CN111173531A - Non-explosive excavation method for urban tunnel - Google Patents

Non-explosive excavation method for urban tunnel Download PDF

Info

Publication number
CN111173531A
CN111173531A CN202010107890.1A CN202010107890A CN111173531A CN 111173531 A CN111173531 A CN 111173531A CN 202010107890 A CN202010107890 A CN 202010107890A CN 111173531 A CN111173531 A CN 111173531A
Authority
CN
China
Prior art keywords
tunnel
heading machine
cutting head
excavation
dust removal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010107890.1A
Other languages
Chinese (zh)
Inventor
陈科
马雪莲
饶勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Construction Engineering Group Co Ltd
Original Assignee
China Metallurgical Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Metallurgical Construction Engineering Group Co Ltd filed Critical China Metallurgical Construction Engineering Group Co Ltd
Priority to CN202010107890.1A priority Critical patent/CN111173531A/en
Publication of CN111173531A publication Critical patent/CN111173531A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F5/00Means or methods for preventing, binding, depositing, or removing dust; Preventing explosions or fires
    • E21F5/02Means or methods for preventing, binding, depositing, or removing dust; Preventing explosions or fires by wetting or spraying
    • E21F5/04Spraying barriers
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/10Making by using boring or cutting machines
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a non-explosive excavation method for an urban tunnel, which comprises the following steps: s1, preparing for excavation; s2, installing a dust removing and settling system in the heading machine, wherein the dust removing and settling system comprises a water pipe, the water pipe at the cutting head section can synchronously rotate with the cutting head, and a plurality of spray heads communicated with the water pipe and extending out of the cutting head are circumferentially arranged on the water pipe; a wet dust removal fan is further arranged in the cab of the heading machine, one end of a suction pipeline of the wet dust removal fan extends out of the cab and is fixed near the cutting head, and the other end of the suction pipeline extends out of the heading machine; and S3, excavating the tunnel by using a heading machine, and opening a water pipe and a wet dust removal fan in the dust removal system in the S2 to perform dust settling and dust removal treatment while excavating. The non-explosive excavation method for the urban tunnel can effectively inhibit the raised dust generated in the tunnel excavation process, effectively relieve the problem that the raised dust is large when the development machine excavates, and do not influence the subsequent inverted arch and second-lining construction.

Description

Non-explosive excavation method for urban tunnel
Technical Field
The invention relates to the field of tunnel excavation, in particular to a non-explosive urban tunnel excavation method.
Background
Urban tunnels are applied to old urban area transformation as more and more modes, but old urban area houses are old, if settlement control is not tight in the tunnel excavation process, residential houses are cracked and damaged, slight claim compensation is required, relocation and removal are seriously required, otherwise normal construction cannot be carried out, and the settlement control requirement in the tunnel excavation process is more and more strict. The development machine has been used in tunnel excavation, but the dust control of development when the development machine excavates can not effectively be solved to the influence is great to follow-up inverted arch excavation and second lining construction.
Disclosure of Invention
Aiming at the defects of the prior art, the technical problems to be solved by the invention are as follows: how to provide a city tunnel non-explosion excavation method which can effectively restrain the raised dust generated in the tunnel excavation process and effectively improve the construction quality.
In order to solve the technical problems, the invention adopts the following technical scheme:
a non-explosive excavation method for urban tunnels is characterized by comprising the following steps: s1, preparing for excavation; driving a tunneling machine required for tunnel excavation into a construction site; s2, installing a dust removal and dust fall system in the heading machine, wherein the dust removal and dust fall system comprises a water pipe, one end of the water pipe is communicated with a water tank on a construction site, the other end of the water pipe is arranged in the heading machine, penetrates through a cab of the heading machine and then is fixed in a cutting head of the heading machine, the water pipe on the section of the cutting head can synchronously rotate with the cutting head, and a plurality of spray heads which are communicated with the water pipe and extend out of the cutting head are circumferentially arranged on the section of the water pipe; the water pipe is also provided with a control valve for controlling the opening and closing of the water pipe pipeline; a wet dust removal fan is further arranged in the cab of the heading machine, one end of a suction pipeline of the wet dust removal fan extends out of the cab and is fixed near the cutting head, and the other end of the suction pipeline extends out of the heading machine; s3, excavating the tunnel by using the tunneling machine, moving the tunneling machine to the excavation face during excavation, starting a cutting head of the tunneling machine, cutting by utilizing the cutting head to move up and down and left and right to cut a preliminary section shape, moving the tunneling machine forwards after the section size requirement is met, and excavating the next section of tunnel according to the tunneling and excavation mode; and (3) opening the water conveying pipe and the wet dust removal fan in the dust removal system in the S2 when the tunnel is excavated, spraying around the tunnel face by the spray head when the cutting head cuts, reducing the temperature of the cutting head and reducing the raised dust generated after the cutting head cuts, and simultaneously, sucking the dust around the tunnel face by the wet dust removal fan and then leading out the dust out of the excavated tunnel through the suction pipeline. Like this, adopt the entry driving machine to cut, can carry out no blasting vibration construction, it is little to the country rock disturbance, it is little to the earth's surface vibration, but continuous excavation operation, efficient, the overbreak is little, can not cause great disturbance to ground, the condition of sinking to the ground can not appear. The dust removal and dust fall system arranged in the heading machine can perform dust fall and dust absorption on the periphery of the tunnel face while the heading machine cuts, and the sucked raised dust is guided out of the excavated tunnel through the suction pipeline, so that the problem that the raised dust is large when the heading machine excavates is effectively solved, and subsequent inverted arch and second-liner construction are not influenced.
Furthermore, an opening spraying dust removal pipeline is arranged at the tunnel opening and along the opening of the tunnel opening; meanwhile, a protective greenhouse is arranged at the hole, and spraying is adopted around the greenhouse for dust reduction. Like this, set up at the entrance to a cave and spray behind the dust removal pipeline, can carry out the dust fall to the raise dust outside the discharge tunnel, simultaneously, the protection big-arch shelter that sets up can effectively control the raise dust in the big-arch shelter, prevents the raise dust diffusion. The dregs after the cutterhead cuts are transported to the conveyer belt through the shovel plate part of the tunneling machine and transported out of the protective greenhouse outside the tunnel by a small-sized transport vehicle, then the dregs are transported in the protective greenhouse by the dregs transport vehicle, and then the generated dust of the dregs is effectively controlled.
Furthermore, before the tunnel is excavated, the tunnel to be excavated is ventilated according to design requirements, and constructors measure whether toxic and harmful gas in the tunnel exceeds the standard or not. Therefore, the ventilation performance of the construction site can be effectively ensured, and the life safety of constructors is ensured.
Furthermore, when cutting slightly hard rock, a method of circularly cutting from bottom to top left and right is adopted, and when the vault exceeds the cutting height of the tunneling machine, a slope needs to be padded by broken stones so as to ensure that the excavation section is not underexcavated. Like this, adopt from bottom to top mode cutting, to the wearing and tearing of drill bit pick when reducible rock excavation, reduce the pick consumption, practice thrift the cost, guarantee that the excavation section is not owed and dig.
Further, when cutting a slightly hard rock, the cutting is carried out according to a snake-shaped line from bottom to top. Therefore, the over-excavation and under-excavation of the heading machine during excavation can be controlled, the operation of a driver is facilitated, and the excavation is carried out according to the designed outline.
Furthermore, after the tunnel face is cut by the tunneling machine, the tunnel face needs to be measured and then manually repaired by an air pick. Therefore, the size of the excavated tunnel can be ensured to be accurate, the design requirement is met, and the surface is smooth.
Further, after each section of tunnel is primarily cut, primary support needs to be constructed according to design requirements; during supporting, according to design requirements, firstly spraying concrete to seal, then erecting a steel arch, then drilling a hollow anchor rod and grouting, then spraying concrete to the designed thickness, then drilling a small advanced guide pipe and grouting, and finally starting the next circular excavation. Therefore, when the next cycle development machine is excavated, the driver is still in the range of primary support or advance support, and the production safety of operators is ensured.
Furthermore, the water delivery pipe comprises a first pipeline communicated with an external water source and a second pipeline assembled at the connecting end of the first pipeline, the connecting end of the first pipeline is arranged in the cab of the heading machine, and the second pipeline can rotate around the axis of the second pipeline as the circle center. Therefore, one of the pipelines can rotate, so that the pipeline can rotate synchronously under the driving of the cutting head.
Furthermore, the spray header is obliquely arranged on the second pipeline, and the inclination angle is 30-60 degrees. In this way, the arranged spray header is inclined, can be sprayed out in a circular ray shape after rotating, has wide coverage and has better dust fall effect.
Drawings
FIG. 1 is a schematic view of the cutting state of the heading machine in the embodiment;
FIG. 2 is a schematic view of a cutting path of a tunnel face in the embodiment;
fig. 3 is a schematic distribution diagram of a spraying system of a tunnel portal in the embodiment.
In the figure: the device comprises a heading machine 1, a heading machine cab 11, a water delivery pipe 2, a first pipeline 21, a second pipeline 22, a spray header 3, a wet dust removal fan 4, a suction pipeline 5 and a spray dust removal pipeline 6.
Detailed Description
The invention is further illustrated with reference to the following figures and examples.
Example (b):
the non-explosive excavation method for the urban tunnel provided by the embodiment comprises the following steps: s1, preparing for excavation; driving a tunneling machine required for tunnel excavation into a construction site; s2, installing a dust removing and falling system (as shown in figure 1) in the heading machine 1, wherein the dust removing and falling system comprises a water pipe 2, one end of the water pipe 2 is communicated with a water tank on a construction site, the other end of the water pipe 2 is arranged in the heading machine 1 and penetrates through a cab 11 of the heading machine to be fixed in a cutting head of the heading machine, the water pipe at the section of the cutting head can synchronously rotate with the cutting head, and a plurality of spray heads 3 which are communicated with the water pipe 2 and extend out of the cutting head are circumferentially arranged on the section of the water pipe 2; the water pipe 2 is also provided with a control valve for controlling the opening and closing of the water pipe pipeline; a wet dust removal fan 4 is further arranged in the cab 11 of the heading machine, one end of a suction pipeline 5 of the wet dust removal fan 4 extends out of the cab and is fixed near the cutting head, and the other end of the suction pipeline extends out of the heading machine; s3, excavating the tunnel by using the heading machine 1, moving the heading machine 1 to the face of the excavated tunnel during excavation, starting a cutting head of the heading machine, cutting by utilizing the cutting head to move up and down and left and right to cut a preliminary section shape, moving the heading machine forward after the section size requirement is met, and excavating the next section of tunnel according to the tunneling and excavation mode; when excavating, open raceway 2 and wet dedusting fan 4 among the dust pelletizing system in S2, when the cutterhead cutting, shower 3 sprays around the face, reduces the temperature of cutterhead and reduces the generated raise dust after the cutterhead cutting, simultaneously, wet dedusting fan draws the tunnel of excavating outside through the suction pipeline behind the dust suction around the face.
Further, an opening spraying dust removal pipeline 6 (shown in fig. 3) is arranged at the tunnel opening and along the opening; meanwhile, a protective greenhouse (not shown in the figure) is arranged at the hole, and spraying is adopted around the greenhouse for dust reduction.
Before the tunnel is excavated, the old tunnel beside the new tunnel to be excavated is ventilated according to the design requirement, and constructors measure whether toxic and harmful gas in the tunnel exceeds the standard or not.
When cutting slightly hard rock, a method of circularly cutting from bottom to top left and right is adopted, and when the vault exceeds the cutting height of the tunneling machine, a slope needs to be padded by broken stones so as to ensure that the excavation section is not underexcavated. When cutting is carried out specifically, cutting can be carried out according to a snake-shaped circuit from bottom to top (as shown in figure 2).
Furthermore, after the tunnel face is cut by the tunneling machine, the tunnel face needs to be measured and then manually repaired by an air pick.
Further, after each section of tunnel is primarily cut, primary support needs to be constructed according to design requirements; during supporting, according to design requirements, firstly spraying concrete to seal, then erecting a steel arch, then drilling a hollow anchor rod and grouting, then spraying concrete to the designed thickness, then drilling a small advanced guide pipe and grouting, and finally starting the next circular excavation.
As shown in fig. 1, the water pipe includes a first pipe 21 communicated with an external water source and a second pipe 22 assembled at a connection end of the first pipe, the connection end of the first pipe 21 is arranged in the cab 11 of the heading machine, and the second pipe 22 can rotate around the axis thereof; the spray headers are obliquely arranged on the second pipeline, the inclination angle is 30-60 degrees, and during specific implementation, the inclination angles of the spray headers can be set to different angles so as to maximize the coverage area of the water mist.
Finally, it should be noted that the above embodiments are only used for illustrating the technical solutions of the present invention and not for limiting the technical solutions, and although the present invention has been described in detail by referring to the preferred embodiments, those skilled in the art should understand that modifications or equivalent substitutions to the technical solutions of the present invention can be made without departing from the spirit and scope of the technical solutions, and all the modifications and equivalent substitutions should be covered by the claims of the present invention.

Claims (9)

1. A non-explosive excavation method for urban tunnels is characterized by comprising the following steps: s1, preparing for excavation; driving a tunneling machine required for tunnel excavation into a construction site; s2, installing a dust removal and dust fall system in the heading machine (1), wherein the dust removal and dust fall system comprises a water pipe (2) with one end communicated with a water tank on a construction site and the other end arranged in the heading machine (1) and fixed in a heading machine cutting head after penetrating through a heading machine cab (11), the water pipe at the cutting head section can rotate synchronously with the cutting head, and a plurality of spray heads (3) communicated with the water pipe and extending out of the cutting head are circumferentially arranged on the water pipe (2) section; the water pipe (2) is also provided with a control valve for controlling the opening and closing of the water pipe pipeline; a wet dust removal fan (4) is further arranged in the cab (11) of the heading machine, one end of a suction pipeline (5) of the wet dust removal fan (4) extends out of the cab and is fixed near the cutting head, and the other end of the suction pipeline extends out of the heading machine; s3, excavating a tunnel by using the heading machine (1), moving the heading machine (1) to an excavation face during excavation, starting a cutting head of the heading machine, cutting by utilizing the cutting head to move up and down and left and right to cut a preliminary section shape, moving the heading machine forwards after the section size requirement is met, and excavating a next section of tunnel according to the excavation mode; when the tunnel is excavated, the water conveying pipe (2) and the wet dust removal fan (4) in the dust removal system in the S2 are opened, the spray head (3) sprays around the face when the cutting head cuts, the temperature of the cutting head is reduced, raised dust generated after the cutting head cuts is reduced, and meanwhile, the wet dust removal fan sucks dust around the face and then leads out the excavated tunnel through the suction pipeline.
2. The non-explosive urban tunnel excavation method according to claim 1, wherein a hole spraying dust removal pipeline (6) is arranged at the tunnel hole and along the hole; meanwhile, a protective greenhouse is arranged at the hole, and spraying is adopted around the greenhouse for dust reduction.
3. The non-explosive urban tunnel excavation method according to claim 1, wherein before the tunnel excavation, the tunnel is ventilated according to design requirements, and constructors measure whether toxic and harmful gases in the tunnel exceed standards.
4. The non-explosive urban tunnel excavation method according to claim 1, wherein when cutting slightly hard rocks, a bottom-up left-right circular cutting method is adopted, and when the vault exceeds the cutting height of the heading machine, a slope needs to be padded with broken stones to ensure that the excavation section is not underexcavated.
5. The non-explosive urban tunnel excavation method according to claim 1, wherein when cutting slightly hard rock, the cutting is performed according to a serpentine path from bottom to top.
6. The non-explosive urban tunnel excavation method according to claim 4 or 5, wherein after the tunnel face is cut by a heading machine, the tunnel face is measured and then manually repaired by an air pick.
7. The non-explosive urban tunnel excavation method according to claim 1, wherein after each section of tunnel is initially cut, primary support is required according to design requirements; during supporting, according to design requirements, firstly spraying concrete to seal, then erecting a steel arch, then drilling a hollow anchor rod and grouting, then spraying concrete to the designed thickness, then drilling a small advanced guide pipe and grouting, and finally starting the next circular excavation.
8. The non-explosive urban tunnel excavation method according to claim 1, wherein the water conveying pipe comprises a first pipeline (21) communicated with an external water source and a second pipeline (22) assembled at a connecting end of the first pipeline, the connecting end of the first pipeline (21) is arranged in the cab (11) of the heading machine, and the second pipeline (22) can rotate around the axis of the second pipeline as a circle center.
9. The non-explosive urban tunnel excavation method according to claim 8, wherein the shower head is obliquely installed on the second pipe at an inclination angle of 30 to 60 °.
CN202010107890.1A 2020-02-21 2020-02-21 Non-explosive excavation method for urban tunnel Pending CN111173531A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010107890.1A CN111173531A (en) 2020-02-21 2020-02-21 Non-explosive excavation method for urban tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010107890.1A CN111173531A (en) 2020-02-21 2020-02-21 Non-explosive excavation method for urban tunnel

Publications (1)

Publication Number Publication Date
CN111173531A true CN111173531A (en) 2020-05-19

Family

ID=70648280

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010107890.1A Pending CN111173531A (en) 2020-02-21 2020-02-21 Non-explosive excavation method for urban tunnel

Country Status (1)

Country Link
CN (1) CN111173531A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112065426A (en) * 2020-10-10 2020-12-11 中铁华铁工程设计集团有限公司 Movable type rotary milling cutter head tunneling machine

Citations (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1373306A (en) * 1972-07-15 1974-11-06 Lemand Eng Ltd Mining machines
JPS60126594U (en) * 1984-01-31 1985-08-26 株式会社三井三池製作所 Excavator water sprinkler dust collector
JP2004225254A (en) * 2003-01-20 2004-08-12 Mitsui Miike Mach Co Ltd Partial dust collector
CN102206997A (en) * 2010-03-15 2011-10-05 桑德威克采矿和建筑有限责任公司 Heading machine
CN102383790A (en) * 2011-10-27 2012-03-21 山西晋煤集团金鼎煤机矿业有限责任公司 Novel cutting head spiral drum used for shearer
CN103291308A (en) * 2013-05-29 2013-09-11 王卓 Boom-type roadheader for tunnel construction and tunnel construction method
CN204002793U (en) * 2014-03-29 2014-12-10 何后田 A kind of dustless development machine
CN204572044U (en) * 2015-01-21 2015-08-19 杭州市建设工程质量安全监督总站 A kind of tunnel portal automatic spray dust fall structure
CN205277418U (en) * 2015-12-23 2016-06-01 林州重机集团股份有限公司 Spraying structure in entry driving machine
CN106246193A (en) * 2016-09-06 2016-12-21 中铁二十四局集团南昌铁路工程有限公司 Strong karst high rich water urban shallow tunnel cantilever excavator construction
CN206000541U (en) * 2016-08-30 2017-03-08 中国铁建股份有限公司 Device is dug in a kind of tunneling and underground engineering tunneling boring cantilever excavator arc milling
CN106907150A (en) * 2017-04-19 2017-06-30 江西理工大学 A kind of improved tunnelling machine
CN206707751U (en) * 2017-05-09 2017-12-05 中交二公局东萌工程有限公司 A kind of spray dust's system for tunnel portal construction slag-soil truck
CN107514275A (en) * 2017-10-19 2017-12-26 淮南矿业(集团)有限责任公司 Tunnelling dust prevention system
CN207093088U (en) * 2017-09-04 2018-03-13 太重煤机有限公司 A kind of digging laneway dust goes out except device
CN109681202A (en) * 2019-01-28 2019-04-26 黄山市徽州安华工程机械有限公司 The spray dust-reducing system of development machine
CN208816126U (en) * 2018-09-30 2019-05-03 朱启杰 A kind of driving face concurrent flow air curtain orientation dust collect plant
CN109779629A (en) * 2019-01-28 2019-05-21 黄山市徽州安华工程机械有限公司 Atomizing de-dusting cutterhead
CN110080790A (en) * 2019-04-03 2019-08-02 中船第九设计研究院工程有限公司 A kind of boom-type roadheader excavated for tunnel
CN210003281U (en) * 2019-05-09 2020-01-31 中铁八局集团第三工程有限公司 cantilever heading machine with dust removal function

Patent Citations (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1373306A (en) * 1972-07-15 1974-11-06 Lemand Eng Ltd Mining machines
JPS60126594U (en) * 1984-01-31 1985-08-26 株式会社三井三池製作所 Excavator water sprinkler dust collector
JP2004225254A (en) * 2003-01-20 2004-08-12 Mitsui Miike Mach Co Ltd Partial dust collector
CN102206997A (en) * 2010-03-15 2011-10-05 桑德威克采矿和建筑有限责任公司 Heading machine
CN102383790A (en) * 2011-10-27 2012-03-21 山西晋煤集团金鼎煤机矿业有限责任公司 Novel cutting head spiral drum used for shearer
CN103291308A (en) * 2013-05-29 2013-09-11 王卓 Boom-type roadheader for tunnel construction and tunnel construction method
CN204002793U (en) * 2014-03-29 2014-12-10 何后田 A kind of dustless development machine
CN204572044U (en) * 2015-01-21 2015-08-19 杭州市建设工程质量安全监督总站 A kind of tunnel portal automatic spray dust fall structure
CN205277418U (en) * 2015-12-23 2016-06-01 林州重机集团股份有限公司 Spraying structure in entry driving machine
CN206000541U (en) * 2016-08-30 2017-03-08 中国铁建股份有限公司 Device is dug in a kind of tunneling and underground engineering tunneling boring cantilever excavator arc milling
CN106246193A (en) * 2016-09-06 2016-12-21 中铁二十四局集团南昌铁路工程有限公司 Strong karst high rich water urban shallow tunnel cantilever excavator construction
CN106907150A (en) * 2017-04-19 2017-06-30 江西理工大学 A kind of improved tunnelling machine
CN206707751U (en) * 2017-05-09 2017-12-05 中交二公局东萌工程有限公司 A kind of spray dust's system for tunnel portal construction slag-soil truck
CN207093088U (en) * 2017-09-04 2018-03-13 太重煤机有限公司 A kind of digging laneway dust goes out except device
CN107514275A (en) * 2017-10-19 2017-12-26 淮南矿业(集团)有限责任公司 Tunnelling dust prevention system
CN208816126U (en) * 2018-09-30 2019-05-03 朱启杰 A kind of driving face concurrent flow air curtain orientation dust collect plant
CN109681202A (en) * 2019-01-28 2019-04-26 黄山市徽州安华工程机械有限公司 The spray dust-reducing system of development machine
CN109779629A (en) * 2019-01-28 2019-05-21 黄山市徽州安华工程机械有限公司 Atomizing de-dusting cutterhead
CN110080790A (en) * 2019-04-03 2019-08-02 中船第九设计研究院工程有限公司 A kind of boom-type roadheader excavated for tunnel
CN210003281U (en) * 2019-05-09 2020-01-31 中铁八局集团第三工程有限公司 cantilever heading machine with dust removal function

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112065426A (en) * 2020-10-10 2020-12-11 中铁华铁工程设计集团有限公司 Movable type rotary milling cutter head tunneling machine

Similar Documents

Publication Publication Date Title
WO2018045746A1 (en) Method for construction of boom-type roadheader for urban shallow tunnel with intensive karst and rich water
CN111119913B (en) TBM escaping treatment method in tunnel construction and tunnel construction structure
CN108691550B (en) Vertical shaft shield machine for underground upward construction and construction method thereof
CN109296378B (en) Down-the-hole drill matched breaking hammer tunneling and excavating construction method
CN103291308A (en) Boom-type roadheader for tunnel construction and tunnel construction method
CN109594988B (en) Excavation construction method for large-section soft rock tunnel
US20230095265A1 (en) Method and system for temporary coating supporting and permanent bolt supporting
CN112228102A (en) Spraying temporary support and anchor rod permanent support method and system
CN111472801A (en) Construction method for passing existing line under shallow-buried underground excavation drainage gallery
CN110500107B (en) Shield tunneling machine normal-pressure warehouse opening front maintenance tool changing construction method
CN111173531A (en) Non-explosive excavation method for urban tunnel
CN111577311A (en) Construction process of cantilever type heading machine in soft rock tunnel
CN114320315A (en) Pre-splitting method for tunnel driving construction
CN207453966U (en) The attached wind booth vertical shaft section in subway station excavates structure of slagging tap
CN112228101B (en) Roadway support forming method and system based on spraying
CN112727467A (en) Chamber construction method for repairing shield cutter head cutter
CN112049647A (en) Construction method for static cutting excavation of hard rock connection channel
CN113266414B (en) Coal roadway tunneling gas control and ventilation method based on large-diameter directional drilling
CN112709579A (en) Quick-forming development machine for river and canal
CN112360502B (en) Coal roadway rapid tunneling method and equipment based on spray layer and atmospheric pressure
CN112761704B (en) Dust removing method and device for ground horizontal well of coal mine tunnel tunneling working face
CN107642359A (en) The attached wind booth vertical shaft section in subway station excavates slag tap structure and construction method
CN115012974A (en) Shield immersed tube combined construction method for butt joint of submarine tunnels
CN210195753U (en) Tunnel blasting excavation system
CN110985017B (en) Construction method for shield tunneling of rainwater box culvert under expansive soil stratum

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200519