CN111119938A - Method for processing karst cave at upper part of tunnel - Google Patents

Method for processing karst cave at upper part of tunnel Download PDF

Info

Publication number
CN111119938A
CN111119938A CN201911397452.7A CN201911397452A CN111119938A CN 111119938 A CN111119938 A CN 111119938A CN 201911397452 A CN201911397452 A CN 201911397452A CN 111119938 A CN111119938 A CN 111119938A
Authority
CN
China
Prior art keywords
tunnel
karst cave
concrete
treating
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911397452.7A
Other languages
Chinese (zh)
Other versions
CN111119938B (en
Inventor
姜冰
王方立
韩晓东
葛浪潮
吴建峰
肖向荣
刘怀刚
高世强
陶坡
韩春鹏
唐代新
赵胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
Road and Bridge South China Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
Road and Bridge South China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, Road and Bridge South China Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN201911397452.7A priority Critical patent/CN111119938B/en
Publication of CN111119938A publication Critical patent/CN111119938A/en
Application granted granted Critical
Publication of CN111119938B publication Critical patent/CN111119938B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere

Abstract

The application discloses a method for processing a karst cave at the upper part of a tunnel, which comprises the following steps: cleaning the interior of the karst cave after the upper part of the tunnel face passes through the bottom of the karst cave; pouring a concrete retaining wall on one side of the karst cave communicated with the ground surface; performing outer-layer arch protection and primary support construction on the tunnel; filling a concrete buffer layer outside the outer layer arch protection; depositing a sandy cushioning layer over the concrete cushioning layer. The method for treating the karst cave in the upper part of the tunnel has the advantages that the construction efficiency is high, the risk of the construction process is low, the karst cave in the upper part of the tunnel can be reasonably treated, the safety and stability of the structure are ensured, the construction quality of tunnel engineering is improved, the construction progress is accelerated, and the safety of the construction period and the stability of the operation period are ensured under the conditions that the karst cave is large in span, is communicated with the earth surface and has mud outburst and water burst disasters.

Description

Method for processing karst cave at upper part of tunnel
Technical Field
The application relates to the field of road and bridge construction, in particular to a method for processing a karst cave in the upper part of a tunnel.
Background
Karst areas have complex geological structures, and are often developed into cracks, faults and karst caves, and have the characteristics of mud, rich water and the like. In the process of tunneling in a tunnel, if a cavity karst cave geologic body appears at the upper part, the danger of disasters such as block falling, collapse, mud outburst, water burst and the like can exist. The karst cave block falling collapse is caused by that the integrity and stability of soluble rocks in a stratum are damaged under the action of corrosion, the strength of surrounding rocks is reduced, the situation that part of rocks are separated from parent rocks or even wholly collapse can occur under construction disturbance, and the mud burst and water burst phenomenon is determined by the hydraulic connection degree of the karst cave, surrounding media and the ground surface and is not random. The geological structure, the water system characteristics and the climatic conditions near the tunnel are investigated, and the karst cave is treated scientifically and reasonably, so that the construction quality and the safety can be ensured, and the risk is reduced.
Traditional tunnel upper portion cavity cavern's reinforcement and processing method of backfilling are generally used for resisting the impact load effect that the cavern top falls the piece and collapses, avoid taking place primary support and suffer destruction, then adopt measures such as slip casting, back stifled, drainage when gushing mud gushing water, if the follow-up condition that takes place many times and suddenly mud and karst continue to develop, these prior art can have great potential safety hazard when handling the large-scale mud cavern that suddenly in tunnel upper portion, can not guarantee construction safety and tunnel stable in structure.
Disclosure of Invention
The application aims to provide a construction method which is scientific and reasonable, has high construction efficiency and low risk, can reasonably treat the cavity cavern at the upper part of the tunnel and ensures that the structure is safe and stable, and particularly relates to a treatment method of the cavity cavern at the upper part of the tunnel.
In order to achieve the technical purpose, the technical scheme adopted by the application is as follows:
a method for processing a karst cave at the upper part of a tunnel comprises the following steps:
cleaning the interior of the karst cave after the upper part of the tunnel face passes through the bottom of the karst cave;
pouring a concrete retaining wall on one side of the karst cave communicated with the ground surface;
performing outer-layer arch protection and primary support construction on the tunnel;
filling a concrete buffer layer outside the outer layer arch protection;
depositing a sandy cushioning layer over the concrete cushioning layer.
Preferably, before the cleaning of the interior of the karst cave, danger elimination and sludge cleaning are carried out on the interior of the tunnel.
Optionally, the inside of the karst cave is cleaned by at least one of the following methods:
excavating by a step method; excavating manually; mechanical excavation; blasting and excavating; and carrying out primary support on the inner wall of the excavated karst cave.
Specifically, when blasting excavation is adopted, a micro-vibration smooth surface blasting method is adopted, the blast hole trace rate is greater than 50%, and the step error between two adjacent blast holes is smaller than 100 mm.
When the concrete retaining wall is poured, a concrete foundation is arranged at the bottom of the karst cave; the concrete retaining wall surface sets up safe rack, the distance of the top of safe rack and solution cavity top is greater than 4.5 m.
When the concrete retaining wall is poured, a drain hole is embedded in the concrete retaining wall, a reverse filtering layer is arranged at the inlet of the drain hole, and the lowest point of the outlet of the drain hole is higher than the foundation of the concrete retaining wall by at least 30 cm.
Preferably, the drainage holes are communicated with other drainage channels in the tunnel.
When the tunnel is subjected to outer-layer arch protection and primary support construction, pumping pipes for conveying concrete are pre-buried on the laid steel skeleton, and the pumping pipes are used for forming an outer-layer arch protection and a concrete buffer layer; the inlet of the pumping pipe is exposed outside the primary support, and the tail end of the pumping pipe extends to the bottom of the preset sand buffer layer.
Preferably, the top of the concrete buffer layer is at least 150cm from the outer arch.
Preferably, the pumping pipe pumps concrete with the thickness less than 50cm each time, and the next pumping is carried out when the strength of the concrete at the uppermost layer reaches more than 70%.
Preferably, the pumping pipe is used for pumping C20 concrete.
Further, when the tunnel is subjected to outer-layer arch protection and primary support construction, sand blowing pipes for conveying sand grains are pre-buried on the laid steel framework, inlets of the sand blowing pipes are exposed outside the primary support, and the tail ends of the sand blowing pipes extend to the top of a preset sandy buffer layer.
Preferably, at least one of the sand-blasting pipes is arranged along the central axis of the tunnel face.
Preferably, the thickness of the sandy buffer layer is at least 200 cm. The sand blowing pipe is used for conveying sand grains with the grain size of 3.1 mm.
Further, when the tunnel is subjected to outer-layer arch protection and primary support construction, an arch protection foundation of the outer-layer arch protection is arranged at the bottom or on the side wall of the karst cave.
Compared with the prior art, the method has the following advantages:
(1) the method for treating the karst cave in the upper part of the tunnel is applied to treatment of the large mud burst karst cave in the upper part of the tunnel with the transverse cutting mountain, and comprises the steps of pouring a concrete retaining wall, installing a water drain pipe for drainage, retaining arch construction, primary support construction, concrete and sand particle backfill construction and the like, karst cave backfill, drainage and tunnel support are effectively combined, impact load of karst cave falling block collapse and influence of mud burst water burst disasters can be resisted, construction efficiency is high, risk is low, and safety and stability of a tunnel structure can be guaranteed.
(2) The treatment method of the karst cave in the upper portion of the tunnel, wherein the treatment method combining the concrete retaining wall and the drainage of the water drain pipe, can effectively solve the problem of water burst and mud pressurization of the mud-containing karst cavity, guarantees the stability of a tunnel supporting structure under the condition that the karst cave continues to develop under the karst effect, avoids the phenomenon of water leakage in the later operation process, and effectively prolongs the service life of the tunnel in the karst strong development area.
(3) According to the method for processing the karst cave in the upper portion of the tunnel, the concrete arch protection construction and the karst cave backfilling can be simultaneously completed, the number of the pumping pipes is reduced, the damage of the pre-buried pumping pipes to a primary supporting structure is reduced, the problem that the pumping pipes are easily blocked during conventional concrete arch protection construction is avoided, and the construction quality and the construction progress are effectively improved.
Drawings
Fig. 1 is a schematic view of a protective structure of a karst cave after being processed by the method for processing a karst cave in an upper portion of a tunnel.
The numbers in the figures illustrate the following:
1-karst cave, 2-concrete retaining wall, 3-drain hole, 4-outer layer arch protection, 5-preliminary bracing, 6-concrete arch protection, 7-pumping pipe, 8-water permeable blind pipe, 9-sand blowing pipe, 10-concrete buffer layer, 11-sand buffer layer and 12-water drain pipe.
Detailed Description
The present application is described in further detail below with reference to the attached drawings and the detailed description.
A method for processing a karst cave at the upper part of a tunnel comprises the following steps:
s1: cleaning the interior of the karst cave after the upper part of the tunnel face passes through the bottom of the karst cave;
when a karst cave at the upper part of a tunnel develops and is accompanied with a mud burst disaster in the tunneling process of the tunnel, the tunnel face excavation and the supporting construction are immediately stopped, field construction personnel are timely evacuated, field investigation is carried out after the condition is stable, and the geological structure characteristics in front of the tunnel face and around the tunnel are confirmed. Carrying out geological investigation work in the area of the tunnel engineering, finding out the structural characteristics, the space distribution rule, the diameter-compensating row condition and the change of the underground water system in the area under the construction condition, and arranging the karst hydrogeological condition of the tunnel engineering into a report to provide reference for subsequent construction.
After danger elimination and sludge cleaning inside the tunnel are finished, settlement and deformation observation points are arranged on the primary support which is not less than 10m around the karst cave and has finished construction, and the surrounding rock conditions are closely monitored.
And (3) excavating the hidden cave at the opening of the karst cave according to the standard of V-level surrounding rock after a large-scale mud-bursting karst cave is exposed on the tunnel face at the upper part of the tunnel to be excavated subsequently, constructing by adopting a step method, wherein the footage of each cycle of the step excavation does not exceed 0.6m, excavating the upper step by adopting an artificial pneumatic pick and a matched machine, exploding and removing together by using a micro-vibration smooth blasting method under the conditions of no obvious change in convergence and good stability of the surrounding rock, and performing primary support on the side wall by using a jet-anchored net system after excavation so as to realize cleaning and reinforcement of the interior of the karst cave.
When the blasting operation is adopted, a micro-vibration smooth surface blasting method is required to be applied, the trace rate of blast holes is not less than 50%, the rock surface between two adjacent holes is smooth, and the hole wall should not have obvious blasting cracks; the step error between two adjacent holes is not more than 100 mm.
S2: pouring a concrete retaining wall on one side of the karst cave communicated with the ground surface;
and in the area where the concrete retaining wall needs to be poured, selecting a rock surface with a wide space and a hard and flat surface to pour a concrete foundation, and arranging a safety shed frame. Enough height (not less than 4.5m in the construction example) is reserved between the shed frame and the top of the karst cave when the shed frame is erected, the top of the shed frame is fully paved by adopting wood boards, and yellow and black safety signs are sprayed on the supports.
The concrete retaining wall is poured on one side, communicated with the earth surface, of the karst cave, the water seepage area of the karst cave and the upper portion of the tunnel contour line are isolated, the concrete retaining wall is poured in layers, the joint surface is roughened to ensure good contact, three layers of drain holes are reserved, the vertical distance is 100cm and is arranged in a quincunx shape, geotextile wrapped broken stones are laid around the inlet of the drain holes to serve as a reverse filter layer, and the bottom of the drain hole at the lowest layer (namely the lowest point of the outlet of the drain hole) is about 30cm higher than the concrete.
And installing a hard hollow pipe with the diameter of 100mm as a water drain pipe, communicating the water drain hole with other drainage pore passages in the tunnel, specifically, connecting the water drain hole with a water-permeable blind pipe of the arch protection outer mold and draining the water to drainage ditches at two sides of the tunnel so as to achieve water pressure balance of surrounding rocks in the dissolving cavity and the periphery and ensure the safety of the tunnel at the section.
S3: performing outer-layer arch protection and primary support construction on the tunnel;
and performing outer-layer arch protection construction, performing accurate lofting positioning on the position of each arch truss at the opening of the karst cavity, and chiseling out bed rock to serve as an arch protection foundation so that the arch protection foundation falls on the bottom or the side wall of the karst cave. Further, a steel bar mesh top die is erected on the back face of the steel arch, a foot locking anchor rod and steel bars are timely constructed to be connected to form a combined support when the I-shaped steel arch is erected, and concrete is sprayed on the combined support layer by layer to reach the designed thickness.
The assembling error of the steel arch frame is not more than +/-3 cm along the designed peripheral outline, the plane warpage is less than +/-2 cm, and a gap of not less than 40cm is reserved on the contact surface of the back surface of the steel arch frame and the reinforcing mesh piece so as to ensure the thickness of the protective layer of the sprayed concrete.
And carrying out primary support construction on the closed rock surface subjected to primary spraying operation, arranging the I-steel arch on a stable foundation vertically to the axis of the tunnel when mounting the I-steel arch, timely constructing a foot locking anchor rod and anchoring reinforcing steel bars for connection, and then hanging a net and spraying concrete layer by layer to the designed thickness.
When the tunnel is subjected to outer-layer arch protection and primary support construction, a pumping pipe for conveying concrete and a sand blowing pipe for conveying a sand buffer layer are pre-buried on the laid steel frameworks (including the steel framework of the outer-layer arch protection and the steel framework of the primary support).
Specifically, the pumping pipe is used for forming an outer layer arch protection and a concrete buffer layer; the inlet of the pumping pipe is exposed outside the primary support, and the tail end of the pumping pipe extends to the bottom of the preset sand buffer layer. The pumping pipes arranged in this way can be used for synchronous construction of the concrete arch protection and the concrete buffer layer, or can be used for sharing the pumping pipes during step-by-step construction. Further, holes with proper sizes are cut on the steel bar framework around the pre-buried pumping pipe, concrete conveyed by the pre-buried pumping pipe can flow into gaps between the primary support and the outer layer arch protection along the holes, and the concrete arch protection is formed after final setting. Furthermore, the pipe wall of the pumping pipe is provided with a plurality of outlets to realize the function of slurry separation, so that the concrete can be filled into a designated area more uniformly and more quickly. Preferably, the pumping pipe pumps concrete with the thickness less than 50cm each time, and the next pumping is carried out when the strength of the concrete at the uppermost layer reaches more than 70%. More preferably, the top of the concrete buffer layer is at least 150cm from the outer arch.
Further, the sand blowing pipe is used for forming a sand buffer layer above the concrete buffer layer; the inlet of the sand blowing pipe is exposed outside the primary support, and the tail end of the sand blowing pipe extends to the top of the preset sand buffer layer. Preferably, at least one of the sand-blasting pipes is arranged along the central axis of the tunnel face. This arrangement of the pumping tubes allows for more uniform deposition of the blown sand particles over the concrete buffer. Preferably, the sand blowing pipe is used for conveying sand grains with the grain size of 3.1 mm. The thickness of the sandy buffer layer is at least 200 cm.
The sand buffer layer and the concrete buffer layer can effectively resist impact load of collapse of the karst cave top surface falling blocks and protect the stability of a tunnel supporting structure. The concrete buffer layer is preferably made of C20 concrete, and the concrete arch protector can also be made of C20 concrete.
S4: filling a concrete buffer layer outside the outer layer arch protection; in particular, the concrete is delivered through said pumping pipe to a predetermined concrete buffer layer area, the content of the concrete buffer layer already mentioned above, which is not repeated here.
S5: depositing a sand buffer layer over the concrete buffer layer; in particular, the sand is conveyed through the sand blow pipe to a predetermined sand cushion area, the contents of the sand cushion already mentioned above are not repeated here.
After the construction of the concrete buffer layer and the sand buffer layer is finished, the pumping pipe and the sand blowing pipe need to be respectively plugged, the outlet of the primary support end and the outlet of the other end, particularly the upper end of the sand blowing pipe (the upper end of the pumping pipe is buried in the sand buffer layer) need to be plugged.
Referring to fig. 1, a karst cave protection structure is formed by applying the method for processing a karst cave in an upper portion of a tunnel described in the present application. The protective structure of the tunnel upper karst cave takes the tunnel as the center and outwards comprises a concrete retaining arch 6, an outer retaining arch 4, a concrete buffer layer 10, a sand buffer layer 11 and a concrete retaining wall 2 in sequence.
The concrete retaining arch 6 is arranged close to the tunnel primary support 5 and is consistent with the outer contour of the tunnel primary support 5;
the outer layer protective arch 4 is tightly attached to the concrete protective arch 6 and is consistent with the outer contour of the concrete protective arch 6; specifically, the outer-layer arch protection 4 comprises steel arch frames arranged in an arch shape, a reinforcing mesh top die erected on the back of the steel arch frames, a concrete layer sprayed and fixed on the reinforcing mesh top die, and a water-permeable blind pipe 8 buried in the steel arch frames; the arch protection foundation of the outer layer arch protection 4 is arranged at the bottom or on the side wall of the karst cave 1; the water-permeable blind pipe 8 is communicated with the tunnel drainage pore passage.
Thus, the concrete retaining arch 6 is formed by filling concrete between the tunnel preliminary bracing 5 and the outer retaining arch 4 after the outer retaining arch 4 is constructed.
The concrete buffer layer 10 is arranged next to the outer layer protection arch 4, and a cavity defined by the outer layer protection arch 4 and the inner wall of the karst cave 1 is filled in a preset height; the sand buffer layer 11 is tightly attached to the concrete buffer layer 10, and a cavity defined by the top of the concrete buffer layer 10 and the inner wall of the karst cave 1 is filled in a preset height;
the concrete buffer layer 10 and the sand buffer layer 11 are constructed through the pumping pipe 7 and the sand blowing pipe 9. In particular, pumping pipes 7 are arranged inside the protective structure from the preliminary bracing 5 of the tunnel to the bottom of the sandy buffer 11. A plurality of outlets are formed in the steel framework around the pumping pipe 7 so as to seep concrete to the preset concrete arch protection 6 area. Furthermore, a sand blowing pipe 9 is arranged in the protective structure from the preliminary bracing 5 of the tunnel to above the top of the sandy buffer layer 11. At least one sand blowing pipe 9 is arranged along the central axis of the tunnel face. In the embodiment, the top of the concrete buffer layer 10 is at least 150cm away from the outer layer arch protection 4; the thickness of the sandy buffer layer 11 is at least 200 cm.
And the concrete retaining wall 2 extends from the bottom of the karst cave 1 to the ground surface at the top of the karst cave 1 along the side wall of the karst cave 1 and is arranged around the tunnel.
The concrete foundation of the concrete retaining wall 2 is arranged at the bottom of the karst cave 1; and a safety shed frame is arranged on the surface of the concrete retaining wall 2, and the distance between the top of the safety shed frame and the top of the karst cave 1 is greater than 4.5 m.
The concrete retaining wall 2 is internally provided with a drain hole 3, the drain hole 3 is communicated with a tunnel drainage pore passage, and particularly communicated with a water permeable blind pipe 8 of the outer layer arch protection 4 through a drain pipe 12 and communicated to a drainage ditch of the tunnel. Further, an inverted filter layer is arranged at the inlet of the drain hole 3. The reverse filter layer comprises stacked gravel wrapped by geotextile. At least three layers of drain holes 3 are formed in the concrete retaining wall 2, the vertical distance between every two layers is 100cm, and the lowest point of the outlet of each drain hole 3 is higher than the foundation of the concrete retaining wall 2 by at least 30 cm.
To sum up, the tunnel upper portion karst cave processing method and the tunnel upper portion karst cave protective structure of this application, large, with the earth's surface intercommunication and exist suddenly under the condition of mud gushing water calamity at the karst cave span, provide a construction efficiency height, the work progress risk is low, can rationally handle tunnel upper portion cavity karst cave and make the safe and stable construction method and protective structure of structure, improve tunnel engineering construction quality for the construction progress, guarantee the safety of construction period and the stability of operation period.
The above embodiments are only preferred embodiments of the present application, but not limited to the above embodiments, and any other changes, modifications, substitutions, combinations, and simplifications which do not depart from the spirit and principle of the present application should be construed as equivalents and are included in the scope of the present application.

Claims (16)

1. A method for processing a karst cave at the upper part of a tunnel is characterized by comprising the following steps:
cleaning the interior of the karst cave after the upper part of the tunnel face passes through the bottom of the karst cave;
pouring a concrete retaining wall on one side of the karst cave communicated with the ground surface;
performing outer-layer arch protection and primary support construction on the tunnel;
filling a concrete buffer layer outside the outer layer arch protection;
depositing a sandy cushioning layer over the concrete cushioning layer.
2. The method for treating the cavern at the upper part of the tunnel as recited in claim 1, wherein before the cleaning of the interior of the cavern, danger elimination and sludge cleaning are performed on the interior of the tunnel.
3. The method for treating the cavern at the upper part of the tunnel as claimed in claim 1, wherein the inner part of the cavern is cleaned by at least one of the following methods:
excavating by a step method;
excavating manually;
mechanical excavation;
blasting and excavating;
and carrying out primary support on the inner wall of the excavated karst cave.
4. The method for treating the karst cave in the upper part of the tunnel according to claim 3, wherein when blasting excavation is adopted, a micro-vibration smooth surface blasting method is adopted, the blast hole trace rate is more than 50%, and the step error between two adjacent blast holes is less than 100 mm.
5. The method for treating the karst cave in the upper part of the tunnel according to claim 1, wherein when the concrete retaining wall is poured, a concrete foundation is arranged at the bottom of the karst cave; the concrete retaining wall surface sets up safe rack, the distance of the top of safe rack and solution cavity top is greater than 4.5 m.
6. The method for treating the karst cave in the upper part of the tunnel according to claim 1, wherein a drain hole is pre-buried in the concrete retaining wall when the concrete retaining wall is poured, a reverse filtering layer is arranged at an inlet of the drain hole, and the lowest point of an outlet of the drain hole is at least 30cm higher than the foundation of the concrete retaining wall.
7. The method for treating the cavern in the upper part of the tunnel as recited in claim 6, wherein the drainage holes are communicated with other drainage channels in the tunnel.
8. The method for treating the karst cave at the upper part of the tunnel according to claim 1, wherein when the outer layer arch protection and the preliminary bracing construction are carried out on the tunnel, pumping pipes for conveying concrete are pre-embedded on the laid steel framework for forming the outer layer arch protection and the concrete buffer layer; the inlet of the pumping pipe is exposed outside the primary support, and the tail end of the pumping pipe extends to the bottom of the preset sand buffer layer.
9. The method of treating a cavern in an upper portion of a tunnel of claim 8, wherein a top of the concrete buffer layer is at least 150cm from the outer shell.
10. The method for treating the karst cave in the upper part of the tunnel according to claim 8, wherein the pumping pipe pumps concrete with a thickness of less than 50cm each time, and the next pumping is performed when the strength of the concrete at the uppermost layer reaches more than 70%.
11. The method for treating the karst cave in the upper portion of the tunnel according to claim 8, wherein the pumping pipe is used for pumping C20 concrete.
12. The method for treating the karst cave in the upper part of the tunnel according to claim 1, wherein when the outer layer arch protection and the preliminary bracing construction are carried out on the tunnel, a sand blowing pipe for conveying sand is pre-embedded on the laid steel framework, the inlet of the sand blowing pipe is exposed outside the preliminary bracing, and the tail end of the sand blowing pipe extends to be above the top of the preset sandy buffer layer.
13. The method for treating a cavern in an upper part of a tunnel as recited in claim 12, wherein at least one of the sand blowing pipes is arranged along a central axis of a tunnel face.
14. The method of treating a cavern in an upper portion of a tunnel of claim 12, wherein the sand cushion layer has a thickness of at least 200 cm.
15. The method for treating the karst cave in the upper portion of the tunnel according to claim 12, wherein the sand blowing pipe is used for conveying sand having a grain size of 3.1 mm.
16. The method for treating the karst cave in the upper part of the tunnel according to claim 1, wherein an arch protection foundation of the outer arch protection is provided on the bottom or the side wall of the karst cave when the outer arch protection and the preliminary bracing are performed on the tunnel.
CN201911397452.7A 2019-12-30 2019-12-30 Method for processing karst cave at upper part of tunnel Active CN111119938B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911397452.7A CN111119938B (en) 2019-12-30 2019-12-30 Method for processing karst cave at upper part of tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911397452.7A CN111119938B (en) 2019-12-30 2019-12-30 Method for processing karst cave at upper part of tunnel

Publications (2)

Publication Number Publication Date
CN111119938A true CN111119938A (en) 2020-05-08
CN111119938B CN111119938B (en) 2022-02-11

Family

ID=70505348

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911397452.7A Active CN111119938B (en) 2019-12-30 2019-12-30 Method for processing karst cave at upper part of tunnel

Country Status (1)

Country Link
CN (1) CN111119938B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113622956A (en) * 2021-08-31 2021-11-09 中铁十八局集团有限公司 Construction method for high-speed railway double-track tunnel to penetrate through vertical mud gushing karst cave
CN113944486A (en) * 2021-11-05 2022-01-18 广西路桥工程集团有限公司 Tunnel hall type karst cave treatment construction method
CN114017058A (en) * 2021-11-11 2022-02-08 中铁十二局集团有限公司 Construction method of fabricated air duct partition plate for plateau railway tunnel double-lane trackless transportation auxiliary gallery
CN114320359A (en) * 2021-12-10 2022-04-12 中国一冶集团有限公司 Method for processing large and deep non-filler karst cave above tunnel arch

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103174438A (en) * 2013-03-25 2013-06-26 中交路桥建设有限公司 Tunnel vault cavity pumping backfill construction method
CN105697033B (en) * 2016-04-01 2017-11-24 长安大学 A kind of construction method of Tunnel Engineering without template punishment rock mass cavity
CN106194196B (en) * 2016-08-22 2019-01-29 北京市政路桥股份有限公司 A kind of large-scale karst cave treatment crossing tunnel trunk and excavation method
CN106988758B (en) * 2017-05-08 2023-09-01 中铁五局集团第五工程有限责任公司 Construction method for crossing large-scale vertical karst cave group tunnel
CN208267867U (en) * 2018-04-10 2018-12-21 惠安华晨贸易有限公司 A kind of tunnel upper large size is without filled-type solution cavity supporting construction
CN109488330A (en) * 2018-12-25 2019-03-19 中铁二院工程集团有限责任公司 The open cut tunnel for passing through half Packing character solution cavity adds the tunnel bottom stake hardened structure of raft
CN110219671A (en) * 2019-03-28 2019-09-10 中铁二院工程集团有限责任公司 It is a kind of to pass through large-scale relieving arch backfill structure and construction method without filling solution cavity tunnel
CN109826081A (en) * 2019-03-29 2019-05-31 中交路桥建设有限公司 Large-scale solution cavity, underground river span of arch structure and construction method in a kind of tunnel

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113622956A (en) * 2021-08-31 2021-11-09 中铁十八局集团有限公司 Construction method for high-speed railway double-track tunnel to penetrate through vertical mud gushing karst cave
US11686198B2 (en) 2021-08-31 2023-06-27 China Railway 18 Bureau Group Co. Ltd. Reinforcement system at railway tunnel section passing through karst cave with large dip angle and construction method
CN113944486A (en) * 2021-11-05 2022-01-18 广西路桥工程集团有限公司 Tunnel hall type karst cave treatment construction method
CN114017058A (en) * 2021-11-11 2022-02-08 中铁十二局集团有限公司 Construction method of fabricated air duct partition plate for plateau railway tunnel double-lane trackless transportation auxiliary gallery
CN114017058B (en) * 2021-11-11 2023-04-25 中铁十二局集团有限公司 Construction method for assembled type wind channel separator of auxiliary tunnel for double-lane trackless transportation of plateau railway tunnel
CN114320359A (en) * 2021-12-10 2022-04-12 中国一冶集团有限公司 Method for processing large and deep non-filler karst cave above tunnel arch

Also Published As

Publication number Publication date
CN111119938B (en) 2022-02-11

Similar Documents

Publication Publication Date Title
CN111119938B (en) Method for processing karst cave at upper part of tunnel
CN110985060A (en) Protective structure of tunnel upper portion solution cavity
CN109854255B (en) Method for processing tunnel unconverged collapse
CN108316339B (en) Construction method of water-permeable geological large arch bridge foundation
CN107905799B (en) Reinforced structure of high-speed rail tunnel bottom water passing karst cave and construction method thereof
CN206495682U (en) A kind of stand quickly handled for Tunnel Landslide
CN107724436A (en) A kind of post-cast strip Seepage method
CN113338970B (en) Shield receiving method
CN109736884B (en) Treatment structure for water gushing in underground river close to tunnel and construction method of treatment structure
CN109236322B (en) Artificial bottom plate for preventing soft rock roadway floor heave and construction and maintenance method thereof
CN110318410A (en) A kind of deep basal pit chance artesian water is prominent to gush decompression drought stress construction method
CN111119904B (en) Construction method of soft surrounding rock karst section tunnel
CN211777473U (en) Protective structure of tunnel upper portion solution cavity
CN110080779B (en) Tunnel bottom karst cave treatment construction method
CN110847929A (en) Tunnel portal section pre-reinforcing and excavating construction method based on partition blasting
CN110953005B (en) Large-deep-buried high-stress coal bunker supporting structure and construction method thereof
CN107869351A (en) A kind of method of the high narrow large-scale solution cavity Cavity treatment security protection of type
CN107218062A (en) A kind of contrary sequence method handles the construction method of Tunnel Collapse
CN111594218A (en) Steep terrain tunnel diagonal hole-entering structure and construction method
CN109209440B (en) Vault settlement treatment method for large-span tunnel
CN206873459U (en) A kind of large-span steel-reinforced concrete foundation ditch support system
CN215292503U (en) Tunnel structure passing through karst cavity
CN115324591A (en) Saturated soft loess tunnel subsection precipitation-support comprehensive construction method
CN210827509U (en) Protective structure of side slope inverted suspension body
CN207062996U (en) Cross the constructing structure of urban road underpass

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant