CN111099494A - Hoisting and hanging bracket device and method for steel reinforcement cage - Google Patents
Hoisting and hanging bracket device and method for steel reinforcement cage Download PDFInfo
- Publication number
- CN111099494A CN111099494A CN202010051058.4A CN202010051058A CN111099494A CN 111099494 A CN111099494 A CN 111099494A CN 202010051058 A CN202010051058 A CN 202010051058A CN 111099494 A CN111099494 A CN 111099494A
- Authority
- CN
- China
- Prior art keywords
- hanger
- lifting
- reinforcement cage
- hoisting
- support arm
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/12—Slings comprising chains, wires, ropes, or bands; Nets
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/22—Rigid members, e.g. L-shaped members, with parts engaging the under surface of the loads; Crane hooks
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
- B66C13/06—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for minimising or preventing longitudinal or transverse swinging of loads
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention discloses a hoisting hanger device and a hoisting hanger method for a reinforcement cage, and the hoisting hanger device comprises a cross-shaped hanger main body, wherein the cross-shaped hanger main body consists of four hanger support arms, a hoisting point is arranged at the center position where the outer end part of each hanger support arm and the four hanger support arms are intersected, a pull rod is connected to the hoisting point, and a hoisting ring is fixed after the five pull rods are intersected; and each hanger support arm is provided with a plurality of mounting holes, and one mounting hole of each hanger support arm is fixedly provided with a lifting hook. The cross-shaped hanging bracket is used for hoisting the reinforcement cage, and when the reinforcement cage is hoisted, the stress of the whole hanging bracket is balanced, so that the reinforcement cage can be stably moved and placed in the pile hole.
Description
Technical Field
The invention belongs to the technical field of building construction, and particularly relates to a hoisting and hanging frame device and method for a reinforcement cage.
Background
The cast-in-situ bored pile technology is a construction technology with high mechanization degree, high construction speed, mature process, strong structural integrity, good earthquake resistance, guaranteed safe operation and remarkable economic comprehensive benefit in the construction of foundation structure engineering in China. When the cast-in-situ bored pile is constructed, a reinforcement cage must be accurately and stably hoisted into a pile hole, and the instability of the reinforcement cage in the hoisting process can influence the quality of the cast-in-situ bored pile and the safety of personnel in the construction process.
Disclosure of Invention
The invention aims to provide a steel reinforcement cage hoisting hanger device and a steel reinforcement cage hoisting hanger method, which are simple in structure and can ensure that a steel reinforcement cage is kept stable in the hoisting process.
Therefore, the first technical scheme of the invention is as follows: the utility model provides a lifting hanger device of steel reinforcement cage which characterized in that: the lifting device comprises a cross-shaped lifting frame main body, wherein the cross-shaped lifting frame main body consists of four lifting frame support arms, a lifting point is arranged at the center position where the outer end part of each lifting frame support arm and the four lifting frame support arms are intersected, a pull rod is connected to the lifting point, and a lifting ring is fixed after the five pull rods are intersected; and each hanger support arm is provided with a plurality of mounting holes, and one mounting hole of each hanger support arm is fixedly provided with a lifting hook.
Furthermore, rings are located the top of gallows main part central point, and the lifting hook is located gallows support arm below.
Furthermore, the upper end of the lifting hook is of a bolt structure and is fixed through a nut after penetrating through the mounting hole of the hanger support arm.
The second technical scheme of the invention is as follows: a hoisting method of a steel reinforcement cage uses the hanger device, when in use, a proper mounting hole is selected on each hanger support arm according to the radius of the steel reinforcement cage, and a lifting hook is mounted; hanging the hoisting ring on the hoisting equipment so that the hanger main body is hoisted to a height suitable for operation; the lifting hook on the hanger support arm is connected with the steel reinforcement cage through a steel wire rope, and the steel reinforcement cage is stably hung in the pile hole through the hanger; and after the hoisting construction is finished, the lifting hook on the hanger support arm is removed, and the hanger is moved to the next construction area.
The cross-shaped hanging bracket is used for hoisting the steel reinforcement cage, the central position and the four end positions of the hanging bracket are provided with the hoisting points, and the hanging ring above the central position is connected with the hoisting points through the pull rods. Be equipped with a plurality of mounting holes on the gallows support arm for the gallows can steadily hoist and mount the steel reinforcement cage of different diameter specifications, but reuse, and enlarge application range.
Drawings
The following detailed description is made with reference to the accompanying drawings and embodiments of the present invention
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a side view of the structure of the present invention;
FIG. 3 is a top view of the structure of the present invention;
fig. 4 is a bottom view of the structure of the present invention.
Labeled as: the hanging bracket comprises a hanging bracket main body 1, a hanging bracket support arm 11, a hanging point 12, a mounting hole 13, a pull rod 2, a hanging ring 3 and a hanging hook 4.
Detailed Description
See the drawings. The hanger device of the embodiment comprises a cross-shaped hanger main body 1, wherein the hanger main body is formed by a cross-shaped steel frame and comprises four hanger support arms 11 which are perpendicular to each other, and the cross-sectional dimension of each hanger support arm is 200mmx100 mm. Lifting points 12 are arranged at the four end points and the center of the hanger main body, round steel pull rods 2 with the diameter of 20mm are connected to the lifting points, and the five pull rods 2 are finally connected to a lifting ring 3 above the center of the hanger main body 1. Each hanger support arm 11 is provided with a first mounting hole 300mm from the center, next mounting holes are formed every other 100mm, and each hanger support arm is provided with 8 mounting holes 13 with the diameter of 20 mm; only install lifting hook 4 on one mounting hole on every gallows support arm 11, the lifting hook is made for 20mm diameter round steel, and the upper end is bolt structure, passes behind the mounting hole of gallows support arm and fixes through the nut.
When the lifting hook is used, a proper mounting hole is selected on each hanger support arm 11 according to the radius of the steel reinforcement cage, and the lifting hook 4 is mounted; hanging the hanging ring 3 on the hoisting equipment, so that the hanger main body 1 is hoisted to a height suitable for operation; the lifting hook 4 on the hanger support arm 11 is connected with the reinforcement cage through a steel wire rope, and the reinforcement cage is stably hung in the pile hole through the hanger device; and after the hoisting construction is finished, removing the lifting hook on the hanger support arm, moving to the next construction area, and continuing hoisting the next reinforcement cage.
Claims (4)
1. The utility model provides a lifting hanger device of steel reinforcement cage which characterized in that: the lifting device comprises a cross-shaped lifting frame main body, wherein the cross-shaped lifting frame main body consists of four lifting frame support arms, a lifting point is arranged at the center position where the outer end part of each lifting frame support arm and the four lifting frame support arms are intersected, a pull rod is connected to the lifting point, and a lifting ring is fixed after the five pull rods are intersected; and each hanger support arm is provided with a plurality of mounting holes, and one mounting hole of each hanger support arm is fixedly provided with a lifting hook.
2. The steel reinforcement cage lifting frame device of claim 1, wherein: the lifting ring is located above the center of the hanger main body, and the lifting hook is located below the hanger supporting arm.
3. The steel reinforcement cage lifting frame device of claim 1, wherein: the upper end of the lifting hook is of a bolt structure and is fixed through a nut after penetrating through the mounting hole of the hanger support arm.
4. A hoisting method of a reinforcement cage is characterized in that: the hanger apparatus of any one of claims 1 to 3, wherein, in use, the hanger is installed by selecting a suitable mounting hole on each hanger arm according to the radius of the reinforcement cage; hanging the hoisting ring on the hoisting equipment so that the hanger main body is hoisted to a height suitable for operation; the lifting hook on the hanger support arm is connected with the steel reinforcement cage through a steel wire rope, and the steel reinforcement cage is stably hung in the pile hole through the hanger; and after the hoisting construction is finished, the lifting hook on the hanger support arm is removed, and the hanger is moved to the next construction area.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010051058.4A CN111099494A (en) | 2020-01-17 | 2020-01-17 | Hoisting and hanging bracket device and method for steel reinforcement cage |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010051058.4A CN111099494A (en) | 2020-01-17 | 2020-01-17 | Hoisting and hanging bracket device and method for steel reinforcement cage |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111099494A true CN111099494A (en) | 2020-05-05 |
Family
ID=70427246
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010051058.4A Pending CN111099494A (en) | 2020-01-17 | 2020-01-17 | Hoisting and hanging bracket device and method for steel reinforcement cage |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111099494A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113268823A (en) * | 2021-04-13 | 2021-08-17 | 中广核工程有限公司 | Lightweight multipoint hoisting distributor and manufacturing method thereof |
CN113268823B (en) * | 2021-04-13 | 2024-06-21 | 中广核工程有限公司 | Lightweight multipoint hoisting distributor and manufacturing method thereof |
-
2020
- 2020-01-17 CN CN202010051058.4A patent/CN111099494A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113268823A (en) * | 2021-04-13 | 2021-08-17 | 中广核工程有限公司 | Lightweight multipoint hoisting distributor and manufacturing method thereof |
CN113268823B (en) * | 2021-04-13 | 2024-06-21 | 中广核工程有限公司 | Lightweight multipoint hoisting distributor and manufacturing method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN113387267B (en) | Safe hoisting and lowering method for underground diaphragm wall reinforcement cage | |
CN213351278U (en) | Lifting device for flip-chip welding of tank wall of vertical storage tank | |
CN201793330U (en) | Gantry hanger frame device | |
CN211846848U (en) | Hoisting hanger device of steel reinforcement cage | |
CN111099494A (en) | Hoisting and hanging bracket device and method for steel reinforcement cage | |
CN211444740U (en) | Shaft pipeline hoist device | |
CN210560547U (en) | Blast furnace surrounding pipe hoisting structure | |
CN214570055U (en) | Bearing hoisting support for construction of steel reinforcement cage | |
CN214574174U (en) | Loading device for single-pile high-strain detection | |
CN112193984B (en) | Steel reinforcement cage lifting and fixing device and steel reinforcement cage lifting method | |
CN210393407U (en) | Elevation positioning control device for hoisting large embedded part | |
CN220813849U (en) | Positioning device for installation and lowering of deep hole large-diameter pile foundation reinforcement cage | |
CN220467316U (en) | Cast-in-place pile reinforcement cage hoisting device | |
CN112694016A (en) | Bridge crane steel wire rope installation auxiliary device and using method thereof | |
CN201850750U (en) | Operation platform for slip form construction of tubular structure | |
CN215558335U (en) | Cross shoulder pole beam for hoisting pile foundation reinforcing steel bars | |
CN220223275U (en) | Pile foundation drill core sampling verticality location promotes support | |
CN212954013U (en) | Material lifting device | |
CN210768082U (en) | Chimney is dead man device for putting on beams in place | |
CN218712914U (en) | Dig a steel reinforcement cage soon and hang and put hole guider | |
CN218027231U (en) | Simple device for lowering bottom basket of hanging basket | |
CN220926076U (en) | Temporary supporting tool convenient for turnover | |
CN220868215U (en) | Assembled steel frame type heavy steel casing temporary hanging bracket and positioning adjusting device | |
CN217148246U (en) | Large-tonnage steel reinforcement cage hoisting accessory | |
CN215593688U (en) | Bridge pipeline mounting platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |