CN111172894A - 分离式钢管拱予应力吊索加固混凝土梁式桥技术 - Google Patents
分离式钢管拱予应力吊索加固混凝土梁式桥技术 Download PDFInfo
- Publication number
- CN111172894A CN111172894A CN201910800081.6A CN201910800081A CN111172894A CN 111172894 A CN111172894 A CN 111172894A CN 201910800081 A CN201910800081 A CN 201910800081A CN 111172894 A CN111172894 A CN 111172894A
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- steel
- sling
- reinforcement
- girder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D22/00—Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/30—Metal
- E01D2101/32—Metal prestressed
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
对予应力混凝土连续箱梁、钢构梁式桥出现的梁体开裂和下挠病害,一般都采用粘贴钢板、炭纤维布,或是增加体内予应力钢束进行加固。如果采用这些传统常规的加固办法仍收不到好的效果,可采用本发明技术进行加固。做法是:在原桥墩柱两侧新增桩基、承台、拱座安装钢管拱,在原桥梁梁底横向设置钢托梁,钢管拱上的吊索与托梁连接,对吊索进行张拉,按设计施加予应力,通过托梁传递向上应力,托住梁体起到加固作用。由于减轻了墩柱压力,对墩柱也起到加固作用。采用本发明技术加固,原桥交通可照常进行。
Description
近年来由于营运交通量大,超载等原因,一些连续箱梁,刚构连续组合体系梁式桥出现了梁体开裂和下挠病害。为消除病害,一般都采用粘贴钢板、高强炭纤维布,或是增加体内、体外予应力钢束进行加固。如果采用这些传统常规的加固办法仍收不到好的效果,无法根治病害可采用“分离式钢管拱予应力吊索加固混凝土梁式桥技术”进行加固。
具体做法是,在原桥墩柱两侧新增柱基,承台、拱座,安装钢拱。桥体与钢管拱分离。在梁底横向设置钢托梁,钢管拱垂下的吊索与钢托梁的两端连接,对吊索进行张拉,按设计施加予应力,通过托梁传递向上应力,托住梁体起到加固作用(见附图一)。
吊索张拉可分两种方式进行:一、钢管拱制作时,通过设计予先设置张拉平台,对吊索进行张拉,吊索托住托梁,在向上的拉力作用下,托梁与梁底紧密贴合,完成吊索的张拉,在钢管拱顶锚固。这种张拉法在国内尚还未见,在技术、工艺上是可行的。钢管拱宽度一般达2.5M 左右,在拱顶上设置张拉平台,上人操作也是可行的。由于梁底成弧形,托梁与梁底贴合处有倾角也需用软钢等材料垫平。二、在梁底植筋与托梁连接,在托梁两端部设置张拉平台,对吊索进行张拉,张拉完后在两端部锚固。植筋数量要足够,防止在张拉过程中托梁与梁底脱离。托梁与梁底的倾角也需用软钢等材料垫平。在张拉进行时,需确保张拉施工时梁体的挠度和应力保持在安全控制范围内。
钢管拱断面尺寸的大小,吊索的根数,施加予应力多少,均根据桥梁的病害程度,是需制止下挠,或是回挠来决定。由于原桥梁体系与钢管拱体系是分离的,在吊索上张拉附加体外予应力,均为竖向受力,受力简单,对主梁体断面不产生任何有害应力,用此种技术加固桥梁相对安全可靠。在多根吊索上千吨甚至多至数于吨的竖向向上的应力作用下,梁体抗剪不足和跨中抗挠将得到大的改善。由于通过吊索附加的竖向向上应力,也减轻了桥梁墩柱的负载,也对墩柱起到了加固作用。
钢管拱有两种安装法:一、采用塔架索道悬拼工艺安装钢管拱。塔架的架设可选用组合式塔架,可用人工配合小型机具进行架设,以方便施工(见附图二)。二、在有通航条件下,采用起重船两段合拢安装(见附图三)。
采用“分离式钢管拱予应力吊索加固梁式桥技术”不影响原桥交通,营运照常进行。
附图说明:
说明书附图一:“分离式钢管拱吊索加固连续梁式桥方案图”该图是新增桩基、承台、拱座、钢管拱的布置示意。
说明书附图二:“钢管拱悬拼方案布置图”该图表明塔架及索道的布置及施工工艺。
说明书附图三:“起重船两段合拢布置图”该图是两艘起重船安装钢管拱的施工状况。
Claims (1)
1.对原桥梁分离的桩基、承台、拱座、钢管拱。吊索予应力张拉,钢管拱顶设置张拉平台张拉及锚固;托梁端部设置张拉平台张拉及锚固,权利要求保护。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910800081.6A CN111172894A (zh) | 2019-08-20 | 2019-08-20 | 分离式钢管拱予应力吊索加固混凝土梁式桥技术 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910800081.6A CN111172894A (zh) | 2019-08-20 | 2019-08-20 | 分离式钢管拱予应力吊索加固混凝土梁式桥技术 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111172894A true CN111172894A (zh) | 2020-05-19 |
Family
ID=70617789
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910800081.6A Pending CN111172894A (zh) | 2019-08-20 | 2019-08-20 | 分离式钢管拱予应力吊索加固混凝土梁式桥技术 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111172894A (zh) |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100991262B1 (ko) * | 2010-02-11 | 2010-11-04 | 민경기술 주식회사 | 교량보강 및 경관 증진 방법 |
CN102286938A (zh) * | 2011-07-28 | 2011-12-21 | 交通运输部公路科学研究所 | 适用于大跨径箱梁桥、连续刚构桥的斜拉体系加固结构 |
CN104264594A (zh) * | 2014-09-10 | 2015-01-07 | 北京工业大学 | 一种用于提高psc连续箱梁桥承载力的自平衡系杆拱体系及运用其加固的方法 |
CN107460833A (zh) * | 2017-08-25 | 2017-12-12 | 中铁大桥勘测设计院集团有限公司 | 用于提高连续梁桥梁承载能力的系统及含有该系统的桥梁 |
CN206800225U (zh) * | 2017-06-14 | 2017-12-26 | 沈阳建筑大学 | 一种连续刚构桥系杆拱加固结构 |
CN206941424U (zh) * | 2017-06-14 | 2018-01-30 | 沈阳建筑大学 | 一种双幅连续刚构桥系杆拱加固结构 |
CN207619860U (zh) * | 2017-11-27 | 2018-07-17 | 广州瀚阳工程咨询有限公司 | 一种梁式桥加固结构 |
CN208844443U (zh) * | 2018-08-02 | 2019-05-10 | 中国建筑股份有限公司 | 一种基于拱的箱型梁加固结构 |
-
2019
- 2019-08-20 CN CN201910800081.6A patent/CN111172894A/zh active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100991262B1 (ko) * | 2010-02-11 | 2010-11-04 | 민경기술 주식회사 | 교량보강 및 경관 증진 방법 |
CN102286938A (zh) * | 2011-07-28 | 2011-12-21 | 交通运输部公路科学研究所 | 适用于大跨径箱梁桥、连续刚构桥的斜拉体系加固结构 |
CN104264594A (zh) * | 2014-09-10 | 2015-01-07 | 北京工业大学 | 一种用于提高psc连续箱梁桥承载力的自平衡系杆拱体系及运用其加固的方法 |
CN206800225U (zh) * | 2017-06-14 | 2017-12-26 | 沈阳建筑大学 | 一种连续刚构桥系杆拱加固结构 |
CN206941424U (zh) * | 2017-06-14 | 2018-01-30 | 沈阳建筑大学 | 一种双幅连续刚构桥系杆拱加固结构 |
CN107460833A (zh) * | 2017-08-25 | 2017-12-12 | 中铁大桥勘测设计院集团有限公司 | 用于提高连续梁桥梁承载能力的系统及含有该系统的桥梁 |
CN207619860U (zh) * | 2017-11-27 | 2018-07-17 | 广州瀚阳工程咨询有限公司 | 一种梁式桥加固结构 |
CN208844443U (zh) * | 2018-08-02 | 2019-05-10 | 中国建筑股份有限公司 | 一种基于拱的箱型梁加固结构 |
Non-Patent Citations (2)
Title |
---|
徐刚年 王有志 王世民 王来永: "东明黄河公路大桥主梁加固关键施工技术", 《桥梁建设》 * |
鲍卫刚: "预应力混凝土连续梁桥维修与加固技术", 《公路》 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104975566B (zh) | 应用在斜拉桥拱塔施工中的钢管支架 | |
CN100543234C (zh) | 一种大跨度连续钢桁拱的合龙方法 | |
CN203768811U (zh) | 一种嵌入型钢锚梁组合索塔锚固结构 | |
KR20150126502A (ko) | 강아치교의 구조와 이의 시공방법 | |
CN106012872B (zh) | 连续刚构桥的无背索斜拉加固体系及施工方法 | |
CN104032668A (zh) | 中承式钢桁-混凝土组合连续钢构桥 | |
CN102535327A (zh) | 下承式预应力钢桁-砼组合连续刚构桥及施工方法 | |
CN110878535A (zh) | 用于刚桁架桥加固的斜拉调载系统及其加固方法 | |
CN111778834A (zh) | 一种大跨度桥梁边墩、辅助墩的抗拉装置 | |
CN106836028B (zh) | 用钢桁梁顶升加固的混凝土连续刚构梁桥及施工方法 | |
CN108999088A (zh) | 一种斜拉桥的施工方法 | |
CN102277836B (zh) | 倾斜式混凝土塔座的施工方法 | |
KR102403925B1 (ko) | 가설교량 및 이의 시공방법 | |
CN104562944B (zh) | 大跨径叠合梁斜拉桥边钢箱临时锚固体系 | |
CN104775363B (zh) | 上塔柱钢筋节段的组拼方法 | |
CN111155412B (zh) | 大摆角钢管砼拱桥吊索体系 | |
CN211666206U (zh) | 一种悬挑落地两用脚手架 | |
JP3877995B2 (ja) | 張弦桁橋の構築方法 | |
CN210140764U (zh) | 一种拉索加劲的双折线形桥跨组件 | |
CN114541283B (zh) | 一种用于解决大跨度pc梁桥持续下挠问题的结构及方法 | |
CN106120573A (zh) | 跨海多跨提篮拱桥自平衡扣挂施工方法 | |
CN111172894A (zh) | 分离式钢管拱予应力吊索加固混凝土梁式桥技术 | |
KR20240060816A (ko) | 복합 rcc 데크 및 압축 응력된 포물선형 바닥 현재 언더슬렁 개방형 웹 스틸 교량 상부구조 | |
CN212801168U (zh) | 一种独柱墩桥梁固结抗倾覆加固结构 | |
WO2006065085A1 (en) | Manufacturing method for prestressed steel composite girder and prestressed steel composite girder thereby |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |