CN111324061A - Equipment verification calibration management method and related equipment and storage device thereof - Google Patents

Equipment verification calibration management method and related equipment and storage device thereof Download PDF

Info

Publication number
CN111324061A
CN111324061A CN202010068879.9A CN202010068879A CN111324061A CN 111324061 A CN111324061 A CN 111324061A CN 202010068879 A CN202010068879 A CN 202010068879A CN 111324061 A CN111324061 A CN 111324061A
Authority
CN
China
Prior art keywords
equipment
power
server
verification
power controller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010068879.9A
Other languages
Chinese (zh)
Other versions
CN111324061B (en
Inventor
刘云兵
孙志伟
吴云丽
卓海华
陈杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YANGTZE RIVER BASIN WATER ENVIRONMENT MONITORING CENTER
Original Assignee
YANGTZE RIVER BASIN WATER ENVIRONMENT MONITORING CENTER
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YANGTZE RIVER BASIN WATER ENVIRONMENT MONITORING CENTER filed Critical YANGTZE RIVER BASIN WATER ENVIRONMENT MONITORING CENTER
Priority to CN202010068879.9A priority Critical patent/CN111324061B/en
Publication of CN111324061A publication Critical patent/CN111324061A/en
Application granted granted Critical
Publication of CN111324061B publication Critical patent/CN111324061B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/04Programme control other than numerical control, i.e. in sequence controllers or logic controllers
    • G05B19/042Programme control other than numerical control, i.e. in sequence controllers or logic controllers using digital processors
    • G05B19/0428Safety, monitoring
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/20Pc systems
    • G05B2219/24Pc safety
    • G05B2219/24215Scada supervisory control and data acquisition

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Automation & Control Theory (AREA)
  • Power Sources (AREA)

Abstract

The invention relates to the field of equipment verification management, in particular to an equipment verification calibration management method and related equipment and a storage device thereof. The equipment verification calibration management method comprises the following steps: the server determines equipment meeting a preset power-off condition; sending a state detection instruction to a power controller of corresponding equipment; and when the server determines that the equipment is in the non-operation state, sending a power-off instruction to a power controller of the equipment. According to the equipment verification calibration management method and the relevant equipment and the storage device thereof, the equipment is subjected to state detection when the equipment is determined to meet the preset power-off condition, and the equipment is controlled to be powered off when the equipment is determined to be in a non-running state, so that the equipment is prevented from being used continuously after exceeding the verification period, and the provided data is guaranteed to be fair.

Description

Equipment verification calibration management method and related equipment and storage device thereof
[ technical field ] A method for producing a semiconductor device
The invention relates to the field of equipment verification management, in particular to an equipment verification calibration management method and related equipment and a storage device thereof.
[ background of the invention ]
The testing and verifying authority providing the notarization data for the society must obtain the measurement certification and qualification certificate. The general requirements of the accreditation qualification capability evaluation test and test institution (RB/T214-2017) of the test and test institution specify: the detection mechanism is used for equipment which has influence on the accuracy or effectiveness of detection results and sampling results or has requirements on metering traceability, and comprises auxiliary measuring equipment for measuring environmental conditions and the like, and the auxiliary measuring equipment is used for carrying out planned verification or calibration. All equipment needing verification, calibration or validity period can be continuously used without verification or after exceeding the verification period, the issued data has no notarization, and the CMA seal is prohibited. In order to complete the verification and calibration work of the equipment and prevent the use of uncertified equipment or over-term verification equipment, the method generally comprises the following steps:
firstly, establishing an equipment verification and calibration machine account. All the equipment needing verification or calibration is brought into the standing book management, the unique identification of the equipment, the name and the model of the equipment and the effective period of the verification or calibration are determined.
And secondly, compiling an equipment verification and calibration plan and strictly executing. And compiling an equipment verification and calibration plan according to the equipment verification regulation requirement, the self quality and stability of the equipment, the use frequency of the equipment, the environment where the equipment is located and the precision requirement of a measurement object, ensuring the use time of the equipment to the maximum extent in a rule range, and saving verification and calibration investment. And (4) strictly executing the plan, and preventing the equipment from missing detection, wrong detection and overdue detection.
And thirdly, managing the identification. And obviously marking the verification valid period on equipment, and reminding an operator.
And fourthly, supervision and inspection. And performing spot check on related data such as instrument use records, detection reports and the like, and immediately correcting the found problems.
In actual work, the management of equipment and the use of instruments belong to different departments, the number of involved personnel is large, the equipment condition is complex, a large amount of manpower and material resources are needed to master the basic information of the equipment, the condition that accounts are inconsistent easily occurs, and great difficulty is brought to the management. In addition, most laboratories do not establish automatic correlation between data, and the condition of illegal use of equipment is difficult to be found, and if a detection report covering the CMA chapter is provided in the condition, the result is very serious. Even if the illegal use condition of the equipment is found before the report is issued, the equipment meeting the requirement is searched for and re-detected, and unnecessary loss is caused.
[ summary of the invention ]
The invention aims to provide an equipment verification calibration management method and related equipment and a storage device thereof, so as to solve the technical problem that the equipment cannot be prevented from being used continuously after exceeding a verification period in the prior art.
The invention provides an equipment verification, calibration and management method, which comprises the following steps:
the server determines equipment meeting a preset power-off condition;
sending a state detection instruction to a power controller of corresponding equipment;
and when the server determines that the equipment is in the non-operation state, sending a power-off instruction to a power controller of the equipment.
Preferably, after the sending of the state detection instruction to the power controller of the corresponding device, the method further includes:
and when the server determines that the equipment is in the running state, sending a state detection instruction according to a preset strategy within first preset time.
Preferably, after the server determines that the device is in the operating state and sends the state detection instruction according to the preset policy within the first preset time, the method further includes:
and the server generates an overdue event record of the equipment, wherein the overdue event record comprises an equipment number and an event time.
Preferably, after the sending of the state detection instruction to the power controller of the corresponding device, the method includes:
receiving state data of the equipment sent by the power controller;
and determining the current state of the equipment according to the state data, wherein the current state comprises a non-running state or a running state.
Preferably, before the server determines the device meeting the preset power-off condition, the method further includes:
the server determines equipment meeting preset reminding conditions;
sending a verification reminding instruction to a power controller of corresponding equipment;
or, before the server determines the device meeting the preset power-off condition, the method includes:
establishing account information of the equipment, wherein the account information comprises an equipment number, verification certificate information, next verification reminding time and verification period expiration time, and the verification period expiration time is obtained according to the verification certificate information of the equipment;
or, after the server sends a power-off instruction to the power controller of the device when determining that the device is in the non-operating state, the method further includes:
and generating an illegal disassembly power supply event record of the equipment according to the received disassembly warning information, wherein the illegal disassembly power supply event record comprises an equipment number and an event time.
The invention also provides an equipment verification, calibration and management method, which comprises the following steps:
the power supply controller receives a state detection instruction;
the method comprises the steps that a power controller obtains state data of equipment and sends the state data to a server;
and the power controller receives a power-off instruction of the server and stops supplying power to the equipment.
Preferably, before the power controller receives the state detection instruction, the method includes:
the power controller receives the verification reminding instruction and displays verification reminding information;
or, the power controller receives a power-off instruction of the server, and after stopping supplying power to the device, the power controller further includes:
and when the acquired pressure value of the pressure sensor is smaller than a preset pressure threshold value, sending disassembly warning information of the corresponding equipment to the server.
The invention also provides a server, which comprises a communication circuit, a memory and a processor, wherein the communication circuit and the memory are respectively coupled with the processor;
the communication circuit is used for communicating with other equipment;
the processor is configured to execute the program instructions stored by the memory to perform the above-described method in conjunction with the communication circuitry.
The invention also provides a power supply controller, which comprises a communication circuit, a memory and a processor, wherein the communication circuit and the memory are respectively coupled with the processor;
the communication circuit is used for communicating with other equipment;
the processor is configured to execute the program instructions stored by the memory to perform the above-described method in conjunction with the communication circuitry.
The invention also provides an equipment verification and calibration management system, which comprises:
the power supply controllers are connected with the equipment and used for controlling the connection or disconnection of the equipment and the power supply;
the power supply controller is connected with the server through a wireless network;
the server executes the method and the power controller executes the method.
The present invention also provides a storage device storing processor-executable program instructions for performing the above-described method.
The invention has the beneficial effects that: according to the equipment verification calibration management method and the relevant equipment and the storage device thereof, the equipment is subjected to state detection when the equipment is determined to meet the preset power-off condition, and the equipment is controlled to be powered off when the equipment is determined to be in a non-running state, so that the equipment is prevented from being used continuously after exceeding the verification period, and the provided data is guaranteed to be fair.
[ description of the drawings ]
Fig. 1 is a schematic structural diagram of an equipment verification calibration management system according to a first embodiment of the present invention;
fig. 2 is a schematic structural diagram of a power manager in the equipment verification calibration management system according to the first embodiment of the present invention;
fig. 3 is a flowchart of a method for managing calibration of equipment according to a second embodiment of the present invention;
fig. 4 is a flowchart of a method for managing calibration of equipment according to a third embodiment of the present invention;
fig. 5 is a flowchart of a method for managing calibration of equipment verification according to a fourth embodiment of the present invention;
fig. 6 is a flowchart of a method for managing calibration of equipment verification according to a fifth embodiment of the present invention;
fig. 7 is a block diagram of a hardware configuration of a server according to a sixth embodiment of the present invention;
fig. 8 is a block diagram of a hardware configuration of a power manager according to a seventh embodiment of the present invention;
fig. 9 is a block diagram of a memory device according to an eighth embodiment of the present invention.
[ detailed description ] embodiments
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The terms "first", "second" and "third" in the present invention are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first," "second," or "third" may explicitly or implicitly include at least one of the feature. In the description of the present invention, "a plurality" means at least two, e.g., two, three, etc., unless specifically limited otherwise. All directional indicators (such as up, down, left, right, front, and rear … …) in the embodiments of the present invention are only used to explain the relative positional relationship between the components, the movement, and the like in a specific posture (as shown in the drawings), and if the specific posture is changed, the directional indicator is changed accordingly. Furthermore, the terms "include" and "have," as well as any variations thereof, are intended to cover non-exclusive inclusions.
Reference herein to "an embodiment" means that a particular feature, structure, or characteristic described in connection with the embodiment can be included in at least one embodiment of the invention. The appearances of the phrase in various places in the specification are not necessarily all referring to the same embodiment, nor are separate or alternative embodiments mutually exclusive of other embodiments. It is explicitly and implicitly understood by one skilled in the art that the embodiments described herein can be combined with other embodiments.
To facilitate an understanding of the present invention, the equipment certification calibration management system of the present invention will be illustrated.
[ first embodiment ]
Referring to fig. 1, fig. 1 is a schematic structural diagram of an embodiment of an equipment verification calibration management system according to the present invention. In this embodiment, the system includes a server 11 and a plurality of power controllers 12 respectively connected to the server 11, where each power controller 12 is arranged corresponding to one device 10 and is used to control whether to supply power to the device 10.
The server 11 establishes ledger information for each device 10, including a device number, verification certificate information, next verification reminding time, and verification cycle expiration time. The server 11 determines whether the equipment meets a preset power-off condition based on the current time and the verification period expiration time, where the preset power-off condition may include (i) the current time exceeds the verification period expiration time; or, (ii) the current time is less than or equal to the first time threshold from the certification period expiration time. For the device meeting the preset power-off condition, the device is not allowed to be used, and the server 11 directly enters the power-off process: firstly, a state detection instruction is sent to the corresponding power controller 12, information fed back by the power controller 12 is received, and when the equipment 10 is determined to be in a non-running state through the fed-back information, a power-off instruction is directly sent.
In an optional embodiment, the ledger information of each device 10 further includes a device type and a detection index. The server 11 is further configured to, when it is determined that the current device meets the preset power-off condition, obtain a substitute device of the current device according to the device type and the detection index of the current device, where the detection index of the substitute device matches the detection index of the current device.
The power controller 12 is disposed at a power socket of the device 10, and after receiving a state detection instruction of the server 11, acquires state data of the device 10, and feeds the state data back to the server 11; after receiving the power-off command from the server 11, the control switch assembly disconnects the power supply from the device 10.
In an optional embodiment, the server 11 determines that the device cannot be directly powered off when the device is in the operating state according to the state data of the device 10, and the server 11 sends a state detection instruction to the power controller 12 according to a preset policy within a first preset time, for example, the server 11 may send the state detection instruction to the power controller 12 at specified time intervals within the first preset time, and after receiving information fed back by the power controller 12 each time, judge that the device is in the non-operating state or the operating state according to the fed-back information, until determining that the device is in the non-operating state, the server 11 sends a power off instruction to the power controller 12 again. When the server 11 determines that the device 10 meets the preset power-off condition, the device 10 is being used, and the direct power-off may damage the device, the server 11 further determines within a first preset time by adopting a delayed power-off mode, and then enters a power-off operation flow when the device 10 is not used.
In an optional embodiment, when the server 11 determines that the device is in the operating state according to the state data of the device 10, an overdue event record of the device 10 is generated, where the overdue event record includes a device number and an event time. When the server 11 determines that the device 10 meets the preset power-off condition, the device 10 is being used, and the current use is likely to involve overdue verification, so that an overdue event record is generated for query.
In an alternative embodiment, referring to fig. 2, the power controller 12 includes a processor 121, a wireless communication module 122, a collector 123, a switch component 124 and a display screen 125, wherein the processor 121 wirelessly communicates with the server 11 through the wireless communication module 122, for example, receives instructions of the server 11 or sends feedback information to the server 11; processor 121 is used to control the operation of collector 123, switch assembly 124 and display 125. The collector 123 is configured to collect status data of the device 10, where the status data may be current, voltage or power, for example, the collector 123 may be a power sensor, and the power sensor senses power of the device 10 and outputs a power signal representing the sensed power; the collector 123 may also be a voltage sensor that senses the voltage of the device 10 and outputs a voltage signal representative of the magnitude of the sensed voltage. Of course, the status data may be other types of data as long as whether the device 10 is powered on or not can be determined by the status data. A switch assembly 124 is provided on the power outlet of the device 10, the switch assembly 124 being configured to be able to disconnect or connect the power supply from the power outlet. The display screen 125 is used for displaying the next certification reminding time and the certification cycle expiration time of the corresponding equipment 10.
In an alternative embodiment, the power socket of the device 10 is further provided with a detachment prevention component, which prevents the user from pulling out the power plug 101 of the device 10 from the power socket and continuing to detect another power socket. In this embodiment, the detachment prevention means may be a pressure sensor 126 disposed on the power socket and connected to the processor 121, the pressure sensor 126 is abutted to or separated from the power plug 101 of the device 10, when the power plug of the device 10 is inserted into the power socket, the power plug 101 applies pressure to the power socket, and the pressure sensor 126 is abutted to the power plug 101 of the device 10 to measure the pressure applied by the power plug 101; when the power line plug 101 is pulled out, the pressure sensor 126 is separated from the power line plug 101 of the device 10, the pressure measured by the pressure sensor 126 changes, and the processor 121 is further configured to send detachment warning information corresponding to the device 10 to the server 11 when the obtained pressure value of the pressure sensor 126 is smaller than a preset pressure threshold value, the server 11 receives the detachment warning information, and generates an illegal detachment power event record of the device 10, wherein the illegal detachment power event record comprises a device number and an event time. Of course, it will be understood by those skilled in the art that in other embodiments, the anti-removal feature may also be a combination lock provided on the power socket housing that is in a closed state when the power cord plug 101 of the device 10 is plugged into an electrical outlet.
In an optional embodiment, the server 11 determines whether the equipment meets a preset reminding condition based on the current time and the next verification reminding time, where the preset reminding condition may include (i) the current time exceeds the next verification reminding time; or, (ii) the current time is less than or equal to the second time threshold from the next certification reminder time. For the device meeting the preset reminding condition, the server 11 directly enters the reminding process: and sending a verification reminding instruction to the power controller 12 of the corresponding equipment. Further, after receiving the verification reminding instruction, the power controller 12 displays the verification reminding instruction on the display screen 125.
In an alternative embodiment, the server 11 is communicatively connected to each power controller 12 through a wireless network, and specifically, one or more power controllers 12 access the network in which the server 11 is located through a wireless access node. More specifically, a wireless connection based on, for example, a SimpliciT1 protocol is used between the power controller 12 and the wireless access node, and if there is a packet to be forwarded to the server 11, the wireless access node directly sends the packet to the server 11, and if there is a new packet to be forwarded to the power controller 12 by the server 11, the wireless access node may directly send the packet to the power controller 12, or the wireless access node may wake up the power controller 12 first and then send the packet to the power controller 12, so as to save the power of the power controller 12.
The system of the embodiment has the following beneficial effects: (1) have mandatory measures to prevent the device from being used illegally; (2) early warning and forecasting of illegal equipment; (3) the equipment ledger accounting condition and the verification calibration plan execution condition are effectively monitored.
[ second embodiment ]
Referring to fig. 3, fig. 3 is a flowchart illustrating a second embodiment of the apparatus verification and calibration management method according to the present invention. It should be noted that the method of the present invention is not limited to the flow sequence shown in fig. 3 if the results are substantially the same. In this embodiment, the method is executed by the server, and specifically includes the following steps:
s201, the server determines the equipment meeting the preset power-off condition.
In this embodiment, the server may continuously monitor whether the one or more devices meet the preset power-off condition according to the standing book information of the one or more devices, so as to obtain the devices meeting the preset power-off condition.
Specifically, the server determines whether the equipment meets a preset power-off condition based on the current time and the verification period expiration time, wherein the preset power-off condition may include (i) the current time exceeds the verification period expiration time; or, (ii) the current time is less than or equal to the first time threshold from the certification period expiration time.
S202, sending a state detection instruction to a power controller of the corresponding equipment.
In this embodiment, the server generates a data packet containing a status detection instruction for a device meeting the power-off condition, and sends the data packet to the power controller of the device via the wireless network.
S203, when the server determines that the equipment is in the non-operation state, sending a power-off instruction to a power controller of the equipment.
In this embodiment, the server determines whether the device is in an operating state according to the feedback information of the state detection instruction sent by the power controller, and directly sends a power-off instruction when determining that the device is in a non-operating state according to the feedback information.
In an optional embodiment, after step S203, the following steps are further included:
and S204, when the server determines that the equipment is in the running state, sending a state detection instruction according to a preset strategy within first preset time.
For example, a state detection instruction is sent to the power controller at a specified time interval within a first preset time, after information fed back by the power controller is received each time, the server judges whether the equipment is in a non-operation state or an operation state according to the fed-back information, and the server sends a power-off instruction to the power controller again until the equipment is determined to be in the non-operation state.
S205, the server generates an overdue event record of the equipment, wherein the overdue event record comprises an equipment number and an event time.
When the server judges that the equipment meets the preset power-off condition, the equipment is used, the current use is likely to involve the overdue verification, and therefore an overdue event record is generated for query.
[ third embodiment ]
Referring to fig. 4, fig. 4 is a flowchart illustrating a third embodiment of the apparatus verification and calibration management method according to the present invention. It should be noted that the method of the present invention is not limited to the flow sequence shown in fig. 4 if the results are substantially the same. In this embodiment, the method is executed by the server, and specifically includes the following steps:
s301, the server determines the equipment meeting the preset reminding condition.
In this embodiment, the server may continuously monitor whether the one or more devices meet the preset reminding condition according to the standing book information of the one or more devices, so as to obtain the devices meeting the preset reminding condition.
Specifically, the server determines whether the equipment meets a preset reminding condition based on the current time and the next verification reminding time, wherein the preset reminding condition may include (i) the current time exceeds the next verification reminding time; or, (ii) the current time is less than or equal to the second time threshold from the next certification reminder time. For the equipment meeting the preset reminding condition, the server is allowed to be used, and directly enters a reminding flow: and sending a verification reminding instruction to a power controller of the corresponding equipment.
And S302, sending a verification reminding instruction to the power controller of the corresponding equipment.
In this embodiment, for a device, the next verification reminding time is earlier than the verification period expiration time, that is, the server first reminds the control flow before entering the power-off control flow for the device.
S303, the server determines the equipment meeting the preset power-off condition.
And S304, sending a state detection instruction to the power supply controller of the corresponding equipment.
S305, when the server determines that the equipment is in the non-operation state, sending a power-off instruction to a power controller of the equipment.
In the present embodiment, steps S303 to S305 are the same as steps S201 to S203 of the second embodiment, specifically referring to the above.
In this embodiment, before step S301, the following steps are further included:
s300, establishing account information of the equipment, wherein the account information comprises an equipment number, verification certificate information, next verification reminding time and verification period expiration time.
In step S300, the expiration time of the verification period is obtained according to the verification certificate information of the device, the next verification reminding time may be preset according to the verification schedule, and a device verification time period is generally reserved between the next verification reminding time and the verification period expiration time.
[ fourth embodiment ]
Referring to fig. 5, fig. 5 is a flowchart illustrating a fourth embodiment of the apparatus verification and calibration management method according to the present invention. It should be noted that the method of the present invention is not limited to the flow sequence shown in fig. 5 if the results are substantially the same. In this embodiment, the method is executed by the power manager, and specifically includes the following steps:
s401, the power controller receives a state detection instruction.
S402, the power controller acquires the state data of the equipment and sends the state data to the server.
And S403, the power controller receives a power-off instruction of the server and stops supplying power to the equipment.
In this embodiment, after receiving a state detection instruction of a server, acquiring state data of a device, and feeding back the state data to the server; and after receiving a power-off instruction of the server, controlling the switch assembly to disconnect the power supply from the equipment.
[ fifth embodiment ]
Referring to fig. 6, fig. 6 is a flowchart illustrating a fifth embodiment of the apparatus verification and calibration management method according to the present invention. It should be noted that the method of the present invention is not limited to the flow sequence shown in fig. 6 if the results are substantially the same. In this embodiment, the method is executed by the power manager, and specifically includes the following steps:
s501, the power controller receives the verification reminding instruction and displays verification reminding information.
In this embodiment, after receiving a verification reminding instruction of the server, verification reminding information carried by the verification reminding instruction is displayed on a display screen of the power manager, where the verification reminding information may include a reminding identifier and verification period expiration time.
S502, the power controller receives a state detection instruction.
S503, the power controller acquires the state data of the equipment and sends the state data to the server.
And S504, the power controller receives a power-off instruction of the server and stops supplying power to the equipment.
In an optional embodiment, the equipment verification calibration management method further comprises the following steps:
and S505, when the acquired pressure value of the pressure sensor is smaller than a preset pressure threshold value, sending detachment warning information of the corresponding equipment to the server.
Accordingly, the server performs the steps of: and generating an illegal disassembly power supply event record of the equipment according to the received disassembly warning information, wherein the illegal disassembly power supply event record comprises an equipment number and an event time.
[ sixth embodiment ]
Referring to fig. 7, fig. 7 is a schematic structural diagram of a server according to an embodiment of the present invention. In this embodiment, the server 70 includes a memory 71, a processor 72, and a communication circuit 73. The communication circuit 73 and the memory 71 are respectively coupled to the processor 72. Specifically, the various components of the server 70 may be coupled together by a bus, or the processors of the server 70 may be connected one-to-one with the other components, respectively.
The communication circuit 73 may communicate with the power manager in the system embodiments described above. The memory 71 is used for storing program instructions executed by the processor 72 and data of the processor 72 in the processing process, wherein the memory 71 comprises a nonvolatile storage part for storing the program instructions. Furthermore, the memory 71 may also store sample or person related data.
The processor 72 controls the operation of the server 70, and the processor 72 may also be referred to as a Central Processing Unit (CPU). The processor 72 may be an integrated circuit chip having signal processing capabilities. The processor 72 may also be a general purpose processor, a Digital Signal Processor (DSP), an Application Specific Integrated Circuit (ASIC), an off-the-shelf programmable gate array (FPGA) or other programmable logic device, discrete gate or transistor logic, discrete hardware components. A general purpose processor may be a microprocessor or the processor may be any conventional processor or the like.
In this embodiment, the processor 72 is configured to execute the functions or steps executed by any node of the server side in the system according to the second embodiment or the third embodiment or the first embodiment by calling the program instructions stored in the memory 71.
[ seventh embodiment ]
Referring to fig. 8, fig. 8 is a schematic structural diagram of a power manager according to an embodiment of the invention. In this embodiment, the power manager 80 includes a memory 81, a processor 82, and a communication circuit 83. The communication circuit 83 and the memory 81 are respectively coupled to the processor 82. Specifically, the various components of power manager 80 may be coupled together by a bus, or the processors of power manager 80 may be connected one-to-one with the other components, respectively.
The communication circuit 83 may communicate with the server in the above-described system embodiment. The memory 81 is used for storing program instructions executed by the processor 82 and data of the processor 82 in the processing process, wherein the memory 81 comprises a nonvolatile storage part for storing the program instructions. Furthermore, the memory 71 may also store sample or person related data.
Processor 82 controls the operation of power manager 80, and processor 82 may also be referred to as a Central Processing Unit (CPU). The processor 82 may be an integrated circuit chip having signal processing capabilities. The processor 72 may also be a general purpose processor, a Digital Signal Processor (DSP), an Application Specific Integrated Circuit (ASIC), an off-the-shelf programmable gate array (FPGA) or other programmable logic device, discrete gate or transistor logic, discrete hardware components. A general purpose processor may be a microprocessor or the processor may be any conventional processor or the like.
In this embodiment, the processor 82 is configured to execute the functions or steps executed by any node on the power manager side in the system according to the fourth embodiment or the fifth embodiment or the first embodiment by calling the program instructions stored in the memory 81.
[ eighth embodiment ]
Referring to fig. 9, the present invention further provides a structural schematic diagram of an embodiment of a memory device. In this embodiment, the memory device 90 stores processor-executable program instructions 91, the program instructions 91 being for performing the methods of the embodiments described above.
The storage device 90 may be a medium that can store program instructions, such as a usb disk, a removable hard disk, a Read-Only Memory (ROM), a Random Access Memory (RAM), a magnetic disk, or an optical disk, or may be a server that stores the program instructions, and the server may send the stored program instructions to other devices for operation, or may self-operate the stored program instructions.
In one embodiment, the storage device 90 may also be a memory as shown in fig. 7 or fig. 8.
In the embodiments provided in the present invention, it should be understood that the disclosed method and apparatus can be implemented in other ways. For example, the above-described apparatus embodiments are merely illustrative, and for example, a division of a module or a unit is merely a logical division, and an actual implementation may have another division, for example, a plurality of units or components may be combined or integrated into another system, or some features may be omitted, or not executed. In addition, the shown or discussed mutual coupling or direct coupling or communication connection may be an indirect coupling or communication connection through some interfaces, devices or units, and may be in an electrical, mechanical or other form.
Units described as separate parts may or may not be physically separate, and parts displayed as units may or may not be physical units, may be located in one place, or may be distributed on a plurality of network units. Some or all of the units can be selected according to actual needs to achieve the purpose of the embodiment.
In addition, functional units in the embodiments of the present invention may be integrated into one processing unit, or each unit may exist alone physically, or two or more units are integrated into one unit. The integrated unit can be realized in a form of hardware, and can also be realized in a form of a software functional unit.
The integrated unit, if implemented in the form of a software functional unit and sold or used as a stand-alone product, may be stored in a computer readable storage medium. Based on such understanding, the technical solution of the present invention may be substantially or partially implemented in the form of a software product stored in a storage medium and including instructions for causing a computer device (which may be a personal computer, a server, a network device, or the like) or a processor (processor) to execute all or part of the steps of the method according to the embodiments of the present invention. And the aforementioned storage medium includes: a U-disk, a removable hard disk, a Read-Only Memory (ROM), a Random Access Memory (RAM), a magnetic disk or an optical disk, and other various media capable of storing program codes.
While the foregoing is directed to embodiments of the present invention, it will be understood by those skilled in the art that various changes may be made without departing from the spirit and scope of the invention.

Claims (11)

1. An equipment certification calibration management method, comprising:
the server determines equipment meeting a preset power-off condition;
sending a state detection instruction to a power controller of corresponding equipment;
and when the server determines that the equipment is in the non-operation state, sending a power-off instruction to a power controller of the equipment.
2. The method of claim 1, further comprising, after sending the state detection instruction to the power controller of the corresponding device:
and when the server determines that the equipment is in the running state, sending a state detection instruction according to a preset strategy within first preset time.
3. The method according to claim 2, wherein after the server determines that the device is in the operating state and sends the state detection instruction according to the preset policy within a first preset time, the method further comprises:
and the server generates an overdue event record of the equipment, wherein the overdue event record comprises an equipment number and an event time.
4. The method according to claim 2, wherein after sending the state detection instruction to the power controller of the corresponding device, the method comprises:
receiving state data of the equipment sent by the power controller;
and determining the current state of the equipment according to the state data, wherein the current state comprises a non-running state or a running state.
5. The method according to claim 1, before the server determines the device meeting the preset power-off condition, further comprising:
the server determines equipment meeting preset reminding conditions;
sending a verification reminding instruction to a power controller of corresponding equipment;
or, before the server determines the device meeting the preset power-off condition, the method includes:
establishing account information of the equipment, wherein the account information comprises an equipment number, verification certificate information, next verification reminding time and verification period expiration time, and the verification period expiration time is obtained according to the verification certificate information of the equipment;
or, after the server sends a power-off instruction to the power controller of the device when determining that the device is in the non-operating state, the method further includes:
and generating an illegal disassembly power supply event record of the equipment according to the received disassembly warning information, wherein the illegal disassembly power supply event record comprises an equipment number and an event time.
6. An equipment certification calibration management method, comprising:
the power supply controller receives a state detection instruction;
the method comprises the steps that a power controller obtains state data of equipment and sends the state data to a server;
and the power controller receives a power-off instruction of the server and stops supplying power to the equipment.
7. The method of claim 6, wherein prior to receiving the state detection instruction, the power controller comprises:
the power controller receives the verification reminding instruction and displays verification reminding information;
or, the power controller receives a power-off instruction of the server, and after stopping supplying power to the device, the power controller further includes:
and when the acquired pressure value of the pressure sensor is smaller than a preset pressure threshold value, sending disassembly warning information of the corresponding equipment to the server.
8. A server comprising communication circuitry, a memory, and a processor, the communication circuitry, the memory being respectively coupled to the processor;
the communication circuit is used for communicating with other equipment;
the processor is configured to execute the program instructions stored by the memory to perform the method of any of claims 1 to 5 in conjunction with the communication circuitry.
9. A power controller is characterized by comprising a communication circuit, a memory and a processor, wherein the communication circuit and the memory are respectively coupled with the processor;
the communication circuit is used for communicating with other equipment;
the processor is configured to execute the program instructions stored by the memory to perform the method of claim 6 or 7 in conjunction with the communication circuitry.
10. An equipment certification calibration management system, the management system comprising:
the power supply controllers are connected with the equipment and used for controlling the connection or disconnection of the equipment and the power supply;
the power supply controller is connected with the server through a wireless network;
the server performs the method of any of claims 1 to 5 and the power controller performs the method of claim 6 or 7.
11. A storage device having stored thereon program instructions executable by a processor to perform the method of any one of claims 1 to 5 or to perform the method of claim 6 or 7.
CN202010068879.9A 2020-01-21 2020-01-21 Equipment verification calibration management method and related equipment and storage device thereof Active CN111324061B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010068879.9A CN111324061B (en) 2020-01-21 2020-01-21 Equipment verification calibration management method and related equipment and storage device thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010068879.9A CN111324061B (en) 2020-01-21 2020-01-21 Equipment verification calibration management method and related equipment and storage device thereof

Publications (2)

Publication Number Publication Date
CN111324061A true CN111324061A (en) 2020-06-23
CN111324061B CN111324061B (en) 2021-07-20

Family

ID=71163297

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010068879.9A Active CN111324061B (en) 2020-01-21 2020-01-21 Equipment verification calibration management method and related equipment and storage device thereof

Country Status (1)

Country Link
CN (1) CN111324061B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113377004A (en) * 2021-06-28 2021-09-10 广州极飞科技股份有限公司 Power-off method of aircraft, control method, application method and flight system of aircraft

Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2441142Y (en) * 2000-07-12 2001-08-01 胡宗泉 Forced inspection controller
CN2706501Y (en) * 2004-04-29 2005-06-29 蔡红星 Self-service intelligent coin-charging full-automatic public washer controller
KR20080020046A (en) * 2006-08-30 2008-03-05 보은군 Interception apparatus of thunderbolt detect
CN101515343A (en) * 2009-03-25 2009-08-26 西安计量技术研究院 Dynamic supervision system for checking equipment of qualification certification products
CN101819660A (en) * 2010-04-10 2010-09-01 西安计量技术研究院 Compulsory verification measuring instrument filing and dynamic management method and system thereof
CN201757670U (en) * 2010-02-05 2011-03-09 凯丰集团有限公司 Electronic scale provided with forced detecting management functions
CN102128647A (en) * 2010-12-31 2011-07-20 浙江中控自动化仪表有限公司 Self-calibration method of calibration instrument
CN103234851A (en) * 2013-04-16 2013-08-07 舟山市博远科技开发有限公司 Digitization resiliometer verification apparatus and verification method
CN104501935A (en) * 2014-12-12 2015-04-08 福建省计量科学研究院 Anti-cheating supervision method and system for electronic scale
CN204441612U (en) * 2015-01-23 2015-07-01 江汉大学 A kind of authority jack system
CN105253731A (en) * 2015-11-20 2016-01-20 宁夏电通物联网科技股份有限公司 Elevator maintenance overdue alarm system and method
CN105867290A (en) * 2016-04-10 2016-08-17 东北电力大学 Office place safe electricity consumption monitoring system and method
CN106767991A (en) * 2017-02-27 2017-05-31 国网山东省电力公司电力科学研究院 A kind of Thermal Meter verification management system and method based on WLAN
CN108494087A (en) * 2018-03-13 2018-09-04 广州华润热电有限公司 A kind of reminding method and relevant device of unit check
CN109269680A (en) * 2018-11-16 2019-01-25 中环天仪(天津)气象仪器有限公司 A kind of device and method for multichannel temperature calibrating
CN109409543A (en) * 2018-11-06 2019-03-01 赵伊苓 Equipment real-time information management system
CN109617243A (en) * 2019-01-14 2019-04-12 北京芯元数科技有限公司 Power monitoring method, apparatus and system based on wireless communication technique

Patent Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2441142Y (en) * 2000-07-12 2001-08-01 胡宗泉 Forced inspection controller
CN2706501Y (en) * 2004-04-29 2005-06-29 蔡红星 Self-service intelligent coin-charging full-automatic public washer controller
KR20080020046A (en) * 2006-08-30 2008-03-05 보은군 Interception apparatus of thunderbolt detect
CN101515343A (en) * 2009-03-25 2009-08-26 西安计量技术研究院 Dynamic supervision system for checking equipment of qualification certification products
CN201757670U (en) * 2010-02-05 2011-03-09 凯丰集团有限公司 Electronic scale provided with forced detecting management functions
CN101819660A (en) * 2010-04-10 2010-09-01 西安计量技术研究院 Compulsory verification measuring instrument filing and dynamic management method and system thereof
CN102128647A (en) * 2010-12-31 2011-07-20 浙江中控自动化仪表有限公司 Self-calibration method of calibration instrument
CN103234851A (en) * 2013-04-16 2013-08-07 舟山市博远科技开发有限公司 Digitization resiliometer verification apparatus and verification method
CN104501935A (en) * 2014-12-12 2015-04-08 福建省计量科学研究院 Anti-cheating supervision method and system for electronic scale
CN204441612U (en) * 2015-01-23 2015-07-01 江汉大学 A kind of authority jack system
CN105253731A (en) * 2015-11-20 2016-01-20 宁夏电通物联网科技股份有限公司 Elevator maintenance overdue alarm system and method
CN105867290A (en) * 2016-04-10 2016-08-17 东北电力大学 Office place safe electricity consumption monitoring system and method
CN106767991A (en) * 2017-02-27 2017-05-31 国网山东省电力公司电力科学研究院 A kind of Thermal Meter verification management system and method based on WLAN
CN108494087A (en) * 2018-03-13 2018-09-04 广州华润热电有限公司 A kind of reminding method and relevant device of unit check
CN109409543A (en) * 2018-11-06 2019-03-01 赵伊苓 Equipment real-time information management system
CN109269680A (en) * 2018-11-16 2019-01-25 中环天仪(天津)气象仪器有限公司 A kind of device and method for multichannel temperature calibrating
CN109617243A (en) * 2019-01-14 2019-04-12 北京芯元数科技有限公司 Power monitoring method, apparatus and system based on wireless communication technique

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
崔玉峰: "温度计量自动检定系统研究", 《 2010年云南电力技术论坛论文集》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113377004A (en) * 2021-06-28 2021-09-10 广州极飞科技股份有限公司 Power-off method of aircraft, control method, application method and flight system of aircraft

Also Published As

Publication number Publication date
CN111324061B (en) 2021-07-20

Similar Documents

Publication Publication Date Title
JP6571144B2 (en) Monitoring system, monitoring device, server, and monitoring method
US20160335391A1 (en) Method and system for interacting rail transit vehicle commissioning task information
US9389253B2 (en) System and method for real time detection and correlation of devices and power outlets
US9916331B2 (en) Method and device for automatically processing static test data of rail transit vehicle
CN104268049B (en) Method, device and terminal for judging storage device abnormity
US20040002349A1 (en) Mobile telephone with environment sensor
CN105204970B (en) Method and device for detecting CPU occupancy rate abnormity of APP and mobile terminal
CN110750413B (en) Multi-machine room temperature alarm method and device and storage medium
CN111324061B (en) Equipment verification calibration management method and related equipment and storage device thereof
CN102486493A (en) Electronic device energy consumption detection system
JP5361532B2 (en) Disaster prevention training support system and disaster prevention training support method
CN105890810B (en) The setting method and grain inspection system of temperature testing equipment
CN100440158C (en) A testing method and system for timer in embedded system
CN217112604U (en) Power amplifier's test system
JP5174762B2 (en) Power monitoring system and system controller
JP7470020B2 (en) Measurement Systems and Instruments
CN115727760A (en) Spatial position identification method, system, equipment and storage medium
CN114373370A (en) Electricity testing simulation device
KR100858911B1 (en) Lift controller
CN111650909A (en) Intelligent control system and method for sewage treatment process, readable storage medium and device
CN109103518B (en) Battery capacity updating method and system
CN106093643A (en) The method of testing of electronic product stability
CN207601174U (en) A kind of taiwan area acquisition terminal and unit-area management system
CN105260830A (en) Partial discharge intelligent assembly performance assessment method
CN115224807B (en) On-site detection device and detection method for power distribution station room

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: No.13 Yongqing Road, Jiang'an District, Wuhan City, Hubei Province 430000

Applicant after: Ecological environment monitoring and scientific research center of Yangtze River basin ecological environment supervision and Administration Bureau, Ministry of ecological environment

Address before: 430000 Guocikou, Hanyang District, Wuhan City, Hubei Province

Applicant before: YANGTZE RIVER BASIN WATER ENVIRONMENT MONITORING CENTER

GR01 Patent grant
GR01 Patent grant