CN111301633A - FPSO ship living building hoisting method - Google Patents

FPSO ship living building hoisting method Download PDF

Info

Publication number
CN111301633A
CN111301633A CN202010183969.2A CN202010183969A CN111301633A CN 111301633 A CN111301633 A CN 111301633A CN 202010183969 A CN202010183969 A CN 202010183969A CN 111301633 A CN111301633 A CN 111301633A
Authority
CN
China
Prior art keywords
hoisting
hanging
lifting
points
block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010183969.2A
Other languages
Chinese (zh)
Inventor
陈小雨
张海甬
练兆华
陈风
王大明
王晓刚
王虎
孙海云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Waigaoqiao Shipbuilding Co Ltd
Original Assignee
Shanghai Waigaoqiao Shipbuilding Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Waigaoqiao Shipbuilding Co Ltd filed Critical Shanghai Waigaoqiao Shipbuilding Co Ltd
Priority to CN202010183969.2A priority Critical patent/CN111301633A/en
Publication of CN111301633A publication Critical patent/CN111301633A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Jib Cranes (AREA)

Abstract

The invention discloses a method for hoisting a living building of an FPSO ship, which comprises the following steps: s10, dividing the FPSO ship life building into a plurality of total sections, wherein the plurality of total sections comprise a first total section and a second total section; s20, arranging a plurality of first hoisting points on the deck surface of the first block; s30, arranging a plurality of second hoisting points on the deck surface of the second total section; s40, hoisting the first total section through the first hoisting point by a crane; s50, hoisting the second total section by the crane ship through the second hoisting point; wherein the first block has a weight less than the lifting capacity of the crane and the second block has a weight greater than the lifting capacity of the crane. The FPSO ship life building is divided into a plurality of total sections to be hoisted, the hoisting difficulty is reduced, and the complexity of hoisting operation is reduced.

Description

FPSO ship living building hoisting method
Technical Field
The invention relates to the technical field of ship construction, in particular to a method for hoisting a living building of an FPSO ship.
Background
As a novel marginal gas field development technology, a liquefied natural gas production storage and offloading (FPSO) is favored due to its advantages of low investment, short construction period, convenient migration, etc. The FPSO is a comprehensive large offshore oil production base integrating personnel living and production command systems into a whole, and is used for carrying out oil-gas separation on the mined oil, treating oily sewage, generating power, supplying heat and storing and transporting crude oil products. Compared with other forms of oil production platforms, the FPSO has the advantages of strong wind and wave resistance, wide range of applicable water depth, large oil storage/discharge capacity, transferability and reusability, is widely suitable for the development of deep sea, shallow sea and marginal oil fields far away from the coast, and becomes a mainstream production mode for the development of offshore oil and gas fields.
FPSO ship building length 33 meters, width 60 meters, height 32 meters, 8 layer structures totally, total weight exceed 3000 tons, and partial structure mainboard that can set up the hoisting point is thick only 8 millimeters ~ 10 millimeters. The FPSO ship life building is large in size, heavy in tonnage, and thin in structure main board capable of being provided with lifting points, so that the lifting difficulty is high.
Disclosure of Invention
The invention aims to overcome the defects of large size, heavy tonnage and large hoisting difficulty of an FPSO ship living building in the prior art, and provides a hoisting method of the FPSO ship living building.
The invention solves the technical problems through the following technical scheme:
a method for hoisting an FPSO ship living building is characterized by comprising the following steps:
s10, dividing the FPSO ship life building into a plurality of total sections, wherein the plurality of total sections comprise a first total section and a second total section;
s20, arranging a plurality of first hoisting points on the deck surface of the first block;
s30, arranging a plurality of second hoisting points on the deck surface of the second total section;
s40, hoisting the first total section through the first hoisting point by a crane;
s50, hoisting the second total section by the crane ship through the second hoisting point;
wherein the first block has a weight less than the lifting capacity of the crane and the second block has a weight greater than the lifting capacity of the crane.
In this scheme, divide FPSO ship life building into a plurality of sections and hoist, reduced the hoist and mount degree of difficulty, wherein, first section uses the hoist to hoist, and the weight of second section is greater than the load capacity of hoist uses the crane ship to hoist.
Preferably, the following steps are further included after step S20:
s21, arranging at least two first hanging rows on the first hanging points respectively;
each row of the first lifting rows is provided with a plurality of first lifting holes, and the number of the first lifting holes is larger than that of the lifting holes needed by actual lifting.
In the scheme, because the deck surface where the first hanging points are located is thin in plate thickness and the longitudinal and transverse strength members of the framework surface are few, at least two rows of first hanging rows are arranged, and the problem of stress concentration caused by arrangement of one row of first hanging rows is avoided; in addition, the number of the lifting holes is set to be larger than the number of the lifting holes needed by actual lifting, so that in the actual lifting process, the distance between the actually-used lifting hooks can be adjusted, and the problem of eccentric lifting caused by the actual weight gravity center deviation of the first total section is avoided.
Preferably, the first hanger bar is provided with a main plate and two webs, the main plate is vertically arranged on the deck surface, the two webs are respectively located on two sides of the main plate, the thickness of the main plate is 18mm to 30mm, and the thickness of the webs is 16 mm.
In this scheme, set up mainboard and two webs and can improve the bearing capacity of first row of hanging.
Preferably, in step S20, the first hanging points are distributed on the deck surface.
In this scheme, first total section has the overhanging structure in its periphery, and first hoisting point is in scatter distribution is in on the deck face for a plurality of first hoisting points all cover in the overhanging structure is last, can avoid overhanging structure to take place to warp at the actual hoist and mount in-process, increases the steadiness of whole first total section at the actual hoist and mount in-process.
Preferably, the first section has a protruding room protruding from the deck surface, and at least one of the first suspension points is located at the top of the protruding room in step S20.
In this scheme, this protrusion room weight is great, and must install and hoist in first total section, with at least one hoisting point set up in the top in protrusion room can avoid this protrusion room to take place to warp at the actual hoist and mount in-process to a certain extent to make first total section more firm at the in-process of actual hoist and mount.
Preferably, in step S21, the first sling rows located in the protruding room extend along the length direction of the first total section, and the other first sling rows extend along the width direction of the first total section.
Preferably, the following steps are further included after step S20:
and S22, increasing the plate thickness of the deck plate corresponding to the position of the first hanging point so that the plate thickness of the deck plate is 12mm to 18 mm.
In this scheme, increase the board of deck face and be thick, can avoid deck face to produce the deformation at the actual hoist and mount in-process.
Preferably, in step S30, the number of the second hanging points is 4, the second block has a front wall panel and a rear wall panel at two ends along the length direction thereof, two second hanging points are respectively located above the front wall panel and the rear wall panel, and a distance is provided between the two second hanging points located on the same wall panel.
In the scheme, the width of the second total section is 60 meters, and an interval is formed between the two second hoisting points, so that the second total section can be prevented from deforming in the width direction in the hoisting process, and the rigidity of the second total section is kept in the actual hoisting process.
Preferably, the following steps are further included after step S30:
and S31, respectively arranging vertical plates at the second hanging points to serve as second hanging rows, wherein the second hanging rows extend along the width direction of the second total section and are provided with a plurality of second hanging holes.
In this scheme, the second hangs the row and is provided with a plurality of second lewis holes, can avoid single lewis hole load too big.
Preferably, after the step S31, the method further comprises the steps of:
s32, increasing the plate thickness of the front wall plate and the rear wall plate corresponding to the position of the second hanging row, and increasing the plate thickness of the deck plate close to the second hanging row.
In this scheme, because the weight of second total section is great, the plate thickness of enclosing wallboard, back wall board and deck face before the increase can avoid enclosing wallboard, back wall board and deck face before taking place to warp at the hoist and mount in-process, strengthens the structural rigidity of second total section.
On the basis of the common knowledge in the field, the above preferred conditions can be combined randomly to obtain the preferred embodiments of the invention.
The positive progress effects of the invention are as follows: for the FPSO ship life building needing to be hoisted, the FPSO ship life building is divided into a plurality of total sections to be hoisted, the total sections are divided into a first total section and a second total section according to the structure, the weight of the first total section is smaller than the hoisting capacity of a crane, the FPSO ship life building is hoisted by using the crane, the weight of the second total section is larger than the hoisting capacity of the crane, the FPSO ship life building needing to be hoisted is hoisted by using the crane ship, the hoisting difficulty is reduced, and the complexity of hoisting operation is reduced.
Drawings
Fig. 1 is a flowchart of a method for hoisting an FPSO vessel living building according to a preferred embodiment of the present invention.
Fig. 2 is a perspective view illustrating a first block according to a preferred embodiment of the present invention.
Fig. 3 is a perspective view illustrating a first hanger row according to a preferred embodiment of the present invention.
Fig. 4 is a perspective view illustrating a part of a second block according to a preferred embodiment of the present invention.
Fig. 5 is a schematic view of the stress state of the second total section lifted by the lifting hook according to the preferred embodiment of the invention.
Fig. 6 is a schematic view of another stress state of the lifting hook for lifting the second total section according to the preferred embodiment of the invention.
Description of reference numerals:
first block 1
First hanger row 12
Main board 121
Web 122
Toggle plate 123
First lifting hole 124
Overhanging structure 13
Protruding room 14
Second block 2
Dash panel 21
Rear wall panel 22
Second hanger row 23
Second lifting hole 24
Second lifting point 25
Lifting hook 3
Included angle a
Length direction x
Width direction y
Detailed Description
The present invention is further illustrated by way of example and not by way of limitation in the scope of the embodiments described below in conjunction with the accompanying drawings.
The embodiment discloses a method for hoisting a living building of an FPSO ship, as shown in fig. 1, the method for hoisting the living building of the FPSO ship comprises the following steps:
s10, dividing the FPSO ship life building into a plurality of total sections, wherein the plurality of total sections comprise a first total section 1 and a second total section 2;
s20, arranging a plurality of first hoisting points on the deck surface of the first block 1;
s30, arranging a plurality of second hoisting points 25 on the deck surface of the second block 2;
s40, hoisting the first block 1 through the first hoisting point by the crane;
s50, hoisting the second block 2 by the crane ship through the second hoisting point 25;
wherein the weight of the first block 1 is less than the lifting capacity of the crane and the weight of the second block 2 is greater than the lifting capacity of the crane.
In this embodiment, divide FPSO ship building for life into a plurality of total sections and hoist, reduced the hoist and mount degree of difficulty, wherein, first total section 1 uses the hoist to hoist, and the weight of second total section 2 is greater than the load capacity of hoist, uses the crane ship to hoist.
Specifically, the first total section comprises a lower layer port 92A total section and a lower layer starboard 93A total section which are hoisted by adopting a dock gantry crane; the second block comprises an upper 90B block, the weight of the upper 90B block reaches 1800 tons, and a crane ship (floating crane) is adopted for hoisting.
As will be understood with reference to fig. 2 and 3, the following steps are also included after step S20:
s21, arranging at least two first hanging rows 12 on the plurality of first hanging points respectively;
wherein, each row of the first hanging rows 12 has a plurality of first hanging holes 124, and the number of the first hanging holes 124 is greater than the number of the hanging holes needed for actual hanging.
In the embodiment, because the plate thickness of the deck surface where the first hanging points are located is thin, and the longitudinal and transverse strength members of the framework surface are few, at least two rows of first hanging rows 12 are arranged, and the problem of stress concentration caused by arranging one row of first hanging rows 12 is avoided; in addition, the number of the first lifting holes 124 is set to be larger than the number of the first lifting holes 124 needed by actual lifting, so that in the actual lifting process, the distance between the actually used lifting hooks can be adjusted, and the problem of eccentric lifting caused by the actual weight gravity center deviation of the first total section 1 is avoided. Specifically, the number of the first hanging holes 124 required for actual hoisting is 4, and the number of the first hanging holes 124 in each row of the first hanging row 12 is set to 6.
As will be understood by referring to fig. 3, the first hanging row 12 has a main plate 121 and two webs 122, the main plate 121 is vertically disposed on the deck surface, the two webs 122 are respectively located on two sides of the main plate 121, the plate thickness of the main plate 121 is 18mm to 30mm, and the plate thickness of the webs 122 is 16 mm.
In the present embodiment, the main plate 121 and the two webs 122 are provided to improve the load-bearing capacity of the first hanger row 12.
In other alternative embodiments, the first sling row 12 is further provided with a toggle plate 123 to increase the load carrying capacity of the first sling row 12.
As will be understood with reference to fig. 2, the first block 1 has an overhanging structure 13 at its periphery, and in step S20, a plurality of first hanging points are distributed on the deck surface so that the plurality of first hanging points are all located on the overhanging structure 13.
In this embodiment, a plurality of first hoisting points are all located overhanging structure 13, can avoid overhanging structure 13 to warp at the actual hoist and mount in-process, increase the steadiness of whole first total section 1 at the actual hoist and mount in-process.
As will be understood with reference to fig. 2, the first block 1 has a protruding room 14, the protruding room 14 protruding from the deck surface of the first block, and in step S20, at least one first hanging point is located at the top of the protruding room 14.
In this embodiment, the protruding room 14 has a heavy weight, and must be installed and hoisted in the first block 1, and at least one hoisting point is disposed at the top of the protruding room 14, so as to prevent the protruding room 14 from deforming in the actual hoisting process to a certain extent, and thus, the first block 1 is more stable in the actual hoisting process.
As shown in fig. 2, in step S21, the first sling row 12 located in the protuberant room 14 extends in the length direction x of the first block 1, and the other first sling rows 12 extend in the width direction y of the first block 1.
Specifically, the first hanging strip 12 located in the protruding room 14 is provided as a full-length hanging strip, that is, penetrates through both sides of the top of the protruding room 14 in the width direction, so that stress transmission and dispersion of the protruding room 14 during hanging are ensured, and excessive stress of the protruding room 14 during hanging is avoided.
In one embodiment, the protruding room 14 is connected to the deck surface by means of a profile, ensuring that the protruding room 14 remains rigid when the first block 1 is hoisted.
In one embodiment, the lower structure of the overhanging structure 13 of the first total section 1 and the inner structure of the first total section 1 are connected by a profile to form a strong frame, thereby ensuring that the overhanging structure 13 remains rigid during hoisting.
The following steps are also included after step S20:
and S22, increasing the plate thickness of the deck plate corresponding to the position of the first hanging point so that the plate thickness of the deck plate is 12mm to 18 mm.
In the present embodiment, the thickness of the deck surface is increased, and the deck surface can be prevented from being deformed in the actual hoisting process.
As shown in fig. 4, 5 and 6, in step S30, the number of the second hanging points 25 is 4, the second block 2 has a front wall panel 21 and a rear wall panel 22 at both ends in the length direction x thereof, two second hanging points 25 are respectively provided above the front wall panel 21 and the rear wall panel 22, and a space is provided between the two second hanging points 25 on the same wall panel.
In this embodiment, since the width of the second block 2 is 60 meters and there is a gap between the two second lifting points 25, the second block 2 can be prevented from deforming in the width direction y during the lifting process, so that the second block 2 can maintain rigidity during the actual lifting process.
It should be noted that, as shown in fig. 5 and fig. 6, since the second suspension points 25 of the second block 2 are higher than the main hull, the distance between the 4 second suspension points 25 should be reasonably selected and not too narrow, that is, the rigidity of the second block 2 in the front-back and left-right directions should be ensured, in consideration of the height capacity of the crane ship (floating crane); too wide, i.e. too large a distance between the hooks 3 resulting in too large a distance to avoid too large a lateral force at the second lifting point 25, thereby avoiding that the second lifting point 25 is subjected to horizontal force components in addition to vertical forces. Specifically, as shown in fig. 5, in the transverse section, the included angle a between the horizontal plane of the second hanging point 25 and the force bearing direction is set to 83.7 °.
As shown in fig. 4, the following steps are also included after step S30:
s31, setting risers as the second hanging rows 23 at the plurality of second hanging points 25, respectively, the second hanging rows 23 extending along the width direction y of the second block 2, and the second hanging rows 23 having a plurality of second hanging holes 24.
In the present embodiment, the second hanger row 23 is provided with a plurality of second hanger holes 24, and thus, an excessive load can be avoided in a single hanger hole. Specifically, each second hanger row 23 is provided with 8 second hanger holes 24.
In other alternative embodiments, a plate may protrude from the front wall panel 21 and the rear wall panel 22 as the second hanger row 23.
The method further comprises the following steps after the step S31:
s32, increasing the plate thicknesses of the dash panel 21 and the rear wall panel 22 corresponding to the position of the second hanger row 23, and increasing the plate thickness of the deck surface near the second hanger row 23.
In this embodiment, since the weight of the second block 2 is large, the thicknesses of the dash panel 21, the rear wall panel 22, and the deck surface are increased, so that the dash panel 21, the rear wall panel 22, and the deck surface can be prevented from being deformed during the hoisting process, and the structural rigidity of the second block 2 is enhanced.
In one embodiment, there are upper and lower steps at some second hanging points 25 of the front and rear wall panels 21 and 22, and a second hanging row 23 stepped up and down is provided at the second hanging points 25.
While specific embodiments of the invention have been described above, it will be appreciated by those skilled in the art that this is by way of example only, and that the scope of the invention is defined by the appended claims. Various changes and modifications to these embodiments may be made by those skilled in the art without departing from the spirit and scope of the invention, and these changes and modifications are within the scope of the invention.

Claims (10)

1. A method for hoisting an FPSO ship living building is characterized by comprising the following steps:
s10, dividing the FPSO ship life building into a plurality of total sections, wherein the plurality of total sections comprise a first total section and a second total section;
s20, arranging a plurality of first hoisting points on the deck surface of the first block;
s30, arranging a plurality of second hoisting points on the deck surface of the second total section;
s40, hoisting the first total section through the first hoisting point by a crane;
s50, hoisting the second total section by the crane ship through the second hoisting point;
wherein the first block has a weight less than the lifting capacity of the crane and the second block has a weight greater than the lifting capacity of the crane.
2. The FPSO vessel living building hoisting method of claim 1 further comprising, after step S20, the steps of:
s21, arranging at least two first hanging rows on the first hanging points respectively;
each row of the first lifting rows is provided with a plurality of first lifting holes, and the number of the first lifting holes is larger than that of the lifting holes needed by actual lifting.
3. The method for hoisting the living building of the FPSO vessel according to claim 2 wherein the first hoisting row has a main plate and two webs, the main plate is vertically disposed on the deck surface, the two webs are respectively disposed on both sides of the main plate, the thickness of the main plate is 18mm to 30mm, and the thickness of the webs is 16 mm.
4. The FPSO vessel living building hoisting method of claim 1 wherein in step S20, the plurality of first hoisting points are distributed on the deck surface.
5. The FPSO vessel living building lifting method of claim 2 wherein the first section has a protruding room which protrudes from the deck surface, and at least one of the first lifting points is located at the top of the protruding room in step S20.
6. The FPSO vessel living building hoisting method of claim 5 wherein in step S21, the first hoist row located in the protruding room extends in the length direction of the first block, and the other first hoist rows extend in the width direction of the first block.
7. The FPSO vessel living building hoisting method of claim 1 further comprising, after step S20, the steps of:
and S22, increasing the plate thickness of the deck plate corresponding to the position of the first hanging point so that the plate thickness of the deck plate is 12mm to 18 mm.
8. The FPSO vessel living building hoisting method of claim 1 wherein in step S30, the number of the second hoisting points is 4, the second block has a front wall panel and a rear wall panel at both ends in the length direction thereof, the front wall panel and the rear wall panel have two of the second hoisting points respectively above, and the two second hoisting points on the same wall panel have a space therebetween.
9. The FPSO vessel living building hoisting method of claim 8 further comprising, after step S30, the steps of:
and S31, respectively arranging vertical plates at the second hanging points to serve as second hanging rows, wherein the second hanging rows extend along the width direction of the second total section and are provided with a plurality of second hanging holes.
10. The FPSO vessel living building hoisting method of claim 9 further comprising, after step S31, the steps of:
s32, increasing the plate thickness of the front wall plate and the rear wall plate corresponding to the position of the second hanging row, and increasing the wall thickness of the deck surface close to the second hanging row.
CN202010183969.2A 2020-03-16 2020-03-16 FPSO ship living building hoisting method Pending CN111301633A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010183969.2A CN111301633A (en) 2020-03-16 2020-03-16 FPSO ship living building hoisting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010183969.2A CN111301633A (en) 2020-03-16 2020-03-16 FPSO ship living building hoisting method

Publications (1)

Publication Number Publication Date
CN111301633A true CN111301633A (en) 2020-06-19

Family

ID=71155284

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010183969.2A Pending CN111301633A (en) 2020-03-16 2020-03-16 FPSO ship living building hoisting method

Country Status (1)

Country Link
CN (1) CN111301633A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113581414A (en) * 2021-09-03 2021-11-02 上海外高桥造船有限公司 Ship hoisting structure and hoisting system
CN115158592A (en) * 2022-08-11 2022-10-11 上海外高桥造船有限公司 Hoisting assembly and hoisting method for ship building block
CN117184359A (en) * 2023-08-07 2023-12-08 中交第四航务工程局有限公司 Hoisting method and hoisting equipment assembly for tower

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1709785A (en) * 2005-06-20 2005-12-21 上海外高桥造船有限公司 Sectional hoisting method
CN201882765U (en) * 2010-12-09 2011-06-29 金海重工股份有限公司 Hoisting ring for wholly hoisting superstructure
CN203094373U (en) * 2012-12-28 2013-07-31 上海中远船务工程有限公司 Living building module for floating production storage offloading (FPSO)
CN105947109A (en) * 2016-06-21 2016-09-21 江苏海通海洋工程装备有限公司 Process for hoisting whole assembly section of upper-layer building living zone of ship
US10023273B1 (en) * 2017-03-31 2018-07-17 Michael Silveri, Sr. Barge and assembly method
CN109052171B (en) * 2018-10-29 2019-11-19 上海外高桥造船有限公司 A kind of stem segmental hoisting method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1709785A (en) * 2005-06-20 2005-12-21 上海外高桥造船有限公司 Sectional hoisting method
CN201882765U (en) * 2010-12-09 2011-06-29 金海重工股份有限公司 Hoisting ring for wholly hoisting superstructure
CN203094373U (en) * 2012-12-28 2013-07-31 上海中远船务工程有限公司 Living building module for floating production storage offloading (FPSO)
CN105947109A (en) * 2016-06-21 2016-09-21 江苏海通海洋工程装备有限公司 Process for hoisting whole assembly section of upper-layer building living zone of ship
US10023273B1 (en) * 2017-03-31 2018-07-17 Michael Silveri, Sr. Barge and assembly method
CN109052171B (en) * 2018-10-29 2019-11-19 上海外高桥造船有限公司 A kind of stem segmental hoisting method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113581414A (en) * 2021-09-03 2021-11-02 上海外高桥造船有限公司 Ship hoisting structure and hoisting system
CN115158592A (en) * 2022-08-11 2022-10-11 上海外高桥造船有限公司 Hoisting assembly and hoisting method for ship building block
CN115158592B (en) * 2022-08-11 2024-03-26 上海外高桥造船有限公司 Hoisting assembly and hoisting method for building block on ship
CN117184359A (en) * 2023-08-07 2023-12-08 中交第四航务工程局有限公司 Hoisting method and hoisting equipment assembly for tower

Similar Documents

Publication Publication Date Title
CN111301633A (en) FPSO ship living building hoisting method
US3986471A (en) Semi-submersible vessels
TW201835444A (en) Floating offshore platform
CN109398599B (en) Installation method of planar insulation module for L NG shipboard containment system
CN101224849A (en) Hanging bracket for integral hoisting of ship superstructure and hoisting process
CN111392001A (en) Integrated hoisting method for hull structure
CN203740647U (en) Trestle for rolling shipment of objects with tubular structure
CN211281408U (en) A assistance-localization real-time frock that is used for different positions of engineering ship to fall mound
CN111056430A (en) Hoisting method of combined pump tower base of dual-fuel large container ship
CN208430499U (en) Large scale ship counterweight catch fixed pattern installation and repairing construction system
CN106628024A (en) Water-borne piling working platform
CN203740103U (en) Water transport system for offshore LNG storage tank
CN113581414B (en) Ship hoisting structure and hoisting system
CN210031511U (en) Anti-slamming fast empting device for offshore hoisting
CN209872190U (en) Heave compensation piston tensioner
CN210797306U (en) Prefabricated pier stud movable type automatic dumping ship
CN205150161U (en) Installation superelevation guide rail put up auxiliary device of usefulness during 45000T collection rolled ship construction
CN210559006U (en) Mounting structure of large crane on self-elevating platform
CN209816667U (en) Lifting lug structure for integral hoisting of anti-collision steel bushing box
CN115158592B (en) Hoisting assembly and hoisting method for building block on ship
CN220618076U (en) Superimposed sheet transportation, hoist device
CN219994596U (en) Pipeline interlayer suspended by hanging column
CN220199523U (en) Auxiliary crane boom rest
CN220098265U (en) Assembled six-ring hanging beam for hanging offshore wind power bucket foundation
CN214399487U (en) Diesel engine lifts by crane frock

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200619

RJ01 Rejection of invention patent application after publication