CN111143380A - Operation control method based on IEC61968 standard - Google Patents

Operation control method based on IEC61968 standard Download PDF

Info

Publication number
CN111143380A
CN111143380A CN201911166496.9A CN201911166496A CN111143380A CN 111143380 A CN111143380 A CN 111143380A CN 201911166496 A CN201911166496 A CN 201911166496A CN 111143380 A CN111143380 A CN 111143380A
Authority
CN
China
Prior art keywords
data
locking device
control method
proof verification
job
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911166496.9A
Other languages
Chinese (zh)
Inventor
顾建炜
张鹏
陈炜
刘宏伟
洪建兵
王群飞
黄卫升
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuhai Unitech Power Technology Co Ltd
Hangzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
Zhuhai Unitech Power Technology Co Ltd
Hangzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhuhai Unitech Power Technology Co Ltd, Hangzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical Zhuhai Unitech Power Technology Co Ltd
Priority to CN201911166496.9A priority Critical patent/CN111143380A/en
Publication of CN111143380A publication Critical patent/CN111143380A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/23Updating
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/27Replication, distribution or synchronisation of data between databases or within a distributed database system; Distributed database system architectures therefor
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • Economics (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • Databases & Information Systems (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Data Mining & Analysis (AREA)
  • Game Theory and Decision Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • Computing Systems (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Primary Health Care (AREA)
  • General Health & Medical Sciences (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

本申请实施例提出了基于IEC61968标准的作业管控方法,应用于闭锁装置的防误操作流程,所述作业管控方法包括获取预设时间周内的作业请求,结合IEC61968标准对作业请求中的有效数据进行分析获取针对闭锁装置的作业请求类型,基于作业类型生成调度操作票;基于调度操作票进行五防校验,获取五防校验结果;如果五防校验成功,则对闭锁装置进行解锁,并更新配电网运行状态。通过使用IEC61968标准对作业请求中的消息进行分析整理,能够将作业请求信息进行合理规划,使管理人员及时获得告警信息,快速、有效找出互操作过程的中断原因,并及时处理,保障信息互操作业务的连续性与稳定性。

Figure 201911166496

The embodiment of the present application proposes a work management and control method based on the IEC61968 standard, which is applied to the anti-misoperation process of the locking device. The work management and control method includes acquiring work requests within a preset time period, and combining the IEC61968 standard with valid data in the work requests. Perform analysis to obtain the job request type for the locking device, and generate a scheduling operation ticket based on the job type; perform five-proof verification based on the scheduling operation ticket, and obtain the five-proof verification result; if the five-proof verification is successful, unlock the locking device, And update the distribution network operating status. By using the IEC61968 standard to analyze and sort out the messages in the job request, the job request information can be reasonably planned, so that the management personnel can obtain the alarm information in time, quickly and effectively find out the reason for the interruption of the interoperability process, and deal with it in time to ensure the information mutual Operational business continuity and stability.

Figure 201911166496

Description

IEC61968 standard-based operation management and control method
Technical Field
The invention belongs to the field of flow control, and particularly relates to an operation control method based on IEC61968 standard.
Background
The method is characterized in that a power distribution network safety operation management system based on IEC61968 standard is researched and realized, the most core is to research and design power distribution network safety operation models which must support related services of power distribution network safety operation, and an extended power distribution network safety operation model based on the IEC61968 standard comprises two parts of contents: and the locking device model and the five-prevention rule model respectively correspond to the forced locking equipment and the five-prevention rule of the related business of the safety operation of the power distribution network.
The locking device is a device for locking primary electric equipment to prevent personal or power production safety accidents caused by misoperation of the electric equipment. For the IEC61968 standard, the locking device is an unknown entity and has an association with existing electrical equipment assets. Therefore, to research a safety operation management and control system and share data and services with other systems, it is necessary to research a lockout of primary electrical equipment and a related model thereof based on the IEC61968 standard, which are collectively referred to as a power distribution network safety operation model. The five-prevention power rule refers to five rules which must be followed in order to ensure the safety of operators and power generation in the process of operating primary electrical equipment in a power system, and is called the five-prevention rule for short.
The five-prevention rule is a core element of the safety operation of the power distribution network, and how to realize the five-prevention rule must be considered when a safety operation system of the power distribution network is researched. Tens of thousands or even hundreds of thousands of primary electrical equipment of the power distribution network are almost tasks which cannot be completed if operation mutual constraint rules among the specific electrical equipment are edited; even if the rules are edited, the correctness and the task continuity are difficult to ensure due to too many devices, so that the method using the substation five-prevention system cannot be used in the power distribution network.
Disclosure of Invention
In order to solve the defects and shortcomings in the prior art, the invention provides the operation management and control method based on the IEC61968 standard, and the information in the operation request is analyzed and arranged by using the IEC61968 standard, so that the operation request information can be reasonably planned, managers can obtain alarm information in time, the interruption reason of the interoperation process can be quickly and effectively found out, and the interruption reason can be processed in time, and the continuity and the stability of the information interoperation service can be guaranteed.
Specifically, the operation control method based on the IEC61968 standard provided in this embodiment is applied to an anti-misoperation process of a locking device, and the operation control method includes:
the method comprises the steps of obtaining a job request within a preset time period, analyzing effective data in the job request by combining with an IEC61968 standard to obtain a job request type aiming at a locking device, and generating a scheduling operation ticket based on the job type;
performing five-prevention verification based on the scheduling operation ticket to obtain a five-prevention verification result;
and if the five-prevention verification is successful, unlocking the locking device and updating the running state of the power distribution network.
Optionally, the obtaining of the job request within the preset time period, analyzing effective data in the job request by combining with an IEC61968 standard to obtain a job request type for the locking device, and generating a scheduling operation ticket based on the job type includes:
screening data in the operation request to obtain effective data based on IEC61968 standard;
and extracting and recording message contents including a source address, a data destination address and a sending time stamp of the effective data.
Optionally, the message content including a source address, a data destination address, and a sending timestamp of valid data is extracted and recorded, including;
reserving data beginning with XML tags in a request message structure, a response message structure, an event message structure or an error message structure based on IEC61968 standard in the data packet;
reserving the data with the child nodes in the remaining data as Header labels;
reserving the data comprising Verb and Noun labels in the residual data;
and reserving the data of verbs and nouns belonging to IEC61968 standard in the values of the Verb and Noun tags in the residual data to obtain the valid data.
Optionally, the performing five-prevention verification based on the scheduling operation ticket to obtain a five-prevention verification result includes:
performing primary five-prevention verification based on the scheduling operation ticket;
if the five-prevention verification is successful, generating a scheduling order, otherwise, recording the failure reason and verifying again;
generating a switching operation ticket based on a scheduling order to perform secondary five-prevention verification;
and if the five-prevention verification is successful, acquiring the computer key to perform subsequent unlocking operation.
Optionally, if the five-prevention verification succeeds, unlocking the locking device, and updating the operation state of the power distribution network, including:
unlocking the locking device by using a computer key;
after the information returned by the computer key is obtained, the running state of the power distribution network is updated;
and carrying out system synchronization processing based on the updated running state of the power distribution network.
The technical scheme provided by the invention has the beneficial effects that:
the method and the system enable managers to obtain alarm information in time, quickly and effectively find out the interruption reason of the interoperation process, process the interruption reason in time and ensure the continuity and stability of the information interoperation service.
Drawings
In order to more clearly illustrate the technical solution of the present invention, the drawings needed to be used in the description of the embodiments will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings based on the drawings without creative efforts.
Fig. 1 is a schematic flowchart of an operation control method based on IEC61968 standard according to an embodiment of the present application.
Detailed Description
To make the structure and advantages of the present invention clearer, the structure of the present invention will be further described with reference to the accompanying drawings.
Example one
Specifically, the operation control method based on the IEC61968 standard (international electrotechnical Commission (IEC for short)) established in 1906 and being the earliest non-government international electrotechnical standardization organization established in the world is applied to the anti-misoperation process of the locking device, as shown in fig. 1, and the operation control method includes:
11. the method comprises the steps of obtaining a job request within a preset time period, analyzing effective data in the job request by combining with an IEC61968 standard to obtain a job request type aiming at a locking device, and generating a scheduling operation ticket based on the job type;
12. performing five-prevention verification based on the scheduling operation ticket to obtain a five-prevention verification result;
13. and if the five-prevention verification is successful, unlocking the locking device and updating the running state of the power distribution network.
In implementation, the present application provides an operation management and control method based on the IEC61968 standard, which is used to implement the anti-misoperation of the locking device, and specifically, the scheduling operation ticket obtaining process based on the IEC61968 standard, which is provided in step 11, includes:
111. screening data in the operation request to obtain effective data based on IEC61968 standard;
112. and extracting and recording message contents including a source address, a data destination address and a sending time stamp of the effective data.
Wherein, the step of obtaining the specific message content proposed in step 112 includes:
reserving data beginning with XML tags in a request message structure, a response message structure, an event message structure or an error message structure based on IEC61968 standard in the data packet;
reserving the data with the child nodes in the remaining data as Header labels;
reserving the data comprising Verb and Noun labels in the residual data;
and reserving the data of verbs and nouns belonging to IEC61968 standard in the values of the Verb and Noun tags in the residual data to obtain the valid data.
Based on the foregoing, the step of obtaining the five-prevention verification result proposed in step 12 includes:
121. performing primary five-prevention verification based on the scheduling operation ticket;
122. if the five-prevention verification is successful, generating a scheduling order, otherwise, recording the failure reason and verifying again;
123. generating a switching operation ticket based on a scheduling order to perform secondary five-prevention verification;
124. and if the five-prevention verification is successful, acquiring the computer key to perform subsequent unlocking operation.
After the five-prevention verification succeeds, the locking device needs to be unlocked and the running state of the power distribution network is updated, including:
131. unlocking the locking device by using a computer key;
132. after the information returned by the computer key is obtained, the running state of the power distribution network is updated;
133. and carrying out system synchronization processing based on the updated running state of the power distribution network.
Judging whether the monitoring system has monitored all data packets based on IEC61968 standard transmitted between the information interaction bus and each application system on line, if so, judging that the monitoring system completes the supervision task and sending the judgment information to a closing module;
and after receiving the judgment information sent by the supervision task judgment module, closing a monitoring module and a data acquisition module in the monitoring system.
By using the priority level of the transmission information on the bus, the information transmission of the designated adapter is dynamically suspended or started according to the use condition of the resource in the operation process of the bus, thereby solving the risk of the bus in overload operation and ensuring the safe and stable operation of the bus. When the bus runs over the rated load, a stop instruction is sent to the adapter with the low priority according to the configured priority, the sending and receiving of the messages of all the adapters are stopped, and a start instruction is sent to the adapter again when the bus resources are normal. For example, the priority levels are 1, 2 and 3 from high to low, the message flow control module of the bus may temporarily set the application system to which the message with the low priority level 3 is addressed, and when the previous priority levels 1 and 2 are finished, restart the application system to which the message with the priority level 3 corresponds.
The sequence numbers in the above embodiments are merely for description, and do not represent the sequence of the assembly or the use of the components. The above description is only exemplary of the present invention and should not be taken as limiting the invention, as any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (5)

1.基于IEC61968标准的作业管控方法,应用于闭锁装置的防误操作流程,其特征在于,所述作业管控方法包括:1. The operation control method based on the IEC61968 standard, applied to the anti-misoperation process of the locking device, is characterized in that, the operation control method comprises: 获取预设时间周内的作业请求,结合IEC61968标准对作业请求中的有效数据进行分析获取针对闭锁装置的作业请求类型,基于作业类型生成调度操作票;Obtain job requests within a preset time week, analyze the valid data in the job request in combination with the IEC61968 standard, obtain the job request type for the locking device, and generate a scheduling operation ticket based on the job type; 基于调度操作票进行五防校验,获取五防校验结果;Perform five-proof verification based on the scheduling operation ticket, and obtain the five-proof verification result; 如果五防校验成功,则对闭锁装置进行解锁,并更新配电网运行状态。If the five-proof verification is successful, the locking device will be unlocked and the operating status of the distribution network will be updated. 2.根据权利要求1所述的基于IEC61968标准的作业管控方法,其特征在于,所述获取预设时间周内的作业请求,结合IEC61968标准对作业请求中的有效数据进行分析获取针对闭锁装置的作业请求类型,基于作业类型生成调度操作票,包括:2 . The work management and control method based on the IEC61968 standard according to claim 1 , wherein the acquisition of the work request within a preset time period is performed in combination with the IEC61968 standard to analyze the valid data in the work request to obtain the data for the locking device. 3 . Job request type, which generates scheduling operation tickets based on the job type, including: 对作业请求中的数据进行筛选,得到基于IEC61968标准的有效数据;Screen the data in the job request to obtain valid data based on the IEC61968 standard; 提取并记录包括有效数据的源地址、数据目标地址、发送时间戳在内的消息内容。Extract and record message content including valid data source address, data destination address, and sending timestamp. 3.根据权利要求2所述的基于IEC61968标准的作业管控方法,其特征在于,所述提取并记录包括有效数据的源地址、数据目标地址、发送时间戳在内的消息内容,包括;3. The job control method based on the IEC61968 standard according to claim 2, wherein the extracting and recording the message content including the source address of the valid data, the data destination address, and the sending time stamp, comprising; 保留所述数据包中的基于IEC 61968标准的请求消息结构、应答消息结构、事件消息结构或错误消息结构中的以XML标签开头的数据;Retain the data beginning with the XML tag in the request message structure, response message structure, event message structure or error message structure based on the IEC 61968 standard in the data packet; 保留剩余所述数据中的子节点为Header标签的所述数据;Retain the data whose child nodes in the remaining data are Header tags; 保留剩余所述数据中包含Verb和Noun标签的所述数据;Retaining said data containing Verb and Noun tags in the remaining said data; 保留剩余所述数据中的Verb和Noun标签中的值属于IEC 61968标准中的动词与名词的所述数据,得到所述有效数据。The valid data is obtained by retaining the data whose values in the Verb and Noun tags belong to the verbs and nouns in the IEC 61968 standard in the remaining data. 4.根据权利要求1所述的基于IEC61968标准的作业管控方法,其特征在于,所述基于调度操作票进行五防校验,获取五防校验结果,包括:4. The job management and control method based on the IEC61968 standard according to claim 1, wherein the performing five-proof verification based on a scheduling operation ticket, and obtaining a five-proof verification result, comprising: 基于调度操作票进行首次五防校验;Perform the first five-proof verification based on the scheduling operation ticket; 如果五防校验成功则生成调度令,否则记录失败原因再次进行校验;If the five-proof verification is successful, a scheduling order will be generated, otherwise, the reason for the failure will be recorded and the verification will be performed again; 基于调度令生成倒闸操作票进行二次五防校验;Based on the dispatching order, the gate operation ticket is generated for secondary five-proof verification; 如果五防校验成功则获取电脑钥匙进行后续解锁操作。If the five-proof verification is successful, obtain the computer key for subsequent unlocking operations. 5.根据权利要求4所述的基于IEC61968标准的作业管控方法,其特征在于,所述如果五防校验成功,则对闭锁装置进行解锁,并更新配电网运行状态,包括:5 . The operation control method based on the IEC61968 standard according to claim 4 , wherein if the five-proof verification is successful, the locking device is unlocked and the operating status of the power distribution network is updated, comprising: 6 . 使用电脑钥匙对闭锁装置进行解锁;Use the computer key to unlock the locking device; 得到电脑钥匙回传信息后,对配电网运行状态进行更新;After getting the information returned by the computer key, update the operation status of the distribution network; 基于更新后的配电网运行状态进行系统同步处理。The system is synchronized based on the updated operating status of the distribution network.
CN201911166496.9A 2019-11-25 2019-11-25 Operation control method based on IEC61968 standard Pending CN111143380A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911166496.9A CN111143380A (en) 2019-11-25 2019-11-25 Operation control method based on IEC61968 standard

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911166496.9A CN111143380A (en) 2019-11-25 2019-11-25 Operation control method based on IEC61968 standard

Publications (1)

Publication Number Publication Date
CN111143380A true CN111143380A (en) 2020-05-12

Family

ID=70516655

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911166496.9A Pending CN111143380A (en) 2019-11-25 2019-11-25 Operation control method based on IEC61968 standard

Country Status (1)

Country Link
CN (1) CN111143380A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113177404A (en) * 2021-03-30 2021-07-27 宁波万德高科智能科技有限公司 Electric power five-prevention logic verification method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104993977A (en) * 2015-07-10 2015-10-21 中国电力科学研究院 IEC 61968 standard-based data online monitoring method and system
CN106329729A (en) * 2016-09-13 2017-01-11 江苏方天电力技术有限公司 Intelligent power distribution terminal based on distributed type virtual plug-in
CN110084946A (en) * 2019-05-23 2019-08-02 国家电网有限公司 A kind of system and method that five-defence block is used for based on wearable device

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104993977A (en) * 2015-07-10 2015-10-21 中国电力科学研究院 IEC 61968 standard-based data online monitoring method and system
CN106329729A (en) * 2016-09-13 2017-01-11 江苏方天电力技术有限公司 Intelligent power distribution terminal based on distributed type virtual plug-in
CN110084946A (en) * 2019-05-23 2019-08-02 国家电网有限公司 A kind of system and method that five-defence block is used for based on wearable device

Non-Patent Citations (10)

* Cited by examiner, † Cited by third party
Title
姚剑峰;赵玉成;倪国强;沈华;刘文峰;胡小锋;: "基于云计算的电网调度防误系统集成架构及关键技术" *
张心心;时金媛;孔锦标;章立宗;张锋明;孙滢涛;马翔;: "基于IEC61968消息集成技术的地区智能电网调配自动化系统贯通模式的研究" *
彭彬;杨阳;吕晓俊;: "电网调度防误操作安全约束系统" *
彭志强;张琦兵;: "电网调度自动化系统信息品质分析新方法及其应用" *
朱静;: "调控一体化新模式研究与应用" *
汤震宇;梁雯;代小翔;尤小明;: "远动程序化操作若干问题的分析" *
胡巨;梁晓兵;高新华;曹丽娟;: "基于GOOSE的变电站在线式五防系统的实现" *
胡巨;陈宏辉;: "一种新型的变电站在线式五防系统的实现" *
谢涛 等: "基于IEC61968的配网系统应用集成技术" *
黄金魁;: "基于典型间隔模型的主接线图分析系统研究与设计" *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113177404A (en) * 2021-03-30 2021-07-27 宁波万德高科智能科技有限公司 Electric power five-prevention logic verification method

Similar Documents

Publication Publication Date Title
CN108600029B (en) Configuration file updating method and device, terminal equipment and storage medium
CN113704089B (en) A full-scenario GSM-R interface server test platform system
CN104036348A (en) Electronic mobile operation order system
CN104933535A (en) An intelligent monitoring operation ticket management method and a system thereof
CN109659936A (en) A kind of smart grid Dispatching Control System failure method of disposal and system
CN115619162A (en) A power supply service command system based on cloud platform and microservice architecture
CN111143380A (en) Operation control method based on IEC61968 standard
CN112565231A (en) Safety II area and III area data synchronization method and device based on power dispatching data network
WO2022088803A1 (en) System information analysis method and apparatus based on cloud environment, electronic device, and medium
CN115277392A (en) System and method for checking configuration compliance of power dispatching data network equipment
CN113222537A (en) Nuclear power plant business service system based on micro-service architecture
CN104993977B (en) Data online monitoring method and system based on IEC61968 standard
CN111447115A (en) State monitoring method for entity of Internet of things
CN110759191B (en) Elevator control method based on 5G smart park
CN116470591A (en) Substation management method and related equipment
CN116028582A (en) Digital unified data platform for hydropower station
CN114679295A (en) Firewall security configuration method and device
CN113722159A (en) Disaster recovery switching system based on ansable
CN116761106B (en) Optical fiber routing service scheduling method and device, electronic equipment and storage medium
CN112580988A (en) Power grid security risk management and control method based on block chain technology
CN105653423A (en) Method for automatically acquiring and analyzing health statuses of distributed information systems and system thereof
CN112464630B (en) Automatic generation method and system for scheduling instruction ticket
Zhang et al. Design of troubleshooting tool for IOT terminal access problems
Zhang et al. Operation Risk Warning of Edge Data Centers
CN115421935A (en) Data interaction method, device and system for basic platform of substation monitoring system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200512

RJ01 Rejection of invention patent application after publication