CN111105051A - Intelligent automation system lightweight master station and information checking method thereof - Google Patents
Intelligent automation system lightweight master station and information checking method thereof Download PDFInfo
- Publication number
- CN111105051A CN111105051A CN201911365191.0A CN201911365191A CN111105051A CN 111105051 A CN111105051 A CN 111105051A CN 201911365191 A CN201911365191 A CN 201911365191A CN 111105051 A CN111105051 A CN 111105051A
- Authority
- CN
- China
- Prior art keywords
- checking
- information
- monitoring
- station
- module
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/20—Administration of product repair or maintenance
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/06—Electricity, gas or water supply
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Abstract
The invention relates to an intelligent automation system light-weight master station and an information checking method thereof. The system comprises a plant site table generating module, a monitoring and auditing module, an automatic operation and maintenance sorting module and a four-remote information input and graph drawing module, wherein the four-remote information and graph and the plant site are debugged and verified, and when the plant site is verified to be correct, monitoring, secondary room checking and automatic three-party checking are carried out. The method comprises the following steps: generating a point table by the station; monitoring an audit point table; judging whether the point table is qualified, if so, automatically performing operation and maintenance arrangement, and performing four-remote information input and graphic drawing; if not, returning to the first step; connecting the factory station end to carry out debugging verification until the verification is correct; and (5) checking information by the monitoring, the secondary room and the automatic three parties until the three parties check the information correctly, and finishing checking. The invention greatly shortens the time for checking the information of the transformer substation; the checking efficiency is improved.
Description
Technical Field
The invention relates to the technical field of power grid intellectualization, in particular to an intelligent automation system light-weight master station and an information checking method thereof.
Background
In the 5G era, the technology is characterized by ultrahigh information transmission rate, all applications based on networks become reliable by 5G, and the Internet of things is the main melody of 5G. The national network proposes to create a ubiquitous power internet of things in a 2019 work meeting.
The automation technology realizes the digitization, the networking and the intellectualization of the power grid, changes the traditional operation mode of the power grid by using a data driving and artificial intelligence method, and realizes the unattended operation of the transformer substation. The transformer substation four-remote information acceptance work is the basic work for creating ubiquitous power internet of things. The accuracy of the information of the system can directly influence the safe and stable operation of the equipment and the power grid.
The three-party check information is the last and most important link of whether the transformer substation has the commissioning condition, when the check information is checked, error information needs to be returned to a station end, the two parties cooperate to perform problem processing and information re-entry, and if omission or errors occur in the operation process, potential safety hazards are generated on the commissioning transformer substation.
When the problem is checked and processed, the problem needs to be analyzed and judged by sending a command by the main station or sending data on the station, and due to mutual influence of personnel, environment and equipment, the checking time of the transformer substation information is too long, so that the time for commissioning and acceptance of the transformer substation is influenced, the burden of operating personnel is invisibly increased, the workload of a cooperative team is increased, and the working efficiency is seriously reduced. Through research, the time consumed by checking the four remote information of the transformer substation exceeds 50% in the whole process, and the whole operation time of the transformer substation is seriously influenced.
Disclosure of Invention
In order to solve the technical problems, the invention provides an intelligent automation system light-weight master station.
In order to achieve the purpose, the invention adopts the following technical scheme:
the utility model provides an intelligence automation system lightweight master station, includes that station point table generates module, control audit module, automatic fortune dimension arrangement module and four distant information input and figure draw module, and four distant information and figure are verified with the debugging of station, and when the station verification is correct, monitor again, secondary room and automatic three-party check.
Has the advantages that: the time for checking the information of the transformer substation is greatly shortened; the checking efficiency is improved; the burden of operators is reduced; and more reliable guarantee is provided for the safety of the commissioning transformer substation.
The invention also provides an information checking method of the light-weight master station of the intelligent automation system.
In order to achieve the purpose, the invention also adopts the following technical scheme:
an information checking method for a lightweight master station of an intelligent automation system comprises the following steps:
(1) generating a point table by the station;
(2) monitoring an audit point table;
(3) judging whether the point table is qualified, if so, automatically performing operation and maintenance arrangement, and performing four-remote information input and graphic drawing; if not, returning to the step (1);
(4) connecting the factory station end to carry out debugging verification until the verification is correct;
(5) and (5) checking information by the monitoring, the secondary room and the automatic three parties until the three parties check the information correctly, and finishing checking.
Has the advantages that: the time for checking the information of the transformer substation is greatly shortened; the checking efficiency is improved; the burden of operators is reduced; and more reliable guarantee is provided for the safety of the commissioning transformer substation.
Drawings
Fig. 1 is a schematic diagram of a checking process of four remote information of a transformer substation in the embodiment;
Detailed Description
The invention is described in further detail below with reference to the figures and specific examples.
Example one
The utility model provides an intelligence automation system lightweight master station, includes that station point table generates module, control audit module, automatic fortune dimension arrangement module and four distant information input and figure draw module, and four distant information and figure are verified with the debugging of station, and when the station verification is correct, monitor again, secondary room and automatic three-party check.
The transformer substation four-remote information checking process is shown in fig. 1, and comprises the following specific steps:
firstly, a point table is generated on the plant station side, and after the monitoring and the verification are qualified, the point table is put into an automatic maintenance personnel for arrangement and information input and graphic drawing of a dispatching automation system.
And then, exporting the single-station graph model information maintained in the dispatching automation system through a CIM format.
And then, the portable master station conducts graph-model import work through a single-station model import tool, and after the model file is verified and analyzed, database updating, graph rationality verification and effective mapping of the graph-model relation of the model library are realized.
Secondly, after the drawing mode is successfully guided in, a transmission test is carried out, the transmission test is pre-checked with a portable main station system while debugging is carried out at a factory station end, and when a problem occurs, data message comparison can be simultaneously opened on site, so that the transmission test is clear and intuitive, and the problem processing speed is accelerated; and combining the checking graph and the model result to modify the information with the wrong graph model.
And thirdly, if the graph model changes, the portable main station exports the graph model information by using a single-station model export tool, and then performs difference comparison on the graph model by using analysis and verification through the single-station import tool in the dispatching automation system so as to form a new mapping model library to generate graph model association.
And finally, after the map model of the dispatching automation system is updated, the dispatching automation system is handed to monitoring personnel, secondary rooms and operation and maintenance personnel for checking, and after the primary correct checking is passed, the transformer substation has operation and acceptance conditions.
When the transformer substation and the portable main station are debugged and the information is checked to be correct, and then the formal telecontrol channel and the actual dispatching automation system main station are checked to be correct, the effect of getting twice with half the effort is achieved no matter all the information is transmitted once again or only the signals are extracted and checked.
Has the advantages that: the time for checking the information of the transformer substation is greatly shortened; the checking efficiency is improved; the burden of operators is reduced; and more reliable guarantee is provided for the safety of the commissioning transformer substation.
Example two
The invention also provides an information checking method of the light-weight master station of the intelligent automation system, which comprises the following steps:
(1) generating a point table by the station;
(2) monitoring an audit point table;
(3) judging whether the point table is qualified, if so, automatically performing operation and maintenance arrangement, and performing four-remote information input and graphic drawing; if not, returning to the step (1);
(4) connecting the factory station end to carry out debugging verification until the verification is correct;
(5) and (5) checking information by the monitoring, the secondary room and the automatic three parties until the three parties check the information correctly, and finishing checking.
In conclusion, the invention has the following obvious advantages: the time for checking the information of the transformer substation is greatly shortened; the checking efficiency is improved; the burden of operators is reduced; and more reliable guarantee is provided for the safety of the commissioning transformer substation.
Claims (2)
1. The light-weight master station of the intelligent automation system is characterized by comprising a plant site table generating module, a monitoring auditing module, an automatic operation and maintenance sorting module and a four-remote information inputting and graph drawing module, wherein the four-remote information and graph and the plant site are debugged and verified, and when the plant site is verified to be correct, monitoring, secondary room checking and automatic three-party checking are carried out.
2. The information checking method of the light-weight master station of the intelligent automation system based on the claim 1 is characterized by comprising the following steps:
(1) generating a point table by the station;
(2) monitoring an audit point table;
(3) judging whether the point table is qualified, if so, automatically performing operation and maintenance arrangement, and performing four-remote information input and graphic drawing; if not, returning to the step (1);
(4) connecting the factory station end to carry out debugging verification until the verification is correct;
(5) and (5) checking information by the monitoring, the secondary room and the automatic three parties until the three parties check the information correctly, and finishing checking.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911365191.0A CN111105051A (en) | 2019-12-26 | 2019-12-26 | Intelligent automation system lightweight master station and information checking method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911365191.0A CN111105051A (en) | 2019-12-26 | 2019-12-26 | Intelligent automation system lightweight master station and information checking method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111105051A true CN111105051A (en) | 2020-05-05 |
Family
ID=70424974
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911365191.0A Pending CN111105051A (en) | 2019-12-26 | 2019-12-26 | Intelligent automation system lightweight master station and information checking method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111105051A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111752981A (en) * | 2020-06-30 | 2020-10-09 | 深圳供电局有限公司 | Power dispatching four-remote data quality detection method |
CN112416487A (en) * | 2020-10-27 | 2021-02-26 | 国网河南省电力公司郑州供电公司 | Substation operation and maintenance basic level work standardization operation and checking application system |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106329730A (en) * | 2016-09-14 | 2017-01-11 | 国网江苏省电力公司连云港供电公司 | Substation monitoring information automatic acceptance system based on intelligent power grid scheduling system |
CN110401692A (en) * | 2019-05-30 | 2019-11-01 | 国网江苏省电力有限公司徐州供电分公司 | A kind of automatic Acceptance Test System of supervisory control of substation information integral and method |
-
2019
- 2019-12-26 CN CN201911365191.0A patent/CN111105051A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106329730A (en) * | 2016-09-14 | 2017-01-11 | 国网江苏省电力公司连云港供电公司 | Substation monitoring information automatic acceptance system based on intelligent power grid scheduling system |
CN110401692A (en) * | 2019-05-30 | 2019-11-01 | 国网江苏省电力有限公司徐州供电分公司 | A kind of automatic Acceptance Test System of supervisory control of substation information integral and method |
Non-Patent Citations (1)
Title |
---|
陈建等: "提高变电站远动信息传动效率的方法研究", 《电工技术》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111752981A (en) * | 2020-06-30 | 2020-10-09 | 深圳供电局有限公司 | Power dispatching four-remote data quality detection method |
CN112416487A (en) * | 2020-10-27 | 2021-02-26 | 国网河南省电力公司郑州供电公司 | Substation operation and maintenance basic level work standardization operation and checking application system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105426300B (en) | Standard conformance test system and method for CIM/E model of power system | |
CN112366818B (en) | Automatic checking and accepting method and system for monitoring information of intelligent substation | |
CN107180314B (en) | Operation and maintenance business model modeling method based on primary and secondary system incidence relation | |
CN104483842A (en) | Regulation and control integrated automatic master station comparison method | |
CN103295163A (en) | Chart-model integrated transformer substation and dispatch master station cooperation modeling method | |
CN102545204B (en) | Automatic generation method and device of power grid fault set | |
CN108512730B (en) | Intelligent substation telecontrol system equipment testing method, device and system | |
CN111105051A (en) | Intelligent automation system lightweight master station and information checking method thereof | |
CN110768372A (en) | IEC61850 standard-based protection information system source end modeling method | |
CN103353857A (en) | Communication test method of integrated monitoring unit in substation | |
CN110611312B (en) | On-line simulation system and method for panoramic data of substation bay level | |
CN106789406A (en) | A kind of IEC61850 communication protocol standards consistency testing system | |
CN102916489A (en) | Virtual terminal automatic wiring method based on primary system structure of regional power grid | |
CN109561155B (en) | Remote centralized monitoring and operation and maintenance method for substation equipment | |
CN111668938B (en) | Method for realizing analog remote control of electric power measurement and control device | |
CN109802487B (en) | Method and device for realizing maintenance function of source end of master station | |
CN110955808B (en) | Method for matching and associating four remote monitoring information of main plant station | |
Shuang et al. | Intelligent mobile operation and maintenance technology and its application of for relay protection based on power wireless virtual private network | |
CN113298342A (en) | Analysis method for safety state of power dispatching instruction | |
CN112636947B (en) | Data network shutdown point table information checking management method | |
CN201898376U (en) | Static safety analysis device of modularization power grid based on communication system | |
CN113131620A (en) | Telecontrol information joint debugging method for transformer substation | |
CN104700232A (en) | Standard auditing system for regulation information point table | |
CN111478433A (en) | Safe intelligent substation sequence control method and system | |
CN110781162A (en) | Database modeling method based on SCD |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20200505 |
|
WD01 | Invention patent application deemed withdrawn after publication |