CN111102002B - Tunnel liquid drainage system - Google Patents

Tunnel liquid drainage system Download PDF

Info

Publication number
CN111102002B
CN111102002B CN201911365320.6A CN201911365320A CN111102002B CN 111102002 B CN111102002 B CN 111102002B CN 201911365320 A CN201911365320 A CN 201911365320A CN 111102002 B CN111102002 B CN 111102002B
Authority
CN
China
Prior art keywords
pipe
drainage
delivery pump
valve
pump
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201911365320.6A
Other languages
Chinese (zh)
Other versions
CN111102002A (en
Inventor
欧智勇
钟玉明
王锡峰
廖伟平
杨乐全
刘永成
彭璞
杨建军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sanchu Co Ltd of China Railway Tunnel Group Co Ltd
Original Assignee
Sanchu Co Ltd of China Railway Tunnel Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sanchu Co Ltd of China Railway Tunnel Group Co Ltd filed Critical Sanchu Co Ltd of China Railway Tunnel Group Co Ltd
Priority to CN201911365320.6A priority Critical patent/CN111102002B/en
Publication of CN111102002A publication Critical patent/CN111102002A/en
Application granted granted Critical
Publication of CN111102002B publication Critical patent/CN111102002B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D21/00Separation of suspended solid particles from liquids by sedimentation
    • B01D21/0012Settling tanks making use of filters, e.g. by floating layers of particulate material
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D21/00Separation of suspended solid particles from liquids by sedimentation
    • B01D21/02Settling tanks with single outlets for the separated liquid
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D21/00Separation of suspended solid particles from liquids by sedimentation
    • B01D21/24Feed or discharge mechanisms for settling tanks
    • B01D21/2444Discharge mechanisms for the classified liquid
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D21/00Separation of suspended solid particles from liquids by sedimentation
    • B01D21/24Feed or discharge mechanisms for settling tanks
    • B01D21/245Discharge mechanisms for the sediments
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D21/00Separation of suspended solid particles from liquids by sedimentation
    • B01D21/30Control equipment
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D21/00Separation of suspended solid particles from liquids by sedimentation
    • B01D21/30Control equipment
    • B01D21/34Controlling the feed distribution; Controlling the liquid level ; Control of process parameters
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F04POSITIVE - DISPLACEMENT MACHINES FOR LIQUIDS; PUMPS FOR LIQUIDS OR ELASTIC FLUIDS
    • F04BPOSITIVE-DISPLACEMENT MACHINES FOR LIQUIDS; PUMPS
    • F04B49/00Control, e.g. of pump delivery, or pump pressure of, or safety measures for, machines, pumps, or pumping installations, not otherwise provided for, or of interest apart from, groups F04B1/00 - F04B47/00
    • F04B49/007Installations or systems with two or more pumps or pump cylinders, wherein the flow-path through the stages can be changed, e.g. from series to parallel
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F04POSITIVE - DISPLACEMENT MACHINES FOR LIQUIDS; PUMPS FOR LIQUIDS OR ELASTIC FLUIDS
    • F04BPOSITIVE-DISPLACEMENT MACHINES FOR LIQUIDS; PUMPS
    • F04B49/00Control, e.g. of pump delivery, or pump pressure of, or safety measures for, machines, pumps, or pumping installations, not otherwise provided for, or of interest apart from, groups F04B1/00 - F04B47/00
    • F04B49/06Control using electricity

Abstract

The invention discloses a tunnel drainage system, which comprises a sedimentation tank, a first drainage structure, a second drainage structure, a diversion structure and a control system, wherein a water level gauge and a floating box are arranged in the sedimentation tank, the first drainage structure comprises a first drainage pipe, a first delivery pump and a first on-off valve, the inlet end of the first drainage pipe is arranged on the floating box, the first delivery pump and the first on-off valve are both arranged on the first drainage pipe, the second drainage structure comprises a second drainage pipe and a second delivery pump, the second delivery pump is arranged on the second drainage pipe, the diversion structure comprises a diversion pipe, a third delivery pump and a one-way valve, the outlet end of the diversion pipe is communicated with the second drainage pipe, the third delivery pump and the one-way valve are arranged on the diversion pipe, and the control system is electrically connected with the water level gauge, the first delivery pump, the second delivery pump and the third delivery pump. Through above-mentioned structure, can discharge mud water and mountain body infiltration reposition of redundant personnel, reduce the water yield that needs the processing, reduce treatment cost.

Description

Tunnel liquid drainage system
Technical Field
The invention relates to the technical field of tunnel construction, in particular to a tunnel drainage system.
Background
In the construction process of some tunnels, mud water is produced by equipment working, and water veins can be met under some conditions, so that mountain body water seepage is generated, and the mud water, the mountain body water seepage and other liquids in the tunnels need to be discharged. The mountain seepage is generally cleaner, and can be directly discharged into the environment or can be used as domestic water after some simple treatment; muddy water is relatively turbid and sometimes contains substances harmful to the environment, so that some muddy water cannot be directly discharged into the environment. In the prior art, slurry water and liquid such as mountain water are generally mixed and discharged together, and the liquid is treated and then discharged into the environment. With the above-described manner, the amount of liquid to be treated is large, which increases the treatment cost.
Disclosure of Invention
The invention aims to solve at least one technical problem in the prior art, and provides a tunnel drainage system which can discharge slurry water and mountain seepage water in a shunting manner and reduce the liquid treatment cost.
The scheme adopted by the invention is as follows: the tunnel drainage system comprises a sedimentation tank, wherein a water level meter and a buoyancy tank are arranged in the sedimentation tank; the first liquid discharging structure comprises a first liquid discharging pipe, a first conveying pump and a first on-off valve, the inlet end of the first liquid discharging pipe is arranged on the floating box, the first conveying pump and the first on-off valve are arranged on the first liquid discharging pipe, and the first on-off valve is positioned on the front side of the first conveying pump; the second liquid discharge structure comprises a second liquid discharge pipe and a second conveying pump, and the second conveying pump is arranged on the second liquid discharge pipe; the inlet end of the shunt pipe is communicated with the first liquid discharge pipe on the rear side of the first conveying pump, the outlet end of the shunt pipe is communicated with the second liquid discharge pipe on the front side of the second conveying pump, and the third conveying pump and the one-way valve are arranged on the shunt pipe; and the control system is electrically connected with the water level gauge, the first conveying pump, the second conveying pump and the third conveying pump.
The beneficial effect that above-mentioned scheme has: through above-mentioned structure, can separate the reposition of redundant personnel discharge with mud water and massif infiltration, reduce the water yield that needs to handle, reduce treatment cost, also be convenient for carry out recovery processing with massif infiltration simultaneously.
According to the tunnel drainage system, the buoyancy tank comprises a net cage, a hook and a buoyancy block, the net cage is hung on the buoyancy block through the hook, and the inlet end of the first drainage pipe extends into the net cage.
According to the tunnel drainage system, the stirring device is arranged in the sedimentation tank, a third drainage pipe is arranged between the second drainage structure and the sedimentation tank, a second on-off valve is arranged on the second drainage pipe, the second on-off valve is positioned at the rear side of the second conveying pump, the inlet end of the third drainage pipe is communicated with the bottom of the sedimentation tank, and the outlet end of the third drainage pipe is communicated with the second drainage pipe between the second conveying pump and the second on-off valve.
According to the tunnel drainage system, the stirring device comprises a fourth conveying pump and a fourth drainage pipe, the fourth conveying pump is arranged on the fourth drainage pipe, the inlet end of the fourth drainage pipe is arranged on the floating box, and the outlet end of the fourth drainage pipe is positioned at the bottom of the sedimentation tank.
According to the tunnel drainage system, the fourth delivery pump is arranged at the top of the side wall of the sedimentation tank.
According to the tunnel drainage system, the shunt pipe is inclined to the first drainage pipe.
According to the tunnel drainage system, the bottom of the sedimentation tank is funnel-shaped.
Additional aspects and advantages of the invention will be set forth in part in the description which follows and, in part, will be obvious from the description, or may be learned by practice of the invention.
Drawings
The invention is further described below with reference to the accompanying drawings and examples;
FIG. 1 is a schematic structural diagram of an embodiment of the present invention;
fig. 2 is a structural view of the buoyancy tank.
Detailed Description
Reference will now be made in detail to the present preferred embodiments of the present invention, examples of which are illustrated in the accompanying drawings, wherein like reference numerals refer to like elements throughout.
In the description of the present invention, unless otherwise explicitly limited, terms such as arrangement, installation, connection and the like should be understood in a broad sense, and those skilled in the art can reasonably determine the specific meanings of the above terms in the present invention in combination with the specific contents of the technical solutions.
Referring to fig. 1 and 2, the tunnel drainage system according to the embodiment of the present invention includes a sedimentation tank 10, a first drainage structure 20, a second drainage structure 30, a diversion structure 40, and a control system (not shown). A water level gauge 11 and a floating box 12 are arranged in the sedimentation tank 10, the first drainage structure 20 comprises a first drainage pipe 21, a first delivery pump 22 and a first on-off valve 23, the inlet end of the first drainage pipe 21 is arranged on the floating box 12, the first delivery pump 22 and the first on-off valve 23 are both arranged on the first drainage pipe 21, and the first on-off valve 23 is positioned at the front side of the first delivery pump 22. The second drain structure 30 includes a second drain pipe 31 and a second transfer pump 32, and the second transfer pump 32 is disposed on the second drain pipe 31. The flow dividing structure 40 includes a flow dividing pipe 41, a third delivery pump 42 and a one-way valve 43, an inlet end of the flow dividing pipe 41 is connected to the first liquid discharge pipe 21 at the rear side of the first delivery pump 22, an outlet end of the flow dividing pipe 41 is connected to the second liquid discharge pipe 31 at the front side of the second delivery pump 32, and the third delivery pump 42 and the one-way valve 43 are disposed on the flow dividing pipe 41. The control system is electrically connected to the water level gauge 11, the first delivery pump 22, the second delivery pump 32, and the third delivery pump 42. The control system receives the signal output by the water level gauge 11 and can control the start and stop of the first conveying pump 22, the second conveying pump 32 and the third conveying pump 42.
The mountain seepage water can be discharged to the sedimentation tank 10, or conveyed into the sedimentation tank 10 through a water pump, and impurities with large specific gravity can be deposited at the bottom of the sedimentation tank 10. When the mountain body seepage water needs to be discharged, the first on-off valve 23 can be opened, and the first delivery pump 22 is started through the control system to discharge the water in the sedimentation tank 10. The buoyancy of the water can make the buoyancy tank 12 and the inlet end of the first drain pipe 21 leave the bottom of the settling tank 10, and prevent impurities from entering the first drain pipe 21. When it is desired to discharge the muddy water, the second transfer pump 32 can be controlled by the control system to be activated to discharge the muddy water. Through above-mentioned structure, can separate the drainage with mud water and massif infiltration, can reduce the water yield that needs to handle, reduce treatment cost, also be convenient for carry out recovery processing with massif infiltration simultaneously.
After a period of use, impurities will accumulate in the second liquid discharge pipe 31, at which time the first on-off valve 23 can be closed, and the control system controls the third delivery pump 42 to be started, so as to feed water in the sedimentation basin 10 into the second liquid discharge pipe 31 and flush the second liquid discharge pipe 31. In the tunnel construction process, the flow rate of the mountain seepage water may increase suddenly, and the mountain seepage water needs to be discharged quickly, and at this time, the first delivery pump 22 and the third delivery pump 42 may be started simultaneously, so that the water in the sedimentation tank 10 is discharged simultaneously through the first drainage pipe 21 and the second drainage pipe 31.
The water level gauge 11 can detect the water level in the sedimentation tank 10 and feed back the value of the water level to the control system. The increment of the water level height in unit time is the rising speed of the water level height. If the rising speed of the water level exceeds the first set value, it can be judged that the mountain seepage quantity suddenly increases, and the control system can control the first delivery pump 22 and the third delivery pump 42 to be started simultaneously. In addition, when the rising speed of the water level does not exceed the first set value, if the value of the water level does not exceed the second set value, the first transfer pump 22 may not be activated; when the value of the water level height exceeds the second set value, the first delivery pump 22 starts draining. The first transfer pump 22 can be operated intermittently, so as to reduce energy consumption, prevent the first transfer pump 22 from idle operation, and prevent the inlet end of the first drainage pipe 21 from falling to the bottom of the sedimentation tank 10 to suck impurities due to the low water level.
The shunt tube 41 is inclined to the first drain tube 21 to facilitate water flow into the shunt tube 41.
Referring to fig. 2, the buoyancy tank 12 includes a netpen 121, a hook 122 and a buoyancy block 123, the hook 122 is disposed on the netpen 121, the hook 122 is hung on the buoyancy block 123, so that the netpen 121 is hung on the buoyancy block 123, and the inlet end of the first drainage pipe 21 extends into the netpen 121. The net cage 121 can prevent suspended impurities in water from being sucked by the first drain pipe 21. The netpen 121 may be removed when it is desired to clean the netpen 121 or when rapid drainage is desired. The buoyancy block 123 may be a wood block, a foam block, or a hollow box structure.
The stirring device 13 is arranged in the sedimentation tank 10, a third liquid discharge pipe 51 is arranged between the second liquid discharge structure 30 and the sedimentation tank 10, a second on-off valve 33 is arranged on the second liquid discharge pipe 31, the second on-off valve 33 is positioned at the rear side of the second conveying pump 32, the inlet end of the third liquid discharge pipe 51 is communicated with the bottom of the sedimentation tank 10, and the outlet end of the third liquid discharge pipe 51 is communicated with the second liquid discharge pipe 31 between the second conveying pump 32 and the second on-off valve 33. The impurities at the bottom of the sedimentation tank 10 can be stirred and lifted by the stirring device 13, and the water at the bottom of the sedimentation tank 10 can be discharged through the second liquid discharge pipe 31 by the third liquid discharge pipe 51 and the second delivery pump 32, so that the impurities in the sedimentation tank 10 can be removed.
Specifically, the stirring device 13 includes a fourth delivery pump 131 and a fourth liquid discharge pipe 132, the fourth delivery pump 131 is disposed on the fourth liquid discharge pipe 132, an inlet end of the fourth liquid discharge pipe 132 is disposed on the floating box 12, and an outlet end of the fourth liquid discharge pipe 132 is located at the bottom of the sedimentation tank 10. The fourth transfer pump 131 is activated to agitate the water to lift the impurities in the bottom of the settling tank 10.
The fourth delivery pump 131 is arranged at the top of the side wall of the sedimentation tank 10, so that the fourth delivery pump 131 is prevented from being immersed in water, and the safety is improved.
In some embodiments, a support may be disposed in the sedimentation basin 10, and the fourth transfer pump 131 may be disposed on the support.
The bottom of the sedimentation tank 10 is funnel-shaped to facilitate the concentrated deposition of impurities.
In some embodiments, the stirring device 13 may further include a motor and a stirring paddle, the motor is fixedly disposed on the sidewall of the sedimentation tank 10, the stirring paddle extends into the bottom of the sedimentation tank 10, and the stirring paddle is connected to the motor.
Preferably, the reservoir is mounted on a carriage which is towed by other power equipment, the sedimentation basin 10 being defined within the interior of the reservoir. Of course, the sedimentation tank 10 may be directly installed in the tunnel.
In the above-described embodiment, for the description of the front-rear direction, reference is made to the liquid flow direction, i.e., the direction in which the liquid flows is the front.
The embodiments of the present invention have been described in detail with reference to the accompanying drawings, but the present invention is not limited to the above embodiments, and various changes can be made within the knowledge of those skilled in the art without departing from the gist of the present invention.

Claims (5)

1. The tunnel drainage system is characterized by comprising
The sedimentation tank is internally provided with a water level gauge and a floating box;
the first drainage structure comprises a first drainage pipe, a first conveying pump and a first on-off valve, the inlet end of the first drainage pipe is arranged on the floating box, the first conveying pump and the first on-off valve are both arranged on the first drainage pipe, the first on-off valve is positioned on the front side of the first conveying pump, and the first drainage structure is used for draining mountain water seepage;
the second liquid discharging structure comprises a second liquid discharging pipe and a second conveying pump, the second conveying pump is arranged on the second liquid discharging pipe, and the second liquid discharging structure is used for discharging muddy water;
the inlet end of the shunt pipe is communicated with the first liquid discharge pipe on the rear side of the first conveying pump, the outlet end of the shunt pipe is communicated with the second liquid discharge pipe on the front side of the second conveying pump, and the third conveying pump and the one-way valve are arranged on the shunt pipe;
a control system electrically connected to the water level gauge, the first delivery pump, the second delivery pump, and the third delivery pump;
a stirring device is arranged in the sedimentation tank, a third liquid discharge pipe is arranged between the second liquid discharge structure and the sedimentation tank, a second on-off valve is arranged on the second liquid discharge pipe, the second on-off valve is positioned at the rear side of the second conveying pump, the inlet end of the third liquid discharge pipe is communicated with the bottom of the sedimentation tank, and the outlet end of the third liquid discharge pipe is communicated with the second liquid discharge pipe between the second conveying pump and the second on-off valve;
the flotation tank includes cylinder mould, couple and buoyancy piece, the cylinder mould passes through the couple articulate in on the buoyancy piece, the entry end of first drain pipe stretches into extremely in the cylinder mould.
2. The tunnel drainage system of claim 1, wherein the agitation device comprises a fourth delivery pump and a fourth drainage pipe, the fourth delivery pump is disposed on the fourth drainage pipe, an inlet end of the fourth drainage pipe is disposed on the buoyancy tank, and an outlet end of the fourth drainage pipe is located at the bottom of the sedimentation basin.
3. The tunnel drainage system of claim 2, wherein the fourth transfer pump is disposed at a top of a side wall of the settling tank.
4. The tunnel drainage system of claim 1, wherein the shunt tube is oblique to the first drainage tube.
5. The tunnel drainage system of claim 1, wherein the bottom of the settling tank is funnel-shaped.
CN201911365320.6A 2019-12-26 2019-12-26 Tunnel liquid drainage system Active CN111102002B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911365320.6A CN111102002B (en) 2019-12-26 2019-12-26 Tunnel liquid drainage system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911365320.6A CN111102002B (en) 2019-12-26 2019-12-26 Tunnel liquid drainage system

Publications (2)

Publication Number Publication Date
CN111102002A CN111102002A (en) 2020-05-05
CN111102002B true CN111102002B (en) 2021-08-24

Family

ID=70424961

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911365320.6A Active CN111102002B (en) 2019-12-26 2019-12-26 Tunnel liquid drainage system

Country Status (1)

Country Link
CN (1) CN111102002B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202001060U (en) * 2010-12-15 2011-10-05 中铁十一局集团城市轨道工程有限公司 Improved shield machine drainage system
CN203342467U (en) * 2013-06-04 2013-12-18 佛山市高明贝斯特陶瓷有限公司 Automatic clear water and slurry pumping device
CN104138673A (en) * 2013-05-10 2014-11-12 天津万联管道工程有限公司 Cylindrical underground spliced horizontal flow sedimentation tank
CN208933149U (en) * 2018-06-08 2019-06-04 南京必蓝环境技术有限公司 A kind of device for exploiting field sewage treatment

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10208745B2 (en) * 2015-12-18 2019-02-19 General Electric Company System and method for controlling a fluid transport system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202001060U (en) * 2010-12-15 2011-10-05 中铁十一局集团城市轨道工程有限公司 Improved shield machine drainage system
CN104138673A (en) * 2013-05-10 2014-11-12 天津万联管道工程有限公司 Cylindrical underground spliced horizontal flow sedimentation tank
CN203342467U (en) * 2013-06-04 2013-12-18 佛山市高明贝斯特陶瓷有限公司 Automatic clear water and slurry pumping device
CN208933149U (en) * 2018-06-08 2019-06-04 南京必蓝环境技术有限公司 A kind of device for exploiting field sewage treatment

Also Published As

Publication number Publication date
CN111102002A (en) 2020-05-05

Similar Documents

Publication Publication Date Title
CN204530819U (en) A kind of small hydropower station Accrete clearing device
CN104712003B (en) A kind of small hydropower station desilting equipment
CN103936255B (en) mud separating device
CN111102002B (en) Tunnel liquid drainage system
CN203807320U (en) Sludge separation equipment
CN212102149U (en) Coal washing wastewater recycling device
CN103910449A (en) Fracturing flow-back fluid treatment device
KR101409735B1 (en) Apparatus for dissolving flocculant
CN212293112U (en) Coal-containing wastewater treatment device of power plant coal conveying purification station
CN213032402U (en) Stirring tank overflow recovery system
CN210237279U (en) Cavitation air flotation for water supply and drainage treatment
CN211141764U (en) Sedimentation tank for sewage treatment
CN209797614U (en) Sewage treatment reactor
CN209143747U (en) A kind of shallow air-floatation effluent filter
CN209378523U (en) A kind of high-efficiency thickener
CN203794718U (en) Fracturing flowback liquid treating device
CN208694330U (en) A kind of device of washing bay rhone and sedimentation basin automatic desilting
CN107285517B (en) Skid-mounted integrated high-oil-content sludge-water separation and oil-sludge concentration device
RU104936U1 (en) CIRCUIT WATER CLEANING SYSTEM WHEN WASHING CARS
CN215206496U (en) Material receiving device
CN209378522U (en) A kind of new structural concentrator
CN219031864U (en) Waste liquid impurity solidification processing device
CN109231335A (en) A kind of shallow air-floatation effluent filter
CN217681641U (en) Deep well pumping and cleaning device
CN215276157U (en) Automatic flushing structure for environment-friendly and energy-saving construction site engineering truck

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant