CN111156030A - Anti-bottom-bulging prefabricated assembled tunnel inverted arch structure, assembled tunnel and method - Google Patents

Anti-bottom-bulging prefabricated assembled tunnel inverted arch structure, assembled tunnel and method Download PDF

Info

Publication number
CN111156030A
CN111156030A CN202010005704.3A CN202010005704A CN111156030A CN 111156030 A CN111156030 A CN 111156030A CN 202010005704 A CN202010005704 A CN 202010005704A CN 111156030 A CN111156030 A CN 111156030A
Authority
CN
China
Prior art keywords
inverted arch
block
tunnel
sub
inverted
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010005704.3A
Other languages
Chinese (zh)
Inventor
邱道宏
于月浩
薛翊国
侯守江
潘建平
公惠民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University
Original Assignee
Shandong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University filed Critical Shandong University
Priority to CN202010005704.3A priority Critical patent/CN111156030A/en
Publication of CN111156030A publication Critical patent/CN111156030A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses an inverted arch structure of a bottom-bulging-resistant prefabricated assembled tunnel, an assembled tunnel and a method, wherein the technical scheme is as follows: the device comprises a first inverted arch sub-block and a second inverted arch sub-block which are symmetrically arranged, wherein a rhombic grid is connected between the first inverted arch sub-block and the second inverted arch sub-block; first inverted arch piecemeal, second inverted arch piecemeal form inverted arch constitutional unit through concreting, and multisection inverted arch constitutional unit vertically splices in proper order and constitutes whole assembled inverted arch structure. The tunnel inverted arch adopts a prefabricated assembly type, and the inverted arch structure adopts industrialized and standardized prefabrication and is easy to install; and the bottom bulge at the uppermost position in the middle of the inverted arch filling can be protected, and the top tensile stress is reduced, so that the development of tensile cracks at the position is reduced.

Description

Anti-bottom-bulging prefabricated assembled tunnel inverted arch structure, assembled tunnel and method
Technical Field
The invention relates to the field of tunnel construction, in particular to an inverted arch structure of a bottom-bulging-resistant prefabricated assembled tunnel, an assembled tunnel and a method.
Background
The inverted arch is a reverse arch structure arranged at the bottom of the tunnel for improving the stress condition of an upper supporting structure, is one of main components of the tunnel structure, and is used for effectively transmitting the pressure of the stratum at the upper part of the tunnel to the ground through a side wall structure of the tunnel or the load on the road surface and also effectively resisting the counter force transmitted from the stratum at the lower part of the tunnel. The inverted arch and the secondary lining form a whole tunnel, so that the structural stability is improved. But the inverted arch structure in the tunnel is often cracked or damaged, and the running safety of the train is seriously influenced. With the continuous improvement of construction technology, construction level and construction requirements, more and more new technologies, new processes and new construction methods are applied to the construction of tunnels and underground engineering. In recent years, with the rapid development of economy in China, the requirement for vigorously developing the assembly type building is already put forward. The assembly type building is a great change of the construction mode, and is beneficial to saving resources, reducing construction pollution, improving the working environment, improving the labor production efficiency, improving the standardized operation and ensuring the quality and the safety level. However, due to various factors, the construction mode of the current drilling and blasting method for constructing the tunnel is mainly cast-in-place operation, the construction proportion of the fabricated tunnel is very low, and the difference is very large compared with the requirement.
The inventor finds that the inverted arch in the tunnel has two kinds of plain concrete and reinforced concrete at present, and the inverted arch is filled and is plain concrete, and the tunnel section is mostly the horseshoe-shaped, and both inverted arch camber is general not big, leads to the inverted arch structure when bearing great buoyancy, can not effectively utilize the arch effect to resist buoyancy for the inverted arch pucking phenomenon is comparatively general. The maximum tensile stress in the structure occurs at a position above the filling center of the inverted arch, where tensile cracks generally develop more. According to the related statistics of the currently operated railway tunnel, particularly a high-speed railway tunnel, diseases such as inverted arch bottom bulging, slurry turning and mud pumping appear in part of the tunnel, and the like, the track bed is cracked and deformed seriously, so that the speed limit of the tunnel during driving is limited, and the normal operation of a high-speed railway is influenced. Through inspection, the insufficient inverted arch quality of the tunnel is also one of the main influencing factors.
Disclosure of Invention
In order to overcome the defects of the prior art, the invention provides a bottom-drum-resistant prefabricated assembled tunnel inverted arch structure, which can protect the bottom drum filled in the middle uppermost position of the inverted arch and reduce the top tensile stress.
The second purpose of the invention is to provide an assembled tunnel, the inverted arch structure of which is prefabricated in a factory and standardized way, and the quality is ensured reliably.
The third purpose of the invention is to provide a construction method of the inverted arch structure of the anti-bottom-bulging prefabricated assembled tunnel, which can realize the rapid installation of the inverted arch and is easy to install.
The invention adopts the following technical scheme:
a prefabricated assembled tunnel inverted arch structure resisting bottom bulging comprises a first inverted arch sub-block and a second inverted arch sub-block which are symmetrically arranged, wherein a rhombic grid is connected between the first inverted arch sub-block and the second inverted arch sub-block; first inverted arch piecemeal, second inverted arch piecemeal form inverted arch constitutional unit through concreting, and multisection inverted arch constitutional unit vertically splices in proper order and constitutes whole assembled inverted arch structure.
Furthermore, the rhombus grid is connected with the first inverted arch block and the second inverted arch block through the cushion blocks respectively, and the rhombus grid comprises four supporting rods which are connected in a head-tail rotating mode in sequence.
Further, adjacent struts are connected by bolts.
Furthermore, the first inverted arch sub-block and the second inverted arch sub-block are used for connecting one end of the secondary lining and respectively reserve a steel bar joint, and the opposite sides of the first inverted arch sub-block and the second inverted arch sub-block respectively reserve a steel bar joint.
Furthermore, the first inverted arch sub-block and the second inverted arch sub-block are provided with a plurality of water drainage channels.
Further, the drainage channel has a downward slope.
Furthermore, a waterproof layer is arranged below the inverted arch structure unit.
The utility model provides an assembled tunnel, includes anti-pucking's prefabricated pin-connected panel tunnel invert structure, the outer end of first invert piecemeal, second invert piecemeal is located tunnel preliminary bracing inboard and links up with arch wall secondary lining, and the joint face department of just first invert piecemeal, second invert piecemeal and arch wall secondary lining sets up tenon fourth of the twelve earthly branches structure.
Furthermore, a base cushion layer is arranged below the assembled tunnel inverted arch structure.
A construction method of a bottom-bulging-resistant prefabricated assembled tunnel inverted arch structure comprises the following steps:
A. excavating the tunnel and constructing primary tunnel support;
B. excavating an inverted arch, leveling and carrying out substrate treatment, transporting the prefabricated first inverted arch block and the prefabricated second inverted arch block to a position to be installed, placing the first inverted arch block firstly, and then placing the second inverted arch block;
C. after the inverted arch sub-blocks are assembled in place, connecting the rhombic grids between the first inverted arch sub-block and the second inverted arch sub-block through bolts, and then connecting and fixing the inverted arch sub-blocks and the primary support of the tunnel;
D. steel bar joints are reserved on two sides of the first inverted arch block and the second inverted arch block and are connected with steel bars of a cast-in-place arch wall secondary lining; pouring arch wall lining concrete again, and closing a lining structure;
E. pouring concrete between the first inverted arch block and the second inverted arch block, and filling a leveling layer;
F. grouting to the bottom through grouting holes reserved in the first inverted arch block and the second inverted arch block;
G. and D, repeating the steps A-F to assemble the next inverted arch structure unit.
Compared with the prior art, the invention has the beneficial effects that:
1. the tunnel inverted arch is prefabricated, the inverted arch structure is prefabricated in an industrialized and standardized mode, the quality is reliable and guaranteed, the conventional inverted arch trestle construction cast-in-place mode is replaced by the tunnel inverted arch assembly construction mode, and the quality, the strength and the like of a prefabricated component are much better than those of a cast-in-place structure;
2. after the bottom of the rhombic grid is acted by a floating force, the angular point at the bottom moves upwards to force the left and right angular points to move leftwards and rightwards respectively, so that the upper end of the rhombic structure tends to move downwards, the bottom drum at the uppermost position in the middle of the inverted arch is protected, the top tensile stress is reduced, and the development of tensile cracks at the position is reduced;
3. the invention can realize the early and rapid placement of the inverted arch; the inverted arch blocks are directly moved into the tunnel without rotating in the tunnel, are offset left and right, are directly placed and are easy to install;
4. according to the invention, the drainage channel is arranged, so that water in surrounding rocks at the bottom of the inverted arch can be effectively drained along the drainage channel of the inverted arch, the high water pressure at the bottom of the inverted arch is released, the effect of external buoyancy on the inverted arch is reduced, and the anti-bottom-bulging capability of the inverted arch structure is improved.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this application, illustrate embodiments of the application and, together with the description, serve to explain the application and are not intended to limit the application.
FIG. 1 is a schematic structural diagram according to a first embodiment of the present invention;
FIG. 2 is a left side view of the first embodiment of the present invention;
FIG. 3 is a top view of a first embodiment of the present invention;
FIG. 4 is a right side view of a first inverted arch segment according to a first embodiment of the present invention;
FIG. 5 is a schematic structural view of a diamond-shaped steel grating according to a first embodiment of the present invention;
FIG. 6 is a cross-sectional view of a tunnel according to a second embodiment of the present invention;
the method comprises the following steps of 1, tunnel primary support, 2, arch wall secondary lining, 3, a leveling layer, 4, a base cushion layer, 5, a waterproof layer, 6, a diamond-shaped grid, 7, a cushion block, 8, a water drainage channel, 9, a steel bar joint, 10, a steel bar joint, 11, a tunnel ditch and a cable trough, 12, a bolt, 13, second inverted arch blocking, 14 and first inverted arch blocking.
Detailed Description
It should be noted that the following detailed description is exemplary and is intended to provide further explanation of the disclosure. Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs.
It is noted that the terminology used herein is for the purpose of describing particular embodiments only and is not intended to be limiting of example embodiments according to the present application. As used herein, the singular forms "a", "an", and/or "the" are intended to include the plural forms as well, and it should be understood that when the terms "comprises" and/or "comprising" are used in this specification, they specify the presence of stated features, steps, operations, devices, components, and/or combinations thereof;
for convenience of description, the words "up", "down", "left" and "right" in this application, if any, merely indicate correspondence with the directions of up, down, left and right of the drawings themselves, and do not limit the structure, but merely facilitate the description of the invention and simplify the description, and do not indicate or imply that the referenced device or element must have a particular orientation, be constructed and operated in a particular orientation, and therefore should not be construed as limiting the application. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
The terms "mounted", "connected", "fixed", and the like in the present application should be understood broadly, and for example, the terms "mounted", "connected", and "fixed" may be fixedly connected, detachably connected, or integrated; the two components can be connected directly or indirectly through an intermediate medium, or the two components can be connected internally or in an interaction relationship, and the terms can be understood by those skilled in the art according to specific situations.
The first embodiment is as follows:
the present invention is described in detail below with reference to fig. 1 to 5, and specifically, the structure is as follows:
the embodiment provides a prefabricated pin-connected panel tunnel invert structure of anti pucking, including first invert piecemeal 14, second invert piecemeal 13, rhombus grid 6, wherein, first invert piecemeal 14 and second invert piecemeal 13 symmetry installation, and rhombus grid 6 connects between first invert piecemeal 14, second invert piecemeal 13. After the first inverted arch sub-block 14 and the second inverted arch sub-block 13 are installed, a transverse inverted arch structural unit is formed by pouring concrete, and the multiple inverted arch structural units are longitudinally and sequentially spliced to form an integral assembly type inverted arch structure.
When the first inverted arch sub-block 14 and the second inverted arch sub-block 13 are installed, the first inverted arch sub-block 14 and the second inverted arch sub-block 13 are connected with the secondary lining 2 of the arch wall, a reinforcing steel bar joint 9 is reserved at the installation end of the first inverted arch sub-block 14, the second inverted arch sub-block 13 and the secondary lining 2 of the arch wall, and a reinforcing steel bar joint 10 is reserved on one side, opposite to the first inverted arch sub-block 14 and the second inverted arch sub-block 13, of each inverted arch sub-block. The rigidity of the structure is increased by using the steel bar connection, and the deformation resistance is enhanced.
The rhombic grids 6 are connected with the first inverted arch sub-block 14 and the second inverted arch sub-block 13 through the cushion blocks 7. In this embodiment, the spacer 7 is a steel spacer. The rhombic grating 6 comprises four supporting rods, the adjacent supporting rods are connected end to form four connecting points, and the supporting rods are connected through bolts 12. After the inverted arch blocks are installed, the upper diagonal and the lower diagonal of the rhombic grating 6 are connected through bolts 12. In this embodiment, the struts are steel rods.
The rhombus grid 6 is formed into two parts which are bilaterally symmetrical by the supporting rods, when the inverted arch structure bears larger upward buoyancy, the bottom connecting point of the bottom of the rhombus grid 6 moves upwards under the action of the upward buoyancy, and the left connecting point and the right connecting point are forced to move leftwards and rightwards respectively, so that the upper end of the rhombus grid 6 tends to move downwards, the bottom drum at the uppermost position in the middle of the inverted arch filling is protected, the top tensile stress is reduced, and the development of tensile cracks at the position is reduced.
When the first inverted arch block 14 and the second inverted arch block 13 are prefabricated, a grouting hole and a water drainage channel 8 are reserved, one end of the water drainage channel 8 enters surrounding rock, and water is drained from the other end of the water drainage channel, so that underground water can be drained in time, and the pressure of a base is reduced. The drainage channel 8 has a slight downward slope to prevent water from flowing backwards into the surrounding rock.
A waterproof layer 5 is arranged below the inverted arch structure unit to prevent the strength of the inverted arch structure from being reduced due to seepage of underground water into the inverted arch. And post-pouring concrete between the first inverted arch sub-block 14 and the second inverted arch sub-block 13 to form a wet joint concrete post-pouring belt.
The construction method of the inverted arch structure comprises the following steps:
A. and (3) excavating the tunnel and constructing a primary tunnel support 1.
B. After the construction of the tunnel primary support 1 is finished, the inverted arch is excavated, leveled and subjected to basement treatment, the inverted arch blocks are prefabricated from the outside of the tunnel and then transported to the position to be installed in the tunnel through equipment, the first inverted arch block 14 (positioned on the left side) is placed at first, and then the second inverted arch block 13 (positioned on the right side) is placed.
C. After the first inverted arch sub-block 14 and the second inverted arch sub-block 13 are assembled in place, firstly, the rhombic grids 6 between the two sub-blocks are connected through the bolts 12, and after the inverted arch sub-blocks are installed, the upper diagonal and the lower diagonal of the rhombic grids 6 are connected through the bolts 12. And then, the first inverted arch sub-block 14 and the second inverted arch sub-block 13 are fixedly connected with a steel frame of the tunnel primary support 1, so that the tunnel primary support 1, the first inverted arch sub-block 14 and the second inverted arch sub-block 13 jointly form a more stable and reliable closed stress system.
D. And the reinforcing steel bar joints 9 are reserved on two sides of the first inverted arch block 14 and the second inverted arch block 13, and are connected with the reinforcing steel bars of the cast-in-place arch wall secondary lining 2 in the later period to ensure that lining reinforcing steel bars form a closed loop, then the arch wall lining concrete is poured, and the lining structure is closed.
E. After the first inverted arch sub-block 14 and the second inverted arch sub-block 13 are assembled, concrete is poured to fill the part between the two sub-blocks, the integrity of the tunnel inverted arch is improved, and the leveling layer 3 is filled until the bottom of the ballast bed has the condition of constructing the ballast bed.
F. The first inverted arch sub-block 14 and the second inverted arch sub-block 13 are assembled in place and are stressed stably, and grouting is performed to the bottom through grouting holes reserved in the first inverted arch sub-block 14 and the second inverted arch sub-block 13 subsequently, so that the inverted arch precast block is filled compactly.
G. And D, repeating the steps A-F, and assembling the next prefabricated block.
Example two:
the embodiment provides an assembled tunnel, as shown in fig. 6, which includes a tunnel primary support 1, an arch wall secondary lining 2 and the inverted arch structure of the prefabricated assembled tunnel described in the first embodiment, wherein the outer ends of the first inverted arch segment 14 and the second inverted arch segment 13 are located inside the tunnel primary support 1 and are connected with the arch wall secondary lining 2. The tenon-and-mortise structures are arranged at the joint surfaces of the first inverted arch sub-block 14, the second inverted arch sub-block 13 and the arch wall secondary lining 2, so that the inverted arch sub-blocks and the arch wall secondary lining 2 are connected more tightly.
A base cushion layer 4 is arranged below the assembled tunnel inverted arch structure, namely the base cushion layer 4 is positioned below the waterproof layer 5. The inner side of the arch wall secondary lining 2 is provided with a tunnel ditch and a cable trough 11.
The above description is only a preferred embodiment of the present application and is not intended to limit the present application, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, improvement and the like made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims (10)

1. The prefabricated assembled tunnel inverted arch structure is characterized by comprising a first inverted arch block and a second inverted arch block which are symmetrically arranged, wherein a rhombic grid is connected between the first inverted arch block and the second inverted arch block; first inverted arch piecemeal, second inverted arch piecemeal form inverted arch constitutional unit through concreting, and multisection inverted arch constitutional unit vertically splices in proper order and constitutes whole assembled inverted arch structure.
2. The anti-bottom-bulging prefabricated assembled tunnel inverted arch structure according to claim 1, wherein the diamond-shaped grating is connected with the first inverted arch sub-block and the second inverted arch sub-block through cushion blocks respectively, and comprises four supporting rods which are connected end to end in a rotating mode.
3. The anti-drumming prefabricated assembly type tunnel inverted arch structure of claim 2, wherein the adjacent struts are connected by bolts.
4. The anti-bulging prefabricated assembly type tunnel inverted arch structure of claim 1, wherein the first inverted arch sub-block and the second inverted arch sub-block are used for connecting one end of the secondary lining and are respectively provided with a steel bar joint, and the opposite sides of the first inverted arch sub-block and the second inverted arch sub-block are respectively provided with a steel bar joint.
5. The anti-drumming prefabricated assembled tunnel inverted arch structure as claimed in claim 1, wherein the first inverted arch sub-block and the second inverted arch sub-block are provided with a plurality of drainage channels.
6. The anti-drumming prefabricated assembly type tunnel inverted arch structure as set forth in claim 5, wherein the drainage passage has a downward slope.
7. The fabricated tunnel of claim 1, wherein a waterproof layer is provided under the inverted arch structure unit.
8. An assembled tunnel, comprising a prefabricated assembled tunnel inverted arch structure resisting a bottom heave according to any one of claims 1 to 7, wherein the outer ends of the first inverted arch segment and the second inverted arch segment are positioned on the inner side of a primary support of the tunnel and are connected with an arch wall secondary lining, and tenon-and-mortise structures are arranged at the connection surfaces of the first inverted arch segment and the second inverted arch segment with the arch wall secondary lining.
9. The fabricated tunnel of claim 8, wherein a base cushion is disposed under the inverted arch structure of the assembled tunnel.
10. The construction method of the anti-drumming prefabricated assembly type tunnel inverted arch structure according to any one of claims 1 to 7, comprising the steps of:
A. excavating the tunnel and constructing primary tunnel support;
B. excavating an inverted arch, leveling and carrying out substrate treatment, transporting the prefabricated first inverted arch block and the prefabricated second inverted arch block to a position to be installed, placing the first inverted arch block firstly, and then placing the second inverted arch block;
C. after the inverted arch sub-blocks are assembled in place, connecting the rhombic grids between the first inverted arch sub-block and the second inverted arch sub-block through bolts, and then connecting and fixing the inverted arch sub-blocks and the primary support of the tunnel;
D. steel bar joints are reserved on two sides of the first inverted arch block and the second inverted arch block and are connected with steel bars of a cast-in-place arch wall secondary lining; pouring arch wall lining concrete again, and closing a lining structure;
E. pouring concrete between the first inverted arch block and the second inverted arch block, and filling a leveling layer;
F. grouting to the bottom through grouting holes reserved in the first inverted arch block and the second inverted arch block;
G. and D, repeating the steps A-F to assemble the next inverted arch structure unit.
CN202010005704.3A 2020-01-03 2020-01-03 Anti-bottom-bulging prefabricated assembled tunnel inverted arch structure, assembled tunnel and method Pending CN111156030A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010005704.3A CN111156030A (en) 2020-01-03 2020-01-03 Anti-bottom-bulging prefabricated assembled tunnel inverted arch structure, assembled tunnel and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010005704.3A CN111156030A (en) 2020-01-03 2020-01-03 Anti-bottom-bulging prefabricated assembled tunnel inverted arch structure, assembled tunnel and method

Publications (1)

Publication Number Publication Date
CN111156030A true CN111156030A (en) 2020-05-15

Family

ID=70561075

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010005704.3A Pending CN111156030A (en) 2020-01-03 2020-01-03 Anti-bottom-bulging prefabricated assembled tunnel inverted arch structure, assembled tunnel and method

Country Status (1)

Country Link
CN (1) CN111156030A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111691897A (en) * 2020-05-20 2020-09-22 济南市市政工程设计研究院(集团)有限责任公司 Inverted arch segment, tunnel inverted arch structure and secondary lining construction method
CN112696212A (en) * 2020-12-31 2021-04-23 中铁二院工程集团有限责任公司 Compressible tunnel bottom structure for inhibiting tunnel bottom bulging and construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106593469A (en) * 2016-12-02 2017-04-26 中铁五局集团第工程有限责任公司 Trolley for construction of inverted arch
CN107387117A (en) * 2017-07-07 2017-11-24 中国铁道科学研究院铁道建筑研究所 A kind of prefabricated assembled tunnel structure in tunnel bottom and its construction method
CN207568626U (en) * 2017-08-29 2018-07-03 中铁第一勘察设计院集团有限公司 A kind of tunnel structure for expansive stratum
CN109578018A (en) * 2019-01-22 2019-04-05 青岛理工大学 A kind of tunnel inverted arch structure of anti-pucking
CN109763838A (en) * 2019-03-13 2019-05-17 中铁第一勘察设计院集团有限公司 Assembled inverted arch structure and its assembling method suitable for drill+blast tunnel

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106593469A (en) * 2016-12-02 2017-04-26 中铁五局集团第工程有限责任公司 Trolley for construction of inverted arch
CN107387117A (en) * 2017-07-07 2017-11-24 中国铁道科学研究院铁道建筑研究所 A kind of prefabricated assembled tunnel structure in tunnel bottom and its construction method
CN207568626U (en) * 2017-08-29 2018-07-03 中铁第一勘察设计院集团有限公司 A kind of tunnel structure for expansive stratum
CN109578018A (en) * 2019-01-22 2019-04-05 青岛理工大学 A kind of tunnel inverted arch structure of anti-pucking
CN109763838A (en) * 2019-03-13 2019-05-17 中铁第一勘察设计院集团有限公司 Assembled inverted arch structure and its assembling method suitable for drill+blast tunnel

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111691897A (en) * 2020-05-20 2020-09-22 济南市市政工程设计研究院(集团)有限责任公司 Inverted arch segment, tunnel inverted arch structure and secondary lining construction method
CN111691897B (en) * 2020-05-20 2022-02-08 济南市市政工程设计研究院(集团)有限责任公司 Inverted arch segment, tunnel inverted arch structure and secondary lining construction method
CN112696212A (en) * 2020-12-31 2021-04-23 中铁二院工程集团有限责任公司 Compressible tunnel bottom structure for inhibiting tunnel bottom bulging and construction method

Similar Documents

Publication Publication Date Title
CN109763838B (en) Assembled inverted arch structure suitable for tunnel by drilling and blasting method and assembling method thereof
CN107119711B (en) Connecting structure for large-range adjacent existing transfer station and construction method
CN108589771B (en) Construction method for layer-adding transfer node of operated underground station
CN108547641B (en) Substrate reinforcing system of heavy-duty railway tunnel in water-rich weak stratum and construction method thereof
CN111156030A (en) Anti-bottom-bulging prefabricated assembled tunnel inverted arch structure, assembled tunnel and method
CN112609730B (en) Assembled retaining wall
CN113502835A (en) Wet cellular assembled gridwork roof beam slope protection structure of connecting
CN111764926A (en) Control structure and control method for long-term settlement of shield or pipe-jacking tunnel
CN113293665B (en) Roadbed reinforcing method for long side of railway bridge and culvert connection
CN211471980U (en) Anti-bump anti-skid structure of ballastless track high-speed railway
CN208184752U (en) The bottom stab ilization system in rich water soft stratum heavy haul railway tunnel
CN108086993B (en) Construction method of haunched floor type tunnel lining and drainage system structure with drainage gallery arranged at tunnel bottom
CN112942148A (en) Method for reinforcing bridge by corrugated steel arch structure
CN206157481U (en) Compound framing type support rail roof beam transition section structure of moderate -low speed magnetic levitation double -line excavation location pile foundation
CN110777827A (en) Structure capable of carrying out deep water area hollowing repair in rapid stream state
CN206157480U (en) Moderate -low speed magnetic levitation traffic engineering double -line excavation location pile foundation combined type support rail girder construction
CN212296394U (en) Control structure for long-term settlement of shield or pipe-jacking tunnel
CN219886925U (en) Pile plate structure combined permanently
CN111236242B (en) Antitorque foundation ditch of bailey beam excavates platform under water
CN218508149U (en) Road subgrade structure near river in steep mountain area
CN216786789U (en) Multi-span simply supported prestressed bridge span in tunnel
CN220620195U (en) Assembled retaining wall
CN102660920B (en) Framework type large-span combined prestressed highway bridge and preparation process thereof
CN215857760U (en) Open cut tunnel extension foam concrete backfill structure
CN217999609U (en) Construction structure for penetrating subway tunnel and river channel on cable tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200515