deformation
adjuster
embankment
foundation
ballastless track
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010134266.0A
Other languages
Chinese (zh)
Inventor
姚裕春
袁碧玉
张耀
刘洋
封志军
房立风
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN202010134266.0A priority Critical patent/CN111218860A/en
Publication of CN111218860A publication Critical patent/CN111218860A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B1/00Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
    • E01B1/002Ballastless track, e.g. concrete slab trackway, or with asphalt layers
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2/00General structure of permanent way

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Machines For Laying And Maintaining Railways (AREA)
  • Railway Tracks (AREA)

Abstract

The invention discloses a ballastless track railway deformation adjusting embankment structure and a construction method thereof, wherein the structure comprises an adjuster fixing foundation, a bearing device and a deformation adjuster, the adjuster fixing foundation is arranged on an embankment filling body, the deformation adjuster is fixedly arranged at the top of the adjuster fixing foundation, and the bearing device is arranged at the upper end of the deformation adjuster; the deformation adjuster is used for driving the bearing device to ascend or descend. The construction method is used for constructing the embankment structure, when the adverse deformation amount generated by the railway foundation exceeds the requirement of a ballastless track railway, the deformation regulator drives the bearing device to ascend or descend upwards or downwards, so that the height of the bearing device is adjusted, the requirement of the ballastless track railway on vertical deformation is met, the treatment strength of the soil foundation can be reduced, the investment of foundation treatment engineering can be saved, adverse effects caused by inaccurate foundation reconnaissance can be avoided, and the problem that the influence of the soil foundation on underground water extraction or loading near the railway can cause new uncertain and uneven settlement deformation can be solved.

Description

Ballastless track railway deformation adjusting embankment structure and construction method
Technical Field
The invention relates to the field of railway engineering, in particular to a ballastless track railway deformation adjusting embankment structure and a construction method thereof.
Background
The ballastless track is a track structure which adopts integral foundations such as concrete and asphalt mixture to replace a loose gravel track bed, is also called ballastless track, and is an advanced track technology in the world today.
In the prior art, when a ballastless track high-speed railway roadbed is constructed on a soil foundation, a embankment project usually needs to adopt foundation treatment measures to reinforce the soil foundation in order to meet the control requirement of settlement after millimeter-scale construction, and such treatment measures can cause high investment in the high-speed railway roadbed project, wherein the cost for soil foundation treatment can reach more than 2000 ten thousand per kilometer sometimes, which brings certain restriction influence on rapid construction and popularization of a high-speed railway. In addition, the reinforced soil foundation can generate new uneven settlement under the influence of underground water extraction or loading near the railway, and the new uneven settlement can bring great influence to the later operation of the ballastless track railway.
Disclosure of Invention
The invention aims to: aiming at the problems of high investment, large influence of later-stage peripheral environment and the like of a soil foundation high-speed railway subgrade in the prior art, the ballastless track railway deformation adjusting embankment structure and the construction method are provided.
In order to achieve the purpose, the invention adopts the technical scheme that:
a ballastless track railway deformation adjusting embankment structure comprises an adjuster fixing foundation, a bearing device and a deformation adjuster, wherein the adjuster fixing foundation is used for being arranged on a railway embankment filling body, the deformation adjuster is fixedly arranged at the top of the adjuster fixing foundation, and the bearing device is arranged at the upper end of the deformation adjuster;
the deformation adjuster is used for driving the bearing device to ascend or descend.
Through the structure, when the unfavorable deflection that the railway foundation produced surpassed ballastless track railway requirement, upwards or drive the load-bearing device through the deformation adjustment ware and rise or descend, thereby adjust the height of load-bearing device, make it satisfy ballastless track railway to the requirement of vertical deformation, thereby can reduce the handling strength of soil texture foundation, the deflection that sinks that produces can adjust through the deformation adjustment ware, so can save ground treatment project investment, or avoid the adverse effect that ground reconnaissance brought, can also solve soil texture foundation and produce new uncertain, the inhomogeneous deformation that subsides in the extraction groundwater or near the railway loading influence.
As a preferred scheme of the invention, the top of the embankment filling body is provided with a groove, the regulator fixing foundation is positioned in the groove, and the two sides of the regulator fixing foundation along the longitudinal direction of the line are respectively provided with a plurality of deformation regulators. Through above-mentioned structure, set up the fixed basis of regulator on the embankment filling body, make it as the fixed basis of deformation adjustment ware, can make the great concentration power of deformation adjustment ware transmission effectively diffuse to the embankment filling body in.
As a preferable aspect of the present invention, the embankment structure further includes a joist, the joist being located between the deformation adjuster and the carrier. Through the structure, the joist is a force transmission structure between the bearing device and the deformation adjuster, and the joist arranged between the bearing device and the deformation adjuster is in direct contact with the bearing device and the deformation adjuster, so that the thickness of the bearing device can be reduced, and the engineering cost is saved.
As a preferable scheme of the invention, the embankment structure further comprises at least two limiting devices, the at least two limiting devices are arranged on the embankment filling body, and the bearing device is positioned between the two limiting devices and is in contact with the inner sides of the two limiting devices. Through the structure, the limiting device can control the horizontal deformation of the bearing device.
As the preferred scheme of the invention, the limiting device comprises a limiting pile.
As a preferred aspect of the present invention, the deformation adjuster includes a hydraulic jack.
A ballastless track railway deformation adjusting embankment construction method is used for constructing the ballastless track railway deformation adjusting embankment structure and comprises the following steps:
s1: constructing and arranging a embankment filling body on a railway foundation;
s2, fixedly mounting a deformation adjuster on the top of the adjuster fixing base;
s3: a carrier is mounted on the upper end of the strain relief.
The construction method ensures effective realization of the embankment structure function, is simple to operate, controllable in quality and beneficial to popularization.
As a preferable aspect of the present invention, after the step S1 is completed, a groove is dug in the top of the embankment filler, and the adjuster fixing foundation is installed in the groove.
As a preferred aspect of the present invention, the embankment structure further includes joists, and in step S3, the joists are installed on top of the deformation adjusters, and the carriers are installed on top of the joists.
As a preferable aspect of the present invention, the embankment structure includes a stopper, and the stopper is installed on the embankment filler after the step of S3 is completed.
In summary, due to the adoption of the technical scheme, the invention has the beneficial effects that:
when the unfavorable deflection that the railway foundation produced exceeds ballastless track railway requirement, thereby drive bearing device through the deformation adjustment ware upwards or descend and rise or descend the height of adjustment bearing device, make it satisfy ballastless track railway to the requirement of vertical deformation, thereby can reduce the handling strength of soil texture foundation, the deflection that sinks that produces can adjust through the deformation adjustment ware, so can save ground treatment engineering investment, or avoid the adverse effect that ground reconnaissance is inaccurate to bring, can also solve soil texture foundation and draw groundwater or near railway loading influence and produce new uncertain, inhomogeneous settlement deformation.
Drawings
Fig. 1 is a schematic plan view of a ballastless track railway deformation adjusting embankment structure according to the invention.
Fig. 2 is a schematic cross-sectional view of the ballastless track railway deformation adjusting embankment structure according to the invention from the I-I side.
FIG. 3 is a schematic section II-II of the ballastless track railway deformation adjusting embankment structure.
Icon: 1-embankment filling; 2-regulator fixed base; 3-a strain adjuster; 4-a joist; 5-a carrying device; 6-a limiting device.
Detailed Description
The present invention will be described in detail below with reference to the accompanying drawings.
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Examples
As shown in fig. 1 to 3, the present embodiment provides a ballastless track railway deformation adjusting embankment structure, which includes an adjuster fixing foundation 2, a deformation adjuster 3, a bearing device 5, a joist 4, and a limiting device 6.
The regulator fixing foundation 2 is arranged on the railway embankment filling body 1, and specifically, the regulator fixing foundation 2 is of a reinforced concrete structure; the embankment filling body 1 is filled on a natural foundation or a foundation after reinforcement treatment in a layered mode, a groove is formed in the top of the embankment filling body 1, and the regulator fixing bases 2 are arranged on the embankment filling body 1 at intervals.
The bottom of the deformation adjuster 3 is fixedly arranged at the top of the adjuster fixing base 2, the deformation adjuster 3 is symmetrically arranged about the longitudinal center line of the adjuster fixing base 2, and specifically, the deformation adjuster 3 comprises a hydraulic jack; the joists 4 are arranged at the tops of the deformation regulators 3 at intervals, the bearing device 5 is arranged at the top of the joists 4 and is in close contact with the tops of the joists 4, specifically, the joists 4 comprise prefabricated joists 4 or cast-in-place reinforced concrete joists 4, the bearing device 5 comprises a prefabricated bearing plate or a cast-in-place reinforced concrete bearing plate, and the deformation regulators 3 are used for driving the bearing device 5 to ascend or descend.
The limiting devices 6 are embedded in the embankment filling body 1 in rows at intervals, and specifically, the limiting devices 6 comprise limiting piles; the two limit devices 6 are positioned on the same horizontal line to form a row, and the bearing device 5 is positioned between the two limit devices 6 in the row and is tightly contacted with the inner sides of the two limit devices 6 in the row.
The embodiment also provides a ballastless track railway deformation adjusting embankment construction method, which is used for constructing the ballastless track railway embankment structure and comprises the following steps:
s1: arranging an embankment filling body 1 on a natural foundation or a reinforced foundation in a layered construction mode;
s2: excavating a groove at the top of the embankment filling body 1, and arranging the regulator fixing foundation 2 in the groove;
s3, mounting the deformation adjuster 3 on the top of the adjuster fixing base 2;
s4: mounting a prefabricated joist 4 or a cast-in-place reinforced concrete joist 4 at the top of the deformation regulator 3;
s5: a prefabricated bearing plate or a cast-in-place reinforced concrete bearing plate is arranged at the top of the joist 4;
s6: two rows of limiting devices 6 are closely contacted with two sides of the bearing device 5, and the two rows of limiting devices 6 are buried in the embankment filling body 1.
The ballastless track railway deformation adjusting embankment structure and the construction method provided by the embodiment have the beneficial effects that:
the top of embankment filling body 1 is equipped with the recess, and regulator fixed foundation 2 is located the recess, and deformation adjustment ware 3 is fixed to be set up on regulator fixed foundation 2, makes it as deformation adjustment ware 3's fixed foundation, can make the great concentrated power of deformation adjustment ware 3 transmission effectively diffuse to embankment filling body 1.
The deformation regulator 3 is fixedly arranged on the regulator fixing foundation 2, the joist 4 is positioned at the top of the deformation regulator 3, the bearing device 5 is positioned at the top of the joist 4, the deformation regulator 3 is used for driving the bearing device 5 to ascend or descend, when the unfavorable deformation generated by the railway foundation exceeds the requirement of a ballastless track railway, the bearing device 5 is driven to ascend or descend upwards or downwards by the deformation regulator 3, so that the height of the bearing device 5 is adjusted, the bearing device meets the requirement of the ballastless track railway on vertical deformation, the treatment strength of the soil foundation can be reduced, the generated subsidence deformation can be adjusted by the deformation regulator 3, the investment of foundation treatment engineering can be saved, the adverse effect caused by inaccurate foundation survey can be avoided, and the problems that new uncertain deformation is generated when the soil foundation is subjected to underground water extraction or loading influence nearby the railway can be solved, And (4) uneven settlement deformation. Meanwhile, the joist 4 is a force transmission structure between the bearing device 5 and the deformation regulator 3, and compared with the joist 4 arranged between the bearing device 5 and the deformation regulator 3 and the joist 4 directly contacted with the bearing device 5 and the deformation regulator 3, the thickness of the bearing device 5 can be reduced, so that the engineering cost is saved.
The two limiting devices 6 are positioned on the same horizontal line to form a row, the bearing device 5 is positioned between the two limiting devices 6 in the row and is in close contact with the inner sides of the two limiting devices 6 in the row, and the limiting devices 6 can control the horizontal deformation of the bearing device 5.
The method for constructing the ballastless track railway deformation adjusting embankment guarantees effective realization of the ballastless track railway deformation adjusting embankment structure function, is simple to operate, controllable in quality and beneficial to popularization.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents and improvements made within the spirit and principle of the present invention are intended to be included within the scope of the present invention.

Claims (10)

1. The ballastless track railway deformation adjusting embankment structure is characterized by comprising an adjuster fixing foundation (2), a bearing device (5) and a deformation adjuster (3), wherein the adjuster fixing foundation (2) is used for being arranged on a railway embankment filling body (1), the deformation adjuster (3) is fixedly arranged at the top of the adjuster fixing foundation (2), and the bearing device (5) is arranged at the upper end of the deformation adjuster (3);
the deformation adjuster (3) is used for driving the bearing device (5) to ascend or descend.
2. The ballastless track railway deformation adjusting embankment structure according to claim 1, wherein a groove is formed at the top of the embankment filling body (1), the adjuster fixing base (2) is located in the groove, and a plurality of deformation adjusters (3) are respectively arranged on the adjuster fixing base (2) along two longitudinal sides of the line.
3. The ballastless track railway deformation adjusting embankment structure of claim 1, further comprising a joist (4), wherein the joist (4) is located between the deformation adjuster (3) and the carrying device (5).
4. The ballastless track railway deformation adjusting embankment structure according to claim 2, further comprising at least two position limiting devices (6), wherein at least two position limiting devices (6) are arranged on the embankment filling body (1), and the bearing device (5) is positioned between the two position limiting devices (6) and is in contact with the inner sides of the two position limiting devices (6).
5. The ballastless track railway deformation adjusting embankment structure of claim 4, wherein the limiting device (6) comprises a limiting pile.
6. The ballastless track railway deformation adjusting embankment structure of claim 1, wherein the deformation adjuster (3) comprises a hydraulic jack.
7. A ballastless track railway deformation adjusting embankment construction method, which is used for constructing the embankment structure of any one of the claims 1-6, and comprises the following steps:
s1: constructing and arranging the embankment filling body (1) on a railway foundation;
s2, fixedly mounting the deformation adjuster (3) on the top of the adjuster fixing base (2);
s3: -mounting the carrier means (5) at the upper end of the deformation adjuster (3).
8. The method for constructing the deformation adjusting embankment for the ballastless track railway according to claim 7, wherein after the step S1 is completed, a groove is dug at the top of the embankment filling body (1), and the adjuster fixing foundation (2) is constructed and arranged in the groove.
9. The ballastless track railway deformation adjusting embankment construction method of claim 7, wherein the embankment structure further comprises a joist (4), and in the step S3, the joist (4) is installed on the top of the deformation adjuster (3), and the bearing device (5) is installed on the top of the joist (4).
10. The method for constructing the deformation adjusting embankment of the ballastless track railway according to claim 7, wherein the embankment structure comprises a limiting device (6), and after the step of S3 is completed, the limiting device (6) is installed on the embankment filling body (1).
CN202010134266.0A 2020-03-02 2020-03-02 Ballastless track railway deformation adjusting embankment structure and construction method Pending CN111218860A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010134266.0A CN111218860A (en) 2020-03-02 2020-03-02 Ballastless track railway deformation adjusting embankment structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010134266.0A CN111218860A (en) 2020-03-02 2020-03-02 Ballastless track railway deformation adjusting embankment structure and construction method

Publications (1)

Publication Number Publication Date
CN111218860A true CN111218860A (en) 2020-06-02

Family

ID=70831421

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010134266.0A Pending CN111218860A (en) 2020-03-02 2020-03-02 Ballastless track railway deformation adjusting embankment structure and construction method

Country Status (1)

Country Link
CN (1) CN111218860A (en)

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06248606A (en) * 1993-02-24 1994-09-06 Sumitomo Rubber Ind Ltd Vibration-proof track
DE19855350A1 (en) * 1998-12-01 2000-06-15 Bahnbau Wels Gmbh Wels Method to construct railway track on base plates of permanent ways uses setting stabilizer asphalt etc. to stabilizer sleepers, to which rails are fastened after setting
JP2011089358A (en) * 2009-10-26 2011-05-06 Jfe Steel Corp Heavy load conveying mechanism and heavy load conveying method using the same
CN201962557U (en) * 2011-03-31 2011-09-07 中铁第四勘察设计院集团有限公司 Plate type structure of unde-crossing line structural joint of railway ballastless track
CN103233400A (en) * 2013-05-22 2013-08-07 中铁二院工程集团有限责任公司 Ballastless track railway bridge joint differential settlement adjusting device
KR20140023724A (en) * 2012-08-17 2014-02-27 주식회사 이알에스 Rail track system having the complex structure for vibration absorption
CN103835191A (en) * 2012-11-21 2014-06-04 中铁第四勘察设计院集团有限公司 Monolithic track bed track structure capable of being rapidly assembled
CN207391939U (en) * 2017-10-30 2018-05-22 青岛科而泰环境控制技术有限公司 Plate-type ballastless railway roadbed
CN109868691A (en) * 2017-12-01 2019-06-11 中铁二院工程集团有限责任公司 It is a kind of to deform adjustable High Speed Railway Subgrade and construction method and sedimentation and deformation method of adjustment
CN209178725U (en) * 2018-09-28 2019-07-30 中铁第一勘察设计院集团有限公司 It is a kind of can fast lifting track structure
CN110195381A (en) * 2019-05-30 2019-09-03 中国铁道科学研究院集团有限公司铁道建筑研究所 Non-fragment orbit lifting method
CN211772439U (en) * 2020-03-02 2020-10-27 中铁二院工程集团有限责任公司 Ballastless track railway deformation adjusting embankment structure

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06248606A (en) * 1993-02-24 1994-09-06 Sumitomo Rubber Ind Ltd Vibration-proof track
DE19855350A1 (en) * 1998-12-01 2000-06-15 Bahnbau Wels Gmbh Wels Method to construct railway track on base plates of permanent ways uses setting stabilizer asphalt etc. to stabilizer sleepers, to which rails are fastened after setting
JP2011089358A (en) * 2009-10-26 2011-05-06 Jfe Steel Corp Heavy load conveying mechanism and heavy load conveying method using the same
CN201962557U (en) * 2011-03-31 2011-09-07 中铁第四勘察设计院集团有限公司 Plate type structure of unde-crossing line structural joint of railway ballastless track
KR20140023724A (en) * 2012-08-17 2014-02-27 주식회사 이알에스 Rail track system having the complex structure for vibration absorption
CN103835191A (en) * 2012-11-21 2014-06-04 中铁第四勘察设计院集团有限公司 Monolithic track bed track structure capable of being rapidly assembled
CN103233400A (en) * 2013-05-22 2013-08-07 中铁二院工程集团有限责任公司 Ballastless track railway bridge joint differential settlement adjusting device
CN207391939U (en) * 2017-10-30 2018-05-22 青岛科而泰环境控制技术有限公司 Plate-type ballastless railway roadbed
CN109868691A (en) * 2017-12-01 2019-06-11 中铁二院工程集团有限责任公司 It is a kind of to deform adjustable High Speed Railway Subgrade and construction method and sedimentation and deformation method of adjustment
CN209178725U (en) * 2018-09-28 2019-07-30 中铁第一勘察设计院集团有限公司 It is a kind of can fast lifting track structure
CN110195381A (en) * 2019-05-30 2019-09-03 中国铁道科学研究院集团有限公司铁道建筑研究所 Non-fragment orbit lifting method
CN211772439U (en) * 2020-03-02 2020-10-27 中铁二院工程集团有限责任公司 Ballastless track railway deformation adjusting embankment structure

Similar Documents

Publication Publication Date Title
CN208219303U (en) A kind of high-speed railway cast-in-situ bored pile frame-type road structure
CN108867200B (en) Anti-bulge rock cutting structure of high-speed railway and design method
CN202466342U (en) Reinforcing structure of deep soil foundation of high speed railway
CN111412002B (en) Construction method of anchor cable opposite-pulling type supporting structure system
CN106638663A (en) Foundation reinforcing and integral inclination rectifying and shifting method for high-voltage transmission tower in subsidence area
CN110107303A (en) The deformation control method of shallow earthing shield boring across underneath high-speed railway
CN211772439U (en) Ballastless track railway deformation adjusting embankment structure
CN107100179B (en) Light combined retaining structure and method for treating large-range high-fill slope engineering
CN107841908A (en) For eliminating the road structure of the high embankment lateral variation sedimentation in high-speed railway abrupt slope
CN116971362B (en) Building terrace reinforcing and lifting method on shallow gravel soil foundation
CN202595581U (en) Improved sleeper railway ballast structure
CN201459525U (en) Foundation structure at tunnel-to-bridge junction of high-speed railway in loess regions
CN111218860A (en) Ballastless track railway deformation adjusting embankment structure and construction method
CN102352582A (en) Reinforced soil-cement pile strengthening structure of railway roadbed
CN211872416U (en) Ballastless track cutting structure and system for expansive and contractive deformation foundation
CN110820817A (en) Bridge pier stud pile foundation combination deviation rectifying method
CN106869198B (en) Method for reinforcing loose soil subsidence space area by using cross beam to reinforce tower foundation
CN113638617B (en) Method for underground layer-adding during trailer shifting
CN211772498U (en) Abrupt slope supports atress type roadbed structure
CN210238530U (en) Foundation pit side wall stress adjusting system for deep and unstable stratum
CN221461258U (en) Abutment structure
CN207525740U (en) Be suitable for soft soil area's barb-shaped precast pile
CN207032274U (en) Heavy stage deviation-rectifying system at the beginning of a kind of open caisson
CN105714633A (en) U-shaped retaining structure for fill subgrade and construction method of U-shaped retaining structure
CN111218859A (en) Ballastless track cutting structure, system and construction method for expansive and contractive deformation foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination