fourth step to the sixth step until the iteration times reach 50 to obtain a final optimization result. Optimizing the individual x in the generated population I by adopting the NSGA-II algorithm to finally obtain RselAnd (3) obtaining a capacity configuration scheme x when the capacity reaches 100%, namely obtaining a capacity optimization configuration scheme of the island micro-grid group, which realizes the power supply target of 100% green energy for all loads.
Claims (5)
1. A capacity optimization configuration method for an island micro-grid group is characterized by comprising the following steps:
step 1), providing a power supply and energy storage device configuration scheme for a resource-enriched microgrid and a high-load proportional microgrid according to regional conditions, resources and loads of different islands; the resource-enriched micro-grid and the high-load proportion micro-grid are interconnected through a submarine cable to form a sea-island micro-grid group;
step 2), establishing a micro-grid group operation rule;
step 3), providing specific models of the power supply and the energy storage device;
step 4), providing a target function and constraint conditions for capacity optimization configuration of the island microgrid group;
step 5), providing a coordination control strategy for 100% green energy power supply of the island microgrid group;
step 6), model solution is carried out on the island micro-grid group by adopting an improved non-inferior sequencing genetic algorithm;
in step 1), according to the regional conditions, resources and load conditions of different islands, the island with rich renewable energy sourcesConstructing a resource-enriched microgrid, and configuring a plurality of wind generating sets and photovoltaic devices; selecting a storage battery as an energy storage device on a resource enrichment island without building a pumped storage power station, and setting the resource enrichment type microgrid as MG1Let t period MG1The power generation powers of the inner wind generating set and the photovoltaic device are respectivelyLoaded withMixing MG1Is set as the source-to-load net power difference Constructing a pumped storage power station as an energy storage device on a resource enrichment island with the pumped storage power station, and setting the resource enrichment type micro-grid as MG2Let t period MG2The power generation powers of the inner wind generating set and the photovoltaic device are respectivelyLoaded withMG2Is set as the source-to-load net power difference
Step 1), a high-load-ratio microgrid is constructed on islands with concentrated loads, and the high-load-ratio microgrid is set to MG3In view of noise and heat island effect caused by renewable energy development of wind and light and limited usable area of small and medium-sized islands, wind turbine units are not installed, photovoltaic devices are installed on the roofs of partial buildings only, and a certain amount of photovoltaic devices are configuredThe storage battery improves the power supply reliability of important loads in a load accumulation area, and the load in a time period t is set asThe generated power of the photovoltaic device isThen MG3A source-to-load net power difference ofSuppose MG3The photovoltaic device is not enough to meet the power demand of the load accumulation area, only plays a role in partially relieving the power consumption voltage of the load accumulation area, and has
The operation rule of the microgrid group in the step 2) is as follows:
rule one is as follows: the power generated by the renewable energy sources of each microgrid is preferentially supplied to the loads in the respective system;
rule two: when the resource-enriched micro-grid still has excess power after meeting the self load demand, the excess power is preferentially supplied to the high-load proportion micro-grid to meet the power consumption demand of the load accumulation area so as to improve the direct consumption rate of renewable energy sources, rather than charging the self energy storage device firstly;
rule three: in a discharging state, setting the priority of the energy storage device in the resource-enriched microgrid to be higher than that of the energy storage device in the high-load proportion microgrid, and according to the rule, when the renewable energy cannot meet the load requirement of the microgrid group, firstly, discharging by the energy storage device of the resource-enriched microgrid to compensate the power shortage of the microgrid group, and only using the energy storage device of the high-load proportion microgrid as the final reserve of a load gathering area; in a charging state, setting the priority of an energy storage device in the resource-enriched microgrid to be lower than that of an energy storage device in the high-load proportion microgrid, and preferentially absorbing the excess power by the energy storage device in the high-load proportion microgrid when the generated energy of the renewable energy exceeds the load requirement according to the rule so as to ensure that the energy storage device has sufficient reserve for a load gathering area;
rule four: when the resource-enriched micro-grid and the high-load proportion micro-grid have power shortage at the same time, the energy storage device compensates the power shortage of the high-load proportion micro-grid preferentially, namely, the power demand of a load center is met firstly; meanwhile, in order to ensure the power supply reliability of a load center, an energy storage device of the high-load proportion type micro-grid is set to supply power only to a load gathering area;
rule five: even if the micro-grid group is connected with a continental main grid, in order to achieve the aim of 100% green energy power supply of the micro-grid group, unidirectional characteristics of power transmission of the micro-grid group and the main grid are set, namely only the micro-grid group is allowed to transmit surplus power to the main grid, and electricity purchasing to the main grid is not allowed;
the specific content of step 5) is as follows:
the island micro-grid group formulates a 100% green energy power supply control strategy according to the actual power output and load consumption condition of each micro-grid and the provided operation rule so as to coordinate the optimal scheduling of the micro-grid group; based onAccording to the source load net power difference of the resource enrichment type microgrid, three scenes that the resource enrichment type microgrid can meet self load requirements and cannot meet the self load requirements and the resource enrichment type microgrid has power shortage appear are divided into four execution strategies aiming at 9 situations under three scenes, wherein the 9 situations are respectively as follows:
Case1:resource-enriched micro-grid MG at the moment1And MG2All can meet the self-load requirement, and MG1And MG2Can compensate for MG3Power deficit of;
Case2:resource-enriched micro-grid MG at the moment1And MG2All can meet the self-load requirement, but MG1And MG2Cannot fully compensate for the MG3Power deficit of;
Case3:at the moment, only MG exists in the resource-enriched microgrid2Power shortage occurs but MG1Can compensate for MG2And MG3Power deficit of;
Case4:but do notAt the moment, only MG exists in the resource-enriched microgrid2Power shortage, MG1Can compensate for MG3But compensated for MG3Excess power after power shortage cannot fully compensate MG2Power deficit of;
Case5:and isAt the moment, only MG exists in the resource-enriched microgrid2Power shortage, MG1Cannot fully compensate for the MG3Power shortage of so as not to continue compensating MG2Power deficit of;
Case6:at the moment, only MG exists in the resource-enriched microgrid1Power shortage occurs but MG2Can compensate for MG1And MG3Power deficit of;
Case7:but do notAt the moment, only MG exists in the resource-enriched microgrid1Power shortage, MG2Can compensate for MG3But compensated for MG3Excess power after power shortage cannot fully compensate MG1Power deficit of;
Case8:and isAt the moment, only MG exists in the resource-enriched microgrid1Power shortage, MG2Cannot fully compensate for the MG3Power shortage of so as not to continue compensating MG1Power deficit of;
Case9:resource-enriched micro-grid MG at the moment1And MG2All the power shortage occurs, and the total power shortage of the micro-grid group is
Executing a first strategy: for Case1, Case3 and Case6, the renewable energy source has an excess power ofCalculating the t-period MG1Internal accumulator BESS1And MG3Internal accumulator BESS3Maximum allowable charging powerAnd MG2The maximum charging power allowed by a water pump of the internal pumping power station is respectivelyAndis provided with
In the formula etac、ηdRespectively charge and discharge efficiency; wtThe water quantity of the reservoir in the period t; wmaxThe maximum water storage capacity of the reservoir; k is a radical ofPThe water quantity-power ratio in the charging state is obtained;are respectively a storage battery BESS1Storage battery BESS3A nominal maximum charging power;the rated upper limit value is the pumping power of the water pump; SoC (system on chip)1 t、SoC3 tStorage battery B for t periods respectivelyESS1Storage battery BESS3The state of charge of; eb1、Eb3Are respectively a storage battery BESS1Storage battery BESS3Rated capacity of (d); according to rule three, when the energy storage device is charged, the excess power of the microgrid group is firstly supplied to the BESS3Charging, so it should be determined that BESS3If the excess power can be completely absorbed, the whole excess power is supplied to BESS3Charging, BESS1And the pumped storage power station is in a standby state; if not, BESS3Can only be achieved byAbsorbing the excess power, the rest of the excess power being BESS1Absorbed by the pumped storage power station and judgedBreak BESS1And whether the pumped storage power station can completely absorb the part of power; if B isESS1And the pumped storage power station can completely absorb the rest of the excess power when BESS1And pumped storage power stations, i.e. having available surplus capacityAndall are not zero, BESS1And pumped storage power station according to The ratio of (a) to (b) together absorb the remaining portion of the excess power, otherwise selecting the device having the remaining available capacity to absorb the remaining portion of the excess power; if B isESS1And the residual part of the excess power which can not be completely absorbed by the pumped storage power station can only be used for charging at the maximum allowable charging power Absorbing the excess power;
and executing a strategy two: aiming at Case2, the power shortage only occurs in the high-load proportional type microgrid, and a t period B is calculatedESS1、BESS3The maximum allowable discharge power and the maximum allowable power generation power of the hydraulic turbine set of the pumped storage power station are respectivelyAnd
in the formula (I), the compound is shown in the specification,are respectively a storage battery BESS1Storage battery BESS3Rated maximum discharge power;the upper limit value is the rated power of the water turbine set; k is a radical ofTThe water quantity-power ratio under the power generation state; according to the third rule, when the energy storage device discharges, the power shortage of the microgrid group is firstly measured by BESS1And discharge compensation of pumped storage power station, so that whether the pumped storage power station and the pumped storage power station can fully compensate MG or not is judged3Power shortage of, if any, when BESS1And pumped storage power stations, i.e. having available surplus capacityAndall are not zero, BESS1And pumped storage power station according to Proportional common discharge compensation MG3Otherwise, selecting the device with available residual capacity among the two to discharge and compensate MG3Power deficit of; if the deficit cannot be fully compensated for, BESS1And the pumped storage power station can only discharge at the maximum power allowed by the pumped storage power stationDischarged and the rest of the power is partially depleted by BESS3Discharge compensation, if the remaining power shortage exceeds BESS3Maximum permitted discharge power, BESS3Can only be achieved byDischarging and cutting off the load of the part with power shortage;
and executing a strategy III: aiming at Case4 and Case7, the power shortage of the microgrid group only exists in the resource-enriched microgrid with the power shortage, the power shortage of the resource-enriched microgrid is the power shortage of the microgrid group, and when B is the power shortage of the microgrid groupESS1When the pumped storage power station can completely compensate the shortage, firstly, the energy storage device in the resource-enriched microgrid with the power shortage discharges to compensate the shortage, and when the shortage cannot be completely compensated, the energy storage device in the other resource-enriched microgrid compensates the rest power shortage part; when B is presentESS1And when the pumped storage power station can not completely compensate the shortage, the pumped storage power station and the pumped storage power station can only compensate the shortageAnddischarge and BESS3Four are MG according to the rule3The load gathering area supplies power, so that the load of the part which cannot compensate the power shortage in the resource-enriched micro-grid is cut off;
and executing a strategy four: for Case5, Case8 and Case9, the power deficit of the microgrid group is given by the MG3And power shortage in resource-rich microgrid, MG in Case5 or Case83Internal power deficit ofOrThe resource-enriched micro-grid has the power shortage ofOrMG in Case93Has a power shortage ofThe resource-enriched micro-grid has the power shortage ofWhen B is presentESS1And the pumped storage power station can fully compensate MG3Judging whether the two can continue to output power to completely compensate the power shortage of the resource-enriched micro-grid or not, if so, completely compensating the power shortage, and BESS1And pumped storage power stations, i.e. having available surplus capacityAndon the premise that all are not zero, BESS1And pumped storage power station according to The proportion of the residual capacity is used for jointly discharging and compensating the whole power shortage, otherwise, a device with available residual capacity is selected from the proportion of the residual capacity and the total power shortage is compensated by discharging; if the two can not completely compensate the power shortage of the resource-enriched micro-grid, BESS1And pumped storage power stations can onlyAnddischarge, first compensating MG3Then compensating partial power shortage of the resource-enriched micro-grid, wherein the load of the residual power shortage part can be only cut off, BESS3According to the fourth rule, the system is always in a standby state; when B is presentESS1And the pumped storage power station cannot fully compensate MG3When the power is in shortage, only the corresponding part of the load can be cut off for the power shortage of the resource-enriched micro-grid, and meanwhile, BESS1And a pumped storage power station toAnddischarge compensated MG3Power shortage of MG3The surplus power is deficient by BESS3Compensation of output if MG3The remaining power shortage still exceeds BESS3Maximum permitted discharge power, BESS3Can only be achieved byApplying force and cutting off MG3There is still a load of the power deficit portion.
2. The island microgrid group capacity optimization configuration method of claim 1, characterized in that in step 3),
the photovoltaic power generation model is as follows: andrespectively the generated power of the photovoltaic device, the actual irradiance and the actual temperature of the photovoltaic component in the period of t,satisfy the requirement of The maximum output power of the photovoltaic device is the t period; r isPVIs the energy conversion efficiency of the photovoltaic device; pratedIs the rated power of the photovoltaic device; a. theratedIs the nominal irradiance of the photovoltaic device; alpha is alphaPIs the power temperature coefficient; t isstIs the temperature of the photovoltaic device under standard test conditions;
for a wind turbine, the actual wind speed model is:v (t) andrespectively setting the wind speed at the hub wheel height of the fan and the wind speed at a crosswind point in a period t; h and HrefThe height of a fan hub wheel and the height of a wind measuring point are respectively; alpha is a surface roughness description factor; the generated power of the wind turbine set in the time period t is as follows;whereinFor the generated power of the wind turbine for a period t,satisfy the requirement of The maximum output power of the wind turbine set; pr、vr、vinAnd voutThe rated power, rated wind speed, cut-in wind speed and cut-out wind speed of the wind turbine set are respectively.
3. The island microgrid group capacity optimization configuration method of claim 2, characterized in that in step 3), the relation between the state of charge and the charge and discharge power of the storage battery isWherein, delta t is a time interval, and the state of charge and the power of the storage battery in the period of t are respectively SoCt、Pb tThe power is negative during charging and positive during discharging; etac、ηdRespectively charge and discharge efficiency; ebThe rated capacity of the storage battery; the state of charge of the storage battery is kept within a safe range to meet the SoCmin≤SoCt≤SoCmax,SoCmax、SoCminUpper and lower limits of the state of charge, respectively; the charging and discharging power of the storage battery is limited by the maximum charging and discharging power, and the requirement of the storage battery on the maximum charging and discharging power is met Rated maximum charging and discharging power of the storage battery respectively, haveEpsilon is the ratio of the maximum charging and discharging power of the storage battery to the rated capacity;
for a pumped storage power station, in order to save construction cost, seawater is used as a lower reservoir of the pumped storage power station, a double-water-channel pumped storage system which is beneficial to regulating system voltage and keeping frequency stable is used, the pumped storage system comprises a water pump and a hydroelectric generating set, and the water pump of the pumped storage power station pumps the seawater to the reservoir by using excess power for pumpingThe charging state of the water energy storage power station, at the moment, the pumping power of the water pump isSet to a negative value, i.e. Satisfy the requirement ofWhereinA binary integer variable for determining whether the pumped storage power station is in a charging state at a time interval of tOtherwise The upper limit value and the lower limit value are rated for the pumping power of the water pump respectively; when the micro-grid group has power shortage and needs a pumped storage power station to generate power, the reservoir discharges water to drive the water turbine set to generate power, and the generating power of the water turbine set is PtTSet to a positive value, satisfying the constraint conditionWhereinA binary integer variable for judging whether the pumped storage power station is in a power generation state or not at the time of t time periodOtherwise Andsatisfy the requirement of The upper limit value and the lower limit value are rated for the generating power of the hydraulic turbine set respectively; the water quantity change relationship of the reservoir is as follows:wherein, delta t is a time interval, and the water quantity of the reservoir in the t period is Wt,WtSatisfies Wmin≤Wt≤Wmax,Wmax、WminThe maximum and minimum water storage capacity of the reservoir respectively.
4. The island microgrid group capacity optimization configuration method of claim 1, characterized in that the specific contents of step 4) are as follows:
defining a self-power rate R of a microgrid groupselThe percentage of the renewable energy output meeting the load requirement in the whole year is represented, and the calculation formula is as follows:whereinThe load power value cut off by the microgrid group in the period of t because the microgrid group can not meet the load demand, and delta t is a time intervalT is the total time period number; when all renewable energy sources and energy storage output of the microgrid group cannot meet load requirements, the load of the part with power shortage is cut off, so that R is causedselLess than 100%, so RselCan represent the proportion of renewable energy power supply meeting the load demand if RselWhen the load reaches 100%, the aim that the load is completely supplied with power by green energy sources can be realized; furthermore, the system satisfies the power constraint:whereinFor the power selling power of the micro-grid group to the main grid in the time period t,subscript i in (A) represents MGiThe charge and discharge power of the internal storage battery,representing the sum of the charging and discharging power of all storage batteries in the microgrid group in the period t,a binary integer variable of whether the pumped storage power station is in a charging state or not in a time period t,a binary integer variable of whether the pumped storage power station is in a power generation state or not in a time period t,the power for pumping water by the water pump is provided,the power generated by the water turbine set.
5. The island microgrid group capacity optimization configuration method of claim 4, characterized in that the specific content of step 6) is as follows:
firstly, initializing, and reading wind speed, illumination intensity, load and simulation duration;
secondly, generating an initial population I with the scale of 100, setting the individual of the population I as x, wherein the x comprises the fan capacity CWTPhotovoltaic capacity CPVCapacity E of storage batterybAnd reservoir capacity W of pumped storage power stationmaxCapacity of water pumpCapacity of water turbine setNamely, it is Wherein, CWT1、CPV1Are respectively MG1Internal fan and photovoltaic capacity; cWT2、CPV2Are respectively MG2Internal fan and photovoltaic capacity; cPV3Is MG3An internal photovoltaic capacity;
thirdly, calculating a capacity optimization target R according to the 100% green energy power supply coordination control strategy provided in the step 5) by using the capacity information of xselAnd performing non-dominant sorting;
selecting a parent population P from the initial population I by adopting a championship selection method to perform genetic operation to obtain a child population C, wherein the crossing rate is 0.9, and the variation rate is 0.1;
fifthly, calculating a related optimization target value of the child population C, and combining the child population C and the parent population P to form an intermediate population M;
sixthly, performing non-dominated sorting on the intermediate population M to form a population I' with the scale of 100;
seventhly, replacing the four by IRepeating the parent population P for four to six times until the iteration number reaches 50 to obtain a final optimization result; optimizing the individual x in the generated population I by adopting the NSGA-II algorithm to finally obtain RselAnd (3) a capacity configuration scheme when 100% is reached, namely the capacity configuration scheme of the island micro-grid group for realizing the power supply target of 100% green energy for all loads is obtained.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010247083.XA CN111355270B (en) | 2020-03-31 | 2020-03-31 | Island micro-grid group capacity optimization configuration method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010247083.XA CN111355270B (en) | 2020-03-31 | 2020-03-31 | Island micro-grid group capacity optimization configuration method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN111355270A CN111355270A (en) | 2020-06-30 |
CN111355270B true CN111355270B (en) | 2021-08-27 |
Family
ID=71194694
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010247083.XA Active CN111355270B (en) | 2020-03-31 | 2020-03-31 | Island micro-grid group capacity optimization configuration method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111355270B (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112713621B (en) * | 2020-12-22 | 2023-06-09 | 广东电网有限责任公司电力科学研究院 | Multi-objective optimal configuration method and system for AC/DC hybrid system |
CN113690930B (en) * | 2021-07-27 | 2022-08-19 | 国网江苏省电力有限公司扬州供电分公司 | NSGA-III algorithm-based medium and long term locating and sizing method for distributed photovoltaic power supply |
CN113872225B (en) * | 2021-11-09 | 2022-06-24 | 国网湖南省电力有限公司 | Energy storage system capacity optimal configuration method based on source-load-storage coordination control |
CN117117906B (en) * | 2023-10-23 | 2024-02-06 | 国网江西省电力有限公司电力科学研究院 | Hybrid energy storage system participation power grid frequency modulation control method and system |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103606014B (en) * | 2013-10-18 | 2017-06-23 | 国家电网公司 | A kind of island distributed power source optimization method based on multiple target |
CN106600022B (en) * | 2015-10-20 | 2020-02-21 | 上海交通大学 | Wind-light-gas-seawater pumped storage isolated power system capacity optimal configuration method based on multi-objective optimization |
CN105576837A (en) * | 2016-03-18 | 2016-05-11 | 东南大学 | Micro-grid-group distribution-type three-level cooperation power control method |
CN106877406B (en) * | 2017-03-23 | 2019-06-07 | 集美大学 | A kind of multiple target power configuration optimization method of multiple-energy-source ship microgrid |
CN110601271A (en) * | 2019-08-08 | 2019-12-20 | 中国电力科学研究院有限公司 | Sea island microgrid control method and device containing seawater desalination load |
CN110445182B (en) * | 2019-09-06 | 2021-01-29 | 集美大学 | High-reliability floating type offshore wind measuring mobile platform wind-solar energy storage direct current power system and control method |
-
2020
- 2020-03-31 CN CN202010247083.XA patent/CN111355270B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN111355270A (en) | 2020-06-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111355270B (en) | Island micro-grid group capacity optimization configuration method | |
Liu et al. | Optimal operation of independent regional power grid with multiple wind-solar-hydro-battery power | |
CN105048516B (en) | A kind of honourable extreme misery multi-source complementation Optimization Scheduling | |
US9985438B2 (en) | Optimization method for independent micro-grid system | |
CN111738497B (en) | Virtual power plant double-layer optimal scheduling method considering demand side response | |
CN110970912B (en) | Operation simulation method for new energy power system containing stored energy | |
CN107425534B (en) | Micro-grid scheduling method based on optimization of storage battery charging and discharging strategy | |
CN105205552B (en) | A kind of independent new energy hybrid power system Method for optimized planning | |
CN105047966B (en) | Flow battery multi-mode operation control method and its system | |
CN107104462B (en) | A method of it is dispatched for wind power plant energy storage | |
CN103944175A (en) | Wind-solar-storage combined power generation system output characteristic optimization method | |
CN112366684A (en) | Island micro-grid system | |
CN110165715B (en) | Method for connecting electric vehicle energy storage type charging station into virtual power plant | |
CN110768303A (en) | Optimization configuration method for equipment capacity of island-type energy system | |
CN104616071A (en) | Wind-solar storage complementary generation system configuration optimization method | |
CN107359611A (en) | Consider the power distribution network equivalence method of a variety of enchancement factors | |
Lazaar et al. | Optimal sizing of marine current energy based hybrid Microgrid | |
CN109873419B (en) | Water-light storage system operation optimization method considering similarity and economic benefits | |
CN110571868A (en) | Optimal configuration method of microgrid | |
CN115796533A (en) | Virtual power plant double-layer optimization scheduling method and device considering clean energy consumption | |
Huang et al. | Optimal design of an island microgrid with considering scheduling optimization | |
El-Hendawi et al. | Enhanced MG with optimum operational cost of pumping water distribution systems | |
CN114914918A (en) | Off-grid sea island seawater desalination system driven by full renewable energy and regulation and control method thereof | |
CN115642620A (en) | Double-layer optimization method for energy storage participation low-carbon flexible peak regulation | |
CN110417002B (en) | Optimization method of island micro-grid energy model |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |